SlideShare a Scribd company logo
Summary Risk Report
Plan Summary
Title Copy of ExampleRegister-DownstreamOG.plan
File name C:UsersburivoyYandexDiskRisksCopy of ExampleRegister-DownstreamOG.plan
Plan finish date 11 Mar 09 Tasks with no progress 33
Plan remaining duration 1247 In progress tasks 0
Normal tasks 26 Completed tasks 0
Summary tasks 5 Total tasks 33
Milestone tasks 2 Resource assignments 44
Hammock tasks 0 Budget cost $67,975,229
Monitor tasks 0 Remaining cost $73,654,301
Calendars 4 Actual cost $0
Links 37 Total cost $73,654,301
Resources 10
Risk Inputs
Task ID: A120 Remaining Duration: 18
Task Description: Tap well-head Remaining Cost: $54
Duration Uncertainty
Distribution Triangle
Minimum 16
Most Likely 18
Maximum 20
Notes
Task ID: A160 Remaining Duration: 42
Task Description: Gas separator Remaining Cost: $1,457,330
Duration Uncertainty
Distribution Triangle
Minimum 37
Most Likely 42
Maximum 46
Notes
Task ID: A180 Remaining Duration: 105
Task Description: FWKO Tank Remaining Cost: $1,751,575
Duration Uncertainty
Distribution Triangle
Minimum 100
Most Likely 105
Maximum 137
Notes
Task ID: A190 Remaining Duration: 85
Task Description: Main water tank Remaining Cost: $751,020
Duration Uncertainty
Distribution Triangle
Minimum 76
Most Likely 85
Maximum 94
Notes
Task ID: A230 Remaining Duration: 50
Task Description: Cooling ponds Remaining Cost: $676,750
Duration Uncertainty
Distribution Triangle
Minimum 45
Most Likely 50
Maximum 55
Notes
Task ID: A250 Remaining Duration: 140
Task Description: Production tanks Remaining Cost: $4,803,500
Duration Uncertainty
Distribution Triangle
Minimum 133
Most Likely 140
Maximum 182
Notes
Task ID: A260 Remaining Duration: 145
Task Description: Production pumps Remaining Cost: $3,131,595
Duration Uncertainty
Distribution Triangle
Minimum 129
Most Likely 145
Maximum 160
Notes
Task ID: A310 Remaining Duration: 142
Task Description: Pumpstation 5 Remaining Cost: $4,904,970
Duration Uncertainty
Distribution Triangle
Minimum 135
Most Likely 142
Maximum 185
Notes
Task ID: A390 Remaining Duration: 0
Task Description: Project completion Remaining Cost: $0
Task ID: A100 Remaining Duration: 0
Task Description: Project Start Remaining Cost: $0
Task ID: A360 Remaining Duration: 26
Task Description: Level production tanks Remaining Cost: $260
Duration Uncertainty
Distribution Triangle
Minimum 23
Most Likely 26
Maximum 31
Notes
Task ID: A110 Remaining Duration: 0
Task Description: Pre-production Remaining Cost: $4,250,114
Task ID: A140 Remaining Duration: 46
Task Description: High pressure stack Remaining Cost: $1,501,150
Duration Uncertainty
Distribution Triangle
Minimum 44
Most Likely 46
Maximum 60
Notes
Task ID: A210 Remaining Duration: 80
Task Description: Auxilary pumps Remaining Cost: $2,002,000
Duration Uncertainty
Distribution Triangle
Minimum 71
Most Likely 80
Maximum 88
Notes
Task ID: A220 Remaining Duration: 145
Task Description: Water treatment facility Remaining Cost: $2,502,610
Duration Uncertainty
Distribution Triangle
Minimum 138
Most Likely 145
Maximum 189
Notes
Task ID: A200 Remaining Duration: 71
Task Description: Secondary water tank Remaining Cost: $346,585
Duration Uncertainty
Distribution Triangle
Minimum 67
Most Likely 71
Maximum 92
Notes
Task ID: A150 Remaining Duration: 57
Task Description: Low pressure stack Remaining Cost: $1,150,855
Duration Uncertainty
Distribution Triangle
Minimum 51
Most Likely 57
Maximum 68
Notes
Task ID: A320 Remaining Duration: 131
Task Description: Depressurizing station Remaining Cost: $6,001,310
Duration Uncertainty
Distribution Triangle
Minimum 118
Most Likely 131
Maximum 157
Notes
Task ID: A330 Remaining Duration: 136
Task Description: Main pipline to terminal Remaining Cost: $17,013,600
Duration Uncertainty
Distribution Triangle
Minimum 121
Most Likely 136
Maximum 150
Notes
Task ID: A350 Remaining Duration: 30
Task Description: Field production facility tests Remaining Cost: $450
Duration Uncertainty
Distribution Triangle
Minimum 27
Most Likely 30
Notes
Maximum 36
Task ID: A380 Remaining Duration: 9
Task Description: Open pipeline to terminal Remaining Cost: $675
Duration Uncertainty
Distribution Triangle
Minimum 8
Most Likely 9
Maximum 10
Notes
Task ID: A370 Remaining Duration: 19
Task Description: Level PS1 tanks Remaining Cost: $152
Duration Uncertainty
Distribution Triangle
Minimum 17
Most Likely 19
Maximum 21
Notes
Task ID: A130 Remaining Duration: 0
Task Description: Construct Field Production Facility Remaining Cost: $4,109,335
Task ID: A170 Remaining Duration: 0
Task Description: Water Flow Remaining Cost: $8,030,540
Task ID: A240 Remaining Duration: 0
Task Description: Crude Flow Remaining Cost: $57,262,775
Task ID: A340 Remaining Duration: 0
Task Description: Production Remaining Cost: $1,537
Task ID: A300 Remaining Duration: 202
Task Description: Pumpstation 4 Remaining Cost: $6,009,090
Duration Uncertainty
Distribution Triangle
Minimum 180
Most Likely 202
Maximum 222
Notes
Task ID: A290 Remaining Duration: 201
Task Description: Pumpstation 3 Remaining Cost: $5,258,040
Duration Uncertainty
Distribution Triangle
Minimum 181
Most Likely 201
Maximum 241
Notes
Task ID: A280 Remaining Duration: 197
Task Description: Pumpstation 2 Remaining Cost: $5,131,895
Duration Uncertainty
Distribution Triangle
Minimum 187
Most Likely 197
Maximum 256
Notes
Task ID: A270 Remaining Duration: 195
Task Description: Pumpstation 1 Remaining Cost: $5,008,775
Duration Uncertainty
Distribution Triangle
Minimum 176
Most Likely 195
Maximum 234
Notes
Task ID: A400 Remaining Duration: 5
Task Description: Vendor installation Remaining Cost: $60
Duration Uncertainty
Distribution Triangle
Minimum 4
Most Likely 5
Maximum 6
Notes
Task ID: A410 Remaining Duration: 12
Task Description: Expedite delivery Remaining Cost: $250,000
Duration Uncertainty
Distribution Triangle
Minimum 11
Most Likely 12
Maximum 13
Notes
Task ID: A420 Remaining Duration: 15
Task Description:
Source suitable uninterruptible power
generators
Remaining Cost: $4,000,000
Duration Uncertainty
Distribution Triangle
Minimum 14
Most Likely 15
Maximum 18
Notes
Templated Quick Risk
Field Value Tasks Distribution Min Likely Max Correlation Description
Uncertainty = L 12 Triangle 89% 100% 110% none
Uncertainty = M 7 Triangle 90% 100% 120% none
Uncertainty = H 7 Triangle 95% 100% 130% none
Probabilistic Calendars
Calendar: WeatherDelay
From To Apply to Block size (days) Non working probability
31/Oct/05 01/Oct/05 Every year 7 15%
30/Nov/05 01/Nov/05 Every year 7 15%
31/Dec/05 01/Dec/05 Every year 7 20%
31/Jan/06 01/Jan/06 Every year 7 30%
28/Feb/06 01/Feb/06 Every year 7 30%
31/Mar/06 01/Mar/06 Every year 7 25%
30/Apr/06 01/Apr/06 Every year 7 15%
31/May/06 01/May/06 Every year 7 10%
30/Jun/06 01/Jun/06 Every year 7 5%
31/Jul/06 01/Jul/06 Every year 7 5%
31/Aug/06 01/Aug/06 Every year 7 10%
30/Sep/06 01/Sep/06 Every year 7 10%
Resources
No Data
Risk Outputs
Project Finish Distribution Graph
Title Value
Minimum 09 Feb 09
Maximum 13 Jul 09
Mean 27 Apr 09
Median 28 Apr 09
Mode 07 May 09
Max Hits 97
Std Deviation 27.59
Variance 761.5
Skewness -0.051
Kurtosis 2.599
Bar Width: week
Project Cost Distribution Graph
Title Value
Minimum $73,653,005
Maximum $73,660,741
Mean $73,656,672
Median $73,656,639
Mode $73,656,750
Max Hits 153
Std Deviation 1,319
Variance 1,739,116
Skewness 0.115
Kurtosis 2.878
Bar Width: $500
Project NPV Distribution Graph
Not Checked
Project IRR Distribution Graph
Not Checked
Project Duration Sensitivity Tornado Graph
The duration sensitivity of a task is a measure of the correlation between its duration and the
duration (or dates) of the project (or a key task or summary).
Project Cost Sensitivity Tornado Graph
The cost sensitivity of a task is a measure of the correlation between its cost and the cost of the
project (or a key task or summary).
Project SSI Tornado Graph
The schedule sensitivity index of a task is calculated by multiplying its criticality index by the ratio of
its variance against the variance of the project (or key task).
Project Criticality Tornado Graph
The criticality index of a task is the proportion of the iterations in which it was critical.
Project Cruciality Tornado Graph
The cruciality of a task is calculated by multiplying its duration sensitivity by its criticality index.
Risk Register
Risk Register Summary
Total Risks 10
Proposed Risks 0
Open Risks 10
High 4
Medium 3
Low 2
Negligible 1
Impacted (Closed) Risks 0
Managed (Closed) Risks 0
Rejected (Closed) Risks 0
Threats 9
Opportunities 1
Risk Scoring
Probability Scale
Very Low Low Medium High Very High
Up to 10% 10% to 35% 35% to 60% 60% to 75% 75% or higher
Impact Scales and Types
Very Low Low Medium High Very High
Schedule* Up to 30 30 to 60 60 to 90 90 to 180 180 or higher
Cost* Up to $500,000 $500,000 to $1,000,000 $1,000,000 to $1,500,000 $1,500,000 to $2,500,000 $2,500,000 or higher
Performance*
Failure to meet a minor
acceptance criteria
Failure to meet more than one
minor acceptance criteria
Shortfall in meeting
acceptance criteria
Significant shortfall in meeting
acceptance criteria
Failure to meet acceptance
criteria
* means impact is used in scoring
Probability and Impact Scoring (PID)
Risk Score is based on: Highest Impact
Impact
Very Low Low Medium High Very High
Very High 5 9 18 36 72
High 4 7 14 28 56
Medium 3 5 10 20 40
Low 2 3 6 12 24
Very Low 1 1 2 4 8
Key
Up to 7 7 to 23 23 or higher
Risk Matrix
Pre-Mitigation
Very Low Low Medium High Very High
Very High
10 - Reuse previous design
work
High
5 - Power outtage,
3 - Attack on pipeline
4 - Key resource
unavailable
Medium
7 - Rework required for
assembly and integration
Low 8 - Testing fails 9 - Design changes
1 - Poor understanding and
detail in specification
Very Low
2 - Auxilary pump system
failure
Post-Mitigation
Very Low Low Medium High Very High
Very High
High 5 - Power outtage 9 - Design changes
10 - Reuse previous design
work
Medium
Low 8 - Testing fails 3 - Attack on pipeline
Very Low
4 - Key resource
unavailable,
1 - Poor understanding and
detail in specification
Risks
ID Title
4 Key resource unavailable
Status Owner
Open DP
RBS Start Date End Date Exposure
Project Level Impact.Crude Flow 07 Jan 2006 07 Jan 2006 $0
Cause Effect
Due to other project commitments. Delay could occur on completion of key activities.
Description
Key resources may be unavailable.
Pre-mitigation Score 56 High
Post-mitigation Score 1 Low
Qualitative Quantitative
Pre-
mitigation
H 67%
Post-
mitigation
VL 5%
Qualitative
Schedule Pre-mitigation L
Post-mitigation L
Cost Pre-mitigation L
Post-mitigation L
Performance Pre-mitigation VH
Post-mitigation L
Mitigation Title: Change resource assignment policy
Description Source additional specialists
