UNIT 4
FLEXIBLE MANUFACTURING SYSTEM
(FMS) AND AUTOMATED GUIDED
VEHICLE SYSTEM (AGVS)
ī‚´ Types of Flexibility - FMS – FMS Components – FMS Application
& Benefits – FMS Planning and Control– Quantitative analysis in
FMS – Simple Problems. Automated Guided Vehicle System
(AGVS) – AGVS Application – Vehicle Guidance technology –
Vehicle Management & Safety.
FMS
ī‚´ FMS may be defined as “a highly automated GT machine cell,
consisting of a group of processing workstations (usually CNC
machine tools), interconnected by an automated material
handling and storage system, and controlled by a distributed
computer system.”
ī‚´ FMS employs a fully integrated handling system with automated
processing stations.
Flexibility and its Types
ī‚´ Flexibility is an attribute that allows a manufacturing system to
cope up with a certain level of variations in part or product type,
without having any interruption in production due to
changeovers between models.
ī‚´ Flexibility measures the ability to adopt “to a wide range of
possible environment”
Tests of Flexibility
ī‚´ Part variety test
ī‚´ Schedule change test
ī‚´ Error recovery test
ī‚´ New part test
Types of Flexibility
ī‚´ Machine flexibility
ī‚´ Production flexibility
ī‚´ Mix (or Process) flexibility
ī‚´ Product flexibility
ī‚´ Routing flexibility
ī‚´ Volume (or capacity) flexibility
ī‚´ Expansion flexibility
Machine flexibility
ī‚´ Definition: Machine flexibility is the capability to adapt a given
machine in the system to a wide range of production operations
and part types.
ī‚´ Influencing factors:
ī‚´Setup or change over time
ī‚´Ease with which part-programs can be downloaded to machines
ī‚´Tool storage capacity of machine
ī‚´Skill and versatility of workers in the systems
Production flexibility
ī‚´ Definition: Production flexibility is the range of part types that
can be produced by a manufacturing system.
ī‚´ Influencing factors:
ī‚´Machine flexibility of individual stations
ī‚´Range of machine flexibilities of all stations in the system
Mix (or Process) flexibility
ī‚´ Definition: Mix flexibility, also known as process flexibility, is
the ability to change the product mix while maintaining the
same production quantity. i.e., producing the same parts only in
different proportions
ī‚´ Influencing factors:
ī‚´Similarity of parts in the mix
ī‚´Machine flexibility
ī‚´Relative work content times of parts produced
Product flexibility
ī‚´ Definition: Product flexibility is the ability to change over to a
new set of products economically and quickly in response to the
changing market requirements.
ī‚´ Influencing factors:
ī‚´Relatedness of new part design with the existing part family
ī‚´Off-line part program preparation
ī‚´Machine flexibility
Routing flexibility
ī‚´ Definition: Routing flexibility is the capacity to produce parts on
alternative workstation in case of equipment breakdowns, tool
failure, and other interruptions at any particular station.
ī‚´ Influencing factors:
ī‚´Similarity of parts in the mix
ī‚´Similarity of workstations
ī‚´Common testing
Volume (or capacity) flexibility
ī‚´ Definition: Volume flexibility, also known as capacity flexibility,
is the ability of the system to vary the production volumes of
different products to accommodate changes in demand while
remaining profitable.
ī‚´ Influencing factors:
ī‚´Level of manual labour performing production
ī‚´Amount invested in capital equipment
Expansion flexibility
ī‚´ Definition: Expansion flexibility is the ease with which the
system can be expanded to foster total production volume.
ī‚´ Influencing factors:
ī‚´Cost incurred in adding new workstations and trained workers
ī‚´Easiness in expansion of layout
ī‚´Type of part handling system
Four Tests of Flexibility Vs Seven Types of Flexibility
Sl No Flexibility Test Type of Flexibility
1 Part Variety īƒŧ Machine
īƒŧ Production
2 Schedule Change īƒŧ Mix
īƒŧ Volume
īƒŧ Expansion
3 Error recovery īƒŧ Routing
4 New part īƒŧ Product
Types of FMS
ī‚´ Classification based on the kinds of operations they perform
ī‚´Processing operation
ī‚´Assembly operation
ī‚´ Classification based on the number of machines in the system
ī‚´Single machine cell (SMC)
ī‚´Flexible machine cell (FMC)
ī‚´Flexible manufacturing system (FMS)
ī‚´ Classification based on the level of flexibility associated with the system
ī‚´Dedicated FMS
ī‚´Random order FMS
Classification based on the kinds of
operations they perform
ī‚´ Processing operation
ī‚´Processing operation transforms a work material from one state to another
moving towards the final desired part or product.
ī‚´It adds value by changing the geometry, properties or appearance of the
starting materials.
ī‚´ Assembly operation
ī‚´Assembly operation involves joining of two or more components to create a
new entity which is called an assembly.
ī‚´Permanent joining processes include welding, brazing, soldering, adhesive
banding, rivets, press fitting and expansion fits.
Classification based on the number
of machines in the system
ī‚´ Single Machine Cell (SMC)
Flexible machine cell (FMC)
Flexible manufacturing system (FMS)
Summary
Classification based on the level of
flexibility associated with the system
ī‚´Dedicated FMS
ī‚´A dedicated FMS is designed to produce a limited variety of part
configurations.
ī‚´Thus the dedicated FMS usually consists of special purpose machines
rather than general purpose machines.
ī‚´Random order FMS
ī‚´The random order FMS is equipped with general purpose machines so as
to meet the product variations. Also FMS type requires a more
sophisticated computer control system.
Components/Elements of FMS
ī‚´ Workstations
ī‚´ Material handling and storage system
ī‚´ Computer control system
ī‚´ Human resources
FMS Workstations
ī‚´ The workstations/processing stations used in FMS depends upon the
type of product manufactured by the system.
ī‚´ The types of workstations that are usually found in a FMS are:
ī‚´Load/unload stations
ī‚´Machining stations
ī‚´Assembly workstations
ī‚´Inspection station
ī‚´Other processing stations
Material handling and storage system
ī‚´ FMS material handling and storage system include part
transportation, raw material and final product transportation
and storage of workpieces, empty pallets, auxiliary materials,
wastes, fixtures and tools.
ī‚´ Functions of the material handling system
ī‚´ Types of FMS layout
ī‚´ Types of handling equipment used in FMS
Functions of the material handling
system
ī‚´ Material handling may be defined as the functions and systems
associated with the transportation, storage, and physical control
to work-in-process material in manufacturing.
ī‚´ The general purpose of material handling in a factory is to move
raw materials, work-in-process, finished parts, tools, and
supplies from one location to another to facilitate the overall
operations of manufacturing.
Types of FMS layout Configurations
ī‚´ In-line layout
ī‚´ Loop layout
ī‚´ Ladder layout
ī‚´ Open-field layout
ī‚´ Robot-centered cell
In-line layout
ī‚´ As the name suggests, the materials and handling systems are
arranged in a straight line in the in-line layout.
Loop layout
ī‚´ In the loop layout, the workstations are arranged in a loop, as
shown in figure.
Ladder layout
ī‚´ The ladder layout, an adaptation of the loop layout, consists of a
loop with rungs on which workstations are located.
Open-field layout
ī‚´ The open field layout, also an adaptation of the loop
configuration, consists of multiple loops, ladders and sliding
organized to achieve the desired processing requirements.
Robot-centered cell
ī‚´ In the robot-centered cell, one or more robots are used as the
material handling system.
Types of handling equipment used in
FMS
ī‚´ Primary Handling System
ī‚´ Secondary Handling System
Primary Handling System
ī‚´ The primary handling system establishes the basic layout of the
FMS and is responsible for moving work parts between work
stations in the system.
Secondary Handling System
ī‚´ The secondary handling system consists of transfer devices,
automatic pallet changers, and similar mechanisms located at
the workstations in the FMS.
ī‚´ The functions of the secondary handling systems are:
ī‚´To transfer work parts from the primary system to the machine
tool or other processing stations.
ī‚´To position the work parts with sufficient accuracy and
repeatability at the workstation for processing.
ī‚´To provide buffer storage of work parts at each workstation.
Types of Material Handling
Equipment
ī‚´ The material handling equipment commonly used to move parts
between stations can be grouped under six categories,
ī‚´ Conveyors
ī‚´ Cranes and hoists
ī‚´ Industrial trucks
ī‚´ Monorails and other rail guided vehicles
ī‚´ Automated guided vehicles (AGVs) and
