Welcome to Phase 3 of Sherwood Close
July 2021
Here, we will tell you about…
Latimer and our wider organisation
An overview of Phase 3 of the Sherwood Close
project
Our response to local housing needs in Ealing.
Our plans for green spaces at Phase 3 of Sherwood
Close
Our approach to transport and access issues
Our programme and next steps
Our approach to working with existing residents and
neighbouring communities
How you can tell us your opinions on our plans
We are Latimer Developments, owned by
Clarion Housing Group
Latimer Developments is the development arm of
Clarion Housing Group.
Alongside Latimer, we have the UK’s largest
Housing Association, a charitable foundation,
Clarion Futures and a repairs and maintenance
service, Clarion Response.
Together, our aim is to:
• Build affordable homes, helping people get on
the property ladder.
• Continually improve design, construction
and sustainability of homes.
• Support residents into work and training through
Clarion Futures.
• Invest £150 million over 10 years through the
work of Clarion Futures.
Clarion Response Clarion Housing
Association
Clarion Futures Latimer Developments
Who is Clarion Housing Group?
• William Richard Sutton was the founder of
Sutton and Co, general carriers, in 1861.
• During his life, he grew the business to 600
branches, with partnerships supplying wines,
tea, coffee and tobacco.
• When he passed away in 1900, he placed most
of his considerable wealth into philanthropic
trusts for housing of the poor.
• The Sutton Model Dwellings Trust, now known
as Clarion Housing Group, was founded and built
estates for those in need across England.
• This started in Bethnal Green, then Chelsea,
Islington, Rotherhithe, Plymouth and
Birmingham.
• In 1939, at the outbreak of the Second World
War, the Trust housed over 32,000 people.
• Today, Clarion manages more than 125,000
affordable homes across the country
• Sherwood Close is in West Ealing, London
Borough of Ealing
• Postcode is W13 9YH
• It’s located to the south of West Ealing
Railway Station which is around a 7
minute walk
• Sherwood Close was previously known as
the Dean Gardens Estate
• It is north of Northfields tube station
which is around 15 minutes walk
Welcome to Sherwood Close. We are here!
• Dean Gardens was a 1970s housing estate owned by Ealing Council
• Over 30 years later, the housing was no longer suitable for today's living standards
• Ealing Council decided to bring the estate and its 209 homes up to the Decent Homes
Standard in 2008
• New plans were prepared for the estate, involving residents, neighbours, local stakeholders
and Ealing Council, renaming it Sherwood Close. Clarion was selected as the preferred
partner to deliver the new proposals
• Sherwood Close had three phases, all securing planning permission in 2015
• Development began on site in August 2016
• Phase 1 is complete and residents moved back into the first 71 homes in spring 2019
• Phase 2 is currently under construction, including 106 homes, to complete in Autumn 2022
• Phase 3 has planning permission to demolish the existing building and provide 142 private
sale homes
The history of Sherwood Close…
Views of the original Dean Gardens Estate,
now demolished
What does Phase 3 of Sherwood Close look like now?
The Sherwood Close Phase 3 site boundary is highlighted
in pink.
It currently includes:
• The last remaining former Dean Gardens Estate block,
Target House, an 8 story block with 47 residential units
(see inset image)
• Surface car parking
• A temporary generator
• The construction compound for Phase 2
Target House. To be demolished under Phase 3 proposals
What does the existing planning permission for Phase 3 of
Sherwood Close look like?
▪ Phase 3 has planning permission (2015) to demolish
Target House and provide 142 homes across two
building ranging in height from 7 to 9 storeys
▪ Current Phase 3 plans include:
Only one pedestrian-only through route to Northfield
Avenue, between the existing residential gardens on
Tawny Close and the proposed building. The other
route serves as an entrance to an under-croft car park
Steps up to the buildings from Northfield Avenue,
which would not be accessible to all
A smaller pocket park but no other publically
assessable green space
A building close to the southern boundary
A long block of 9 storeys height along Northfield
Avenue, which we feel could be improved to create a
more interesting set of buildings
Small pocket park (Not to scale)
Pedestrian-only route
Vehicular access to car park
Non-level access points Concept image of the consented 7 and
9 storey buildings
Time has passed since the original permission was granted in 2015.
With the successful delivery of Phase 1 and with Phase 2 now under construction
(see images), we see this an opportunity to revisit and improve the Phase 3 plans.
We are proposing to make the following improvements:
• Provide more homes, increasing from 142 to 185
• Provide more public green space
• Provide better permeability for pedestrians and cyclists
• Deliver a more interesting massing of buildings
• Deliver improved layouts of homes to fit modern living
• Adhere to the latest planning policies e.g. safety; sustainability; cycles