Responsibility DP Status Proposed Mitigated Cost $4,500,000 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 12 Dec 2005 Target Finish Date 12 Dec 2005
Description Overbook key resources
Responsibility DP Status Proposed Mitigated Cost $3,250,000 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 03 Jan 2006 Target Finish Date 03 Jan 2006
Description Increase contract incentive
Responsibility DP Status Proposed Mitigated Cost $800,000 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 07 Jan 2006 Target Finish Date 07 Jan 2006
Risk Plan: Pre-mitigation
Impacting Task: A340 - Production
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
Impacting Task: A330 - Main pipline to terminal
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
Impacting Task: A260 - Production pumps
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
Risk Plan: Post-mitigation
Impacting Task: A340 - Production
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
Impacting Task: A330 - Main pipline to terminal
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
Impacting Task: A260 - Production pumps
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
ID Title
10 Reuse previous design work
Status Owner
Open TS
RBS Start Date End Date Exposure
Project Level Impact.Gas
separation
12 Oct 2005 12 Oct 2005 $0
Cause Effect
Due to the similar nature of the design. Saving time and money during the initial design phase.
Description
It may be possible to use designs created for previous project.
Pre-mitigation Score 36 High
Post-mitigation Score 28 High
Qualitative Quantitative
Pre-
mitigation
VH 87%
Post-
mitigation
H 67%
Qualitative
Schedule Pre-mitigation M
Post-mitigation M
Cost Pre-mitigation H
Post-mitigation H
Performance Pre-mitigation N
Post-mitigation N
Risk Plan: Pre-mitigation
Impacting Task: A330 - Main pipline to terminal
Schedule Triangle 60 75 90
Cost Triangle $1,500,000 $2,000,000 $2,500,000
Risk Plan: Post-mitigation
Impacting Task: A330 - Main pipline to terminal
Schedule Triangle 60 75 90
Cost Triangle $1,500,000 $2,000,000 $2,500,000
ID Title
5 Power outtage
Status Owner
Open TR
RBS Start Date End Date Exposure
Project Level Impact 05 Jan 2006 05 Jan 2006 $0
Cause Effect
Government power plant failure. Power dependent activities will be delayed.
Description
It may be necessary to find an alternative or supplemental power source.
Pre-mitigation Score 28 High
Post-mitigation Score 4 Low
Qualitative Quantitative
Pre-
mitigation
H 67%
Post-
mitigation
H 67%
Qualitative
Schedule Pre-mitigation H
Post-mitigation VL
Cost Pre-mitigation H
Post-mitigation N
Performance Pre-mitigation VL
Post-mitigation N
Mitigation Title: Source alternative power supply
Description Source suitable uninterruptible power generators
Responsibility TR Status Planned Mitigated Cost $4,000,000 Actual Cost $0
TaskID A420 Task Description Source suitable uninterruptible power generators
Start Date 12 Oct 2005 Finish Date 01 Nov 2005 Target Start Date 30 Dec 1899 Target Finish Date 30 Dec 1899
Description Expedite delivery
Responsibility TR Status Planned Mitigated Cost $250,000 Actual Cost $0
TaskID A410 Task Description Expedite delivery
Start Date 02 Nov 2005 Finish Date 17 Nov 2005 Target Start Date 30 Dec 1899 Target Finish Date 30 Dec 1899
Description Vendor fees for travel and installation
Responsibility TR Status Planned Mitigated Cost $60 Actual Cost $0
TaskID A400 Task Description Vendor installation
Start Date 18 Nov 2005 Finish Date 24 Nov 2005 Target Start Date 30 Dec 1899 Target Finish Date 30 Dec 1899
Risk Plan: Pre-mitigation
Impacting Task: A180 - FWKO Tank
Schedule Triangle 9 13 18
Cost Triangle $150,000 $200,000 $250,000
Impacting Task: A190 - Main water tank
Schedule Triangle 9 13 18
Cost Triangle $150,000 $200,000 $250,000
Impacting Task: A200 - Secondary water tank
Schedule Triangle 9 13 18
Cost Triangle $150,000 $200,000 $250,000
Impacting Task: A210 - Auxilary pumps
Schedule Triangle 9 13 18
Cost Triangle $150,000 $200,000 $250,000
Impacting Task: A220 - Water treatment facility
Schedule Triangle 9 13 18
Cost Triangle $150,000 $200,000 $250,000
Impacting Task: A260 - Production pumps
Schedule Triangle 9 13 18
Cost Triangle $150,000 $200,000 $250,000
Impacting Task: A250 - Production tanks
Schedule Triangle 9 13 18
Cost Triangle $150,000 $200,000 $250,000
Impacting Task: A350 - Field production facility tests
Schedule Triangle 9 13 18
Cost Triangle $150,000 $200,000 $250,000
Impacting Task: A360 - Level production tanks
Schedule Triangle 9 13 18
Cost Triangle $150,000 $200,000 $250,000
Impacting Task: A370 - Level PS1 tanks
Schedule Triangle 9 13 18
Cost Triangle $150,000 $200,000 $250,000
Risk Plan: Post-mitigation
Impacting Task: A180 - FWKO Tank
Schedule Triangle 0 1 3
Cost Triangle $0 $0 $0
Impacting Task: A190 - Main water tank
Schedule Triangle 0 1 3
Cost Triangle $0 $0 $0
Impacting Task: A200 - Secondary water tank
Schedule Triangle 0 1 3
Cost Triangle $0 $0 $0
Impacting Task: A210 - Auxilary pumps
Schedule Triangle 0 1 3
Cost Triangle $0 $0 $0
Impacting Task: A220 - Water treatment facility
Schedule Triangle 0 1 3
Cost Triangle $0 $0 $0
Impacting Task: A260 - Production pumps
Schedule Triangle 0 1 3
Cost Triangle $0 $0 $0
Impacting Task: A250 - Production tanks
Schedule Triangle 0 1 3
Cost Triangle $0 $0 $0
Impacting Task: A350 - Field production facility tests
Schedule Triangle 0 1 3
Cost Triangle $0 $0 $0
Impacting Task: A360 - Level production tanks
Schedule Triangle 0 1 3
Cost Triangle $0 $0 $0
Impacting Task: A370 - Level PS1 tanks
Schedule Triangle 0 1 3
Cost Triangle $0 $0 $0
ID Title
3 Attack on pipeline
Status Owner
Open DP
RBS Start Date End Date Exposure
Project Level Impact.Production 15 Nov 2005 15 Nov 2005 $0
Cause Effect
Due to lack of stability in the region local guerillas may attack the pipeline. Delay in bringing the field production facility online.
Description
Local guerilla groups have attacked other pipelines in the past. As a sort of ransome, they will repeatedly threaten to attack unless paid-off by the government or
the foriegn contractors.
Pre-mitigation Score 28 High
Post-mitigation Score 12 Medium
Qualitative Quantitative
Pre-
mitigation
H 67%
Post-
mitigation
L 22%
Qualitative
Schedule Pre-mitigation L
Post-mitigation M
Cost Pre-mitigation M
Post-mitigation L
Performance Pre-mitigation H
Post-mitigation H
Mitigation Title: Source extra security with local government
Description Use standard form of contract
Responsibility DP Status Proposed Mitigated Cost $400,000 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 01 Nov 2005 Target Finish Date 01 Nov 2005
Description Pre contract negotiation
Responsibility DP Status Proposed Mitigated Cost $100,000 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 15 Nov 2005 Target Finish Date 15 Nov 2005
Risk Plan: Pre-mitigation
Impacting Task: A380 - Open pipeline to terminal
Schedule Triangle 15 22 30
Cost Triangle $500,000 $625,000 $750,000
Impacting Task: A370 - Level PS1 tanks
Schedule Triangle 15 22 30
Cost Triangle $500,000 $625,000 $750,000
Risk Plan: Post-mitigation
Impacting Task: A380 - Open pipeline to terminal
Schedule Triangle 30 37 45
Cost Triangle $250,000 $375,000 $500,000
Impacting Task: A370 - Level PS1 tanks
Schedule Triangle 30 37 45
Cost Triangle $250,000 $375,000 $500,000
ID Title
1 Poor understanding and detail in specification
Status Owner
Open TS
RBS Start Date End Date Exposure
Project Level Impact.Crude Flow 01 Nov 2006 01 Nov 2006 $0
Cause Effect
Due to poor understanding and detail in the initial specification. Could delay the project schedule and increase cost.
Description
The design is more complex than expected.
Pre-mitigation Score 12 Medium
Post-mitigation Score 1 Low
Qualitative Quantitative
Pre-
mitigation
L 22%
Post-
mitigation
VL 5%
Qualitative
Schedule Pre-mitigation H
Post-mitigation L
Cost Pre-mitigation M
Post-mitigation L
Performance Pre-mitigation VL
Post-mitigation VL
Mitigation Title: Introduce penalties for design changes
Description Include penalties for any design changes
Responsibility TS Status Proposed Mitigated Cost $10,000 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 01 Nov 2005 Target Finish Date 01 Nov 2005
Description Use supported design methodologies
Responsibility TS Status Proposed Mitigated Cost $0 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 02 Jan 2006 Target Finish Date 02 Jan 2006
Risk Plan: Pre-mitigation
Impacting Task: A270 - Pumpstation 1
Schedule Triangle 12 19 25
Cost Triangle $142,857 $178,571 $214,286
Impacting Task: A280 - Pumpstation 2
Schedule Triangle 12 19 25
Cost Triangle $142,857 $178,571 $214,286
Impacting Task: A290 - Pumpstation 3
Schedule Triangle 12 19 25
Cost Triangle $142,857 $178,571 $214,286
Impacting Task: A300 - Pumpstation 4
Schedule Triangle 12 19 25
Cost Triangle $142,857 $178,571 $214,286
Impacting Task: A310 - Pumpstation 5
Schedule Triangle 12 19 25
Cost Triangle $142,857 $178,571 $214,286
Impacting Task: A320 - Depressurizing station
Schedule Triangle 12 19 25
Cost Triangle $142,857 $178,571 $214,286
Impacting Task: A250 - Production tanks
Schedule Triangle 12 19 25
Cost Triangle $142,857 $178,571 $214,286
Risk Plan: Post-mitigation
Impacting Task: A270 - Pumpstation 1
Schedule Triangle 4 6 8
Cost Triangle $71,429 $107,143 $142,857
Impacting Task: A280 - Pumpstation 2
Schedule Triangle 4 6 8
Cost Triangle $71,429 $107,143 $142,857
Impacting Task: A290 - Pumpstation 3
Schedule Triangle 4 6 8
Cost Triangle $71,429 $107,143 $142,857
Impacting Task: A300 - Pumpstation 4
Schedule Triangle 4 6 8
Cost Triangle $71,429 $107,143 $142,857
Impacting Task: A310 - Pumpstation 5
Schedule Triangle 4 6 8
Cost Triangle $71,429 $107,143 $142,857
Impacting Task: A320 - Depressurizing station
Schedule Triangle 4 6 8
Cost Triangle $71,429 $107,143 $142,857
Impacting Task: A250 - Production tanks
Schedule Triangle 4 6 8
Cost Triangle $71,429 $107,143 $142,857
ID Title
7 Rework required for assembly and integration
Status Owner
Open BJ
RBS Start Date End Date Exposure
Project Level Impact 01 Nov 2006 01 Nov 2006 $0
Cause Effect
Due to incorrect tolerances in manufacturing. Which would delay the time taken to complete the assembly.
Description
The assembly may need to be reworked to allow a satisfactory integration of the components.
Pre-mitigation Score 10 Medium
Post-mitigation Score 0 Negligible
Qualitative Quantitative
Pre-
mitigation
M 47%
Post-
mitigation
N 0%
Qualitative
Schedule Pre-mitigation M
Post-mitigation M
Cost Pre-mitigation M
Post-mitigation M
Performance Pre-mitigation L
Post-mitigation L
Mitigation Title: Check manufacturing tolerances
Description Check all manufacturing equipment can handle required tolerances
Responsibility BJ Status Proposed Mitigated Cost $200,000 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 01 Nov 2005 Target Finish Date 01 Nov 2005