ī‚´ Industrial robots.
Computer control system
ī‚´ In flexible manufacturing systems, computers are required to
control the automated and semi-automated equipment and to
participate in the over all coordination and management of the
manufacturing system.
ī‚´ A typical FMS computer control system consists of a central
computer and micro computers controlling the individual
machines and other components.
Functions of a FMS computer control
system
ī‚´ Workstation/processing station control
ī‚´ Distribution of control instructions to workstations
ī‚´ Production control
ī‚´ Material handling system control
ī‚´ Workpiece monitoring
ī‚´ Tool control
ī‚´ Quality control
ī‚´ Failure diagnosis
ī‚´ Safety monitoring
ī‚´ Performance monitoring and reporting
Structure of FMS Application software systems
Types of FMS Data Files
ī‚´ Part program file
ī‚´ Routing file
ī‚´ Part production file
ī‚´ Pallet reference file
ī‚´ Station tool file
ī‚´ Tool life file
Human Resources
ī‚´ In FMS, human labours are needed to perform the following functions
ī‚´To load raw work parts into the system
ī‚´To unload finished work parts from the system
ī‚´For tool changing and tool setting
ī‚´For equipment maintenance and repair
ī‚´To program and operate the computer system
ī‚´To accomplish overall management of the system
Example of Flexible
Manufacturing System
ī‚´ FMS installed at Vought Aerospace in Dallas
FMS Applications
ī‚´ Machining
ī‚´ Assembly
ī‚´ Sheet-metal press working
ī‚´ Forging
ī‚´ Plastic injection moulding
ī‚´ Welding
ī‚´ Textile machinery manufacture
ī‚´ Semiconductor component manufacture
Economics of FMS
ī‚´ 5-20% reduction in personnel
ī‚´ 15-30% reduction in engineering design cost
ī‚´ 30-60% reduction in overall lead time
ī‚´ 30-60% reduction in work-in-process
ī‚´ 40-70% gain in overall production
ī‚´ 200-300% gain in capital equipment operating time
ī‚´ 200-500% gain in product quality
ī‚´ 300-500% gain in engineering productivity
Advantages of FMS
(Benefits of FMS)
ī‚´ Increased machine utilization
ī‚´ Reduced inventory
ī‚´ Reduced manufacturing lead time
ī‚´ Greater flexibility in production scheduling
ī‚´ Reduced direct labour cost
ī‚´ Increased labour productivity
ī‚´ Shorter response time
ī‚´ Consistent quality
ī‚´ Reduced factory floor space
ī‚´ Reduced number of tools and machines required
ī‚´ Improved product quality
Disadvantages of FMS
ī‚´ Very high capital investment is required to implement a FMS
ī‚´ Acquiring, training and maintaining the knowledgeable labour
pool requires heavy investment
ī‚´ Fixtures can sometimes cost much more with FMS, and software
development costs could be as much as 12-20% of the total
expense
ī‚´ Tool performance and condition monitoring can also be
expensive since tool variety could undermine efficiency
ī‚´ Complex design estimating methodology requires optimizing
the degree of flexibility and finding a trade off between
flexibility and specialization
FMS Planning and Control
(FMS Planning and Implementation
issues)
ī‚´ FMS planning and design issues
ī‚´ FMS control (or operational) issues
FMS Planning issues
ī‚´ Part family considerations
ī‚´ Processing requirements
ī‚´ Physical characteristics of the work parts
ī‚´ Production volume
FMS design issues
ī‚´ Type of work stations
ī‚´ Variations in process routings and FMS layout
ī‚´ Material handling system
ī‚´ Work-in-process and storage capacity
ī‚´ Tooling
ī‚´ Pallet fixtures
FMS operational issues
ī‚´ Scheduling and dispatching
ī‚´ Machine loading
ī‚´ Part routing
ī‚´ Part grouping
ī‚´ Tool management
ī‚´ Pallet and fixture allocation
Quantitative analysis of Flexible
Manufacturing System
ī‚´ Flexible manufacturing system can be analysed using different
models. The four different categories of FMS analysis models
are:
ī‚´Deterministic models
ī‚´Queuing models
ī‚´Discrete event simulation
ī‚´Other techniques
Bottleneck model
ī‚´ The bottleneck model is a simple and intuitive approach to
determine the starting estimates of FMS design parameters such
as production rate, capacity and utilization.
Terminology and symbols
FMS operational Parameters
System Performance Measures
Automated Guided Vehicle System
(AGVS)
ī‚´ An Automated Guided Vehicle System (AGVS) is a computer
controlled, driverless vehicle used for transporting materials
from point to point in a manufacturing setting.
ī‚´ An AGVS uses independently operated, self-propelled vehicles
that are guided along pre-defined paths, and are powered by
means of on-board batteries.
ī‚´ The AGVs are highly flexible, intelligent, and versatile material
handling systems used to transport materials from various
loading locations to various unloading locations throughout the
manufacturing facility.
Strengths of AGVs
ī‚´ Space
ī‚´ Economical
ī‚´ Agile
ī‚´ Flexible
ī‚´ Dynamic
ī‚´ Redundancy
Benefits of AGVs
ī‚´ Labour
ī‚´ Damage
ī‚´ Shipping accuracy
ī‚´ Energy
ī‚´ Safety
Types of AGVs
ī‚´ Guided driverless trains
ī‚´ Guided pallet trucks
ī‚´ Guided unit load carriers
Guided Driverless Trains
ī‚´ The Guided driverless trains, also known as towing vehicles or
automated guided tractors, are most commonly used for
transporting large amount of bulky and heavy materials from
the warehouse to various locations in the manufacturing plant.
Guided Pallet Trucks
ī‚´ The guided pallet trucks are designed to lift and transport palletized
loads.
ī‚´ It is used for picking up or dropping off loads from and on to floor level.
Thus it eliminates the need for fixed load stands.
ī‚´ There is no need for any special accessories for loading and unloading
the guided pallet except that the loads should be on a pallet.
ī‚´ Usually the following sequence of operations are being carried out in
pallet trucks
ī‚´Loads are pulled off onto a pallet forks
ī‚´Lowering of the pallet forks to the floor
ī‚´Pulling out from the pallet
ī‚´Finally automatically returns empty to the loading area.
Guided unit load carriers
ī‚´ Guided unit load carries have a deck that permits unit-load
transport operation.
ī‚´ They are used in settings with short/medium guide paths, high
volume, and need for independent and versatility.
ī‚´ They are used in warehousing and distribution systems.
ī‚´ They can operate in an environment where there is not much
room and movement is restricted.
Applications of AGVS
ī‚´ Automated Guided Vehicles are used in a variety of areas to
support processing and handling throughout a manufacturing
facility.
ī‚´Assembly
ī‚´Kitting
ī‚´Transportation
ī‚´Staging
ī‚´Warehousing
ī‚´Order picking
ī‚´Parts/just-in-time delivery
ī‚´Transfer/shuttle
Applications of AGVs based on
types of AGVs employed
ī‚´ Driverless train operations
ī‚´ Storage and distribution operations
ī‚´ Assembly line applications
ī‚´ Flexible manufacturing systems.
Vehicle Guidance Technology
ī‚´ The goal of an AGVS guidance system is to keep the AGV on track
or on predefined path.
ī‚´ Types of AGV Guidance approach
ī‚´Fixed-route guidance method
ī‚´Free – route guidance method
Fixed-route guidance method
ī‚´ Fixed route guidance is to set medium guidance information in
the path, AGV can drive with it, such as electromagnetic
guidance, tape guidance, etc.
Free – route guidance method
ī‚´ Free-route guidance stores the size of the coordinates, AGV can
identify current position and decide driving path, such as laser-
guidance and image recognition guidance.
Types of vehicle Guidance
Technologies
ī‚´ There are many AGV guidance technologies/methods available
and their selection will depend on need, application, and
environmental constraints.
ī‚´Wire guidance system
ī‚´Paint strips system
ī‚´Self-guided vehicles
Vehicle Management
ī‚´ Traffic control
ī‚´ Vehicle dispatching
Traffic control
ī‚´ The purpose of traffic control in an automated guided vehicle
system is to minimise interference between vehicles and
prevent collisions.
ī‚´ Methods of traffic control
ī‚´Forward-sensing control
ī‚´Zone sensing control
ī‚´Combinational control
Forward-sensing control system
Zone sensing control
Vehicle Dispatching
ī‚´ For an effective functioning of AGVS, AGVS must be dispatched in
a timely manner, as and when they are needed.
ī‚´ Dispatching methods:
ī‚´Vehicle Dispatching using On-board control panels
ī‚´Vehicle Dispatching using Remote call stations
ī‚´Vehicle Dispatching using Supervisory central computer control
ī‚´Combinatorial method
Vehicle Safety
ī‚´ An automated guided vehicle system should be designed taking
into account the safety of human personnel in the shop floor.
ī‚´ Safety features provided for AGVs:
ī‚´Movement speeds of less than walking pace
ī‚´Automatic stopping of the vehicle
ī‚´Obstacle detection sensors on the vehicle
ī‚´Emergency bumper
ī‚´Additional features