We are consulting local residents and stakeholders again to get your feedback on
our revised proposals for Phase 3. This will help us prepare a new and updated
planning application.
We are consulting now on our proposed improved Phase
3 plans…
Phase 1 completed 2019
Artist impression Phase 2, subject to changes
What we have done so far in developing our proposals
for an improved Phase 3…
Initial feasibility pre-
application meeting* with LB
Ealing planning officers to
discuss the concept
Autumn 2020
Selection of design team
Winter 2020 / 2021
Two formal pre-application
meetings* with LB Ealing
planning officers to seek
feedback and develop
proposals
Spring – Summer 2021
Proposals presented to LB
Ealing’s Design Review
Panel** for feedback on the
proposed height, massing and
overall scheme design
Summer 2021
*A pre-application meeting is where an applicant can meet with LB Ealing
planning officers to discuss proposals in advance of submitting final plans.
It gives an opportunity for planning officers to feedback on the proposals
and for the applicant to make changes in response to any feedback
provided.
**The Ealing Design Review Panel provides independent, objective, expert
advice on development proposals across Ealing. It provides advice to
scheme promoters and the planning authority as a ‘critical friend’ to
support delivery of high quality development.
Generally, schemes are referred to the panel by planning officers at
an early stage to identify and consider the key assumptions of the
proposed design.
Introducing our new plans for Phase 3 of Sherwood Close
Drawing is artists impression, final design will be subject to change
Our Phase 3 proposals include:
• 185 homes in three buildings of
varying size:
• 6 storeys
• 9 storeys
• Part 14 storeys, reducing
to part 9 storeys
• 17 car parking spaces
• An enhanced pocket park
• A new communal garden
• Narrow pedestrian route off
Tawny Close removed and
replaced by two more generous
pedestrian through routes to
Northfield Avenue
• All access points proposed to be
level access
• Increased building set-back from
the southern boundary
Pocket park
Landscaped pedestrian link to Northfield Avenue
Community garden and pedestrian link to Northfield
Avenue
Public realm
Private outdoor spaces with landscaped boundaries
Native hedgerow & ecological planting to Northfield
Avenue
Car parking
Our proposed emerging masterplan for Phase 3
3
Key
6
5
4
3
2
1
1
5
7
3
4
6
2
5
Concept image of our vision
View from Dean Gardens (North)
Concept image only. Final design will be subject to change
Concept image of our vision
Tawny Street Looking South
Concept image only. Final design will be subject to change
Concept image of our vision
View from Northfield Avenue
(North East)
Concept image only. Final design will be subject to change
A mix of housing types and tenures across the whole
of Sherwood Close…
Key
Houses (social rented)
Maisonettes (social rented)
Apartments (social rented)
Apartments (social rented & shared ownership)
Apartments (shared ownership)
Apartments (private sale)
Private gardens
Phase 3 will deliver the final element of the mix, with
our proposals including 185 private sale apartments,
ranging in size from 1 Bedroom homes to 3 Bedroom
homes.
Phase
3
Phase
3
Phase 1
A mix of housing tenures across the whole of
Sherwood Close
There is a mix of tenures across the whole of Sherwood Close designed to
meet local need and support a sustainable mixed community.
Approximately 50% of housing (*habitable rooms) across the whole of
Sherwood Close will be affordable.
Affordable Housing
Two types of affordable housing are provided in Phases 1 and 2. These
comprise:
• Social Rent: Rented to residents at 100% of prescribed target rent.
• Shared ownership: Residents purchase a share of the property and pay a
subsidised rent on the rest. They can buy a larger share at a later date or sell
and move on.
Leaseholder
This is where owners of homes within the existing Target House have opted to
purchase a new home within the new development at the same value as their
existing home.
Private Sale
We are now proposing 185 private sale homes within Phase 3, up from
the currently consented 142 private sale homes. The private sale homes
help to deliver the new affordable homes, which will all be delivered first
as part of Phases 1 and 2.
Tenure type Number of Homes
Social Rent 111
Shared Ownership 60
Private Sale 142 (Currently approved)
185 (New proposals)
+43 Homes
Leaseholder 6
Total 319 (Currently approved)
362 (New proposals)
+43 homes
*A habitable room is usually defined as: “any room used or intended to be
used for sleeping, cooking, living or eating.” e.g. bedroom, kitchen, living
room
Making green spaces a key feature
Green space is vitally important to
wellbeing and healthy living, so we have
developed a landscape-led masterplan
which proposes to:
• Provide an improved landscaped
communal public space for the whole
neighbourhood including:
• An enhanced pocket park for
community use
• A new community garden
• Play space and seating opportunities
• Incorporate green roofs and Sustainable
Urban Drainage features which enhances
biodiversity and adds value to the design
Sustainable travel & connectivity
We will promote walking and
cycling through:
