ALGERIA
DYWIDAG International GmbH member of group.
ALGERIA
METRO D’ALGER LIGNE 1 - 3éme PHASE
lot 1:EXTENSION C
Hai El Badr – Ain Naadja 2
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
STAKEHOLDERS:
• CLIENT :
• CONSULTANT: MIT
• CONTRACTORS:
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
INICIAL CONTRACT VALUE: 61.766.766
€
ESTIMATED CONTRACT VALUE:
83.547.479 €
EXECUTION TIME : June 2015
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
DYWIDAG MAIN WORKS:
• D1 – Retaining Walls and Viaduct.
• D2 – Excavation and Retaining walls.
• D3 – Halte Ateliers Station.
• D4 –Tunnel and Ventilation Pit.
• D5 – Ain Naadja Station.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
PROJECT:
• D1 – Retain Walls and Viaduct.
• D1.1 / D1.3 – 203 m
• D1.2 – Viaduct » » 133 m.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D1 – Retain Walls and Viaduct.
• QUANTITIES OF THE MAIN WORKS
EXCAVATION/ BACKFILLING (m3
) 57.920
PILES WORKS (m) 4.593
ANCRAGES (m) 1.302
CONCRETE (m3
) 5.260
FORMWORK (m2
) 8.919
STEEL WORKS (kg) 1.083.458
PRESTRESSED (kNm) 5.351.128
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D1 – Retain Walls and Viaduct.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D1 – Retain Walls and Viaduct.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D1 – Retain Walls and Viaduct.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
PROJECT:
• D2 – Excavation and Retaining walls.
• D2.21/ D2.2.2 / D2.2.3
– 277 m
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D2 – Excavation and Retaining walls.
• QUANTITIES OF THE MAIN WORKS
EXCAVATION/ BACKFILLING (m3
) 50.277
PILES WORKS (m) 2.475
ANCRAGES (m) 1.700
CONCRETE (m3
) 3.302
FORMWORK (m2
) 3.164
STEEL WORKS (kg) 540.304
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D2 – Excavation and Retaining walls.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
PROJECT:
• D3 – Halte Ateliers Station.
• D3 – 110 m
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D3 – Halte Ateliers Station.
• QUANTITIES OF THE MAIN WORKS
EXCAVATION/ BACKFILLING (m3
) 43.282
PILES WORKS (m) 2.127
ANCRAGES (m) 1.901
CONCRETE (m3
) 5.329
FORMWORK (m2
) 6.723
STEEL WORKS (kg) 838.367
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D3 – Halte Ateliers Station.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
PROJECT:
• D4 –Tunnel and Ventilation Pit.
• D4.6/4.7/4.8 – 834 m
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D4 –Tunnel and Ventilation Pit.
• QUANTITIES OF THE MAIN WORKS
EXCAVATION NATM (m3
) 75.713
STEEL PROFILES (kg) 466.628
CONCRETE (m3
) 22.799
SEALING SYSTEMS (m2
) 18.487
FORMWORK (m2
) 21.721
STEEL WORKS (kg) 1.390.896
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D4 –Tunnel and Ventilation Pit.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D4 –Tunnel and Ventilation Pit.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D4 –Tunnel and Ventilation Pit.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D4 –Tunnel and Ventilation Pit.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
PROJECT:
• D5 – Ain Naadja Station.
• D5 – 115 m
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D5 – Ain Naadja Station.
• QUANTITIES OF THE MAIN WORKS
EXCAVATION/ BACKFILLING (m3
) 108.322
PILES WORKS (m) 11.385
ANCRAGES (m) 61.842
CONCRETE (m3
) 18.828
FORMWORK (m2
) 24.627
STEEL WORKS (kg) 2.824.134
PRECAST BEAMS (m) 3.724
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D5 – Ain Naadja Station.
• MAIN DATES:
o SITE INSTALLATION ……………………………… 11 FEBRUARY 2012
o PILE WORKS ………………………………………. 05 MARCH 2012
o ANCRAGE WORKS ……………………………… 29 MAY 2012
o SLAB AXIS 1 to 5 ……………………………....... 07 MAY 2013
o END OF EXCAVATION …………………………. 05 AUGUST 2013
o END OF WORKS …………… ……………………. 31 MARCH 2015
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D5 – Ain Naadja Station.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D5 – Ain Naadja Station.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D5 – Ain Naadja Station.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D5 – Ain Naadja Station.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
• D5 – Ain Naadja Station.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
D5 – Ain Naadja Station.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
D5 – Ain Naadja Station.
LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
END

More Related Content

Similar to STRABAG-Algiers_Metro

FINAL YEAR DIPLOMA PROJECT (ESTIMATION, PLANNING AND DESIGNING OF PROPOSED SC...
FINAL YEAR DIPLOMA PROJECT (ESTIMATION, PLANNING AND DESIGNING OF PROPOSED SC...FINAL YEAR DIPLOMA PROJECT (ESTIMATION, PLANNING AND DESIGNING OF PROPOSED SC...
FINAL YEAR DIPLOMA PROJECT (ESTIMATION, PLANNING AND DESIGNING OF PROPOSED SC...
JeslinJose8
 