More Related Content

What's hot

Automated assembly systems
Automated assembly systemsAutomated assembly systems
Automated assembly systemsVibhas Purushu
 
Manufacturing systems
Manufacturing systemsManufacturing systems
Manufacturing systemsAbu Bashar
 
Automated storage and retrieval systems
Automated storage and retrieval systemsAutomated storage and retrieval systems
Automated storage and retrieval systemsRAJA GAUTAM
 
Computer aided quality control
Computer aided quality controlComputer aided quality control
Computer aided quality controlAhmad Bajwa
 
Introduction to flexible manufacturing system (fms)
Introduction to flexible manufacturing system (fms)Introduction to flexible manufacturing system (fms)
Introduction to flexible manufacturing system (fms)Nilraj Vasandia
 
Material Handling System in Industries
Material Handling System in IndustriesMaterial Handling System in Industries
Material Handling System in IndustriesRahul Bhardwaj
 
cAdaptive control
cAdaptive controlcAdaptive control
cAdaptive controlAkash Maurya
 
Adaptive Control System
Adaptive Control SystemAdaptive Control System
Adaptive Control SystemShreyashPatel24
 
Automated guided vehicle
Automated guided vehicle Automated guided vehicle
Automated guided vehicle Jagannath12345
 
Agv and asrs
Agv and asrsAgv and asrs
Agv and asrsAkash Maurya
 
Automated material handling org PEC UNIVERSITY TECHNOLOGY
Automated material handling org PEC UNIVERSITY TECHNOLOGY Automated material handling org PEC UNIVERSITY TECHNOLOGY
Automated material handling org PEC UNIVERSITY TECHNOLOGY PEC University Chandigarh
 