• Creating new connections and
routes through the site.
• Shared surfaces on a
pedestrian-first basis.
• Providing an appropriate
balance of car parking provision
and secure cycle storage.
• Developing a site that is already
well connected to public
transport routes.
N
We also encourage low carbon transport
Electric vehicles
We support sustainable travel and
the Government’s commitment to
transfer to electric cars by 2030:
• Electric vehicle charging points in at
least 20% of communal car parking
spaces across the development.
• Further infrastructure for future
charging point connections.
Cycling
Our proposals also include adequate
cycle storage to make cycling an easier
option for residents.
Key
Parallel parking
On street parking
Parking court
Cycle store
Phase
3
Phase 1
Construction traffic and access to the site
• The whole masterplan has been
under construction since 2016.
• Phase 2 is due to be completed
in Autumn 2022.
• Phase 3 is planned in early 2023
and would complete in Summer
of 2025.
• Construction access will primarily
be from Northfield Avenue
similar to Phase 2.
Key
Phase 1
Phase 2
Phase 3
Construction
access
Benefits and opportunities for local communities
An inclusive and sustainable new residential community
across the phases:
• A mix of homes for rent, shared ownership and sale
• Well designed high quality homes across the phases
New green spaces for the whole community:
• Enhanced pocket park
• Usable and sustainable community garden that facilitates
local interest in growing
• Young children’s play space
Helping reduce our environmental impact:
• Electric car charging points
• Encouraging walking and cycling
• Sustainable urban drainage solutions (SUDs)
• Biodiverse planting
• Green roofs
• Solar panels
Our approach to working with communities
Throughout the project, we have actively consulted, researched
and engaged to identify and deliver locally specific objectives
covering social, economic and environmental issues. We want to
continue this approach.
We welcome your thoughts and ideas on how we could work with
the local community in London Borough of Ealing.
This could include opportunities through:
• Training and employment
• Health and Wellbeing
• Social isolation and loneliness
• Youth engagement and education programmes
• Homelessness
• Environmental enhancement
• Business support
• Charity support
Examples of community relationship building
• Working with Clarion Futures, to support people with skills and employment
opportunities.
• Engaging local education institutes for work related learning activities so the
development becomes a unique learning opportunity.
• Community fund and sponsorship access to fund local initiatives, bringing
communities and local groups to our development.
• Skilled volunteering enabling us to share our varied skills and expertise with
communities including mentoring.
• Becoming Trustees at educational institutes and third sector organisations
which may require additional strategic support.
• Awarding tenders with local business and suppliers where feasible and possible.
• Encouraging communities to take ownership of their environment following project
completion, with support in place to facilitate this.
Wewanttobuildstrongcommunityrelationshipsandmaximisebenefitsforlocals.Ourcommunitycollaborationisongoing throughoutdevelopment
(before,duringandafter).Examplesofourinitiativesinclude:
Our programme and next steps
SPRING
2021
SPRING
2023
Public
consultation
Validation and
statutory
consultation
period
Final
approval
Target start on
site
Planning
submission to LBE
SPRING
2021
SPRING
2022
WINTER
2021
WINTER
2021
Review of feedback
received
Application heard
at Planning
Committee
AUTUMN
2021
Communicate
scheme changes /
updates
SUMMER
2021
SUMMER
2021
AUTUMN
2021
We want ongoing dialogue with you…
We like to be visible and accessible, offering ongoing communication, updating you on development progress as well as
opportunities. Wedo this in different ways throughout delivery of our projects, for example:
Regular project update newsletters, with digital options posted on the project-specific website.
Regular meetings held with the Latimer delivery team.
Noticeboards with key contact personnel details including in emergencies so you can contact us when you need to.
A dedicated community engagement officer and regeneration manager will be on hand to help resolve concerns and find
opportunities to collaborate with the community.
Tell us what you think and ask us any questions…
Our current planning consultation is open until 27th August 2021. We welcome your feedback. Tell us what you think in the way that
suits you. You can:
Under this planning consultation, all
comments will be considered carefully as
we design our planning application for
submission in Autumn 2021.
We want to continue a conversation with
our communities throughout our
planning and construction phases and
beyond, so please register so we can stay
in touch with you!
Register your interest in our project at www.clarionconsults.co.uk
Take our quick survey to tell us what you think
Contact us with your questions
Attend one of our webinars
Show us on a map what is important to you near our site
REGISTER
Thank you for visiting us!