Description Communicate importance of tolerances to manufacturing
Responsibility BJ Status Proposed Mitigated Cost $0 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 02 Jan 2006 Target Finish Date 02 Jan 2006
Risk Plan: Pre-mitigation
Impacting Task: A140 - High pressure stack
Schedule Triangle 15 18 22
Cost Triangle $250,000 $312,500 $375,000
Impacting Task: A150 - Low pressure stack
Schedule Triangle 15 18 22
Cost Triangle $250,000 $312,500 $375,000
Impacting Task: A160 - Gas separator
Schedule Triangle 15 18 22
Cost Triangle $250,000 $312,500 $375,000
Impacting Task: A180 - FWKO Tank
Schedule Triangle 15 18 22
Cost Triangle $250,000 $312,500 $375,000
Risk Plan: Post-mitigation
Impacting Task: A140 - High pressure stack
Schedule Triangle 15 18 22
Cost Triangle $250,000 $312,500 $375,000
Impacting Task: A150 - Low pressure stack
Schedule Triangle 15 18 22
Cost Triangle $250,000 $312,500 $375,000
Impacting Task: A160 - Gas separator
Schedule Triangle 15 18 22
Cost Triangle $250,000 $312,500 $375,000
Impacting Task: A180 - FWKO Tank
Schedule Triangle 15 18 22
Cost Triangle $250,000 $312,500 $375,000
ID Title
2 Auxilary pump system failure
Status Owner
Open RB
RBS Start Date End Date Exposure
Project Level Impact.Water Flow 02 Jan 2006 02 Jan 2006 $0
Cause Effect
Due to the novel nature of the auxilary pump system. Auxilary pump system would need to be modified.
Description
There may be a major failure of auxilary pump system.
Pre-mitigation Score 8 Medium
Post-mitigation Score 0 Negligible
Qualitative Quantitative
Pre-
mitigation
VL 5%
Post-
mitigation
N 0%
Qualitative
Schedule Pre-mitigation VH
Post-mitigation VH
Cost Pre-mitigation VH
Post-mitigation VH
Performance Pre-mitigation VH
Post-mitigation VH
Mitigation Title: Improve initial specification
Description Spend more money on the initial specification
Responsibility RB Status Proposed Mitigated Cost $250,000 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 10 Nov 2005 Target Finish Date 10 Nov 2005
Description Use off-the-shelf pump systems
Responsibility RB Status Proposed Mitigated Cost $500,000 Actual Cost $0
TaskID Task Description undefined
Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 02 Jan 2006 Target Finish Date 02 Jan 2006
Risk Plan: Pre-mitigation
Impacting Task: A210 - Auxilary pumps
Schedule Triangle 90 135 180
Cost Triangle $1,250,000 $1,875,000 $2,500,000
Impacting Task: A220 - Water treatment facility
Schedule Triangle 90 135 180
Cost Triangle $1,250,000 $1,875,000 $2,500,000
Risk Plan: Post-mitigation
Impacting Task: A210 - Auxilary pumps
Schedule Triangle 90 135 180
Cost Triangle $1,250,000 $1,875,000 $2,500,000
Impacting Task: A220 - Water treatment facility
Schedule Triangle 90 135 180
Cost Triangle $1,250,000 $1,875,000 $2,500,000
ID Title
9 Design changes
Status Owner
Open LM
RBS Start Date End Date Exposure
Project Level Impact.Gas
separation
12 Oct 2005 12 Oct 2005 $0
Cause Effect
Due to client changing their mind. Which would delay the schedule.
Description
The design needs to be altered.
Pre-mitigation Score 6 Low
Post-mitigation Score 14 Medium
Qualitative Quantitative
Pre-
mitigation
L 22%
Post-
mitigation
H 67%
Qualitative
Schedule Pre-mitigation M
Post-mitigation M
Cost Pre-mitigation M
Post-mitigation M
Performance Pre-mitigation N
Post-mitigation N
Risk Plan: Pre-mitigation
Impacting Task: A140 - High pressure stack
Schedule Triangle 20 25 30
Cost Triangle $333,333 $416,667 $500,000
Impacting Task: A150 - Low pressure stack
Schedule Triangle 20 25 30
Cost Triangle $333,333 $416,667 $500,000
Impacting Task: A160 - Gas separator
Schedule Triangle 20 25 30
Cost Triangle $333,333 $416,667 $500,000
Risk Plan: Post-mitigation
Impacting Task: A140 - High pressure stack
Schedule Triangle 20 25 30
Cost Triangle $333,333 $416,667 $500,000
Impacting Task: A150 - Low pressure stack
Schedule Triangle 20 25 30
Cost Triangle $333,333 $416,667 $500,000
Impacting Task: A160 - Gas separator
Schedule Triangle 20 25 30
Cost Triangle $333,333 $416,667 $500,000
ID Title
8 Testing fails
Status Owner
Open LM
RBS Start Date End Date Exposure
Project Level Impact.Production 12 Oct 2005 12 Oct 2005 $0
Cause Effect
Due to problems in design and fabrication. Rework would be required and retesting would need to take place.
Description
Testing fails to meet the clients performance criteria.
Pre-mitigation Score 3 Low
Post-mitigation Score 3 Low
Qualitative Quantitative
Pre-
mitigation
L 22%
Post-
mitigation
L 22%
Qualitative
Schedule Pre-mitigation L
Post-mitigation L
Cost Pre-mitigation L
Post-mitigation L
Performance Pre-mitigation N
Post-mitigation N
Risk Plan: Pre-mitigation
Impacting Task: A350 - Field production facility tests
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
Impacting Task: A360 - Level production tanks
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
Impacting Task: A370 - Level PS1 tanks
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
Risk Plan: Post-mitigation
Impacting Task: A350 - Field production facility tests
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
Impacting Task: A360 - Level production tanks
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
Impacting Task: A370 - Level PS1 tanks
Schedule Triangle 10 15 20
Cost Triangle $166,667 $250,000 $333,333
ID Title
6 Fabrication contractor goes bust
Status Owner
Open TR
RBS Start Date End Date Exposure
Project Level Impact 12 Oct 2005 12 Oct 2005 $0
Cause Effect
Due to poor business conditions in the current fabrication market.
A new fabrication company would need to be sourced causing delay to the
fabrication tasks.
Description
The fabrication contractor may go bust.
Pre-mitigation Score 0 Negligible
Post-mitigation Score 0 Negligible
Qualitative Quantitative
Pre-
mitigation
N 0%
Post-
mitigation
N 0%
Qualitative
Schedule Pre-mitigation M
Post-mitigation M
Cost Pre-mitigation M
Post-mitigation M
Performance Pre-mitigation M
Post-mitigation M
Risk Plan: Pre-mitigation
Impacting Task: A170 - Water Flow
Schedule Triangle 30 37 45
Cost Triangle $500,000 $625,000 $750,000
Impacting Task: A240 - Crude Flow
Schedule Triangle 30 37 45
Cost Triangle $500,000 $625,000 $750,000
Risk Plan: Post-mitigation
Impacting Task: A170 - Water Flow
Schedule Triangle 30 37 45
Cost Triangle $500,000 $625,000 $750,000
Impacting Task: A240 - Crude Flow
Schedule Triangle 30 37 45
Cost Triangle $500,000 $625,000 $750,000
Risk Tornado
Not Checked
13 Feb 06 28 Jun 07 09 Nov 08
Time
0
20,000,000
40,000,000
60,000,000
Cumulative
Resource Flow for Cost
Filter: Entire Plan
Mean P0
Analysis
Simulation: Latin Hypercu...
Iterations: 1000
Correlation
Pearson's 58.4%
Spearman's 57.7%
Highlighters
x-axis 50% (28 Apr 0...
y-axis 50% ($73,656...
Inside both li... 36%
Outside both l... 35%
1
% 3
%
17 Feb 09 28 May 09
Entire Plan: Finish
50%
$73,654,000
$73,656,000
$73,658,000
$73,660,000
EntirePlan:Cost
50%
DownstreamOG
Deterministic Point
Inside both limits
Outside both limits
Data
NPV of:
Entire Plan
Discount Rate: 0%
Analysis
Simulation: Latin Hypercube
Iterations: 1000
Convergence at mean
Mean Plan Finish Date:
Converged in 0 iterations
(variation < 1% over 100 iterations)
Mean Total Plan Cost:
Converged in 0 iterations
(variation < 1% over 100 iterations)
Statistics
Minimum: $73,653,005
Maximum: $73,660,741
Mean: $73,656,672
Median: $73,656,639
Mode: $73,656,750
Max Hits: 153
Std Deviation: 1,319
Variance: 1,739,116
Skewness: 0.115
Kurtosis: 2.878
Bar Width: $500
Highlighters
20% $73,657,767
Deterministic 96%
50% $73,656,639
80% $73,655,501
$73,660,000
Distribution (start of interval)
0
50
100
150
Hits
0% $73,660,741
5% $73,658,881
10% $73,658,306
15% $73,658,044
20% $73,657,767
25% $73,657,572
30% $73,657,398
35% $73,657,166
40% $73,656,986
45% $73,656,818
50% $73,656,639
55% $73,656,497
60% $73,656,291
65% $73,656,151
70% $73,655,926
75% $73,655,752
80% $73,655,501
85% $73,655,336
90% $73,655,033
95% $73,654,514
100% $73,653,005
CumulativeFrequency
DownstreamOG
Entire Plan : NPV
Data
Cost of:
Entire Plan
Analysis
Simulation: Latin Hypercube
Iterations: 1000
Convergence at mean
Mean Plan Finish Date:
Converged in 0 iterations
(variation < 1% over 100 iterations)
Mean Total Plan Cost:
Converged in 0 iterations
(variation < 1% over 100 iterations)
Statistics
Minimum: $73,653,005
Maximum: $73,660,741
Mean: $73,656,672
Median: $73,656,639
Mode: $73,656,750
Max Hits: 153
Std Deviation: 1,319
Variance: 1,739,116
Skewness: 0.115
Kurtosis: 2.878
Bar Width: $500
Highlighters
50% $73,656,639
20% $73,655,501
Deterministic 4%
50% $73,656,639
80% $73,657,767
$73,660,000
Distribution (start of interval)
0
50
100
150
Hits
0% $73,653,005
5% $73,654,502
10% $73,655,033
15% $73,655,334
20% $73,655,501
25% $73,655,752
30% $73,655,926
35% $73,656,151
40% $73,656,291
45% $73,656,497
50% $73,656,639
55% $73,656,818
60% $73,656,986
65% $73,657,166
70% $73,657,398
75% $73,657,572
80% $73,657,767
85% $73,658,044
90% $73,658,306
95% $73,658,881
100% $73,660,741
CumulativeFrequency
DownstreamOG
Entire Plan : Cost
Data
Duration of:
Entire Plan
Analysis
Simulation: Latin Hypercu...
Iterations: 1000
Convergence at mean
Mean Plan Finish Date:
Converged in 0 iterations
(variation < 1% over 100 iteratio...
Mean Total Plan Cost:
Converged in 0 iterations
(variation < 1% over 100 iteratio...
Statistics
Minimum: 1217
Maximum: 1371
Mean: 1294
Median: 1295
Mode: 1299
Max Hits: 103
Std Deviation: 27.59
Variance: 761.5
Skewness: -0.051
Kurtosis: 2.599
Bar Width: week
Highlighters
Deterministic 5%
50% 1295
80% 1317
Distribution (start of interval)
0
50
100
Hits
0% 1217
5% 1248
10% 1259
15% 1263
20% 1269
25% 1274
30% 1277
35% 1282
40% 1288
45% 1290
50% 1295
55% 1298
60% 1302
65% 1305
70% 1310
75% 1315
80% 1317
85% 1324
90% 1330
95% 1338
100% 1371
CumulativeFrequency
DownstreamOG
Entire Plan : Duration
Data
Finish Date of:
Entire Plan
Analysis
Simulation: Latin Hypercube
Iterations: 1000
Convergence at mean
Mean Plan Finish Date:
Converged in 0 iterations
(variation < 1% over 100 iterations)
Mean Total Plan Cost:
Converged in 0 iterations
(variation < 1% over 100 iterations)
Statistics
Minimum: 09 Feb 09
Maximum: 13 Jul 09
Mean: 27 Apr 09
Median: 28 Apr 09
Mode: 07 May 09
Max Hits: 97
Std Deviation: 27.59
Variance: 761.5
Skewness: -0.051
Kurtosis: 2.599
Bar Width: week
Highlighters
20% 02 Apr 09
Deterministic 5%
50% 28 Apr 09
80% 20 May 09
17 Feb 09
Distribution (start of interval)
0
50
100
Hits
0% 09 Feb 09
5% 12 Mar 09
10% 23 Mar 09
15% 27 Mar 09
20% 02 Apr 09
25% 07 Apr 09
30% 10 Apr 09
35% 15 Apr 09
40% 21 Apr 09
45% 23 Apr 09
50% 28 Apr 09
55% 01 May 09
60% 05 May 09
65% 08 May 09
70% 13 May 09
75% 18 May 09
80% 20 May 09
85% 27 May 09
90% 02 Jun 09
95% 10 Jun 09
100% 13 Jul 09
CumulativeFrequency
DownstreamOG
Entire Plan : Finish Date