Automated Production Lines.ppt
Automated Production Lines.pptAutomated Production Lines.ppt
Automated Production Lines.pptAbhishekChavan77
 
Automated material handling
Automated material handlingAutomated material handling
Automated material handlingDINBANDHU SINGH
 
Introduction to Flexible Manufacturing System (FMS)
Introduction to Flexible Manufacturing System (FMS)Introduction to Flexible Manufacturing System (FMS)
Introduction to Flexible Manufacturing System (FMS)VADLAJAGADEESHWARAAC
 
Unit 5 cim
Unit 5 cimUnit 5 cim
Unit 5 cimdinesh babu
 
Automated Guided Vehicles
Automated Guided VehiclesAutomated Guided Vehicles
Automated Guided VehiclesJaideepInaganti
 

What's hot (20)

Automated assembly systems
Automated assembly systemsAutomated assembly systems
Automated assembly systems
 
Manufacturing systems
Manufacturing systemsManufacturing systems
Manufacturing systems
 
Automated storage and retrieval systems
Automated storage and retrieval systemsAutomated storage and retrieval systems
Automated storage and retrieval systems
 
Computer aided quality control
Computer aided quality controlComputer aided quality control
Computer aided quality control
 
Introduction to flexible manufacturing system (fms)
Introduction to flexible manufacturing system (fms)Introduction to flexible manufacturing system (fms)
Introduction to flexible manufacturing system (fms)
 
Material Handling System in Industries
Material Handling System in IndustriesMaterial Handling System in Industries
Material Handling System in Industries
 
cAdaptive control
cAdaptive controlcAdaptive control
cAdaptive control
 
Automated Production Lines
Automated Production LinesAutomated Production Lines
Automated Production Lines
 
Automated guided vehicle systems (AGVs)
Automated guided vehicle systems (AGVs)Automated guided vehicle systems (AGVs)
Automated guided vehicle systems (AGVs)
 
Adaptive Control System
Adaptive Control SystemAdaptive Control System
Adaptive Control System
 
Automated guided vehicle
Automated guided vehicle Automated guided vehicle
Automated guided vehicle
 
Agv and asrs
Agv and asrsAgv and asrs
Agv and asrs
 
Automated material handling org PEC UNIVERSITY TECHNOLOGY
Automated material handling org PEC UNIVERSITY TECHNOLOGY Automated material handling org PEC UNIVERSITY TECHNOLOGY
Automated material handling org PEC UNIVERSITY TECHNOLOGY
 
Automated Production Lines.ppt
Automated Production Lines.pptAutomated Production Lines.ppt
Automated Production Lines.ppt
 
Automated material handling
Automated material handlingAutomated material handling
Automated material handling
 
Introduction to Flexible Manufacturing System (FMS)
Introduction to Flexible Manufacturing System (FMS)Introduction to Flexible Manufacturing System (FMS)
Introduction to Flexible Manufacturing System (FMS)
 
Asrs
AsrsAsrs
Asrs
 
ASRS
ASRSASRS
ASRS
 
Unit 5 cim
Unit 5 cimUnit 5 cim
Unit 5 cim
 
Automated Guided Vehicles
Automated Guided VehiclesAutomated Guided Vehicles
Automated Guided Vehicles
 

Similar to Unit 4 cim

Unit 5 2nd-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
Unit 5 2nd-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURINGUnit 5 2nd-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURING
Unit 5 2nd-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURINGMohanumar S
 
Unit 4 cim
Unit 4 cimUnit 4 cim
Unit 4 cimrknatarajan
 
Flexible manufacturing syatem
Flexible manufacturing syatemFlexible manufacturing syatem
Flexible manufacturing syatemDobariya Gautam
 
FMS IN CAD/CAM TYPES HISTORY ADVANTAGES PPT_final.pptx
FMS IN CAD/CAM  TYPES HISTORY ADVANTAGES PPT_final.pptxFMS IN CAD/CAM  TYPES HISTORY ADVANTAGES PPT_final.pptx
FMS IN CAD/CAM TYPES HISTORY ADVANTAGES PPT_final.pptxPraveenVundrajavarap
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing SystemVishal Jadhav
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing SystemDesai Vaishali
 
Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)SERCOD
 
MANUFACTURING SYSTEMS PROJECT
MANUFACTURING SYSTEMS PROJECTMANUFACTURING SYSTEMS PROJECT
MANUFACTURING SYSTEMS PROJECTVADLAJAGADEESHWARAAC
 
flexible manufacturing system
flexible manufacturing systemflexible manufacturing system
flexible manufacturing systemPAARTH GUPTA
 
flexible manufacturing systems
flexible manufacturing systemsflexible manufacturing systems
flexible manufacturing systemsShivam Joshi
 
Flexible manufacturing _system by fateh singh
Flexible manufacturing _system by fateh singhFlexible manufacturing _system by fateh singh
Flexible manufacturing _system by fateh singhFateh Singh
 
CAD CAM 1 Module-3 Part-A 18ME72
CAD CAM  1 Module-3 Part-A 18ME72CAD CAM  1 Module-3 Part-A 18ME72
CAD CAM 1 Module-3 Part-A 18ME72Mohammed Imran
 
Flexible manufacturing systems
Flexible manufacturing systems Flexible manufacturing systems
Flexible manufacturing systems Nityanand Yadav
 
66281324-Flexible-Manufacturing-Systems.ppt
66281324-Flexible-Manufacturing-Systems.ppt66281324-Flexible-Manufacturing-Systems.ppt
66281324-Flexible-Manufacturing-Systems.pptTAMILSELVANNATARAJAN3
 

Similar to Unit 4 cim (20)

CIM unit-4
CIM  unit-4CIM  unit-4
CIM unit-4
 
Unit 5 2nd-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
Unit 5 2nd-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURINGUnit 5 2nd-ME8691 & COMPUTER AIDED DESIGN AND    MANUFACTURING
Unit 5 2nd-ME8691 & COMPUTER AIDED DESIGN AND MANUFACTURING
 
Unit 4 cim
Unit 4 cimUnit 4 cim
Unit 4 cim
 
Flexible manufacturing syatem
Flexible manufacturing syatemFlexible manufacturing syatem
Flexible manufacturing syatem
 
FMS IN CAD/CAM TYPES HISTORY ADVANTAGES PPT_final.pptx
FMS IN CAD/CAM  TYPES HISTORY ADVANTAGES PPT_final.pptxFMS IN CAD/CAM  TYPES HISTORY ADVANTAGES PPT_final.pptx
FMS IN CAD/CAM TYPES HISTORY ADVANTAGES PPT_final.pptx
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing System
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing System
 