02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS
Mary Calkins
 
Semimechanization sdls&lh ds
Semimechanization sdls&lh dsSemimechanization sdls&lh ds
Semimechanization sdls&lh dsSATYANARAYANA I
 
02_Determination_of_Quantities.pdf
02_Determination_of_Quantities.pdf02_Determination_of_Quantities.pdf
02_Determination_of_Quantities.pdf
kiransreekumar6
 
02_Determination_of_Quantities.pdf
02_Determination_of_Quantities.pdf02_Determination_of_Quantities.pdf
02_Determination_of_Quantities.pdf
kiransreekumar6
 
Wisma atlet asiangameskemayoran-bahandirjen.3feb2016
Wisma atlet asiangameskemayoran-bahandirjen.3feb2016Wisma atlet asiangameskemayoran-bahandirjen.3feb2016
Wisma atlet asiangameskemayoran-bahandirjen.3feb2016
galih wahyu
 
Review file
Review fileReview file
Review file
mages_muni2
 
Method Statement Kota Kasablanka 3
Method Statement Kota Kasablanka 3Method Statement Kota Kasablanka 3
Method Statement Kota Kasablanka 3Panji Krisnamurti
 
EarthQuake Reistant Building
EarthQuake Reistant BuildingEarthQuake Reistant Building
EarthQuake Reistant Building
Hemant Srivastava
 
Wael Portofolio___Dec_2016 REDUCED
Wael Portofolio___Dec_2016 REDUCEDWael Portofolio___Dec_2016 REDUCED
Wael Portofolio___Dec_2016 REDUCEDwael elbana
 
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide ToolsFlank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
IRJET Journal
 
Prima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptxPrima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptx
Ziyad Zaidi
 
M.i tank
M.i  tankM.i  tank
M.i tank
beerappa143
 

Similar to STRABAG-Algiers_Metro (20)

FINAL YEAR DIPLOMA PROJECT (ESTIMATION, PLANNING AND DESIGNING OF PROPOSED SC...
FINAL YEAR DIPLOMA PROJECT (ESTIMATION, PLANNING AND DESIGNING OF PROPOSED SC...FINAL YEAR DIPLOMA PROJECT (ESTIMATION, PLANNING AND DESIGNING OF PROPOSED SC...
FINAL YEAR DIPLOMA PROJECT (ESTIMATION, PLANNING AND DESIGNING OF PROPOSED SC...
 
02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS
 
Semimechanization sdls&lh ds
Semimechanization sdls&lh dsSemimechanization sdls&lh ds
Semimechanization sdls&lh ds
 
RESUME-01
RESUME-01RESUME-01
RESUME-01
 
02_Determination_of_Quantities.pdf
02_Determination_of_Quantities.pdf02_Determination_of_Quantities.pdf
02_Determination_of_Quantities.pdf
 
02_Determination_of_Quantities.pdf
02_Determination_of_Quantities.pdf02_Determination_of_Quantities.pdf
02_Determination_of_Quantities.pdf
 
Wisma atlet asiangameskemayoran-bahandirjen.3feb2016
Wisma atlet asiangameskemayoran-bahandirjen.3feb2016Wisma atlet asiangameskemayoran-bahandirjen.3feb2016
Wisma atlet asiangameskemayoran-bahandirjen.3feb2016
 
Review file
Review fileReview file
Review file
 
SMHB
SMHBSMHB
SMHB
 
Method Statement Kota Kasablanka 3
Method Statement Kota Kasablanka 3Method Statement Kota Kasablanka 3
Method Statement Kota Kasablanka 3
 
EarthQuake Reistant Building
EarthQuake Reistant BuildingEarthQuake Reistant Building
EarthQuake Reistant Building
 
Wael Portofolio___Dec_2016 REDUCED
Wael Portofolio___Dec_2016 REDUCEDWael Portofolio___Dec_2016 REDUCED
Wael Portofolio___Dec_2016 REDUCED
 
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide ToolsFlank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
Flank Wear Measurement of INCONEL 825 using CVD and PVD Carbide Tools
 
Report
ReportReport
Report
 
Prima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptxPrima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptx
 
C.V
C.VC.V
C.V
 
reda cv EN
reda cv ENreda cv EN
reda cv EN
 
PG Thesis Presentation
PG Thesis PresentationPG Thesis Presentation
PG Thesis Presentation
 
