This project charter outlines an internship to evaluate and optimize the patient scheduling system at St. Joseph's Family Medicine Residency Program. The intern will analyze reasons patients are not seen in a timely manner, research other residency programs' scheduling models, and make suggestions to improve St. Joseph's system. The goals are to increase patient satisfaction by 25% and help St. Joseph's earn NCQA medical home certification. Over 12 weeks, the intern will define the project, analyze issues, summarize findings, propose solutions, and deliver a final report. Benefits include identifying scheduling barriers and enhancing patient access.
Philippines Field Management Training Program curriculum outlineSMDPalums
Outline of Two-module Management Training Curriculum for local public health program managers adapted from CDC's Sustainable Management Development Program (SMDP)
Project Management in Health and Human ServicesBrandon Olson
A presentation on applying a small-scale project management practice to the health and human services field. Presented at the 2014 Minnesota Social Services Association conference.
WBS ExampleWBS #Task DescriptionDuration (hours)Milestone (Y/N)Start DateEnd DateWork Effort 1 (hours)Resource 1Work Effort 2 (hours)Resource 2Starts After TaskComments1Prepare room0YMilestone tasks have 0 duration1.1Protect or remove furniture2N1-Jan1-Jan2Painter2Helper1.2Lay down canvas or plastic floor covering2N1-Jan1-Jan2Painter2Helper1.11.3Sand and scrape walls and ceiling4N1-Jan1-Jan4Painter4Helper1.22Paint room0YMilestone tasks have 0 duration2.1Paint ceiling2N2-Jan2-Jan2Painter1.32.2Paint walls4N2-Jan2-Jan4Painter2.12.3Paint doors, windows, and trim4N2-Jan3-Jan4Painter2.23Clean up room0Y3.1Remove protective materials1N4-Jan4-Jan1Helper2.2 + 1 dayAllow day for drying3.2Vacuum floors1N4-Jan4-Jan1Helper3.13.3Touch up missed spots1N4-Jan4-Jan1Painter3.1Can start at same time as 3.23.4Secure signoff from client1N5-Jan5-Jan1Owner3.2, 3.34Project complete0Y5-Jan5-Jan1OwnerMilestone tasks have 0 duration
Resource ExampleResource NameCost per HourCost per UnitTotal UnitsTotal CostCommentsPainter2519$475Helper1010$100Owner501$50Paint (gallons)155$75Other supplies1001$100TOTAL$800
Gantt Chart ExampleWBS #Task DescriptionDuration (hours)Milestone (Y/N)Start DateEnd Date11-Dec12-Dec13-Dec14-Dec15-Dec16-Dec17-Dec1. My Health eVet Registration0Y11-Dec12-Dec1.1.1.Clinical staff3N11-Dec11-Dec1.1.2Service members2N12-Dec12-Dec2Training4Y12-Dec16-Dec2.1.How to use the online portal4N12-Dec16-Dec2.1.1.Clinical staff2N12-Dec12-Dec2.1.2.Service members4N13-Dec13-Dec2.1.3.Existing Patients1N16-Dec16-Dec3HIPPA Compliance1N11-Dec15-Dec3.1Privacy Compliance documentation1N11-Dec11-Dec3.1.1. Ensure clinical staff have read and agree to HIPPA regulations1N13-Dec13-Dec3.1.2.Ensure service members have read and agree to HIPPA regulations1N15-Dec15-Dec4Computer Access for the patient4.1Purchase72Y11-Dec13-Dec4.1.1Interion privacy study Carrel TeakN4.1.2ComputersN4.1.3PrintersN4.2Installation4.2.1Property management install the booths4Y14-Dec14-Dec4.2.2IT Helpdesk install the computer and printers2Y15-Dec15-Dec
Network ExamplePrepare in Visio, PowerPoint, or on paper and scan in
Budget ExampleFixed Costs$10,000PhaselabormaterialsTOTAL COST2 interion Carrel Teak$800.00$3,000.00$3,800.002 Computers$0.00$3,500.00$3,500.002 Printers$0.00$500.00$500.00TOTAL$800.00$7,000.00GRAND TOTAL$7,800.00
<Project Name> Version: <1.0> <Draft>
Healthcare Community Outreach
HealthCare Community outreachproject Management plan
Version 1.5
12/17/2018
<Project Name> Project Management Plan Version: <1.0> <Draft>
[Insert appropriate disclaimer(s)]
Revision Date: Error! Unknown document property name.Page 2 of 21
CDC_UP_Project_Management_Plan_Template_v1.1.docVERSION HISTORY
Version #
Implemented
By
Revision
Date
Approved
By
Approval
Date
Reason
12/10/2018
Veteran Affairs System for the homeless and low -income individuals
12/10/2018
Veteran Affairs System for the homeless and low -income individuals
12/10/2018
Veteran Affairs System for the homeless and low -i ...