Fms
FmsFms
Fms
 
Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)
 
Unit 4
Unit 4Unit 4
Unit 4
 
MANUFACTURING SYSTEMS PROJECT
MANUFACTURING SYSTEMS PROJECTMANUFACTURING SYSTEMS PROJECT
MANUFACTURING SYSTEMS PROJECT
 
flexible manufacturing system
flexible manufacturing systemflexible manufacturing system
flexible manufacturing system
 
Flexible Manufacturing Systems V2 090310
Flexible Manufacturing Systems V2 090310Flexible Manufacturing Systems V2 090310
Flexible Manufacturing Systems V2 090310
 
flexible manufacturing systems
flexible manufacturing systemsflexible manufacturing systems
flexible manufacturing systems
 
Flexible manufacturing _system by fateh singh
Flexible manufacturing _system by fateh singhFlexible manufacturing _system by fateh singh
Flexible manufacturing _system by fateh singh
 
CAD CAM 1 Module-3 Part-A 18ME72
CAD CAM  1 Module-3 Part-A 18ME72CAD CAM  1 Module-3 Part-A 18ME72
CAD CAM 1 Module-3 Part-A 18ME72
 
Unit6 55
Unit6 55Unit6 55
Unit6 55
 
Flexible manufacturing systems
Flexible manufacturing systems Flexible manufacturing systems
Flexible manufacturing systems
 
FMS_2021.pptx
FMS_2021.pptxFMS_2021.pptx
FMS_2021.pptx
 
66281324-Flexible-Manufacturing-Systems.ppt
66281324-Flexible-Manufacturing-Systems.ppt66281324-Flexible-Manufacturing-Systems.ppt
66281324-Flexible-Manufacturing-Systems.ppt
 

More from dinesh babu

Metrology Measurements and All units PPT
Metrology Measurements and  All units PPTMetrology Measurements and  All units PPT
Metrology Measurements and All units PPTdinesh babu
 
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptxUnit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptxdinesh babu
 
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptxUnit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptxdinesh babu
 
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptxUnit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptxdinesh babu
 
UNIT 2-Geometric Modeling.pptx
UNIT 2-Geometric Modeling.pptxUNIT 2-Geometric Modeling.pptx
UNIT 2-Geometric Modeling.pptxdinesh babu
 
UNIT 1-INTRODUCTION.pptx
UNIT 1-INTRODUCTION.pptxUNIT 1-INTRODUCTION.pptx
UNIT 1-INTRODUCTION.pptxdinesh babu
 
UNIT-5FIRE SAFETY AND INSTALLATION.pptx
UNIT-5FIRE SAFETY AND INSTALLATION.pptxUNIT-5FIRE SAFETY AND INSTALLATION.pptx
UNIT-5FIRE SAFETY AND INSTALLATION.pptxdinesh babu
 
UNIT-4-REFIGERATION PRINCIPLES.pptx
UNIT-4-REFIGERATION PRINCIPLES.pptxUNIT-4-REFIGERATION PRINCIPLES.pptx
UNIT-4-REFIGERATION PRINCIPLES.pptxdinesh babu
 
UNIT-3-Principles of illumination.pptx
UNIT-3-Principles of illumination.pptxUNIT-3-Principles of illumination.pptx
UNIT-3-Principles of illumination.pptxdinesh babu
 
UNIT-2-Electrical Systems.pptx
UNIT-2-Electrical Systems.pptxUNIT-2-Electrical Systems.pptx
UNIT-2-Electrical Systems.pptxdinesh babu
 
UNIT-1-MACHINERIES.pptx
UNIT-1-MACHINERIES.pptxUNIT-1-MACHINERIES.pptx
UNIT-1-MACHINERIES.pptxdinesh babu
 
UNIT- 2&3 based on gear life.pdf
UNIT- 2&3 based on gear life.pdfUNIT- 2&3 based on gear life.pdf
UNIT- 2&3 based on gear life.pdfdinesh babu
 
ELEMENTS OF TECHNOLOGY.pdf
ELEMENTS OF TECHNOLOGY.pdfELEMENTS OF TECHNOLOGY.pdf
ELEMENTS OF TECHNOLOGY.pdfdinesh babu
 
belt_drive.ppt
belt_drive.pptbelt_drive.ppt
belt_drive.pptdinesh babu
 
Unit ii engine auxiliary systems
Unit ii engine auxiliary systemsUnit ii engine auxiliary systems
Unit ii engine auxiliary systemsdinesh babu
 
Mm -unit iii
Mm -unit iii Mm -unit iii
Mm -unit iii dinesh babu
 

More from dinesh babu (20)

Metrology Measurements and All units PPT
Metrology Measurements and  All units PPTMetrology Measurements and  All units PPT
Metrology Measurements and All units PPT
 
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptxUnit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
Unit 5-CELLULAR MANUFACTURING AND FLEXIBLE MANUFACTURING SYSTEM (FMS) .pptx
 
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptxUnit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
Unit 4-FUNDAMENTAL OF CNC AND PART PROGRAMING.pptx
 
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptxUnit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
Unit 3-ASSEMBLY OF PARTS AND CAD STANDARDS.pptx
 
UNIT 2-Geometric Modeling.pptx
UNIT 2-Geometric Modeling.pptxUNIT 2-Geometric Modeling.pptx
UNIT 2-Geometric Modeling.pptx
 
UNIT 1-INTRODUCTION.pptx
UNIT 1-INTRODUCTION.pptxUNIT 1-INTRODUCTION.pptx
UNIT 1-INTRODUCTION.pptx
 
UNIT-5FIRE SAFETY AND INSTALLATION.pptx
UNIT-5FIRE SAFETY AND INSTALLATION.pptxUNIT-5FIRE SAFETY AND INSTALLATION.pptx
UNIT-5FIRE SAFETY AND INSTALLATION.pptx
 
UNIT-4-REFIGERATION PRINCIPLES.pptx
UNIT-4-REFIGERATION PRINCIPLES.pptxUNIT-4-REFIGERATION PRINCIPLES.pptx
UNIT-4-REFIGERATION PRINCIPLES.pptx
 
UNIT-3-Principles of illumination.pptx
UNIT-3-Principles of illumination.pptxUNIT-3-Principles of illumination.pptx
UNIT-3-Principles of illumination.pptx
 
