SlideShare a Scribd company logo
Drainage Assessment of Tete Bayou




                                       Experience · Innovation · Results


       PRESENTED TO




IBERIA PARISH    CITY OF
GOVERNMENT      NEW IBERIA


                                     Engineers ∙ Surveyors · Environmental Consultants
Organizational Chart
                      Dr. Ehab Meselhe,
                             P.E.
                       Senior Hydraulic
                          Engineering
                          Consultant


                                                                        Raymond Reaux, P.E.
                                                                     Vice President – Engineering



Jeanne Arceneaux                               Robert Miller
     M.S., E.I.                                   MS, P.E.
Hydraulics Engineer                          Hydraulics Engineer

                        Dax Douet, P.E.
                       Engineering Project
                            Manager
                            Director

                         Justin Shaw
                           M.S., E.I.                                       Ivan Diaz, P.E.
                                                                   Drainage Engineer for City of New
                      Hydraulics Engineer                                       Iberia
                                                                              (33 Years)
General Scope of Work
• INVESTIGATE HISTORICAL FLOODING IN UPPER
  PORTION OF TETE BAYOU
• EXAMINE REPETIVE LOSSES DUE TO OVERBANK
  FLOODING
• DEVELOP POSSIBLE DRAINAGE IMPROVEMENT
  SCENARIOS
• PERFORM FIELD SURVEYING
• ANALYZE IMPROVEMENT SCENARIOS THROUGH
  HYDROLOGIC AND HYDRAULIC MODELS
• PRESENT QUANTITATIVE SOLUTIONS ALONG
  WITH REPORT
Study Area




             4/XX
Project Objectives
• Develop Numerical Models to Study Tete Bayou and Pharr Canal
• Examine Four Proposed Drainage Improvement Scenarios:
    Scenario No. 1: Cleaning of Tete Bayou and the Pharr Canal;
    Scenario No. 2: Scenario No. 1 + widening of the Pharr Canal intake, and removing
                    existing spoil banks along Tete Bayou;
    Scenario No. 3: Scenario No. 2 + diverting flow from Tete Bayou to Bayou Teche
                    through a sub-surface box culvert system; and
    Scenario No. 4: Scenario No. 1 + widening of Pharr Canal.
Analysis Timeline
• Contract Execution Date: January 19, 2011

• Field Survey Collection Start Date: February 8, 2011

• Numerical Model Development Start: February 21, 2011

• Agency Meeting with City and Parish Date: April 5, 2011

• Draft Report to City and Parish Date: July 22, 2011
Data Collected
• Survey Date Collected By C.H.
  Fenstermaker & Associates, Inc.
• 1,589 Survey Points Collected
• Historical Hydrologic Data
• Land Use/Land Cover Maps
• Soil Type Maps
• LiDAR Data
• FEMA Flood Zones
FEMA Calibration
                                                                                    Existing 100-year Storm Event
                 15




                 10   CALIBRATION
                        CHECKS
                                                    Emile Verret Rd


                                                                      Mullins Rd




                                                                                            Belle Place Olivier Rd
                 5
Elevation (ft)




                                                                                                                     Crochet Rd

                 0




                            100-year Rainfall Event
                           1% Chance that a 12.6 inch
                 -5        Rainfall over 24 hours will
                             Occur in a Given Year
                              Existing 100-yr WSE
                              Ground
                              FEMA BFE
           -10
                  60,000                     50,000                                40,000                                    30,000               20,000   10,000   0
                                                                                                                     Main Channel Distance (ft)
December 2006 Storm Event Calibration



           Tete Bayou at Belle Place Olivier Rd Facing South   Tete Bayou near Candleglow Dr Facing East




               Tete Bayou at Emile Verret Rd Facing East       Tete Bayou at Emile Verret Rd Facing West



 Estimated Rainfall Event
  5.02” Rainfall (24 hours)
Approx. 3-yr., 24-hour Storm
December 2006 Storm Event Calibration
                                                                                December 2006 Storm Event
                 15




                 10
                                               Emile Verret Rd


                                                                 Mullins Rd




                                                                                       Belle Place Olivier Rd
                 5
Elevation (ft)