WQD2011 - Breakthrough Process Improvement - Tawam Hospital - The Surgical Ad...Dubai Quality Group
Breakthrough Process Improvement case study submitted by Tawam Hospital during 3rd Continual Improvement & Innovation Symposium organized by Dubai Quality Group's Continual Improvement Subgroup to celebrate World Quality Day 2011.
Philippines Field Management Training Program curriculum outlineSMDPalums
Outline of Two-module Management Training Curriculum for local public health program managers adapted from CDC's Sustainable Management Development Program (SMDP)
Project Management in Health and Human ServicesBrandon Olson
A presentation on applying a small-scale project management practice to the health and human services field. Presented at the 2014 Minnesota Social Services Association conference.
WBS ExampleWBS #Task DescriptionDuration (hours)Milestone (Y/N)Start DateEnd DateWork Effort 1 (hours)Resource 1Work Effort 2 (hours)Resource 2Starts After TaskComments1Prepare room0YMilestone tasks have 0 duration1.1Protect or remove furniture2N1-Jan1-Jan2Painter2Helper1.2Lay down canvas or plastic floor covering2N1-Jan1-Jan2Painter2Helper1.11.3Sand and scrape walls and ceiling4N1-Jan1-Jan4Painter4Helper1.22Paint room0YMilestone tasks have 0 duration2.1Paint ceiling2N2-Jan2-Jan2Painter1.32.2Paint walls4N2-Jan2-Jan4Painter2.12.3Paint doors, windows, and trim4N2-Jan3-Jan4Painter2.23Clean up room0Y3.1Remove protective materials1N4-Jan4-Jan1Helper2.2 + 1 dayAllow day for drying3.2Vacuum floors1N4-Jan4-Jan1Helper3.13.3Touch up missed spots1N4-Jan4-Jan1Painter3.1Can start at same time as 3.23.4Secure signoff from client1N5-Jan5-Jan1Owner3.2, 3.34Project complete0Y5-Jan5-Jan1OwnerMilestone tasks have 0 duration
Resource ExampleResource NameCost per HourCost per UnitTotal UnitsTotal CostCommentsPainter2519$475Helper1010$100Owner501$50Paint (gallons)155$75Other supplies1001$100TOTAL$800
Gantt Chart ExampleWBS #Task DescriptionDuration (hours)Milestone (Y/N)Start DateEnd Date11-Dec12-Dec13-Dec14-Dec15-Dec16-Dec17-Dec1. My Health eVet Registration0Y11-Dec12-Dec1.1.1.Clinical staff3N11-Dec11-Dec1.1.2Service members2N12-Dec12-Dec2Training4Y12-Dec16-Dec2.1.How to use the online portal4N12-Dec16-Dec2.1.1.Clinical staff2N12-Dec12-Dec2.1.2.Service members4N13-Dec13-Dec2.1.3.Existing Patients1N16-Dec16-Dec3HIPPA Compliance1N11-Dec15-Dec3.1Privacy Compliance documentation1N11-Dec11-Dec3.1.1. Ensure clinical staff have read and agree to HIPPA regulations1N13-Dec13-Dec3.1.2.Ensure service members have read and agree to HIPPA regulations1N15-Dec15-Dec4Computer Access for the patient4.1Purchase72Y11-Dec13-Dec4.1.1Interion privacy study Carrel TeakN4.1.2ComputersN4.1.3PrintersN4.2Installation4.2.1Property management install the booths4Y14-Dec14-Dec4.2.2IT Helpdesk install the computer and printers2Y15-Dec15-Dec
Network ExamplePrepare in Visio, PowerPoint, or on paper and scan in
Budget ExampleFixed Costs$10,000PhaselabormaterialsTOTAL COST2 interion Carrel Teak$800.00$3,000.00$3,800.002 Computers$0.00$3,500.00$3,500.002 Printers$0.00$500.00$500.00TOTAL$800.00$7,000.00GRAND TOTAL$7,800.00
<Project Name> Version: <1.0> <Draft>
Healthcare Community Outreach
HealthCare Community outreachproject Management plan
Version 1.5
12/17/2018
<Project Name> Project Management Plan Version: <1.0> <Draft>
[Insert appropriate disclaimer(s)]
Revision Date: Error! Unknown document property name.Page 2 of 21
CDC_UP_Project_Management_Plan_Template_v1.1.docVERSION HISTORY
Version #
Implemented
By
Revision
Date
Approved
By
Approval
Date
Reason
12/10/2018
Veteran Affairs System for the homeless and low -income individuals
12/10/2018
Veteran Affairs System for the homeless and low -income individuals
12/10/2018
Veteran Affairs System for the homeless and low -i ...