UNIT-2-Electrical Systems.pptx
UNIT-2-Electrical Systems.pptxUNIT-2-Electrical Systems.pptx
UNIT-2-Electrical Systems.pptx
 
UNIT-1-MACHINERIES.pptx
UNIT-1-MACHINERIES.pptxUNIT-1-MACHINERIES.pptx
UNIT-1-MACHINERIES.pptx
 
UNIT- 2&3 based on gear life.pdf
UNIT- 2&3 based on gear life.pdfUNIT- 2&3 based on gear life.pdf
UNIT- 2&3 based on gear life.pdf
 
ELEMENTS OF TECHNOLOGY.pdf
ELEMENTS OF TECHNOLOGY.pdfELEMENTS OF TECHNOLOGY.pdf
ELEMENTS OF TECHNOLOGY.pdf
 
belt_drive.ppt
belt_drive.pptbelt_drive.ppt
belt_drive.ppt
 
Unit iii
Unit iiiUnit iii
Unit iii
 
Unit ii engine auxiliary systems
Unit ii engine auxiliary systemsUnit ii engine auxiliary systems
Unit ii engine auxiliary systems
 
Unit i
Unit iUnit i
Unit i
 
Unitv
Unitv   Unitv
Unitv
 
Unit iv
Unit ivUnit iv
Unit iv
 
Mm -unit iii
Mm -unit iii Mm -unit iii
Mm -unit iii
 

Recently uploaded

Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Gurgaon ✡ī¸9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡ī¸9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡ī¸9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡ī¸9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 

Recently uploaded (20)

Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Gurgaon ✡ī¸9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡ī¸9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡ī¸9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡ī¸9711147426✨Call In girls Gurgaon Sector 51 escort service
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 