M.i tank
M.i  tankM.i  tank
M.i tank
 
CV Yasin
CV YasinCV Yasin
CV Yasin
 

STRABAG-Algiers_Metro

  • 2. ALGERIA METRO D’ALGER LIGNE 1 - 3éme PHASE lot 1:EXTENSION C Hai El Badr – Ain Naadja 2
  • 3. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 STAKEHOLDERS: • CLIENT : • CONSULTANT: MIT • CONTRACTORS:
  • 4. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 INICIAL CONTRACT VALUE: 61.766.766 € ESTIMATED CONTRACT VALUE: 83.547.479 € EXECUTION TIME : June 2015
  • 5. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2
  • 6. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 DYWIDAG MAIN WORKS: • D1 – Retaining Walls and Viaduct. • D2 – Excavation and Retaining walls. • D3 – Halte Ateliers Station. • D4 –Tunnel and Ventilation Pit. • D5 – Ain Naadja Station.
  • 7. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 PROJECT: • D1 – Retain Walls and Viaduct. • D1.1 / D1.3 – 203 m • D1.2 – Viaduct » » 133 m.
  • 8. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D1 – Retain Walls and Viaduct. • QUANTITIES OF THE MAIN WORKS EXCAVATION/ BACKFILLING (m3 ) 57.920 PILES WORKS (m) 4.593 ANCRAGES (m) 1.302 CONCRETE (m3 ) 5.260 FORMWORK (m2 ) 8.919 STEEL WORKS (kg) 1.083.458 PRESTRESSED (kNm) 5.351.128
  • 9. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D1 – Retain Walls and Viaduct.
  • 10. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D1 – Retain Walls and Viaduct.
  • 11. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D1 – Retain Walls and Viaduct.
  • 12. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 PROJECT: • D2 – Excavation and Retaining walls. • D2.21/ D2.2.2 / D2.2.3 – 277 m
  • 13. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D2 – Excavation and Retaining walls. • QUANTITIES OF THE MAIN WORKS EXCAVATION/ BACKFILLING (m3 ) 50.277 PILES WORKS (m) 2.475 ANCRAGES (m) 1.700 CONCRETE (m3 ) 3.302 FORMWORK (m2 ) 3.164 STEEL WORKS (kg) 540.304
  • 14. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D2 – Excavation and Retaining walls.
  • 15. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 PROJECT: • D3 – Halte Ateliers Station. • D3 – 110 m
  • 16. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D3 – Halte Ateliers Station. • QUANTITIES OF THE MAIN WORKS EXCAVATION/ BACKFILLING (m3 ) 43.282 PILES WORKS (m) 2.127 ANCRAGES (m) 1.901 CONCRETE (m3 ) 5.329 FORMWORK (m2 ) 6.723 STEEL WORKS (kg) 838.367
  • 17. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D3 – Halte Ateliers Station.
  • 18. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 PROJECT: • D4 –Tunnel and Ventilation Pit. • D4.6/4.7/4.8 – 834 m
  • 19. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D4 –Tunnel and Ventilation Pit. • QUANTITIES OF THE MAIN WORKS EXCAVATION NATM (m3 ) 75.713 STEEL PROFILES (kg) 466.628 CONCRETE (m3 ) 22.799 SEALING SYSTEMS (m2 ) 18.487 FORMWORK (m2 ) 21.721 STEEL WORKS (kg) 1.390.896
  • 20. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D4 –Tunnel and Ventilation Pit.
  • 21. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D4 –Tunnel and Ventilation Pit.
  • 22. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D4 –Tunnel and Ventilation Pit.
  • 23. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D4 –Tunnel and Ventilation Pit.
  • 24. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 PROJECT: • D5 – Ain Naadja Station. • D5 – 115 m
  • 25. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D5 – Ain Naadja Station. • QUANTITIES OF THE MAIN WORKS EXCAVATION/ BACKFILLING (m3 ) 108.322 PILES WORKS (m) 11.385 ANCRAGES (m) 61.842 CONCRETE (m3 ) 18.828 FORMWORK (m2 ) 24.627 STEEL WORKS (kg) 2.824.134 PRECAST BEAMS (m) 3.724
  • 26. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D5 – Ain Naadja Station. • MAIN DATES: o SITE INSTALLATION ……………………………… 11 FEBRUARY 2012 o PILE WORKS ………………………………………. 05 MARCH 2012 o ANCRAGE WORKS ……………………………… 29 MAY 2012 o SLAB AXIS 1 to 5 ……………………………....... 07 MAY 2013 o END OF EXCAVATION …………………………. 05 AUGUST 2013 o END OF WORKS …………… ……………………. 31 MARCH 2015
  • 27. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D5 – Ain Naadja Station.
  • 28. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D5 – Ain Naadja Station.
  • 29. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D5 – Ain Naadja Station.
  • 30. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D5 – Ain Naadja Station.
  • 31. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 • D5 – Ain Naadja Station.
  • 32. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 D5 – Ain Naadja Station.
  • 33. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 D5 – Ain Naadja Station.
  • 34. LINE 1 – SECTION HAI EL BADR – AIN NAADJA 2 END

Editor's Notes

  1. 83.547.479 – 50.483.294= 33.064.185 / 16 meses »» 2.066.511 €