SlideShare a Scribd company logo
Presented by:
Christopher Braund
Director

TSV Mining Pty Ltd
M: +61 438 886 473

cbraund@tsvmining.com.au
www.tsvmining.com.au
Total System Value
Why would there be variation outside of
planning?



Because you do not plan for events that do not often occur….
When was the last time someone actually planned for a:
1 in 10 year wet weather event
2.
poor blasted horizon
3.
geotechnical event
4.
mistake in a plan
5.
equipment not performing as planned
6.
third party supplier unable to meet requirements
7.
major breakdown
8.
geological information being incorrect
9.
excessive coal loss
10. safety incident changing site policy
11. poor ground conditions
12. etc
1.

NOTE: Current count is over 65 variables unplanned for that historically have occurred at least once a decade

Total System Value
But for one of these events to occur and
to have a large impact on a plan would
be rare


Individually, yes they are rare, but the odds of just one occurring that
will significantly impact on the plan is actually quite high:

EVENT
1 in 10 year wet weather event
poor blasted horizon
geotechnical event
mistake in a plan
equipment not performing as planned
third party supplier unable to meet requirements
major breakdown
geological information being incorrect
excessive coal loss
safety incident changing site policy
poor ground conditions
CHANCE OF ANY ONE OF THESE OCCURING

Chance of event occurring in a 1 year plan
10%
20%
20%
30%
20%
10%
10%
10%
20%
20%
10%
86.5%

NOTE: This is just for the 11 events listed here, there are many more and they eventually get the
chance of occurring to over 99% (usually takes 16 to 20)
Total System Value
The odds are not good


The chance of an event occurring that will have a major impact on
a budget or 1 year mine plan are usually in the order of 99% or
higher (long term plans are lotto tickets, but an operation does get
some direction from them)



With such a high chance of the mine failing to meet the plan, why
is it that not all mines are seen as constantly failing?



It will depend on what is seen as a failure

Total System Value
What is a failure for a mining operation?


Keeping to the operational side of the mine, a failure is usually
seen in two ways:
1.
2.

Production was not met – as in final product sales
Costs were not met



Failure is rarely viewed as no longer having the ability to follow the
mine plan



But if the mine plan can no longer be followed, shouldn’t the
production or costs no longer be met?



This depends on the layout and strategy of the operation

Total System Value
Layout and strategy


Factors that impact on how an operation can recover on production
and costs include:
 Timing on sales requirements

 Processing plant capacity and requirements
 Pit configuration
 Mine sequencing requirements
 The capacity and location of inventories
 The ability to expedite product and delay cost
 The intensity of operations (overall and in certain locations)
 Contingency in the plan
 And many more….





Even when excluding contingency, some operations can put off a
measurable failure for years
However, only the time from failure to the end of the budget needs to
be covered (less then a year) as the new budget will make up what
was used to cover the previous budget
Total System Value
Something must always be replaced
each budget


Unless there was contingency already contained in the plan that
was able to cover the failure with no loss of production or cost,
there must have been something consumed in the budgeted
period that needs to be put back in the next budget



It is usually inventories*

*There can be other options such as expenditure that can be pushed into a future
budget, most of the time it is inventories
Total System Value
Contingency and inventory






Contingency for some sites is a necessity, not a hidden cost.
Unfortunately, this risk mitigation can often be seen as an
unnecessary factor that sites put into their plans to make their life
easy (“fat” in the plan). It is perceived this way, as there is a lack of
explanation or science behind why it is required. It was typically
added due to individual tacit knowledge that there was a need for it.
As this knowledge disappears, so does the contingency.
As the contingency disappears, the inventory plays a larger part in
the operation to recover from unplanned events and prevent the plan
from failing (ahhh inventory, the visa card we don’t want to pay off,
particularly in a downturn).
The less contingency is used, and avoiding replacing used inventory
regularly creates a building requirement of inventory needing to be
replaced

Total System Value
Replacing used inventory





If the inventory is allowed to constantly deplete, and assuming that
there has been no significant reduction in variation (to reduce
variation not planned for significantly would not be economically
viable), costs per production unit will eventually escalate
dramatically as throughput collapses
Trying to put back inventory once throughput has started to be
impacted significantly can be very difficult
Steady, consistent return of inventories in each budget is important
to keep production sustainable in an operation, particularly for
operations working in a high intensity environment

Total System Value
Replacing inventory and maximum
production






When planning the production out of a highly profitable operation or
an area of an operation, they are the most likely to be pushed to the
production limit – the pit operations will be at the higher end of
intensity
At the higher end of intensity returning used inventory can be
difficult. It becomes even more difficult when the inventory is not
consistently returned
Maximum production out of an area or an operation is only
sustainable when it still has capacity to replace used inventory at
the rate it typically gets consumed