Unit 4 cim

  • 2. FLEXIBLE MANUFACTURING SYSTEM (FMS) AND AUTOMATED GUIDED VEHICLE SYSTEM (AGVS) ī‚´ Types of Flexibility - FMS – FMS Components – FMS Application & Benefits – FMS Planning and Control– Quantitative analysis in FMS – Simple Problems. Automated Guided Vehicle System (AGVS) – AGVS Application – Vehicle Guidance technology – Vehicle Management & Safety.
  • 3. FMS ī‚´ FMS may be defined as “a highly automated GT machine cell, consisting of a group of processing workstations (usually CNC machine tools), interconnected by an automated material handling and storage system, and controlled by a distributed computer system.” ī‚´ FMS employs a fully integrated handling system with automated processing stations.
  • 4.
  • 5.
  • 6. Flexibility and its Types ī‚´ Flexibility is an attribute that allows a manufacturing system to cope up with a certain level of variations in part or product type, without having any interruption in production due to changeovers between models. ī‚´ Flexibility measures the ability to adopt “to a wide range of possible environment”
  • 7. Tests of Flexibility ī‚´ Part variety test ī‚´ Schedule change test ī‚´ Error recovery test ī‚´ New part test
  • 8.
  • 9. Types of Flexibility ī‚´ Machine flexibility ī‚´ Production flexibility ī‚´ Mix (or Process) flexibility ī‚´ Product flexibility ī‚´ Routing flexibility ī‚´ Volume (or capacity) flexibility ī‚´ Expansion flexibility
  • 10. Machine flexibility ī‚´ Definition: Machine flexibility is the capability to adapt a given machine in the system to a wide range of production operations and part types. ī‚´ Influencing factors: ī‚´Setup or change over time ī‚´Ease with which part-programs can be downloaded to machines ī‚´Tool storage capacity of machine ī‚´Skill and versatility of workers in the systems
  • 11. Production flexibility ī‚´ Definition: Production flexibility is the range of part types that can be produced by a manufacturing system. ī‚´ Influencing factors: ī‚´Machine flexibility of individual stations ī‚´Range of machine flexibilities of all stations in the system
  • 12. Mix (or Process) flexibility ī‚´ Definition: Mix flexibility, also known as process flexibility, is the ability to change the product mix while maintaining the same production quantity. i.e., producing the same parts only in different proportions ī‚´ Influencing factors: ī‚´Similarity of parts in the mix ī‚´Machine flexibility ī‚´Relative work content times of parts produced
  • 13. Product flexibility ī‚´ Definition: Product flexibility is the ability to change over to a new set of products economically and quickly in response to the changing market requirements. ī‚´ Influencing factors: ī‚´Relatedness of new part design with the existing part family ī‚´Off-line part program preparation ī‚´Machine flexibility
  • 14. Routing flexibility ī‚´ Definition: Routing flexibility is the capacity to produce parts on alternative workstation in case of equipment breakdowns, tool failure, and other interruptions at any particular station. ī‚´ Influencing factors: ī‚´Similarity of parts in the mix ī‚´Similarity of workstations ī‚´Common testing
  • 15. Volume (or capacity) flexibility ī‚´ Definition: Volume flexibility, also known as capacity flexibility, is the ability of the system to vary the production volumes of different products to accommodate changes in demand while remaining profitable. ī‚´ Influencing factors: ī‚´Level of manual labour performing production ī‚´Amount invested in capital equipment
  • 16. Expansion flexibility ī‚´ Definition: Expansion flexibility is the ease with which the system can be expanded to foster total production volume. ī‚´ Influencing factors: ī‚´Cost incurred in adding new workstations and trained workers ī‚´Easiness in expansion of layout ī‚´Type of part handling system
  • 17. Four Tests of Flexibility Vs Seven Types of Flexibility Sl No Flexibility Test Type of Flexibility 1 Part Variety īƒŧ Machine īƒŧ Production 2 Schedule Change īƒŧ Mix īƒŧ Volume īƒŧ Expansion 3 Error recovery īƒŧ Routing 4 New part īƒŧ Product
  • 18. Types of FMS ī‚´ Classification based on the kinds of operations they perform ī‚´Processing operation ī‚´Assembly operation ī‚´ Classification based on the number of machines in the system ī‚´Single machine cell (SMC) ī‚´Flexible machine cell (FMC) ī‚´Flexible manufacturing system (FMS) ī‚´ Classification based on the level of flexibility associated with the system ī‚´Dedicated FMS ī‚´Random order FMS
  • 19. Classification based on the kinds of operations they perform ī‚´ Processing operation ī‚´Processing operation transforms a work material from one state to another moving towards the final desired part or product. ī‚´It adds value by changing the geometry, properties or appearance of the starting materials. ī‚´ Assembly operation ī‚´Assembly operation involves joining of two or more components to create a new entity which is called an assembly. ī‚´Permanent joining processes include welding, brazing, soldering, adhesive banding, rivets, press fitting and expansion fits.
  • 20. Classification based on the number of machines in the system ī‚´ Single Machine Cell (SMC)
  • 24.
  • 25. Classification based on the level of flexibility associated with the system ī‚´Dedicated FMS ī‚´A dedicated FMS is designed to produce a limited variety of part configurations. ī‚´Thus the dedicated FMS usually consists of special purpose machines rather than general purpose machines. ī‚´Random order FMS ī‚´The random order FMS is equipped with general purpose machines so as to meet the product variations. Also FMS type requires a more sophisticated computer control system.
  • 26.
  • 27.
  • 28. Components/Elements of FMS ī‚´ Workstations ī‚´ Material handling and storage system ī‚´ Computer control system ī‚´ Human resources
  • 29. FMS Workstations ī‚´ The workstations/processing stations used in FMS depends upon the type of product manufactured by the system. ī‚´ The types of workstations that are usually found in a FMS are: ī‚´Load/unload stations ī‚´Machining stations ī‚´Assembly workstations ī‚´Inspection station ī‚´Other processing stations
  • 30. Material handling and storage system ī‚´ FMS material handling and storage system include part transportation, raw material and final product transportation and storage of workpieces, empty pallets, auxiliary materials, wastes, fixtures and tools. ī‚´ Functions of the material handling system ī‚´ Types of FMS layout ī‚´ Types of handling equipment used in FMS
  • 31. Functions of the material handling system ī‚´ Material handling may be defined as the functions and systems associated with the transportation, storage, and physical control to work-in-process material in manufacturing. ī‚´ The general purpose of material handling in a factory is to move raw materials, work-in-process, finished parts, tools, and supplies from one location to another to facilitate the overall operations of manufacturing.
  • 32.
  • 33. Types of FMS layout Configurations ī‚´ In-line layout ī‚´ Loop layout ī‚´ Ladder layout ī‚´ Open-field layout ī‚´ Robot-centered cell
  • 34. In-line layout ī‚´ As the name suggests, the materials and handling systems are arranged in a straight line in the in-line layout.
  • 35.
  • 36. Loop layout ī‚´ In the loop layout, the workstations are arranged in a loop, as shown in figure.
  • 37.
  • 38. Ladder layout ī‚´ The ladder layout, an adaptation of the loop layout, consists of a loop with rungs on which workstations are located.
  • 39.
  • 40. Open-field layout ī‚´ The open field layout, also an adaptation of the loop configuration, consists of multiple loops, ladders and sliding organized to achieve the desired processing requirements.
  • 41.
  • 42. Robot-centered cell ī‚´ In the robot-centered cell, one or more robots are used as the material handling system.
  • 43.
  • 44. Types of handling equipment used in FMS ī‚´ Primary Handling System ī‚´ Secondary Handling System
  • 45. Primary Handling System ī‚´ The primary handling system establishes the basic layout of the FMS and is responsible for moving work parts between work stations in the system.
  • 46.
  • 47. Secondary Handling System ī‚´ The secondary handling system consists of transfer devices, automatic pallet changers, and similar mechanisms located at the workstations in the FMS. ī‚´ The functions of the secondary handling systems are: ī‚´To transfer work parts from the primary system to the machine tool or other processing stations. ī‚´To position the work parts with sufficient accuracy and repeatability at the workstation for processing. ī‚´To provide buffer storage of work parts at each workstation.
  • 48. Types of Material Handling Equipment ī‚´ The material handling equipment commonly used to move parts between stations can be grouped under six categories, ī‚´ Conveyors ī‚´ Cranes and hoists ī‚´ Industrial trucks ī‚´ Monorails and other rail guided vehicles ī‚´ Automated guided vehicles (AGVs) and ī‚´ Industrial robots.