                                                                                                                Crochet Rd

                 0




                                                                                                                               Tete Bayou at Belle Place Olivier Rd Facing South
                 -5


                           December 2006 WSE
                           Ground
                           December 2006 High Water Mark
           -10
                  60,000                50,000                                40,000                                    30,000                           20,000                    10,000   0
                                                                                                                Main Channel Distance (ft)
Scenario No. 1




                 Definition:
                 Channel Cleaning of Tete
                 Bayou and the Pharr Canal



                                  11/XX
Scenario No. 1 – Water Surface Elevation Comparison
                                                                                    Existing - Scenario 1 Comparison
                 15

                                                                                      0.6’ Reduction in
                                                                                      Water Surface Elevation

                 10
                                                     Emile Verret Rd


                                                                       Mullins Rd




                                                                                             Belle Place Olivier Rd
                 5
Elevation (ft)




                                                                                                                      Crochet Rd

                 0



                            10-year Rainfall Event
                           10% Chance that a 7.8 inch
                           Rainfall over 24 hours will
                 -5
                             Occur in a Given Year
                              10-yr Existing WSE
                              10-yr Scenario 1 WSE
                              Ground
           -10                                                                                                                                                       12/XX
                  60,000                     50,000                                 40,000                                    30,000               20,000   10,000           0
                                                                                                                      Main Channel Distance (ft)
Scenario No. 1 – Inundation Comparison




                                         13/XX
Scenario No. 1 – Results

               Scenario No. 1 Inundation Area Comparison
 Existing Conditions     Scenario No. 1     Scenario No. 1   Scenario No. 1      Scenario No. 1
10-yr Inundation Area   10-yr Inundation   10-yr Reduction   10-yr Increase   10-yr Total Reduction
        (acres)           Area (acres)       Area (acres)     Area (acres)    Area Reduction (acres)

       6,390                6,366               220               197                  24




                  Scenario No. 1 Flood Duration Comparison
                                            Water Surface Elevation > 7’ NAVD 88
                         Bridge
                                                Existing           Scenario No. 1
               Emile Verret Rd                   24 hrs             15 hrs (37%)
               Belle Place Olivier Rd            18 hrs             12 hrs (33%)
Scenario No. 2




                 Definition:
                 Channel Cleaning, Widening of the
                 Pharr Canal, and Removing Existing
                 Spoil Banks Along Tete Bayou



                                       15/XX
Scenario No. 2 – Water Surface Elevation Comparison
                                                                                  Existing - Scenario 2 Comparison
                 15

                                                                                      0.6’ Reduction in
                                                                                      Water Surface Elevation

                 10
                                                   Emile Verret Rd


                                                                     Mullins Rd




                                                                                           Belle Place Olivier Rd
                 5
Elevation (ft)




                                                                                                                    Crochet Rd

                 0




                 -5


                            10-yr Existing WSE
                            10-yr Scenario 2 WSE
                            Ground
           -10                                                                                                                                                     16/XX
                  60,000                   50,000                                 40,000                                    30,000               20,000   10,000           0
                                                                                                                    Main Channel Distance (ft)
Scenario No.2 – Inundation Comparison




                                        17/XX
Scenario No. 2 – Results

               Scenario No. 2 Inundation Area Comparison
 Existing Conditions     Scenario No. 2     Scenario No. 2   Scenario No. 2      Scenario No. 2
10-yr Inundation Area   10-yr Inundation   10-yr Reduction   10-yr Increase   10-yr Total Reduction
        (acres)           Area (acres)       Area (acres)     Area (acres)    Area Reduction (acres)

       6,390                6,209               289               108                 181




                  Scenario No. 2 Flood Duration Comparison
                                            Water Surface Elevation > 7’ NAVD 88
                         Bridge
                                                Existing           Scenario No. 2
               Emile Verret Rd                   24 hrs             14 hrs (42%)
               Belle Place Olivier Rd            18 hrs             12 hrs (33%)
Scenario No. 3




