7. Specific regulatory lessons learnt
Taqa field P18-4 – draft permit
+ experienced authorities
+ room for direct contact
+ clear competences - responsibilities
+ balance: rules & compliance
+ "future proof": work with updates
8. Specific regulatory lessons learnt
Taqa field P18-4 – draft permit
Issues:
• length of procedure (change in legislation)
• timing:
• need to know everything upfront: evolving
knowledge
• operational status of plans: evolving
• post closure – transfer: uncertainty
• financial security – content
• ETS rights (3 months uncontrolled leakage)
• measures for wells in adjacent reservoir (P15-9)
9. Specific regulatory lessons learnt
Taqa field P18-4 – draft permit
Commission Advisory Opinion
• 6 months (documents, meetings)
• enabled corrections to draft permit for public consultation
round
• positive opinion: suitability storage location, delimitation
storage site, requirements for storage, CO2 stream, financial
security
• general comment on present operational status of plans, Cion
to be contacted on updates