More Related Content

What's hot

Mvat community hall presentation rev3
Mvat community hall presentation rev3Mvat community hall presentation rev3
Mvat community hall presentation rev3mccadmin
 
Board of Aldermen Presentation 11/11/13
Board of Aldermen Presentation 11/11/13Board of Aldermen Presentation 11/11/13
Board of Aldermen Presentation 11/11/13dangrossman
 
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...Fairfax County
 
12_Certificate_Baily Garner LLP_Aya
12_Certificate_Baily Garner LLP_Aya12_Certificate_Baily Garner LLP_Aya
12_Certificate_Baily Garner LLP_AyaAya Irin
 
Vancouver Centre Case Study
Vancouver Centre Case StudyVancouver Centre Case Study
Vancouver Centre Case StudyJon Vehlow
 
Wesley mimico june 26, 2012 repurpose renew add
Wesley mimico june 26, 2012  repurpose renew addWesley mimico june 26, 2012  repurpose renew add
Wesley mimico june 26, 2012 repurpose renew addrwtobiassen
 
RE developement of Bhindhi baazar
RE developement of Bhindhi baazarRE developement of Bhindhi baazar
RE developement of Bhindhi baazarYash Agrawal
 
Tantallon tweaks slideshow nwcc
Tantallon tweaks slideshow nwccTantallon tweaks slideshow nwcc
Tantallon tweaks slideshow nwccMarcus Garnet
 
Eastgate Neighborhood Plan Amendment - Developer Presentation
Eastgate Neighborhood Plan Amendment - Developer PresentationEastgate Neighborhood Plan Amendment - Developer Presentation
Eastgate Neighborhood Plan Amendment - Developer PresentationCity of College Station
 
University Town Center Rezoning - Developer Presentation
University Town Center Rezoning - Developer PresentationUniversity Town Center Rezoning - Developer Presentation
University Town Center Rezoning - Developer PresentationCity of College Station
 
Union Square Open Space Plan
Union Square Open Space PlanUnion Square Open Space Plan
Union Square Open Space PlanRob May
 

What's hot (17)

Mvat community hall presentation rev3
Mvat community hall presentation rev3Mvat community hall presentation rev3
Mvat community hall presentation rev3
 
Board of Aldermen Presentation 11/11/13
Board of Aldermen Presentation 11/11/13Board of Aldermen Presentation 11/11/13
Board of Aldermen Presentation 11/11/13
 
FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
 
Wellborn Zoning Districts
Wellborn Zoning DistrictsWellborn Zoning Districts
Wellborn Zoning Districts
 
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
 
12_Certificate_Baily Garner LLP_Aya
12_Certificate_Baily Garner LLP_Aya12_Certificate_Baily Garner LLP_Aya
12_Certificate_Baily Garner LLP_Aya
 
Housing design in the North
Housing design in the NorthHousing design in the North
Housing design in the North
 
Vancouver Centre Case Study
Vancouver Centre Case StudyVancouver Centre Case Study
Vancouver Centre Case Study
 
Wesley mimico june 26, 2012 repurpose renew add
Wesley mimico june 26, 2012  repurpose renew addWesley mimico june 26, 2012  repurpose renew add
Wesley mimico june 26, 2012 repurpose renew add
 
Gaap info
Gaap infoGaap info
Gaap info
 
RE developement of Bhindhi baazar
RE developement of Bhindhi baazarRE developement of Bhindhi baazar
RE developement of Bhindhi baazar
 
Tantallon tweaks slideshow nwcc
Tantallon tweaks slideshow nwccTantallon tweaks slideshow nwcc
Tantallon tweaks slideshow nwcc
 
Woburn Park Design Guidelines
Woburn Park Design GuidelinesWoburn Park Design Guidelines
Woburn Park Design Guidelines
 
Eastgate Neighborhood Plan Amendment - Developer Presentation
Eastgate Neighborhood Plan Amendment - Developer PresentationEastgate Neighborhood Plan Amendment - Developer Presentation
Eastgate Neighborhood Plan Amendment - Developer Presentation
 
University Town Center Rezoning - Developer Presentation
University Town Center Rezoning - Developer PresentationUniversity Town Center Rezoning - Developer Presentation
University Town Center Rezoning - Developer Presentation
 
Craig Kelley, Housing Development Center
Craig Kelley, Housing Development CenterCraig Kelley, Housing Development Center
Craig Kelley, Housing Development Center
 
Union Square Open Space Plan
Union Square Open Space PlanUnion Square Open Space Plan
Union Square Open Space Plan
 

Similar to Sherwood Close Phase 3 Ealing

Dorking Station Approach Consultation Slides.pdf
Dorking Station Approach Consultation Slides.pdfDorking Station Approach Consultation Slides.pdf
Dorking Station Approach Consultation Slides.pdfkevinduxbury
 
Dorking St Ap Public Cons Stage 1 V8.pdf
Dorking St Ap Public Cons Stage 1 V8.pdfDorking St Ap Public Cons Stage 1 V8.pdf
Dorking St Ap Public Cons Stage 1 V8.pdfNiamh60
 