Definition:
Channel Cleaning, Widening of the
Pharr Canal, Removing Spoil
Banks, and Diverting Flow From
Tete Bayou to Bayou Teche Through
a Sub-surface Box Culvert System



                                                     19/XX
Scenario No. 3 – Water Surface Elevation Comparison
                                                                                            Existing - Scenario 3 Comparison
                 15

                                                                                              1.7’ Reduction in
                                                 Emile Verret Rd                              Water Surface Elevation

                 10
                                                                               Mullins Rd




                                                                                                     Belle Place Olivier Rd
                 5
Elevation (ft)




                                                                                                                              Crochet Rd
                                                                   Diversion




                 0




                 -5


                            10-yr Existing WSE
                            10-yr Scenario 3 WSE
                            Ground
           -10                                                                                                                                                               20/XX
                  60,000                   50,000                                           40,000                                    30,000               20,000   10,000           0
                                                                                                                              Main Channel Distance (ft)
Scenario No. 3 – Inundation Comparison




                                         21/XX
Scenario No. 3 – Results

               Scenario No. 3 Inundation Area Comparison
 Existing Conditions     Scenario No. 3     Scenario No. 3   Scenario No. 3      Scenario No. 3
10-yr Inundation Area   10-yr Inundation   10-yr Reduction   10-yr Increase   10-yr Total Reduction
        (acres)           Area (acres)       Area (acres)     Area (acres)    Area Reduction (acres)

       6,390                5,835               619               64                  555




                 Scenario No. 3 Flood Duration Comparison
                                            Water Surface Elevation > 7’ NAVD 88
                         Bridge
                                               Existing           Scenario No. 3
               Emile Verret Rd                   24 hrs             5 hrs (79%)
               Belle Place Olivier Rd            18 hrs            10 hrs (44%)
Scenario No. 4




Definition:
Channel Cleaning and Pharr Canal
Diversion



                                                    23/XX
Scenario No. 4 – Water Surface Elevation Comparison
                                                                                  Existing - Scenario 4 Comparison
                 15



                                                                                                          1.5’ Reduction in
                                                                                                          Water Surface Elevation
                 10
                                                   Emile Verret Rd




                                                                                  Diversion


                                                                                              Belle Place Olivier Rd
                                                                     Mullins Rd




                 5
Elevation (ft)




                                                                                                                       Crochet Rd

                 0




                 -5


                            10-yr Existing WSE
                            10-yr Scenario 4 WSE
                            Ground
           -10                                                                                                                                                        24/XX
                  60,000                   50,000                                   40,000                                     30,000               20,000   10,000           0
                                                                                                                       Main Channel Distance (ft)
Scenario No. 4 – Inundation Comparison




                                         25/XX
Scenario No. 4 – Results

               Scenario No. 4 Inundation Area Comparison
 Existing Conditions     Scenario No. 4     Scenario No. 4    Scenario No. 4       Scenario No. 4
10-yr Inundation Area   10-yr Inundation   10-yr Reduction    10-yr Increase    10-yr Total Reduction
        (acres)           Area (acres)       Area (acres)      Area (acres)     Area Reduction (acres)

       6,390                5,977               463                  50                 414




                Scenario No. 4 Flood Duration Comparison
                                             Water Surface Elevation >   7’ NAVD 88
                        Bridge
                                              Existing            Scenario No. 4
               Emile Verret Rd                 24 hrs               9 hrs (62%)
               Belle Place Olivier Rd          18 hrs              10 hrs (44%)
Scenario Comparisons and Costs


         Flood Duration Flood Duration                                      Inundation            Inundation     Total
          Reduction at   Reduction at                                       Reduction              Increase    Planning
Scenario
          Emile Verret Belle Place Olivier                                     Area                  Area
              (hrs)           (hrs)                                           (acres)               (acres)     Cost*
 No. 1          9               6                                               220                   197      $1,177,000
 No. 2         10               6                                               289                   108      $1,964,000
 No. 3         19               8                                               619                    64      $6,416,000
 No. 4         15               8                                               463                    50      $2,641,000
 * It should be noted that these figures represent approximated cost only to be used for planning purposes.
Additional Analysis – Dredge Tete Bayou Mouth
                                                                                              Dredging Tete Bayou
                 15
                                                                                                                                                            Definition:
                                                                                                                                                            Dredging of Tete Bayou into Lake
                                                                                                                                                            Fausse Pointe