Total System Value
Where things can go wrong






Some operations do not (and it is not viable to) contain the right
inventories in the right locations to cater for variation not planned
for, they will always need to use a contingency
Most operations only track certain key inventories, which many not
be the only inventories that get consumed to recover a plan
Inventories that are not tracked, may be depleting without the
operation knowing
Any consistently depleting inventory is a lead indicator that current
resource allocation and production levels are unsustainable

Total System Value
Summary







Operations will not be able to follow the plan for a year, and it
will be due to a negative impact
All operations are different, and the ability to delay failure will
change site to site
The less contingency in the plan, the more inventory will be
consumed within the budgeted period
In order to be sustainable, inventory needs to be replaced
consistently
High intensity plans need to include the ability to replace used
inventory

Total System Value
Always customised – no two sites are
the same

Thank you

Total System Value

More Related Content

Viewers also liked

The Future of Technology in 2023 A.D.
The Future of Technology in 2023 A.D.The Future of Technology in 2023 A.D.
The Future of Technology in 2023 A.D.
emlabarb
 
Swimming pool equipments
Swimming pool equipmentsSwimming pool equipments
Swimming pool equipments
aqua-me
 
Escuelas y precursores
Escuelas y precursoresEscuelas y precursores
Escuelas y precursoresabelunid
 
TSV Mining: Overburden fleet analysis, overstating benefits and statistical i...
TSV Mining: Overburden fleet analysis, overstating benefits and statistical i...TSV Mining: Overburden fleet analysis, overstating benefits and statistical i...
TSV Mining: Overburden fleet analysis, overstating benefits and statistical i...
Totius Mining
 
Grupo m.01 andreu,bori,sedes el ray
Grupo m.01 andreu,bori,sedes el rayGrupo m.01 andreu,bori,sedes el ray
Grupo m.01 andreu,bori,sedes el raysole_andrew
 
Marketing and social media campaigns. (Old Spice)
Marketing and social media campaigns. (Old Spice)Marketing and social media campaigns. (Old Spice)
Marketing and social media campaigns. (Old Spice)
Utsav Ojha
 
TSV Mining: Critical density in mining and changes to sustainable low cost pr...
TSV Mining: Critical density in mining and changes to sustainable low cost pr...TSV Mining: Critical density in mining and changes to sustainable low cost pr...
TSV Mining: Critical density in mining and changes to sustainable low cost pr...
Totius Mining
 
Green technology
Green technologyGreen technology
Green technology
AMIT KUMAR
 
Industrial visit to samsonite, Nashik
Industrial visit to samsonite, NashikIndustrial visit to samsonite, Nashik
Industrial visit to samsonite, NashikAMIT KUMAR
 
Handwritten character recognition using artificial neural network
Handwritten character recognition using artificial neural networkHandwritten character recognition using artificial neural network
Handwritten character recognition using artificial neural network
Harshana Madusanka Jayamaha
 
Momotarou
MomotarouMomotarou
Momotarouydnvn
 
SIRIUSの教科書サンプル
SIRIUSの教科書サンプルSIRIUSの教科書サンプル
SIRIUSの教科書サンプル
ydnvn
 

Viewers also liked (13)

The Future of Technology in 2023 A.D.
The Future of Technology in 2023 A.D.The Future of Technology in 2023 A.D.
The Future of Technology in 2023 A.D.
 
Swimming pool equipments
Swimming pool equipmentsSwimming pool equipments
Swimming pool equipments
 
Escuelas y precursores
Escuelas y precursoresEscuelas y precursores
Escuelas y precursores
 
TSV Mining: Overburden fleet analysis, overstating benefits and statistical i...
TSV Mining: Overburden fleet analysis, overstating benefits and statistical i...TSV Mining: Overburden fleet analysis, overstating benefits and statistical i...
TSV Mining: Overburden fleet analysis, overstating benefits and statistical i...
 
Grupo m.01 andreu,bori,sedes el ray
Grupo m.01 andreu,bori,sedes el rayGrupo m.01 andreu,bori,sedes el ray
Grupo m.01 andreu,bori,sedes el ray
 
Marketing and social media campaigns. (Old Spice)
Marketing and social media campaigns. (Old Spice)Marketing and social media campaigns. (Old Spice)
Marketing and social media campaigns. (Old Spice)
 
TSV Mining: Critical density in mining and changes to sustainable low cost pr...
TSV Mining: Critical density in mining and changes to sustainable low cost pr...TSV Mining: Critical density in mining and changes to sustainable low cost pr...
TSV Mining: Critical density in mining and changes to sustainable low cost pr...
 