  • 49. Computer control system ī‚´ In flexible manufacturing systems, computers are required to control the automated and semi-automated equipment and to participate in the over all coordination and management of the manufacturing system. ī‚´ A typical FMS computer control system consists of a central computer and micro computers controlling the individual machines and other components.
  • 50. Functions of a FMS computer control system ī‚´ Workstation/processing station control ī‚´ Distribution of control instructions to workstations ī‚´ Production control ī‚´ Material handling system control ī‚´ Workpiece monitoring ī‚´ Tool control ī‚´ Quality control ī‚´ Failure diagnosis ī‚´ Safety monitoring ī‚´ Performance monitoring and reporting
  • 51. Structure of FMS Application software systems
  • 52. Types of FMS Data Files ī‚´ Part program file ī‚´ Routing file ī‚´ Part production file ī‚´ Pallet reference file ī‚´ Station tool file ī‚´ Tool life file
  • 53.
  • 54. Human Resources ī‚´ In FMS, human labours are needed to perform the following functions ī‚´To load raw work parts into the system ī‚´To unload finished work parts from the system ī‚´For tool changing and tool setting ī‚´For equipment maintenance and repair ī‚´To program and operate the computer system ī‚´To accomplish overall management of the system
  • 55. Example of Flexible Manufacturing System ī‚´ FMS installed at Vought Aerospace in Dallas
  • 56.
  • 57. FMS Applications ī‚´ Machining ī‚´ Assembly ī‚´ Sheet-metal press working ī‚´ Forging ī‚´ Plastic injection moulding ī‚´ Welding ī‚´ Textile machinery manufacture ī‚´ Semiconductor component manufacture
  • 58. Economics of FMS ī‚´ 5-20% reduction in personnel ī‚´ 15-30% reduction in engineering design cost ī‚´ 30-60% reduction in overall lead time ī‚´ 30-60% reduction in work-in-process ī‚´ 40-70% gain in overall production ī‚´ 200-300% gain in capital equipment operating time ī‚´ 200-500% gain in product quality ī‚´ 300-500% gain in engineering productivity
  • 59. Advantages of FMS (Benefits of FMS) ī‚´ Increased machine utilization ī‚´ Reduced inventory ī‚´ Reduced manufacturing lead time ī‚´ Greater flexibility in production scheduling ī‚´ Reduced direct labour cost ī‚´ Increased labour productivity ī‚´ Shorter response time ī‚´ Consistent quality ī‚´ Reduced factory floor space ī‚´ Reduced number of tools and machines required ī‚´ Improved product quality
  • 60. Disadvantages of FMS ī‚´ Very high capital investment is required to implement a FMS ī‚´ Acquiring, training and maintaining the knowledgeable labour pool requires heavy investment ī‚´ Fixtures can sometimes cost much more with FMS, and software development costs could be as much as 12-20% of the total expense ī‚´ Tool performance and condition monitoring can also be expensive since tool variety could undermine efficiency ī‚´ Complex design estimating methodology requires optimizing the degree of flexibility and finding a trade off between flexibility and specialization
  • 61. FMS Planning and Control (FMS Planning and Implementation issues) ī‚´ FMS planning and design issues ī‚´ FMS control (or operational) issues
  • 62. FMS Planning issues ī‚´ Part family considerations ī‚´ Processing requirements ī‚´ Physical characteristics of the work parts ī‚´ Production volume
  • 63. FMS design issues ī‚´ Type of work stations ī‚´ Variations in process routings and FMS layout ī‚´ Material handling system ī‚´ Work-in-process and storage capacity ī‚´ Tooling ī‚´ Pallet fixtures
  • 64. FMS operational issues ī‚´ Scheduling and dispatching ī‚´ Machine loading ī‚´ Part routing ī‚´ Part grouping ī‚´ Tool management ī‚´ Pallet and fixture allocation
  • 65. Quantitative analysis of Flexible Manufacturing System ī‚´ Flexible manufacturing system can be analysed using different models. The four different categories of FMS analysis models are: ī‚´Deterministic models ī‚´Queuing models ī‚´Discrete event simulation ī‚´Other techniques
  • 66. Bottleneck model ī‚´ The bottleneck model is a simple and intuitive approach to determine the starting estimates of FMS design parameters such as production rate, capacity and utilization.
  • 68.
  • 69.
  • 71.
  • 73.
  • 74.
  • 75. Automated Guided Vehicle System (AGVS) ī‚´ An Automated Guided Vehicle System (AGVS) is a computer controlled, driverless vehicle used for transporting materials from point to point in a manufacturing setting. ī‚´ An AGVS uses independently operated, self-propelled vehicles that are guided along pre-defined paths, and are powered by means of on-board batteries. ī‚´ The AGVs are highly flexible, intelligent, and versatile material handling systems used to transport materials from various loading locations to various unloading locations throughout the manufacturing facility.
  • 76. Strengths of AGVs ī‚´ Space ī‚´ Economical ī‚´ Agile ī‚´ Flexible ī‚´ Dynamic ī‚´ Redundancy
  • 77. Benefits of AGVs ī‚´ Labour ī‚´ Damage ī‚´ Shipping accuracy ī‚´ Energy ī‚´ Safety
  • 78.
  • 79. Types of AGVs ī‚´ Guided driverless trains ī‚´ Guided pallet trucks ī‚´ Guided unit load carriers
  • 80. Guided Driverless Trains ī‚´ The Guided driverless trains, also known as towing vehicles or automated guided tractors, are most commonly used for transporting large amount of bulky and heavy materials from the warehouse to various locations in the manufacturing plant.
  • 81. Guided Pallet Trucks ī‚´ The guided pallet trucks are designed to lift and transport palletized loads. ī‚´ It is used for picking up or dropping off loads from and on to floor level. Thus it eliminates the need for fixed load stands. ī‚´ There is no need for any special accessories for loading and unloading the guided pallet except that the loads should be on a pallet. ī‚´ Usually the following sequence of operations are being carried out in pallet trucks ī‚´Loads are pulled off onto a pallet forks ī‚´Lowering of the pallet forks to the floor ī‚´Pulling out from the pallet ī‚´Finally automatically returns empty to the loading area.
  • 82.
  • 83. Guided unit load carriers ī‚´ Guided unit load carries have a deck that permits unit-load transport operation. ī‚´ They are used in settings with short/medium guide paths, high volume, and need for independent and versatility. ī‚´ They are used in warehousing and distribution systems. ī‚´ They can operate in an environment where there is not much room and movement is restricted.
  • 84.
  • 85. Applications of AGVS ī‚´ Automated Guided Vehicles are used in a variety of areas to support processing and handling throughout a manufacturing facility. ī‚´Assembly ī‚´Kitting ī‚´Transportation ī‚´Staging ī‚´Warehousing ī‚´Order picking ī‚´Parts/just-in-time delivery ī‚´Transfer/shuttle
  • 86. Applications of AGVs based on types of AGVs employed ī‚´ Driverless train operations ī‚´ Storage and distribution operations ī‚´ Assembly line applications ī‚´ Flexible manufacturing systems.
  • 87. Vehicle Guidance Technology ī‚´ The goal of an AGVS guidance system is to keep the AGV on track or on predefined path. ī‚´ Types of AGV Guidance approach ī‚´Fixed-route guidance method ī‚´Free – route guidance method
  • 88. Fixed-route guidance method ī‚´ Fixed route guidance is to set medium guidance information in the path, AGV can drive with it, such as electromagnetic guidance, tape guidance, etc.
  • 89. Free – route guidance method ī‚´ Free-route guidance stores the size of the coordinates, AGV can identify current position and decide driving path, such as laser- guidance and image recognition guidance.
  • 90. Types of vehicle Guidance Technologies ī‚´ There are many AGV guidance technologies/methods available and their selection will depend on need, application, and environmental constraints. ī‚´Wire guidance system ī‚´Paint strips system ī‚´Self-guided vehicles
  • 91.
  • 92.
  • 93. Vehicle Management ī‚´ Traffic control ī‚´ Vehicle dispatching
  • 94. Traffic control ī‚´ The purpose of traffic control in an automated guided vehicle system is to minimise interference between vehicles and prevent collisions. ī‚´ Methods of traffic control ī‚´Forward-sensing control ī‚´Zone sensing control ī‚´Combinational control
  • 97. Vehicle Dispatching ī‚´ For an effective functioning of AGVS, AGVS must be dispatched in a timely manner, as and when they are needed. ī‚´ Dispatching methods: ī‚´Vehicle Dispatching using On-board control panels ī‚´Vehicle Dispatching using Remote call stations ī‚´Vehicle Dispatching using Supervisory central computer control ī‚´Combinatorial method
  • 98. Vehicle Safety ī‚´ An automated guided vehicle system should be designed taking into account the safety of human personnel in the shop floor. ī‚´ Safety features provided for AGVs: ī‚´Movement speeds of less than walking pace ī‚´Automatic stopping of the vehicle ī‚´Obstacle detection sensors on the vehicle ī‚´Emergency bumper ī‚´Additional features