                 10
                                                  Emile Verret Rd


                                                                    Mullins Rd




                                                                                          Belle Place Olivier Rd
                 5
Elevation (ft)




                                                                                                                   Crochet Rd
                                                                                                                                           Negligible Water Surface
                 0
                                                                                                                                           Elevation Change




                 -5
                           10-yr Existing WSE
                           Existing Ground
                           Dredged 10-yr WSE
                           Dredged Ground
           -10
                  60,000                     50,000                              40,000                                    30,000                  20,000                10,000                0
                                                                                                                   Main Channel Distance (ft)
Drainage Assessment of Tete Bayou




                                              Experience · Innovation · Results




Visit Our Website at www.fenstermaker.com




                                            Engineers ∙ Surveyors · Environmental Consultants

More Related Content

What's hot

GIS User for Countywide Groundwater Assessment, Jefferson County, WV
GIS User for Countywide Groundwater Assessment, Jefferson County, WVGIS User for Countywide Groundwater Assessment, Jefferson County, WV
GIS User for Countywide Groundwater Assessment, Jefferson County, WV
WV Assocation of Geospatial Professionals
 
Ash Creek Ecological Master Plan - Phase I
Ash Creek Ecological Master Plan - Phase IAsh Creek Ecological Master Plan - Phase I
Ash Creek Ecological Master Plan - Phase I
Ash Creek Conservation Assoc
 
Salmons lbe planning panel 9 jul12 final (1)
Salmons lbe planning panel 9 jul12 final (1)Salmons lbe planning panel 9 jul12 final (1)
Salmons lbe planning panel 9 jul12 final (1)
helenos
 
Integrated modeling of RMS impacts: Hydrological processes, and water resourc...
Integrated modeling of RMS impacts: Hydrological processes, and water resourc...Integrated modeling of RMS impacts: Hydrological processes, and water resourc...
Integrated modeling of RMS impacts: Hydrological processes, and water resourc...
International Water Management Institute (IWMI)
 
Esl 2005 04_tuba
Esl 2005 04_tubaEsl 2005 04_tuba
Esl 2005 04_tuba
Usama Waly
 
Diagram
DiagramDiagram
Diagram
Rae Anggraeni
 
UW GIGSS Presentation 2011.02.23
UW GIGSS Presentation 2011.02.23UW GIGSS Presentation 2011.02.23
UW GIGSS Presentation 2011.02.23
bhaladog
 
Tracy - Urban Subwatershed Stormwater Retrofit Analysis
Tracy - Urban Subwatershed Stormwater Retrofit AnalysisTracy - Urban Subwatershed Stormwater Retrofit Analysis
Tracy - Urban Subwatershed Stormwater Retrofit Analysis
Environmental Initiative
 
Ss 5 design_trust
Ss 5 design_trustSs 5 design_trust
Ss 5 design_trust
Elisabetta Di Stefano
 
resume
resumeresume
Reconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
Reconstructing Water Levels in the Lake Michigan Basin from Embayed LakesReconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
Reconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
SERC at Carleton College
 

What's hot (11)

GIS User for Countywide Groundwater Assessment, Jefferson County, WV
GIS User for Countywide Groundwater Assessment, Jefferson County, WVGIS User for Countywide Groundwater Assessment, Jefferson County, WV
GIS User for Countywide Groundwater Assessment, Jefferson County, WV
 
Ash Creek Ecological Master Plan - Phase I
Ash Creek Ecological Master Plan - Phase IAsh Creek Ecological Master Plan - Phase I
Ash Creek Ecological Master Plan - Phase I
 
Salmons lbe planning panel 9 jul12 final (1)
Salmons lbe planning panel 9 jul12 final (1)Salmons lbe planning panel 9 jul12 final (1)
Salmons lbe planning panel 9 jul12 final (1)
 
Integrated modeling of RMS impacts: Hydrological processes, and water resourc...
Integrated modeling of RMS impacts: Hydrological processes, and water resourc...Integrated modeling of RMS impacts: Hydrological processes, and water resourc...
Integrated modeling of RMS impacts: Hydrological processes, and water resourc...
 