Green technology
Green technologyGreen technology
Green technology
 
Industrial visit to samsonite, Nashik
Industrial visit to samsonite, NashikIndustrial visit to samsonite, Nashik
Industrial visit to samsonite, Nashik
 
Whirlpool
WhirlpoolWhirlpool
Whirlpool
 
Handwritten character recognition using artificial neural network
Handwritten character recognition using artificial neural networkHandwritten character recognition using artificial neural network
Handwritten character recognition using artificial neural network
 
Momotarou
MomotarouMomotarou
Momotarou
 
SIRIUSの教科書サンプル
SIRIUSの教科書サンプルSIRIUSの教科書サンプル
SIRIUSの教科書サンプル
 

Similar to TSV Mining: Variation outside of planning, contingency, inventory and intensity

Impact of Planning Decision Support Tools on Mining Operations Profitability
Impact of Planning Decision Support Tools on Mining Operations ProfitabilityImpact of Planning Decision Support Tools on Mining Operations Profitability
Impact of Planning Decision Support Tools on Mining Operations Profitability
Schneider Electric
 
LESS CRISIS, MORE PROJECTS: TRENDS IN SHUTDOWN & TURNAROUND MANAGEMENT
LESS CRISIS, MORE PROJECTS: TRENDS IN SHUTDOWN & TURNAROUND MANAGEMENTLESS CRISIS, MORE PROJECTS: TRENDS IN SHUTDOWN & TURNAROUND MANAGEMENT
LESS CRISIS, MORE PROJECTS: TRENDS IN SHUTDOWN & TURNAROUND MANAGEMENTMateus Siwek
 
OR&A - Bridging the gap
OR&A - Bridging the gapOR&A - Bridging the gap
OR&A - Bridging the gap
uak10
 
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
Naveen Kumar
 
JR Dickens - IWCS 2007
JR Dickens - IWCS 2007JR Dickens - IWCS 2007
JR Dickens - IWCS 2007
jrd9234
 
industrial microbial culture (1).pdf
industrial microbial culture (1).pdfindustrial microbial culture (1).pdf
industrial microbial culture (1).pdf
RupajitBhattacharjee1
 
Predictive maintenance
Predictive maintenancePredictive maintenance
Predictive maintenance
Advisian
 
How to switch from reactive maintenance to preventive maintenance complete ...
How to switch from reactive maintenance to preventive maintenance   complete ...How to switch from reactive maintenance to preventive maintenance   complete ...
How to switch from reactive maintenance to preventive maintenance complete ...
BryanLimble
 
Newparadigmdigitaloilfield
NewparadigmdigitaloilfieldNewparadigmdigitaloilfield
Newparadigmdigitaloilfield
Nick Warren CEng FIChemE FCMI
 
Tracker Lifetime Cost: MTBF, Lifetime and Other Events
Tracker Lifetime Cost: MTBF, Lifetime and Other EventsTracker Lifetime Cost: MTBF, Lifetime and Other Events
Tracker Lifetime Cost: MTBF, Lifetime and Other Events
Array Technologies, Inc.
 
Perspectiveson Asset Management
Perspectiveson Asset ManagementPerspectiveson Asset Management
Perspectiveson Asset ManagementSteve Turner
 
Proper Asset Maintenance Improves Safety, Reliability, and Profitability
Proper Asset Maintenance Improves Safety, Reliability, and ProfitabilityProper Asset Maintenance Improves Safety, Reliability, and Profitability
Proper Asset Maintenance Improves Safety, Reliability, and Profitability
USC Consulting Group
 
Ageing of Industrial Plant (BPPT_Jakarta_06-08-2003)
Ageing of Industrial Plant (BPPT_Jakarta_06-08-2003)Ageing of Industrial Plant (BPPT_Jakarta_06-08-2003)
Ageing of Industrial Plant (BPPT_Jakarta_06-08-2003)Jonathan Lloyd
 
Sales & Operations Planning
Sales & Operations PlanningSales & Operations Planning
Sales & Operations Planning
mubarak2009
 
Aggregate Planning, Guide numericals
Aggregate Planning, Guide numericalsAggregate Planning, Guide numericals
Aggregate Planning, Guide numericals
Osama Yousaf
 
Evolution of maintenance_practices
Evolution of maintenance_practicesEvolution of maintenance_practices
Evolution of maintenance_practices
Danny Khudu
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
PMA Consultants
 
HALT value FMS Reliability
HALT value FMS ReliabilityHALT value FMS Reliability
HALT value FMS Reliability
Accendo Reliability
 