More Related Content

Similar to Summary Risk Report

Page 1 Front PagePage 2 Stocks & BondsPage 3 Financial Sum.docx
Page 1 Front PagePage 2 Stocks & BondsPage 3 Financial Sum.docxPage 1 Front PagePage 2 Stocks & BondsPage 3 Financial Sum.docx
Page 1 Front PagePage 2 Stocks & BondsPage 3 Financial Sum.docx
gerardkortney
 
OxygenBottleA3
OxygenBottleA3OxygenBottleA3
OxygenBottleA3
Konrad Hubbard
 
Iron Cast and Machined Components Case study
Iron Cast and Machined Components Case studyIron Cast and Machined Components Case study
Iron Cast and Machined Components Case study
Dragon Sourcing
 
Graphical tools
Graphical toolsGraphical tools
Graphical tools
Cynthia Cumby
 
Scoring_model.pdf
Scoring_model.pdfScoring_model.pdf
Scoring_model.pdf
FabrizioLanubile
 
The Numbers
The NumbersThe Numbers
The Numbers
Yul Prince
 
Boeing Undergraduate Case Competition 2016
Boeing Undergraduate Case Competition 2016 Boeing Undergraduate Case Competition 2016
Boeing Undergraduate Case Competition 2016
Caleb Kwok
 
Forecasting Uncertainty - Obermeyer Case Study
Forecasting Uncertainty - Obermeyer Case StudyForecasting Uncertainty - Obermeyer Case Study
Forecasting Uncertainty - Obermeyer Case Study
Paris Photographer | Février Photography
 
Chapter 16
Chapter 16Chapter 16
Chapter 16
Rashedur Rahman
 
Шаблон KPI от YouExec
Шаблон KPI от YouExecШаблон KPI от YouExec
Шаблон KPI от YouExec
Danil Dintsis, Ph. D., PgMP
 
Project KPI presentation sample by YouExec
Project KPI presentation sample by YouExecProject KPI presentation sample by YouExec
Project KPI presentation sample by YouExec
IE Private Consulting in PM & ITSM
 
Group Project - Final - Linked in
Group Project - Final - Linked inGroup Project - Final - Linked in
Group Project - Final - Linked in
Sanket Butoliya
 
Theory of cost
Theory of costTheory of cost
Theory of cost
MuhammadMukitulBari
 
Supply chain - project
Supply chain - projectSupply chain - project
Supply chain - project
szrehman
 
BCAD Building Project
BCAD Building ProjectBCAD Building Project
BCAD Building Project
City of College Station
 