Esl 2005 04_tuba
Esl 2005 04_tubaEsl 2005 04_tuba
Esl 2005 04_tuba
 
Diagram
DiagramDiagram
Diagram
 
UW GIGSS Presentation 2011.02.23
UW GIGSS Presentation 2011.02.23UW GIGSS Presentation 2011.02.23
UW GIGSS Presentation 2011.02.23
 
Tracy - Urban Subwatershed Stormwater Retrofit Analysis
Tracy - Urban Subwatershed Stormwater Retrofit AnalysisTracy - Urban Subwatershed Stormwater Retrofit Analysis
Tracy - Urban Subwatershed Stormwater Retrofit Analysis
 
Ss 5 design_trust
Ss 5 design_trustSs 5 design_trust
Ss 5 design_trust
 
resume
resumeresume
resume
 
Reconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
Reconstructing Water Levels in the Lake Michigan Basin from Embayed LakesReconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
Reconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
 

Tete Bayou Presentation Ehab Edits

  • 1. Drainage Assessment of Tete Bayou Experience · Innovation · Results PRESENTED TO IBERIA PARISH CITY OF GOVERNMENT NEW IBERIA Engineers ∙ Surveyors · Environmental Consultants
  • 2. Organizational Chart Dr. Ehab Meselhe, P.E. Senior Hydraulic Engineering Consultant Raymond Reaux, P.E. Vice President – Engineering Jeanne Arceneaux Robert Miller M.S., E.I. MS, P.E. Hydraulics Engineer Hydraulics Engineer Dax Douet, P.E. Engineering Project Manager Director Justin Shaw M.S., E.I. Ivan Diaz, P.E. Drainage Engineer for City of New Hydraulics Engineer Iberia (33 Years)
  • 3. General Scope of Work • INVESTIGATE HISTORICAL FLOODING IN UPPER PORTION OF TETE BAYOU • EXAMINE REPETIVE LOSSES DUE TO OVERBANK FLOODING • DEVELOP POSSIBLE DRAINAGE IMPROVEMENT SCENARIOS • PERFORM FIELD SURVEYING • ANALYZE IMPROVEMENT SCENARIOS THROUGH HYDROLOGIC AND HYDRAULIC MODELS • PRESENT QUANTITATIVE SOLUTIONS ALONG WITH REPORT
  • 4. Study Area 4/XX
  • 5. Project Objectives • Develop Numerical Models to Study Tete Bayou and Pharr Canal • Examine Four Proposed Drainage Improvement Scenarios: Scenario No. 1: Cleaning of Tete Bayou and the Pharr Canal; Scenario No. 2: Scenario No. 1 + widening of the Pharr Canal intake, and removing existing spoil banks along Tete Bayou; Scenario No. 3: Scenario No. 2 + diverting flow from Tete Bayou to Bayou Teche through a sub-surface box culvert system; and Scenario No. 4: Scenario No. 1 + widening of Pharr Canal.
  • 6. Analysis Timeline • Contract Execution Date: January 19, 2011 • Field Survey Collection Start Date: February 8, 2011 • Numerical Model Development Start: February 21, 2011 • Agency Meeting with City and Parish Date: April 5, 2011 • Draft Report to City and Parish Date: July 22, 2011
  • 7. Data Collected • Survey Date Collected By C.H. Fenstermaker & Associates, Inc. • 1,589 Survey Points Collected • Historical Hydrologic Data • Land Use/Land Cover Maps • Soil Type Maps • LiDAR Data • FEMA Flood Zones
  • 8. FEMA Calibration Existing 100-year Storm Event 15 10 CALIBRATION CHECKS Emile Verret Rd Mullins Rd Belle Place Olivier Rd 5 Elevation (ft) Crochet Rd 0 100-year Rainfall Event 1% Chance that a 12.6 inch -5 Rainfall over 24 hours will Occur in a Given Year Existing 100-yr WSE Ground FEMA BFE -10 60,000 50,000 40,000 30,000 20,000 10,000 0 Main Channel Distance (ft)