Operations managementppt
Operations managementpptOperations managementppt
Operations managementppt
MaChere Reyes
 

Similar to TSV Mining: Variation outside of planning, contingency, inventory and intensity (20)

Impact of Planning Decision Support Tools on Mining Operations Profitability
Impact of Planning Decision Support Tools on Mining Operations ProfitabilityImpact of Planning Decision Support Tools on Mining Operations Profitability
Impact of Planning Decision Support Tools on Mining Operations Profitability
 
LESS CRISIS, MORE PROJECTS: TRENDS IN SHUTDOWN & TURNAROUND MANAGEMENT
LESS CRISIS, MORE PROJECTS: TRENDS IN SHUTDOWN & TURNAROUND MANAGEMENTLESS CRISIS, MORE PROJECTS: TRENDS IN SHUTDOWN & TURNAROUND MANAGEMENT
LESS CRISIS, MORE PROJECTS: TRENDS IN SHUTDOWN & TURNAROUND MANAGEMENT
 
OR&A - Bridging the gap
OR&A - Bridging the gapOR&A - Bridging the gap
OR&A - Bridging the gap
 
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
 
JR Dickens - IWCS 2007
JR Dickens - IWCS 2007JR Dickens - IWCS 2007
JR Dickens - IWCS 2007
 
industrial microbial culture (1).pdf
industrial microbial culture (1).pdfindustrial microbial culture (1).pdf
industrial microbial culture (1).pdf
 
Predictive maintenance
Predictive maintenancePredictive maintenance
Predictive maintenance
 
How to switch from reactive maintenance to preventive maintenance complete ...
How to switch from reactive maintenance to preventive maintenance   complete ...How to switch from reactive maintenance to preventive maintenance   complete ...
How to switch from reactive maintenance to preventive maintenance complete ...
 
Newparadigmdigitaloilfield
NewparadigmdigitaloilfieldNewparadigmdigitaloilfield
Newparadigmdigitaloilfield
 
Tracker Lifetime Cost: MTBF, Lifetime and Other Events
Tracker Lifetime Cost: MTBF, Lifetime and Other EventsTracker Lifetime Cost: MTBF, Lifetime and Other Events
Tracker Lifetime Cost: MTBF, Lifetime and Other Events
 
Perspectiveson Asset Management
Perspectiveson Asset ManagementPerspectiveson Asset Management
Perspectiveson Asset Management
 
Proper Asset Maintenance Improves Safety, Reliability, and Profitability
Proper Asset Maintenance Improves Safety, Reliability, and ProfitabilityProper Asset Maintenance Improves Safety, Reliability, and Profitability
Proper Asset Maintenance Improves Safety, Reliability, and Profitability
 
Om 5
Om 5Om 5
Om 5
 
Ageing of Industrial Plant (BPPT_Jakarta_06-08-2003)
Ageing of Industrial Plant (BPPT_Jakarta_06-08-2003)Ageing of Industrial Plant (BPPT_Jakarta_06-08-2003)
Ageing of Industrial Plant (BPPT_Jakarta_06-08-2003)
 
Sales & Operations Planning
Sales & Operations PlanningSales & Operations Planning
Sales & Operations Planning
 
Aggregate Planning, Guide numericals
Aggregate Planning, Guide numericalsAggregate Planning, Guide numericals
Aggregate Planning, Guide numericals
 
Evolution of maintenance_practices
Evolution of maintenance_practicesEvolution of maintenance_practices
Evolution of maintenance_practices
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
HALT value FMS Reliability
HALT value FMS ReliabilityHALT value FMS Reliability
HALT value FMS Reliability
 
Operations managementppt
Operations managementpptOperations managementppt
Operations managementppt
 

Recently uploaded

The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 

Recently uploaded (20)

