1. Time & Activity Schedule
Sr. Name of Division Date Duration Mentor
No. (days)
1. Spinning 28/12/10-30/12/10 3 Mr. A.K.Jain
2. Weaving 31/12/10-01/01/11 2 Mr. D.B. Muley
3. Processing 03/01/11-05/01/11 3 Mr. A. Zaroo
4. Design Development 06/01/11-07/01/11 2 Mr. Maheshwari
& Marketing
5. Project Preparation 08/01/11 1 Mr. K. M.
& Report Kogata
Submission