  • 9. December 2006 Storm Event Calibration Tete Bayou at Belle Place Olivier Rd Facing South Tete Bayou near Candleglow Dr Facing East Tete Bayou at Emile Verret Rd Facing East Tete Bayou at Emile Verret Rd Facing West Estimated Rainfall Event 5.02” Rainfall (24 hours) Approx. 3-yr., 24-hour Storm
  • 10. December 2006 Storm Event Calibration December 2006 Storm Event 15 10 Emile Verret Rd Mullins Rd Belle Place Olivier Rd 5 Elevation (ft) Crochet Rd 0 Tete Bayou at Belle Place Olivier Rd Facing South -5 December 2006 WSE Ground December 2006 High Water Mark -10 60,000 50,000 40,000 30,000 20,000 10,000 0 Main Channel Distance (ft)
  • 11. Scenario No. 1 Definition: Channel Cleaning of Tete Bayou and the Pharr Canal 11/XX
  • 12. Scenario No. 1 – Water Surface Elevation Comparison Existing - Scenario 1 Comparison 15 0.6’ Reduction in Water Surface Elevation 10 Emile Verret Rd Mullins Rd Belle Place Olivier Rd 5 Elevation (ft) Crochet Rd 0 10-year Rainfall Event 10% Chance that a 7.8 inch Rainfall over 24 hours will -5 Occur in a Given Year 10-yr Existing WSE 10-yr Scenario 1 WSE Ground -10 12/XX 60,000 50,000 40,000 30,000 20,000 10,000 0 Main Channel Distance (ft)
  • 13. Scenario No. 1 – Inundation Comparison 13/XX
  • 14. Scenario No. 1 – Results Scenario No. 1 Inundation Area Comparison Existing Conditions Scenario No. 1 Scenario No. 1 Scenario No. 1 Scenario No. 1 10-yr Inundation Area 10-yr Inundation 10-yr Reduction 10-yr Increase 10-yr Total Reduction (acres) Area (acres) Area (acres) Area (acres) Area Reduction (acres) 6,390 6,366 220 197 24 Scenario No. 1 Flood Duration Comparison Water Surface Elevation > 7’ NAVD 88 Bridge Existing Scenario No. 1 Emile Verret Rd 24 hrs 15 hrs (37%) Belle Place Olivier Rd 18 hrs 12 hrs (33%)
  • 15. Scenario No. 2 Definition: Channel Cleaning, Widening of the Pharr Canal, and Removing Existing Spoil Banks Along Tete Bayou 15/XX
  • 16. Scenario No. 2 – Water Surface Elevation Comparison Existing - Scenario 2 Comparison 15 0.6’ Reduction in Water Surface Elevation 10 Emile Verret Rd Mullins Rd Belle Place Olivier Rd 5 Elevation (ft) Crochet Rd 0 -5 10-yr Existing WSE 10-yr Scenario 2 WSE Ground -10 16/XX 60,000 50,000 40,000 30,000 20,000 10,000 0 Main Channel Distance (ft)
  • 17. Scenario No.2 – Inundation Comparison 17/XX
  • 18. Scenario No. 2 – Results Scenario No. 2 Inundation Area Comparison Existing Conditions Scenario No. 2 Scenario No. 2 Scenario No. 2 Scenario No. 2 10-yr Inundation Area 10-yr Inundation 10-yr Reduction 10-yr Increase 10-yr Total Reduction (acres) Area (acres) Area (acres) Area (acres) Area Reduction (acres) 6,390 6,209 289 108 181 Scenario No. 2 Flood Duration Comparison Water Surface Elevation > 7’ NAVD 88 Bridge Existing Scenario No. 2 Emile Verret Rd 24 hrs 14 hrs (42%) Belle Place Olivier Rd 18 hrs 12 hrs (33%)
  • 19. Scenario No. 3 Definition: Channel Cleaning, Widening of the Pharr Canal, Removing Spoil Banks, and Diverting Flow From Tete Bayou to Bayou Teche Through a Sub-surface Box Culvert System 19/XX