The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 

TSV Mining: Variation outside of planning, contingency, inventory and intensity

  • 1. Presented by: Christopher Braund Director TSV Mining Pty Ltd M: +61 438 886 473 cbraund@tsvmining.com.au www.tsvmining.com.au Total System Value
  • 2. Why would there be variation outside of planning?   Because you do not plan for events that do not often occur…. When was the last time someone actually planned for a: 1 in 10 year wet weather event 2. poor blasted horizon 3. geotechnical event 4. mistake in a plan 5. equipment not performing as planned 6. third party supplier unable to meet requirements 7. major breakdown 8. geological information being incorrect 9. excessive coal loss 10. safety incident changing site policy 11. poor ground conditions 12. etc 1. NOTE: Current count is over 65 variables unplanned for that historically have occurred at least once a decade Total System Value
  • 3. But for one of these events to occur and to have a large impact on a plan would be rare  Individually, yes they are rare, but the odds of just one occurring that will significantly impact on the plan is actually quite high: EVENT 1 in 10 year wet weather event poor blasted horizon geotechnical event mistake in a plan equipment not performing as planned third party supplier unable to meet requirements major breakdown geological information being incorrect excessive coal loss safety incident changing site policy poor ground conditions CHANCE OF ANY ONE OF THESE OCCURING Chance of event occurring in a 1 year plan 10% 20% 20% 30% 20% 10% 10% 10% 20% 20% 10% 86.5% NOTE: This is just for the 11 events listed here, there are many more and they eventually get the chance of occurring to over 99% (usually takes 16 to 20) Total System Value
  • 4. The odds are not good  The chance of an event occurring that will have a major impact on a budget or 1 year mine plan are usually in the order of 99% or higher (long term plans are lotto tickets, but an operation does get some direction from them)  With such a high chance of the mine failing to meet the plan, why is it that not all mines are seen as constantly failing?  It will depend on what is seen as a failure Total System Value
  • 5. What is a failure for a mining operation?  Keeping to the operational side of the mine, a failure is usually seen in two ways: 1. 2. Production was not met – as in final product sales Costs were not met  Failure is rarely viewed as no longer having the ability to follow the mine plan  But if the mine plan can no longer be followed, shouldn’t the production or costs no longer be met?  This depends on the layout and strategy of the operation Total System Value
  • 6. Layout and strategy  Factors that impact on how an operation can recover on production and costs include:  Timing on sales requirements  Processing plant capacity and requirements  Pit configuration  Mine sequencing requirements  The capacity and location of inventories  The ability to expedite product and delay cost  The intensity of operations (overall and in certain locations)  Contingency in the plan  And many more….   Even when excluding contingency, some operations can put off a measurable failure for years However, only the time from failure to the end of the budget needs to be covered (less then a year) as the new budget will make up what was used to cover the previous budget Total System Value
  • 7. Something must always be replaced each budget  Unless there was contingency already contained in the plan that was able to cover the failure with no loss of production or cost, there must have been something consumed in the budgeted period that needs to be put back in the next budget  It is usually inventories* *There can be other options such as expenditure that can be pushed into a future budget, most of the time it is inventories Total System Value
  • 8. Contingency and inventory    Contingency for some sites is a necessity, not a hidden cost. Unfortunately, this risk mitigation can often be seen as an unnecessary factor that sites put into their plans to make their life easy (“fat” in the plan). It is perceived this way, as there is a lack of explanation or science behind why it is required. It was typically added due to individual tacit knowledge that there was a need for it. As this knowledge disappears, so does the contingency. As the contingency disappears, the inventory plays a larger part in the operation to recover from unplanned events and prevent the plan from failing (ahhh inventory, the visa card we don’t want to pay off, particularly in a downturn). The less contingency is used, and avoiding replacing used inventory regularly creates a building requirement of inventory needing to be replaced Total System Value
  • 9. Replacing used inventory    If the inventory is allowed to constantly deplete, and assuming that there has been no significant reduction in variation (to reduce variation not planned for significantly would not be economically viable), costs per production unit will eventually escalate dramatically as throughput collapses Trying to put back inventory once throughput has started to be impacted significantly can be very difficult Steady, consistent return of inventories in each budget is important to keep production sustainable in an operation, particularly for operations working in a high intensity environment Total System Value
  • 10. Replacing inventory and maximum production    When planning the production out of a highly profitable operation or an area of an operation, they are the most likely to be pushed to the production limit – the pit operations will be at the higher end of intensity At the higher end of intensity returning used inventory can be difficult. It becomes even more difficult when the inventory is not consistently returned Maximum production out of an area or an operation is only sustainable when it still has capacity to replace used inventory at the rate it typically gets consumed Total System Value
  • 11. Where things can go wrong     Some operations do not (and it is not viable to) contain the right inventories in the right locations to cater for variation not planned for, they will always need to use a contingency Most operations only track certain key inventories, which many not be the only inventories that get consumed to recover a plan Inventories that are not tracked, may be depleting without the operation knowing Any consistently depleting inventory is a lead indicator that current resource allocation and production levels are unsustainable Total System Value
  • 12. Summary      Operations will not be able to follow the plan for a year, and it will be due to a negative impact All operations are different, and the ability to delay failure will change site to site The less contingency in the plan, the more inventory will be consumed within the budgeted period In order to be sustainable, inventory needs to be replaced consistently High intensity plans need to include the ability to replace used inventory Total System Value
  • 13. Always customised – no two sites are the same Thank you Total System Value