High Path Regeneration Update
High Path Regeneration UpdateHigh Path Regeneration Update
High Path Regeneration Updatekevinduxbury
 
Small sites -large potential
Small sites   -large potentialSmall sites   -large potential
Small sites -large potentialCiarán Cuffe
 
15-6-9 DH Development CV
15-6-9 DH Development CV15-6-9 DH Development CV
15-6-9 DH Development CVDavid Hunt
 
Louise wymandelivering quality_places
Louise wymandelivering quality_placesLouise wymandelivering quality_places
Louise wymandelivering quality_placesDesign South East
 
15-6-9 DH Development CV
15-6-9 DH Development CV15-6-9 DH Development CV
15-6-9 DH Development CVDavid Hunt
 
Place RESI 2014: Kevin McGeough, Homes & Communities Agency
Place RESI 2014: Kevin McGeough, Homes & Communities AgencyPlace RESI 2014: Kevin McGeough, Homes & Communities Agency
Place RESI 2014: Kevin McGeough, Homes & Communities AgencyPlace North West
 
Adam Roberts Consultancy - Property Development Services
Adam Roberts Consultancy - Property Development ServicesAdam Roberts Consultancy - Property Development Services
Adam Roberts Consultancy - Property Development ServicesDenny Adam
 
Equis Lake Design Guidelines Brochure
Equis Lake Design Guidelines BrochureEquis Lake Design Guidelines Brochure
Equis Lake Design Guidelines BrochureEquisLake the Vine
 
City council presentation 05.14.12 revised
City council presentation 05.14.12 revisedCity council presentation 05.14.12 revised
City council presentation 05.14.12 revisedcityofevanston
 
Hyde Housing's Public Consultation document 9 April 2014
Hyde Housing's Public Consultation document 9 April 2014Hyde Housing's Public Consultation document 9 April 2014
Hyde Housing's Public Consultation document 9 April 2014Davigdor Towerblock
 
Stage 13 revised design guidelines grand vista release
Stage 13 revised design guidelines grand vista releaseStage 13 revised design guidelines grand vista release
Stage 13 revised design guidelines grand vista releaseProvidence Ripley Valley
 

Similar to Sherwood Close Phase 3 Ealing (20)

Dorking Station Approach Consultation Slides.pdf
Dorking Station Approach Consultation Slides.pdfDorking Station Approach Consultation Slides.pdf
Dorking Station Approach Consultation Slides.pdf
 
Dorking St Ap Public Cons Stage 1 V8.pdf
Dorking St Ap Public Cons Stage 1 V8.pdfDorking St Ap Public Cons Stage 1 V8.pdf
Dorking St Ap Public Cons Stage 1 V8.pdf
 
High Path Regeneration Update
High Path Regeneration UpdateHigh Path Regeneration Update
High Path Regeneration Update
 
Small sites -large potential
Small sites   -large potentialSmall sites   -large potential
Small sites -large potential
 
15-6-9 DH Development CV
15-6-9 DH Development CV15-6-9 DH Development CV
15-6-9 DH Development CV
 
Louise wymandelivering quality_places
Louise wymandelivering quality_placesLouise wymandelivering quality_places
Louise wymandelivering quality_places
 
15-6-9 DH Development CV
15-6-9 DH Development CV15-6-9 DH Development CV
15-6-9 DH Development CV
 
141203 presentation woden valley community council
141203   presentation woden valley community council141203   presentation woden valley community council
141203 presentation woden valley community council
 
Practice Profile
Practice ProfilePractice Profile
Practice Profile
 
Place RESI 2014: Kevin McGeough, Homes & Communities Agency
Place RESI 2014: Kevin McGeough, Homes & Communities AgencyPlace RESI 2014: Kevin McGeough, Homes & Communities Agency
Place RESI 2014: Kevin McGeough, Homes & Communities Agency
 
Adam Roberts Consultancy - Property Development Services
Adam Roberts Consultancy - Property Development ServicesAdam Roberts Consultancy - Property Development Services
Adam Roberts Consultancy - Property Development Services
 
JG Molloy Brochure - Building On Our Reputation
JG Molloy Brochure - Building On Our ReputationJG Molloy Brochure - Building On Our Reputation
JG Molloy Brochure - Building On Our Reputation
 
Equis Lake Design Guidelines Brochure
Equis Lake Design Guidelines BrochureEquis Lake Design Guidelines Brochure
Equis Lake Design Guidelines Brochure
 
City council presentation 05.14.12 revised
City council presentation 05.14.12 revisedCity council presentation 05.14.12 revised
City council presentation 05.14.12 revised
 
Hyde Housing's Public Consultation document 9 April 2014
Hyde Housing's Public Consultation document 9 April 2014Hyde Housing's Public Consultation document 9 April 2014
Hyde Housing's Public Consultation document 9 April 2014
 