Negotiation PowerPoint
Negotiation PowerPointNegotiation PowerPoint
Negotiation PowerPoint
KeithByrd
 
Microeconomics-The cost of production.ppt
Microeconomics-The cost of production.pptMicroeconomics-The cost of production.ppt
Microeconomics-The cost of production.ppt
mayamonfori
 
Micro 12
Micro 12Micro 12
Micro 12
Gale Pooley
 
Aminullah assagaf time value of money
Aminullah assagaf time value of moneyAminullah assagaf time value of money
Aminullah assagaf time value of money
Aminullah Assagaf
 
Aminullah assagaf time value of money
Aminullah assagaf time value of moneyAminullah assagaf time value of money
Aminullah assagaf time value of money
Aminullah Assagaf
 

Similar to Summary Risk Report (20)

Page 1 Front PagePage 2 Stocks & BondsPage 3 Financial Sum.docx
Page 1 Front PagePage 2 Stocks & BondsPage 3 Financial Sum.docxPage 1 Front PagePage 2 Stocks & BondsPage 3 Financial Sum.docx
Page 1 Front PagePage 2 Stocks & BondsPage 3 Financial Sum.docx
 
OxygenBottleA3
OxygenBottleA3OxygenBottleA3
OxygenBottleA3
 
Iron Cast and Machined Components Case study
Iron Cast and Machined Components Case studyIron Cast and Machined Components Case study
Iron Cast and Machined Components Case study
 
Graphical tools
Graphical toolsGraphical tools
Graphical tools
 
Scoring_model.pdf
Scoring_model.pdfScoring_model.pdf
Scoring_model.pdf
 
The Numbers
The NumbersThe Numbers
The Numbers
 
Boeing Undergraduate Case Competition 2016
Boeing Undergraduate Case Competition 2016 Boeing Undergraduate Case Competition 2016
Boeing Undergraduate Case Competition 2016
 
Forecasting Uncertainty - Obermeyer Case Study
Forecasting Uncertainty - Obermeyer Case StudyForecasting Uncertainty - Obermeyer Case Study
Forecasting Uncertainty - Obermeyer Case Study
 
Chapter 16
Chapter 16Chapter 16
Chapter 16
 
Шаблон KPI от YouExec
Шаблон KPI от YouExecШаблон KPI от YouExec
Шаблон KPI от YouExec
 
Project KPI presentation sample by YouExec
Project KPI presentation sample by YouExecProject KPI presentation sample by YouExec
Project KPI presentation sample by YouExec
 
Group Project - Final - Linked in
Group Project - Final - Linked inGroup Project - Final - Linked in
Group Project - Final - Linked in
 
Theory of cost
Theory of costTheory of cost
Theory of cost
 
Supply chain - project
Supply chain - projectSupply chain - project
Supply chain - project
 
BCAD Building Project
BCAD Building ProjectBCAD Building Project
BCAD Building Project
 
Negotiation PowerPoint
Negotiation PowerPointNegotiation PowerPoint
Negotiation PowerPoint
 
Microeconomics-The cost of production.ppt
Microeconomics-The cost of production.pptMicroeconomics-The cost of production.ppt
Microeconomics-The cost of production.ppt
 
Micro 12
Micro 12Micro 12
Micro 12
 
Aminullah assagaf time value of money
Aminullah assagaf time value of moneyAminullah assagaf time value of money
Aminullah assagaf time value of money
 
Aminullah assagaf time value of money
Aminullah assagaf time value of moneyAminullah assagaf time value of money
Aminullah assagaf time value of money
 