  • 20. Scenario No. 3 – Water Surface Elevation Comparison Existing - Scenario 3 Comparison 15 1.7’ Reduction in Emile Verret Rd Water Surface Elevation 10 Mullins Rd Belle Place Olivier Rd 5 Elevation (ft) Crochet Rd Diversion 0 -5 10-yr Existing WSE 10-yr Scenario 3 WSE Ground -10 20/XX 60,000 50,000 40,000 30,000 20,000 10,000 0 Main Channel Distance (ft)
  • 21. Scenario No. 3 – Inundation Comparison 21/XX
  • 22. Scenario No. 3 – Results Scenario No. 3 Inundation Area Comparison Existing Conditions Scenario No. 3 Scenario No. 3 Scenario No. 3 Scenario No. 3 10-yr Inundation Area 10-yr Inundation 10-yr Reduction 10-yr Increase 10-yr Total Reduction (acres) Area (acres) Area (acres) Area (acres) Area Reduction (acres) 6,390 5,835 619 64 555 Scenario No. 3 Flood Duration Comparison Water Surface Elevation > 7’ NAVD 88 Bridge Existing Scenario No. 3 Emile Verret Rd 24 hrs 5 hrs (79%) Belle Place Olivier Rd 18 hrs 10 hrs (44%)
  • 23. Scenario No. 4 Definition: Channel Cleaning and Pharr Canal Diversion 23/XX
  • 24. Scenario No. 4 – Water Surface Elevation Comparison Existing - Scenario 4 Comparison 15 1.5’ Reduction in Water Surface Elevation 10 Emile Verret Rd Diversion Belle Place Olivier Rd Mullins Rd 5 Elevation (ft) Crochet Rd 0 -5 10-yr Existing WSE 10-yr Scenario 4 WSE Ground -10 24/XX 60,000 50,000 40,000 30,000 20,000 10,000 0 Main Channel Distance (ft)
  • 25. Scenario No. 4 – Inundation Comparison 25/XX
  • 26. Scenario No. 4 – Results Scenario No. 4 Inundation Area Comparison Existing Conditions Scenario No. 4 Scenario No. 4 Scenario No. 4 Scenario No. 4 10-yr Inundation Area 10-yr Inundation 10-yr Reduction 10-yr Increase 10-yr Total Reduction (acres) Area (acres) Area (acres) Area (acres) Area Reduction (acres) 6,390 5,977 463 50 414 Scenario No. 4 Flood Duration Comparison Water Surface Elevation > 7’ NAVD 88 Bridge Existing Scenario No. 4 Emile Verret Rd 24 hrs 9 hrs (62%) Belle Place Olivier Rd 18 hrs 10 hrs (44%)
  • 27. Scenario Comparisons and Costs Flood Duration Flood Duration Inundation Inundation Total Reduction at Reduction at Reduction Increase Planning Scenario Emile Verret Belle Place Olivier Area Area (hrs) (hrs) (acres) (acres) Cost* No. 1 9 6 220 197 $1,177,000 No. 2 10 6 289 108 $1,964,000 No. 3 19 8 619 64 $6,416,000 No. 4 15 8 463 50 $2,641,000 * It should be noted that these figures represent approximated cost only to be used for planning purposes.
  • 28. Additional Analysis – Dredge Tete Bayou Mouth Dredging Tete Bayou 15 Definition: Dredging of Tete Bayou into Lake Fausse Pointe 10 Emile Verret Rd Mullins Rd Belle Place Olivier Rd 5 Elevation (ft) Crochet Rd Negligible Water Surface 0 Elevation Change -5 10-yr Existing WSE Existing Ground Dredged 10-yr WSE Dredged Ground -10 60,000 50,000 40,000 30,000 20,000 10,000 0 Main Channel Distance (ft)
  • 29. Drainage Assessment of Tete Bayou Experience · Innovation · Results Visit Our Website at www.fenstermaker.com Engineers ∙ Surveyors · Environmental Consultants