Stage 13 revised design guidelines grand vista release
Stage 13 revised design guidelines grand vista releaseStage 13 revised design guidelines grand vista release
Stage 13 revised design guidelines grand vista release
 
7 Bromley
7 Bromley7 Bromley
7 Bromley
 
housingk-171005105018.pdf
housingk-171005105018.pdfhousingk-171005105018.pdf
housingk-171005105018.pdf
 
Housing
Housing Housing
Housing
 
Village green release design guidelines
Village green release design guidelinesVillage green release design guidelines
Village green release design guidelines
 

Recently uploaded

Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiMalviyaNagarCallGirl
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCRsoniya singh
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxAbhayThakur200703
 
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxBanana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxgeorgebrinton95
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756dollysharma2066
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 

Recently uploaded (20)

Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptx
 
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxBanana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 

Sherwood Close Phase 3 Ealing

  • 1. Building Homes. Developingfutures. Drawing is artist impression, final design will be subject to change Welcome to Phase 3 of Sherwood Close July 2021
  • 2. Here, we will tell you about… Latimer and our wider organisation An overview of Phase 3 of the Sherwood Close project Our response to local housing needs in Ealing. Our plans for green spaces at Phase 3 of Sherwood Close Our approach to transport and access issues Our programme and next steps Our approach to working with existing residents and neighbouring communities How you can tell us your opinions on our plans
  • 3. We are Latimer Developments, owned by Clarion Housing Group Latimer Developments is the development arm of Clarion Housing Group. Alongside Latimer, we have the UK’s largest Housing Association, a charitable foundation, Clarion Futures and a repairs and maintenance service, Clarion Response. Together, our aim is to: • Build affordable homes, helping people get on the property ladder. • Continually improve design, construction and sustainability of homes. • Support residents into work and training through Clarion Futures. • Invest £150 million over 10 years through the work of Clarion Futures. Clarion Response Clarion Housing Association Clarion Futures Latimer Developments
  • 4. Who is Clarion Housing Group? • William Richard Sutton was the founder of Sutton and Co, general carriers, in 1861. • During his life, he grew the business to 600 branches, with partnerships supplying wines, tea, coffee and tobacco. • When he passed away in 1900, he placed most of his considerable wealth into philanthropic trusts for housing of the poor. • The Sutton Model Dwellings Trust, now known as Clarion Housing Group, was founded and built estates for those in need across England. • This started in Bethnal Green, then Chelsea, Islington, Rotherhithe, Plymouth and Birmingham. • In 1939, at the outbreak of the Second World War, the Trust housed over 32,000 people. • Today, Clarion manages more than 125,000 affordable homes across the country
  • 5. • Sherwood Close is in West Ealing, London Borough of Ealing • Postcode is W13 9YH • It’s located to the south of West Ealing Railway Station which is around a 7 minute walk • Sherwood Close was previously known as the Dean Gardens Estate • It is north of Northfields tube station which is around 15 minutes walk Welcome to Sherwood Close. We are here!
  • 6. • Dean Gardens was a 1970s housing estate owned by Ealing Council • Over 30 years later, the housing was no longer suitable for today's living standards • Ealing Council decided to bring the estate and its 209 homes up to the Decent Homes Standard in 2008 • New plans were prepared for the estate, involving residents, neighbours, local stakeholders and Ealing Council, renaming it Sherwood Close. Clarion was selected as the preferred partner to deliver the new proposals • Sherwood Close had three phases, all securing planning permission in 2015 • Development began on site in August 2016 • Phase 1 is complete and residents moved back into the first 71 homes in spring 2019 • Phase 2 is currently under construction, including 106 homes, to complete in Autumn 2022 • Phase 3 has planning permission to demolish the existing building and provide 142 private sale homes The history of Sherwood Close… Views of the original Dean Gardens Estate, now demolished
  • 7. What does Phase 3 of Sherwood Close look like now? The Sherwood Close Phase 3 site boundary is highlighted in pink. It currently includes: • The last remaining former Dean Gardens Estate block, Target House, an 8 story block with 47 residential units (see inset image) • Surface car parking • A temporary generator • The construction compound for Phase 2 Target House. To be demolished under Phase 3 proposals
  • 8. What does the existing planning permission for Phase 3 of Sherwood Close look like? ▪ Phase 3 has planning permission (2015) to demolish Target House and provide 142 homes across two building ranging in height from 7 to 9 storeys ▪ Current Phase 3 plans include: Only one pedestrian-only through route to Northfield Avenue, between the existing residential gardens on Tawny Close and the proposed building. The other route serves as an entrance to an under-croft car park Steps up to the buildings from Northfield Avenue, which would not be accessible to all A smaller pocket park but no other publically assessable green space A building close to the southern boundary A long block of 9 storeys height along Northfield Avenue, which we feel could be improved to create a more interesting set of buildings Small pocket park (Not to scale) Pedestrian-only route Vehicular access to car park Non-level access points Concept image of the consented 7 and 9 storey buildings