Summary Risk Report

  • 1. Summary Risk Report Plan Summary Title Copy of ExampleRegister-DownstreamOG.plan File name C:UsersburivoyYandexDiskRisksCopy of ExampleRegister-DownstreamOG.plan Plan finish date 11 Mar 09 Tasks with no progress 33 Plan remaining duration 1247 In progress tasks 0 Normal tasks 26 Completed tasks 0 Summary tasks 5 Total tasks 33 Milestone tasks 2 Resource assignments 44 Hammock tasks 0 Budget cost $67,975,229 Monitor tasks 0 Remaining cost $73,654,301 Calendars 4 Actual cost $0 Links 37 Total cost $73,654,301 Resources 10
  • 2. Risk Inputs Task ID: A120 Remaining Duration: 18 Task Description: Tap well-head Remaining Cost: $54 Duration Uncertainty Distribution Triangle Minimum 16 Most Likely 18 Maximum 20 Notes Task ID: A160 Remaining Duration: 42 Task Description: Gas separator Remaining Cost: $1,457,330 Duration Uncertainty Distribution Triangle Minimum 37 Most Likely 42 Maximum 46 Notes Task ID: A180 Remaining Duration: 105 Task Description: FWKO Tank Remaining Cost: $1,751,575 Duration Uncertainty Distribution Triangle Minimum 100 Most Likely 105 Maximum 137 Notes Task ID: A190 Remaining Duration: 85 Task Description: Main water tank Remaining Cost: $751,020 Duration Uncertainty
  • 3. Distribution Triangle Minimum 76 Most Likely 85 Maximum 94 Notes Task ID: A230 Remaining Duration: 50 Task Description: Cooling ponds Remaining Cost: $676,750 Duration Uncertainty Distribution Triangle Minimum 45 Most Likely 50 Maximum 55 Notes Task ID: A250 Remaining Duration: 140 Task Description: Production tanks Remaining Cost: $4,803,500 Duration Uncertainty Distribution Triangle Minimum 133 Most Likely 140 Maximum 182 Notes Task ID: A260 Remaining Duration: 145 Task Description: Production pumps Remaining Cost: $3,131,595 Duration Uncertainty Distribution Triangle Minimum 129 Most Likely 145 Maximum 160 Notes
  • 4. Task ID: A310 Remaining Duration: 142 Task Description: Pumpstation 5 Remaining Cost: $4,904,970 Duration Uncertainty Distribution Triangle Minimum 135 Most Likely 142 Maximum 185 Notes Task ID: A390 Remaining Duration: 0 Task Description: Project completion Remaining Cost: $0 Task ID: A100 Remaining Duration: 0 Task Description: Project Start Remaining Cost: $0 Task ID: A360 Remaining Duration: 26 Task Description: Level production tanks Remaining Cost: $260 Duration Uncertainty Distribution Triangle Minimum 23 Most Likely 26 Maximum 31 Notes Task ID: A110 Remaining Duration: 0 Task Description: Pre-production Remaining Cost: $4,250,114 Task ID: A140 Remaining Duration: 46 Task Description: High pressure stack Remaining Cost: $1,501,150 Duration Uncertainty
  • 5. Distribution Triangle Minimum 44 Most Likely 46 Maximum 60 Notes Task ID: A210 Remaining Duration: 80 Task Description: Auxilary pumps Remaining Cost: $2,002,000 Duration Uncertainty Distribution Triangle Minimum 71 Most Likely 80 Maximum 88 Notes Task ID: A220 Remaining Duration: 145 Task Description: Water treatment facility Remaining Cost: $2,502,610 Duration Uncertainty Distribution Triangle Minimum 138 Most Likely 145 Maximum 189 Notes Task ID: A200 Remaining Duration: 71 Task Description: Secondary water tank Remaining Cost: $346,585 Duration Uncertainty Distribution Triangle Minimum 67 Most Likely 71 Maximum 92 Notes
  • 6. Task ID: A150 Remaining Duration: 57 Task Description: Low pressure stack Remaining Cost: $1,150,855 Duration Uncertainty Distribution Triangle Minimum 51 Most Likely 57 Maximum 68 Notes Task ID: A320 Remaining Duration: 131 Task Description: Depressurizing station Remaining Cost: $6,001,310 Duration Uncertainty Distribution Triangle Minimum 118 Most Likely 131 Maximum 157 Notes Task ID: A330 Remaining Duration: 136 Task Description: Main pipline to terminal Remaining Cost: $17,013,600 Duration Uncertainty Distribution Triangle Minimum 121 Most Likely 136 Maximum 150 Notes Task ID: A350 Remaining Duration: 30 Task Description: Field production facility tests Remaining Cost: $450 Duration Uncertainty Distribution Triangle Minimum 27 Most Likely 30 Notes
  • 7. Maximum 36 Task ID: A380 Remaining Duration: 9 Task Description: Open pipeline to terminal Remaining Cost: $675 Duration Uncertainty Distribution Triangle Minimum 8 Most Likely 9 Maximum 10 Notes Task ID: A370 Remaining Duration: 19 Task Description: Level PS1 tanks Remaining Cost: $152 Duration Uncertainty Distribution Triangle Minimum 17 Most Likely 19 Maximum 21 Notes Task ID: A130 Remaining Duration: 0 Task Description: Construct Field Production Facility Remaining Cost: $4,109,335 Task ID: A170 Remaining Duration: 0 Task Description: Water Flow Remaining Cost: $8,030,540 Task ID: A240 Remaining Duration: 0 Task Description: Crude Flow Remaining Cost: $57,262,775 Task ID: A340 Remaining Duration: 0
  • 8. Task Description: Production Remaining Cost: $1,537 Task ID: A300 Remaining Duration: 202 Task Description: Pumpstation 4 Remaining Cost: $6,009,090 Duration Uncertainty Distribution Triangle Minimum 180 Most Likely 202 Maximum 222 Notes Task ID: A290 Remaining Duration: 201 Task Description: Pumpstation 3 Remaining Cost: $5,258,040 Duration Uncertainty Distribution Triangle Minimum 181 Most Likely 201 Maximum 241 Notes Task ID: A280 Remaining Duration: 197 Task Description: Pumpstation 2 Remaining Cost: $5,131,895 Duration Uncertainty Distribution Triangle Minimum 187 Most Likely 197 Maximum 256 Notes Task ID: A270 Remaining Duration: 195 Task Description: Pumpstation 1 Remaining Cost: $5,008,775 Duration Uncertainty
  • 9. Distribution Triangle Minimum 176 Most Likely 195 Maximum 234 Notes Task ID: A400 Remaining Duration: 5 Task Description: Vendor installation Remaining Cost: $60 Duration Uncertainty Distribution Triangle Minimum 4 Most Likely 5 Maximum 6 Notes Task ID: A410 Remaining Duration: 12 Task Description: Expedite delivery Remaining Cost: $250,000 Duration Uncertainty Distribution Triangle Minimum 11 Most Likely 12 Maximum 13 Notes Task ID: A420 Remaining Duration: 15 Task Description: Source suitable uninterruptible power generators Remaining Cost: $4,000,000 Duration Uncertainty Distribution Triangle Minimum 14 Most Likely 15 Maximum 18 Notes
  • 10. Templated Quick Risk Field Value Tasks Distribution Min Likely Max Correlation Description Uncertainty = L 12 Triangle 89% 100% 110% none Uncertainty = M 7 Triangle 90% 100% 120% none Uncertainty = H 7 Triangle 95% 100% 130% none Probabilistic Calendars Calendar: WeatherDelay From To Apply to Block size (days) Non working probability 31/Oct/05 01/Oct/05 Every year 7 15% 30/Nov/05 01/Nov/05 Every year 7 15% 31/Dec/05 01/Dec/05 Every year 7 20% 31/Jan/06 01/Jan/06 Every year 7 30% 28/Feb/06 01/Feb/06 Every year 7 30% 31/Mar/06 01/Mar/06 Every year 7 25% 30/Apr/06 01/Apr/06 Every year 7 15% 31/May/06 01/May/06 Every year 7 10% 30/Jun/06 01/Jun/06 Every year 7 5% 31/Jul/06 01/Jul/06 Every year 7 5% 31/Aug/06 01/Aug/06 Every year 7 10% 30/Sep/06 01/Sep/06 Every year 7 10% Resources No Data
  • 11. Risk Outputs Project Finish Distribution Graph Title Value Minimum 09 Feb 09 Maximum 13 Jul 09 Mean 27 Apr 09 Median 28 Apr 09 Mode 07 May 09 Max Hits 97 Std Deviation 27.59 Variance 761.5 Skewness -0.051
  • 13. Project Cost Distribution Graph Title Value Minimum $73,653,005 Maximum $73,660,741 Mean $73,656,672 Median $73,656,639 Mode $73,656,750 Max Hits 153 Std Deviation 1,319 Variance 1,739,116 Skewness 0.115 Kurtosis 2.878 Bar Width: $500
  • 14. Project NPV Distribution Graph Not Checked Project IRR Distribution Graph Not Checked Project Duration Sensitivity Tornado Graph The duration sensitivity of a task is a measure of the correlation between its duration and the duration (or dates) of the project (or a key task or summary).
  • 15. Project Cost Sensitivity Tornado Graph The cost sensitivity of a task is a measure of the correlation between its cost and the cost of the project (or a key task or summary).
  • 16. Project SSI Tornado Graph The schedule sensitivity index of a task is calculated by multiplying its criticality index by the ratio of its variance against the variance of the project (or key task).
  • 17. Project Criticality Tornado Graph The criticality index of a task is the proportion of the iterations in which it was critical.
  • 18. Project Cruciality Tornado Graph The cruciality of a task is calculated by multiplying its duration sensitivity by its criticality index.
  • 19. Risk Register Risk Register Summary Total Risks 10 Proposed Risks 0 Open Risks 10 High 4 Medium 3 Low 2 Negligible 1 Impacted (Closed) Risks 0 Managed (Closed) Risks 0 Rejected (Closed) Risks 0 Threats 9 Opportunities 1 Risk Scoring Probability Scale Very Low Low Medium High Very High Up to 10% 10% to 35% 35% to 60% 60% to 75% 75% or higher Impact Scales and Types Very Low Low Medium High Very High Schedule* Up to 30 30 to 60 60 to 90 90 to 180 180 or higher Cost* Up to $500,000 $500,000 to $1,000,000 $1,000,000 to $1,500,000 $1,500,000 to $2,500,000 $2,500,000 or higher Performance* Failure to meet a minor acceptance criteria Failure to meet more than one minor acceptance criteria Shortfall in meeting acceptance criteria Significant shortfall in meeting acceptance criteria Failure to meet acceptance criteria * means impact is used in scoring Probability and Impact Scoring (PID) Risk Score is based on: Highest Impact Impact
  • 20. Very Low Low Medium High Very High Very High 5 9 18 36 72 High 4 7 14 28 56 Medium 3 5 10 20 40 Low 2 3 6 12 24 Very Low 1 1 2 4 8 Key Up to 7 7 to 23 23 or higher Risk Matrix Pre-Mitigation Very Low Low Medium High Very High Very High 10 - Reuse previous design work High 5 - Power outtage, 3 - Attack on pipeline 4 - Key resource unavailable Medium 7 - Rework required for assembly and integration Low 8 - Testing fails 9 - Design changes 1 - Poor understanding and detail in specification Very Low 2 - Auxilary pump system failure
  • 21. Post-Mitigation Very Low Low Medium High Very High Very High High 5 - Power outtage 9 - Design changes 10 - Reuse previous design work Medium Low 8 - Testing fails 3 - Attack on pipeline Very Low 4 - Key resource unavailable, 1 - Poor understanding and detail in specification Risks ID Title 4 Key resource unavailable Status Owner Open DP RBS Start Date End Date Exposure Project Level Impact.Crude Flow 07 Jan 2006 07 Jan 2006 $0 Cause Effect Due to other project commitments. Delay could occur on completion of key activities. Description Key resources may be unavailable.