  • 9. Time has passed since the original permission was granted in 2015. With the successful delivery of Phase 1 and with Phase 2 now under construction (see images), we see this an opportunity to revisit and improve the Phase 3 plans. We are proposing to make the following improvements: • Provide more homes, increasing from 142 to 185 • Provide more public green space • Provide better permeability for pedestrians and cyclists • Deliver a more interesting massing of buildings • Deliver improved layouts of homes to fit modern living • Adhere to the latest planning policies e.g. safety; sustainability; cycles We are consulting local residents and stakeholders again to get your feedback on our revised proposals for Phase 3. This will help us prepare a new and updated planning application. We are consulting now on our proposed improved Phase 3 plans… Phase 1 completed 2019 Artist impression Phase 2, subject to changes
  • 10. What we have done so far in developing our proposals for an improved Phase 3… Initial feasibility pre- application meeting* with LB Ealing planning officers to discuss the concept Autumn 2020 Selection of design team Winter 2020 / 2021 Two formal pre-application meetings* with LB Ealing planning officers to seek feedback and develop proposals Spring – Summer 2021 Proposals presented to LB Ealing’s Design Review Panel** for feedback on the proposed height, massing and overall scheme design Summer 2021 *A pre-application meeting is where an applicant can meet with LB Ealing planning officers to discuss proposals in advance of submitting final plans. It gives an opportunity for planning officers to feedback on the proposals and for the applicant to make changes in response to any feedback provided. **The Ealing Design Review Panel provides independent, objective, expert advice on development proposals across Ealing. It provides advice to scheme promoters and the planning authority as a ‘critical friend’ to support delivery of high quality development. Generally, schemes are referred to the panel by planning officers at an early stage to identify and consider the key assumptions of the proposed design.
  • 11. Introducing our new plans for Phase 3 of Sherwood Close Drawing is artists impression, final design will be subject to change Our Phase 3 proposals include: • 185 homes in three buildings of varying size: • 6 storeys • 9 storeys • Part 14 storeys, reducing to part 9 storeys • 17 car parking spaces • An enhanced pocket park • A new communal garden • Narrow pedestrian route off Tawny Close removed and replaced by two more generous pedestrian through routes to Northfield Avenue • All access points proposed to be level access • Increased building set-back from the southern boundary
  • 12. Pocket park Landscaped pedestrian link to Northfield Avenue Community garden and pedestrian link to Northfield Avenue Public realm Private outdoor spaces with landscaped boundaries Native hedgerow & ecological planting to Northfield Avenue Car parking Our proposed emerging masterplan for Phase 3 3 Key 6 5 4 3 2 1 1 5 7 3 4 6 2 5
  • 13. Concept image of our vision View from Dean Gardens (North) Concept image only. Final design will be subject to change
  • 14. Concept image of our vision Tawny Street Looking South Concept image only. Final design will be subject to change
  • 15. Concept image of our vision View from Northfield Avenue (North East) Concept image only. Final design will be subject to change
  • 16. A mix of housing types and tenures across the whole of Sherwood Close… Key Houses (social rented) Maisonettes (social rented) Apartments (social rented) Apartments (social rented & shared ownership) Apartments (shared ownership) Apartments (private sale) Private gardens Phase 3 will deliver the final element of the mix, with our proposals including 185 private sale apartments, ranging in size from 1 Bedroom homes to 3 Bedroom homes. Phase 3 Phase 3 Phase 1
  • 17. A mix of housing tenures across the whole of Sherwood Close There is a mix of tenures across the whole of Sherwood Close designed to meet local need and support a sustainable mixed community. Approximately 50% of housing (*habitable rooms) across the whole of Sherwood Close will be affordable. Affordable Housing Two types of affordable housing are provided in Phases 1 and 2. These comprise: • Social Rent: Rented to residents at 100% of prescribed target rent. • Shared ownership: Residents purchase a share of the property and pay a subsidised rent on the rest. They can buy a larger share at a later date or sell and move on. Leaseholder This is where owners of homes within the existing Target House have opted to purchase a new home within the new development at the same value as their existing home. Private Sale We are now proposing 185 private sale homes within Phase 3, up from the currently consented 142 private sale homes. The private sale homes help to deliver the new affordable homes, which will all be delivered first as part of Phases 1 and 2. Tenure type Number of Homes Social Rent 111 Shared Ownership 60 Private Sale 142 (Currently approved) 185 (New proposals) +43 Homes Leaseholder 6 Total 319 (Currently approved) 362 (New proposals) +43 homes *A habitable room is usually defined as: “any room used or intended to be used for sleeping, cooking, living or eating.” e.g. bedroom, kitchen, living room