  • 22. Pre-mitigation Score 56 High Post-mitigation Score 1 Low Qualitative Quantitative Pre- mitigation H 67% Post- mitigation VL 5% Qualitative Schedule Pre-mitigation L Post-mitigation L Cost Pre-mitigation L Post-mitigation L Performance Pre-mitigation VH Post-mitigation L Mitigation Title: Change resource assignment policy Description Source additional specialists Responsibility DP Status Proposed Mitigated Cost $4,500,000 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 12 Dec 2005 Target Finish Date 12 Dec 2005 Description Overbook key resources Responsibility DP Status Proposed Mitigated Cost $3,250,000 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 03 Jan 2006 Target Finish Date 03 Jan 2006 Description Increase contract incentive Responsibility DP Status Proposed Mitigated Cost $800,000 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 07 Jan 2006 Target Finish Date 07 Jan 2006 Risk Plan: Pre-mitigation Impacting Task: A340 - Production Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333 Impacting Task: A330 - Main pipline to terminal Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333 Impacting Task: A260 - Production pumps Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333
  • 23. Risk Plan: Post-mitigation Impacting Task: A340 - Production Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333 Impacting Task: A330 - Main pipline to terminal Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333 Impacting Task: A260 - Production pumps Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333
  • 24. ID Title 10 Reuse previous design work Status Owner Open TS RBS Start Date End Date Exposure Project Level Impact.Gas separation 12 Oct 2005 12 Oct 2005 $0 Cause Effect Due to the similar nature of the design. Saving time and money during the initial design phase. Description It may be possible to use designs created for previous project. Pre-mitigation Score 36 High Post-mitigation Score 28 High Qualitative Quantitative Pre- mitigation VH 87% Post- mitigation H 67% Qualitative Schedule Pre-mitigation M Post-mitigation M Cost Pre-mitigation H Post-mitigation H Performance Pre-mitigation N Post-mitigation N Risk Plan: Pre-mitigation Impacting Task: A330 - Main pipline to terminal Schedule Triangle 60 75 90 Cost Triangle $1,500,000 $2,000,000 $2,500,000 Risk Plan: Post-mitigation Impacting Task: A330 - Main pipline to terminal Schedule Triangle 60 75 90 Cost Triangle $1,500,000 $2,000,000 $2,500,000
  • 25. ID Title 5 Power outtage Status Owner Open TR RBS Start Date End Date Exposure Project Level Impact 05 Jan 2006 05 Jan 2006 $0 Cause Effect Government power plant failure. Power dependent activities will be delayed. Description It may be necessary to find an alternative or supplemental power source. Pre-mitigation Score 28 High Post-mitigation Score 4 Low Qualitative Quantitative Pre- mitigation H 67% Post- mitigation H 67% Qualitative Schedule Pre-mitigation H Post-mitigation VL Cost Pre-mitigation H Post-mitigation N Performance Pre-mitigation VL Post-mitigation N Mitigation Title: Source alternative power supply Description Source suitable uninterruptible power generators Responsibility TR Status Planned Mitigated Cost $4,000,000 Actual Cost $0 TaskID A420 Task Description Source suitable uninterruptible power generators Start Date 12 Oct 2005 Finish Date 01 Nov 2005 Target Start Date 30 Dec 1899 Target Finish Date 30 Dec 1899 Description Expedite delivery Responsibility TR Status Planned Mitigated Cost $250,000 Actual Cost $0 TaskID A410 Task Description Expedite delivery Start Date 02 Nov 2005 Finish Date 17 Nov 2005 Target Start Date 30 Dec 1899 Target Finish Date 30 Dec 1899 Description Vendor fees for travel and installation Responsibility TR Status Planned Mitigated Cost $60 Actual Cost $0 TaskID A400 Task Description Vendor installation Start Date 18 Nov 2005 Finish Date 24 Nov 2005 Target Start Date 30 Dec 1899 Target Finish Date 30 Dec 1899
  • 26. Risk Plan: Pre-mitigation Impacting Task: A180 - FWKO Tank Schedule Triangle 9 13 18 Cost Triangle $150,000 $200,000 $250,000 Impacting Task: A190 - Main water tank Schedule Triangle 9 13 18 Cost Triangle $150,000 $200,000 $250,000 Impacting Task: A200 - Secondary water tank Schedule Triangle 9 13 18 Cost Triangle $150,000 $200,000 $250,000 Impacting Task: A210 - Auxilary pumps Schedule Triangle 9 13 18 Cost Triangle $150,000 $200,000 $250,000 Impacting Task: A220 - Water treatment facility Schedule Triangle 9 13 18 Cost Triangle $150,000 $200,000 $250,000 Impacting Task: A260 - Production pumps Schedule Triangle 9 13 18 Cost Triangle $150,000 $200,000 $250,000 Impacting Task: A250 - Production tanks Schedule Triangle 9 13 18 Cost Triangle $150,000 $200,000 $250,000 Impacting Task: A350 - Field production facility tests Schedule Triangle 9 13 18 Cost Triangle $150,000 $200,000 $250,000 Impacting Task: A360 - Level production tanks Schedule Triangle 9 13 18 Cost Triangle $150,000 $200,000 $250,000 Impacting Task: A370 - Level PS1 tanks Schedule Triangle 9 13 18 Cost Triangle $150,000 $200,000 $250,000
  • 27. Risk Plan: Post-mitigation Impacting Task: A180 - FWKO Tank Schedule Triangle 0 1 3 Cost Triangle $0 $0 $0 Impacting Task: A190 - Main water tank Schedule Triangle 0 1 3 Cost Triangle $0 $0 $0 Impacting Task: A200 - Secondary water tank Schedule Triangle 0 1 3 Cost Triangle $0 $0 $0 Impacting Task: A210 - Auxilary pumps Schedule Triangle 0 1 3 Cost Triangle $0 $0 $0 Impacting Task: A220 - Water treatment facility Schedule Triangle 0 1 3 Cost Triangle $0 $0 $0 Impacting Task: A260 - Production pumps Schedule Triangle 0 1 3 Cost Triangle $0 $0 $0 Impacting Task: A250 - Production tanks Schedule Triangle 0 1 3 Cost Triangle $0 $0 $0 Impacting Task: A350 - Field production facility tests Schedule Triangle 0 1 3 Cost Triangle $0 $0 $0 Impacting Task: A360 - Level production tanks Schedule Triangle 0 1 3 Cost Triangle $0 $0 $0 Impacting Task: A370 - Level PS1 tanks Schedule Triangle 0 1 3
  • 29. ID Title 3 Attack on pipeline Status Owner Open DP RBS Start Date End Date Exposure Project Level Impact.Production 15 Nov 2005 15 Nov 2005 $0 Cause Effect Due to lack of stability in the region local guerillas may attack the pipeline. Delay in bringing the field production facility online. Description Local guerilla groups have attacked other pipelines in the past. As a sort of ransome, they will repeatedly threaten to attack unless paid-off by the government or the foriegn contractors. Pre-mitigation Score 28 High Post-mitigation Score 12 Medium Qualitative Quantitative Pre- mitigation H 67% Post- mitigation L 22% Qualitative Schedule Pre-mitigation L Post-mitigation M Cost Pre-mitigation M Post-mitigation L Performance Pre-mitigation H Post-mitigation H Mitigation Title: Source extra security with local government Description Use standard form of contract Responsibility DP Status Proposed Mitigated Cost $400,000 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 01 Nov 2005 Target Finish Date 01 Nov 2005 Description Pre contract negotiation Responsibility DP Status Proposed Mitigated Cost $100,000 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 15 Nov 2005 Target Finish Date 15 Nov 2005 Risk Plan: Pre-mitigation Impacting Task: A380 - Open pipeline to terminal Schedule Triangle 15 22 30
  • 30. Cost Triangle $500,000 $625,000 $750,000 Impacting Task: A370 - Level PS1 tanks Schedule Triangle 15 22 30 Cost Triangle $500,000 $625,000 $750,000 Risk Plan: Post-mitigation Impacting Task: A380 - Open pipeline to terminal Schedule Triangle 30 37 45 Cost Triangle $250,000 $375,000 $500,000 Impacting Task: A370 - Level PS1 tanks Schedule Triangle 30 37 45 Cost Triangle $250,000 $375,000 $500,000
  • 31. ID Title 1 Poor understanding and detail in specification Status Owner Open TS RBS Start Date End Date Exposure Project Level Impact.Crude Flow 01 Nov 2006 01 Nov 2006 $0 Cause Effect Due to poor understanding and detail in the initial specification. Could delay the project schedule and increase cost. Description The design is more complex than expected. Pre-mitigation Score 12 Medium Post-mitigation Score 1 Low Qualitative Quantitative Pre- mitigation L 22% Post- mitigation VL 5% Qualitative Schedule Pre-mitigation H Post-mitigation L Cost Pre-mitigation M Post-mitigation L Performance Pre-mitigation VL Post-mitigation VL Mitigation Title: Introduce penalties for design changes Description Include penalties for any design changes Responsibility TS Status Proposed Mitigated Cost $10,000 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 01 Nov 2005 Target Finish Date 01 Nov 2005 Description Use supported design methodologies Responsibility TS Status Proposed Mitigated Cost $0 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 02 Jan 2006 Target Finish Date 02 Jan 2006 Risk Plan: Pre-mitigation Impacting Task: A270 - Pumpstation 1 Schedule Triangle 12 19 25
  • 32. Cost Triangle $142,857 $178,571 $214,286 Impacting Task: A280 - Pumpstation 2 Schedule Triangle 12 19 25 Cost Triangle $142,857 $178,571 $214,286 Impacting Task: A290 - Pumpstation 3 Schedule Triangle 12 19 25 Cost Triangle $142,857 $178,571 $214,286 Impacting Task: A300 - Pumpstation 4 Schedule Triangle 12 19 25 Cost Triangle $142,857 $178,571 $214,286 Impacting Task: A310 - Pumpstation 5 Schedule Triangle 12 19 25 Cost Triangle $142,857 $178,571 $214,286 Impacting Task: A320 - Depressurizing station Schedule Triangle 12 19 25 Cost Triangle $142,857 $178,571 $214,286 Impacting Task: A250 - Production tanks Schedule Triangle 12 19 25 Cost Triangle $142,857 $178,571 $214,286 Risk Plan: Post-mitigation Impacting Task: A270 - Pumpstation 1 Schedule Triangle 4 6 8 Cost Triangle $71,429 $107,143 $142,857 Impacting Task: A280 - Pumpstation 2 Schedule Triangle 4 6 8 Cost Triangle $71,429 $107,143 $142,857 Impacting Task: A290 - Pumpstation 3 Schedule Triangle 4 6 8 Cost Triangle $71,429 $107,143 $142,857 Impacting Task: A300 - Pumpstation 4
  • 33. Schedule Triangle 4 6 8 Cost Triangle $71,429 $107,143 $142,857 Impacting Task: A310 - Pumpstation 5 Schedule Triangle 4 6 8 Cost Triangle $71,429 $107,143 $142,857 Impacting Task: A320 - Depressurizing station Schedule Triangle 4 6 8 Cost Triangle $71,429 $107,143 $142,857 Impacting Task: A250 - Production tanks Schedule Triangle 4 6 8 Cost Triangle $71,429 $107,143 $142,857
  • 34. ID Title 7 Rework required for assembly and integration Status Owner Open BJ RBS Start Date End Date Exposure Project Level Impact 01 Nov 2006 01 Nov 2006 $0 Cause Effect Due to incorrect tolerances in manufacturing. Which would delay the time taken to complete the assembly. Description The assembly may need to be reworked to allow a satisfactory integration of the components. Pre-mitigation Score 10 Medium Post-mitigation Score 0 Negligible Qualitative Quantitative Pre- mitigation M 47% Post- mitigation N 0% Qualitative Schedule Pre-mitigation M Post-mitigation M Cost Pre-mitigation M Post-mitigation M Performance Pre-mitigation L Post-mitigation L Mitigation Title: Check manufacturing tolerances Description Check all manufacturing equipment can handle required tolerances Responsibility BJ Status Proposed Mitigated Cost $200,000 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 01 Nov 2005 Target Finish Date 01 Nov 2005 Description Communicate importance of tolerances to manufacturing Responsibility BJ Status Proposed Mitigated Cost $0 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 02 Jan 2006 Target Finish Date 02 Jan 2006 Risk Plan: Pre-mitigation Impacting Task: A140 - High pressure stack Schedule Triangle 15 18 22