  • 18. Making green spaces a key feature Green space is vitally important to wellbeing and healthy living, so we have developed a landscape-led masterplan which proposes to: • Provide an improved landscaped communal public space for the whole neighbourhood including: • An enhanced pocket park for community use • A new community garden • Play space and seating opportunities • Incorporate green roofs and Sustainable Urban Drainage features which enhances biodiversity and adds value to the design
  • 19. Sustainable travel & connectivity We will promote walking and cycling through: • Creating new connections and routes through the site. • Shared surfaces on a pedestrian-first basis. • Providing an appropriate balance of car parking provision and secure cycle storage. • Developing a site that is already well connected to public transport routes. N
  • 20. We also encourage low carbon transport Electric vehicles We support sustainable travel and the Government’s commitment to transfer to electric cars by 2030: • Electric vehicle charging points in at least 20% of communal car parking spaces across the development. • Further infrastructure for future charging point connections. Cycling Our proposals also include adequate cycle storage to make cycling an easier option for residents. Key Parallel parking On street parking Parking court Cycle store Phase 3 Phase 1
  • 21. Construction traffic and access to the site • The whole masterplan has been under construction since 2016. • Phase 2 is due to be completed in Autumn 2022. • Phase 3 is planned in early 2023 and would complete in Summer of 2025. • Construction access will primarily be from Northfield Avenue similar to Phase 2. Key Phase 1 Phase 2 Phase 3 Construction access
  • 22. Benefits and opportunities for local communities An inclusive and sustainable new residential community across the phases: • A mix of homes for rent, shared ownership and sale • Well designed high quality homes across the phases New green spaces for the whole community: • Enhanced pocket park • Usable and sustainable community garden that facilitates local interest in growing • Young children’s play space Helping reduce our environmental impact: • Electric car charging points • Encouraging walking and cycling • Sustainable urban drainage solutions (SUDs) • Biodiverse planting • Green roofs • Solar panels
  • 23. Our approach to working with communities Throughout the project, we have actively consulted, researched and engaged to identify and deliver locally specific objectives covering social, economic and environmental issues. We want to continue this approach. We welcome your thoughts and ideas on how we could work with the local community in London Borough of Ealing. This could include opportunities through: • Training and employment • Health and Wellbeing • Social isolation and loneliness • Youth engagement and education programmes • Homelessness • Environmental enhancement • Business support • Charity support
  • 24. Examples of community relationship building • Working with Clarion Futures, to support people with skills and employment opportunities. • Engaging local education institutes for work related learning activities so the development becomes a unique learning opportunity. • Community fund and sponsorship access to fund local initiatives, bringing communities and local groups to our development. • Skilled volunteering enabling us to share our varied skills and expertise with communities including mentoring. • Becoming Trustees at educational institutes and third sector organisations which may require additional strategic support. • Awarding tenders with local business and suppliers where feasible and possible. • Encouraging communities to take ownership of their environment following project completion, with support in place to facilitate this. Wewanttobuildstrongcommunityrelationshipsandmaximisebenefitsforlocals.Ourcommunitycollaborationisongoing throughoutdevelopment (before,duringandafter).Examplesofourinitiativesinclude:
  • 25. Our programme and next steps SPRING 2021 SPRING 2023 Public consultation Validation and statutory consultation period Final approval Target start on site Planning submission to LBE SPRING 2021 SPRING 2022 WINTER 2021 WINTER 2021 Review of feedback received Application heard at Planning Committee AUTUMN 2021 Communicate scheme changes / updates SUMMER 2021 SUMMER 2021 AUTUMN 2021
  • 26. We want ongoing dialogue with you… We like to be visible and accessible, offering ongoing communication, updating you on development progress as well as opportunities. Wedo this in different ways throughout delivery of our projects, for example: Regular project update newsletters, with digital options posted on the project-specific website. Regular meetings held with the Latimer delivery team. Noticeboards with key contact personnel details including in emergencies so you can contact us when you need to. A dedicated community engagement officer and regeneration manager will be on hand to help resolve concerns and find opportunities to collaborate with the community.
  • 27. Tell us what you think and ask us any questions… Our current planning consultation is open until 27th August 2021. We welcome your feedback. Tell us what you think in the way that suits you. You can: Under this planning consultation, all comments will be considered carefully as we design our planning application for submission in Autumn 2021. We want to continue a conversation with our communities throughout our planning and construction phases and beyond, so please register so we can stay in touch with you! Register your interest in our project at www.clarionconsults.co.uk Take our quick survey to tell us what you think Contact us with your questions Attend one of our webinars Show us on a map what is important to you near our site REGISTER
  • 28. Thank you for visiting us!