  • 35. Cost Triangle $250,000 $312,500 $375,000 Impacting Task: A150 - Low pressure stack Schedule Triangle 15 18 22 Cost Triangle $250,000 $312,500 $375,000 Impacting Task: A160 - Gas separator Schedule Triangle 15 18 22 Cost Triangle $250,000 $312,500 $375,000 Impacting Task: A180 - FWKO Tank Schedule Triangle 15 18 22 Cost Triangle $250,000 $312,500 $375,000 Risk Plan: Post-mitigation Impacting Task: A140 - High pressure stack Schedule Triangle 15 18 22 Cost Triangle $250,000 $312,500 $375,000 Impacting Task: A150 - Low pressure stack Schedule Triangle 15 18 22 Cost Triangle $250,000 $312,500 $375,000 Impacting Task: A160 - Gas separator Schedule Triangle 15 18 22 Cost Triangle $250,000 $312,500 $375,000 Impacting Task: A180 - FWKO Tank Schedule Triangle 15 18 22 Cost Triangle $250,000 $312,500 $375,000
  • 36. ID Title 2 Auxilary pump system failure Status Owner Open RB RBS Start Date End Date Exposure Project Level Impact.Water Flow 02 Jan 2006 02 Jan 2006 $0 Cause Effect Due to the novel nature of the auxilary pump system. Auxilary pump system would need to be modified. Description There may be a major failure of auxilary pump system. Pre-mitigation Score 8 Medium Post-mitigation Score 0 Negligible Qualitative Quantitative Pre- mitigation VL 5% Post- mitigation N 0% Qualitative Schedule Pre-mitigation VH Post-mitigation VH Cost Pre-mitigation VH Post-mitigation VH Performance Pre-mitigation VH Post-mitigation VH Mitigation Title: Improve initial specification Description Spend more money on the initial specification Responsibility RB Status Proposed Mitigated Cost $250,000 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 10 Nov 2005 Target Finish Date 10 Nov 2005 Description Use off-the-shelf pump systems Responsibility RB Status Proposed Mitigated Cost $500,000 Actual Cost $0 TaskID Task Description undefined Start Date 12 Oct 2005 Finish Date 12 Oct 2005 Target Start Date 02 Jan 2006 Target Finish Date 02 Jan 2006 Risk Plan: Pre-mitigation Impacting Task: A210 - Auxilary pumps Schedule Triangle 90 135 180
  • 37. Cost Triangle $1,250,000 $1,875,000 $2,500,000 Impacting Task: A220 - Water treatment facility Schedule Triangle 90 135 180 Cost Triangle $1,250,000 $1,875,000 $2,500,000 Risk Plan: Post-mitigation Impacting Task: A210 - Auxilary pumps Schedule Triangle 90 135 180 Cost Triangle $1,250,000 $1,875,000 $2,500,000 Impacting Task: A220 - Water treatment facility Schedule Triangle 90 135 180 Cost Triangle $1,250,000 $1,875,000 $2,500,000
  • 38. ID Title 9 Design changes Status Owner Open LM RBS Start Date End Date Exposure Project Level Impact.Gas separation 12 Oct 2005 12 Oct 2005 $0 Cause Effect Due to client changing their mind. Which would delay the schedule. Description The design needs to be altered. Pre-mitigation Score 6 Low Post-mitigation Score 14 Medium Qualitative Quantitative Pre- mitigation L 22% Post- mitigation H 67% Qualitative Schedule Pre-mitigation M Post-mitigation M Cost Pre-mitigation M Post-mitigation M Performance Pre-mitigation N Post-mitigation N Risk Plan: Pre-mitigation Impacting Task: A140 - High pressure stack Schedule Triangle 20 25 30 Cost Triangle $333,333 $416,667 $500,000 Impacting Task: A150 - Low pressure stack Schedule Triangle 20 25 30 Cost Triangle $333,333 $416,667 $500,000 Impacting Task: A160 - Gas separator Schedule Triangle 20 25 30 Cost Triangle $333,333 $416,667 $500,000
  • 39. Risk Plan: Post-mitigation Impacting Task: A140 - High pressure stack Schedule Triangle 20 25 30 Cost Triangle $333,333 $416,667 $500,000 Impacting Task: A150 - Low pressure stack Schedule Triangle 20 25 30 Cost Triangle $333,333 $416,667 $500,000 Impacting Task: A160 - Gas separator Schedule Triangle 20 25 30 Cost Triangle $333,333 $416,667 $500,000
  • 40. ID Title 8 Testing fails Status Owner Open LM RBS Start Date End Date Exposure Project Level Impact.Production 12 Oct 2005 12 Oct 2005 $0 Cause Effect Due to problems in design and fabrication. Rework would be required and retesting would need to take place. Description Testing fails to meet the clients performance criteria. Pre-mitigation Score 3 Low Post-mitigation Score 3 Low Qualitative Quantitative Pre- mitigation L 22% Post- mitigation L 22% Qualitative Schedule Pre-mitigation L Post-mitigation L Cost Pre-mitigation L Post-mitigation L Performance Pre-mitigation N Post-mitigation N Risk Plan: Pre-mitigation Impacting Task: A350 - Field production facility tests Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333 Impacting Task: A360 - Level production tanks Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333 Impacting Task: A370 - Level PS1 tanks Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333 Risk Plan: Post-mitigation
  • 41. Impacting Task: A350 - Field production facility tests Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333 Impacting Task: A360 - Level production tanks Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333 Impacting Task: A370 - Level PS1 tanks Schedule Triangle 10 15 20 Cost Triangle $166,667 $250,000 $333,333
  • 42. ID Title 6 Fabrication contractor goes bust Status Owner Open TR RBS Start Date End Date Exposure Project Level Impact 12 Oct 2005 12 Oct 2005 $0 Cause Effect Due to poor business conditions in the current fabrication market. A new fabrication company would need to be sourced causing delay to the fabrication tasks. Description The fabrication contractor may go bust. Pre-mitigation Score 0 Negligible Post-mitigation Score 0 Negligible Qualitative Quantitative Pre- mitigation N 0% Post- mitigation N 0% Qualitative Schedule Pre-mitigation M Post-mitigation M Cost Pre-mitigation M Post-mitigation M Performance Pre-mitigation M Post-mitigation M Risk Plan: Pre-mitigation Impacting Task: A170 - Water Flow Schedule Triangle 30 37 45 Cost Triangle $500,000 $625,000 $750,000 Impacting Task: A240 - Crude Flow Schedule Triangle 30 37 45 Cost Triangle $500,000 $625,000 $750,000 Risk Plan: Post-mitigation Impacting Task: A170 - Water Flow Schedule Triangle 30 37 45 Cost Triangle $500,000 $625,000 $750,000
  • 43. Impacting Task: A240 - Crude Flow Schedule Triangle 30 37 45 Cost Triangle $500,000 $625,000 $750,000
  • 45. 13 Feb 06 28 Jun 07 09 Nov 08 Time 0 20,000,000 40,000,000 60,000,000 Cumulative Resource Flow for Cost Filter: Entire Plan Mean P0
  • 46. Analysis Simulation: Latin Hypercu... Iterations: 1000 Correlation Pearson's 58.4% Spearman's 57.7% Highlighters x-axis 50% (28 Apr 0... y-axis 50% ($73,656... Inside both li... 36% Outside both l... 35% 1 % 3 % 17 Feb 09 28 May 09 Entire Plan: Finish 50% $73,654,000 $73,656,000 $73,658,000 $73,660,000 EntirePlan:Cost 50% DownstreamOG Deterministic Point Inside both limits Outside both limits
  • 47. Data NPV of: Entire Plan Discount Rate: 0% Analysis Simulation: Latin Hypercube Iterations: 1000 Convergence at mean Mean Plan Finish Date: Converged in 0 iterations (variation < 1% over 100 iterations) Mean Total Plan Cost: Converged in 0 iterations (variation < 1% over 100 iterations) Statistics Minimum: $73,653,005 Maximum: $73,660,741 Mean: $73,656,672 Median: $73,656,639 Mode: $73,656,750 Max Hits: 153 Std Deviation: 1,319 Variance: 1,739,116 Skewness: 0.115 Kurtosis: 2.878 Bar Width: $500 Highlighters 20% $73,657,767 Deterministic 96% 50% $73,656,639 80% $73,655,501 $73,660,000 Distribution (start of interval) 0 50 100 150 Hits 0% $73,660,741 5% $73,658,881 10% $73,658,306 15% $73,658,044 20% $73,657,767 25% $73,657,572 30% $73,657,398 35% $73,657,166 40% $73,656,986 45% $73,656,818 50% $73,656,639 55% $73,656,497 60% $73,656,291 65% $73,656,151 70% $73,655,926 75% $73,655,752 80% $73,655,501 85% $73,655,336 90% $73,655,033 95% $73,654,514 100% $73,653,005 CumulativeFrequency DownstreamOG Entire Plan : NPV
  • 48. Data Cost of: Entire Plan Analysis Simulation: Latin Hypercube Iterations: 1000 Convergence at mean Mean Plan Finish Date: Converged in 0 iterations (variation < 1% over 100 iterations) Mean Total Plan Cost: Converged in 0 iterations (variation < 1% over 100 iterations) Statistics Minimum: $73,653,005 Maximum: $73,660,741 Mean: $73,656,672 Median: $73,656,639 Mode: $73,656,750 Max Hits: 153 Std Deviation: 1,319 Variance: 1,739,116 Skewness: 0.115 Kurtosis: 2.878 Bar Width: $500 Highlighters 50% $73,656,639 20% $73,655,501 Deterministic 4% 50% $73,656,639 80% $73,657,767 $73,660,000 Distribution (start of interval) 0 50 100 150 Hits 0% $73,653,005 5% $73,654,502 10% $73,655,033 15% $73,655,334 20% $73,655,501 25% $73,655,752 30% $73,655,926 35% $73,656,151 40% $73,656,291 45% $73,656,497 50% $73,656,639 55% $73,656,818 60% $73,656,986 65% $73,657,166 70% $73,657,398 75% $73,657,572 80% $73,657,767 85% $73,658,044 90% $73,658,306 95% $73,658,881 100% $73,660,741 CumulativeFrequency DownstreamOG Entire Plan : Cost
  • 49. Data Duration of: Entire Plan Analysis Simulation: Latin Hypercu... Iterations: 1000 Convergence at mean Mean Plan Finish Date: Converged in 0 iterations (variation < 1% over 100 iteratio... Mean Total Plan Cost: Converged in 0 iterations (variation < 1% over 100 iteratio... Statistics Minimum: 1217 Maximum: 1371 Mean: 1294 Median: 1295 Mode: 1299 Max Hits: 103 Std Deviation: 27.59 Variance: 761.5 Skewness: -0.051 Kurtosis: 2.599 Bar Width: week Highlighters Deterministic 5% 50% 1295 80% 1317 Distribution (start of interval) 0 50 100 Hits 0% 1217 5% 1248 10% 1259 15% 1263 20% 1269 25% 1274 30% 1277 35% 1282 40% 1288 45% 1290 50% 1295 55% 1298 60% 1302 65% 1305 70% 1310 75% 1315 80% 1317 85% 1324 90% 1330 95% 1338 100% 1371 CumulativeFrequency DownstreamOG Entire Plan : Duration
  • 50. Data Finish Date of: Entire Plan Analysis Simulation: Latin Hypercube Iterations: 1000 Convergence at mean Mean Plan Finish Date: Converged in 0 iterations (variation < 1% over 100 iterations) Mean Total Plan Cost: Converged in 0 iterations (variation < 1% over 100 iterations) Statistics Minimum: 09 Feb 09 Maximum: 13 Jul 09 Mean: 27 Apr 09 Median: 28 Apr 09 Mode: 07 May 09 Max Hits: 97 Std Deviation: 27.59 Variance: 761.5 Skewness: -0.051 Kurtosis: 2.599 Bar Width: week Highlighters 20% 02 Apr 09 Deterministic 5% 50% 28 Apr 09 80% 20 May 09 17 Feb 09 Distribution (start of interval) 0 50 100 Hits 0% 09 Feb 09 5% 12 Mar 09 10% 23 Mar 09 15% 27 Mar 09 20% 02 Apr 09 25% 07 Apr 09 30% 10 Apr 09 35% 15 Apr 09 40% 21 Apr 09 45% 23 Apr 09 50% 28 Apr 09 55% 01 May 09 60% 05 May 09 65% 08 May 09 70% 13 May 09 75% 18 May 09 80% 20 May 09 85% 27 May 09 90% 02 Jun 09 95% 10 Jun 09 100% 13 Jul 09 CumulativeFrequency DownstreamOG Entire Plan : Finish Date