WQD2011 - Breakthrough Process Improvement - Tawam Hospital - The Surgical Ad...Dubai Quality Group
Breakthrough Process Improvement case study submitted by Tawam Hospital during 3rd Continual Improvement & Innovation Symposium organized by Dubai Quality Group's Continual Improvement Subgroup to celebrate World Quality Day 2011.
Scheduling System Optimization Project Chater Draft 04 13 11
1. Scheduling System Optimization
Project
St. Joseph’s Hospital Family Medicine Residency Program
Project Charter
Mariana Sabeva
Graduate Student - Intern
Masters of Health Sector Management
W. P. Carey School of Business
Arizona State University
Faculty Advisor:
Marjorie Baldwin, PhD
Site Supervisor:
Robert Garcia, MD
Associate Director, St. Joseph’s Family Medicine Residency Program
2. Scheduling System Optimization Project – Project Charter
Table of Contents
1. Executive Summary ............................................................................................................................................ 3
2. Project Overview ................................................................................................................................................. 4
A. Problem/Opportunity Statement .................................................................................................................... 4
B. Business Objectives and Goals ..................................................................................................................... 4
C. Project Description......................................................................................................................................... 4
D. Scope ............................................................................................................................................................. 5
E. Timeline ......................................................................................................................................................... 5
F. Benefits .......................................................................................................................................................... 5
3. Project Organization ........................................................................................................................................... 6
A. Organizational Structure .............................................................................................................................. 66
B. Project Roles and Phase End Approvers ...................................................................................................... 6
4. Major Assumptions, Risks and Dependencies ................................................................................................ 7
Project Charter v 1.0
Prepared by Mariana Sabeva Page 2 of 7
3. Scheduling System Optimization Project – Project Charter
1. Executive Summary
Starting on March 7, 2011 my internship project will take place at Peppertree Family Practice Center, St. Joseph
Hospital. I will work under the supervision of the medical director Robert Garcia, MD. The goal of the project I
will lead is to evaluate patient satisfaction with the process of scheduling appointments at the clinic.
Dr. Garcia wants to apply for National Committee for Quality Assurance (NCQA) Medical Home Certification
and one of the requirements is to measure the patient satisfaction with the appointment scheduling. At present
they don’t know where they fall.
Eventual patient dissatisfaction with the scheduling process could be related to:
1) The automated phone system;
2) Front office staff;
3) Availability of physicians;
4) The current “partial access” system;
In order to manage risks, issues and dependencies, this project will have a multi-step approach. The intern will
need the support of the site supervisor - Dr. Garcia and the case manager – Nida Torres to be successful with
completing the goals and objectives that have been set.
The key benefits to for this project include:
Find the reasons why patients are not seen in a timely manner
Make suggestions for improvements in the scheduling system area
Project Charter v 1.0
Prepared by Mariana Sabeva Page 3 of 7
4. Scheduling System Optimization Project – Project Charter
2. Project Overview
A. Problem/Opportunity Statement
Dr. Garcia is aware of the problem of patients not to be seen in a timely manner.
The guiding principles of the project will be:
Find reasons for the problem
Investigate other Phoenix area based Family Medicine Residency programs to assess effectiveness of
“open-access” scheduling system on their programs
Perform a literature search to assess effectiveness and feasibility of implementation of an “open-access”
system at St. Joseph’s Family Medicine Residency program
B. Business Objectives and Goals
Business Objective Business Goal Project Measure of Success
Find reasons why patients are not be Make suggestions in that area. 25% increase of customer
seen in a timely manner satisfaction
C. Project Description
The objective of the Scheduling System Optimization project is to find out what are the reasons for the inability of patients to
be seen in a timely manner. In addition the intern will make suggestions to make improvement in the area of the scheduling
system.
Define phase - the internship coordinator, Dr. C.J. O’Connor will meet with St. Joseph’s Family Medicine Residency
Program representative and define the site supervisor and the business need.
Analyze phase – the intern will finalize the project charter and present it to project stakeholders for approval. “Afterwards the
intern will start working toward the project goals.
Summarize findings – the intern will summarize the findings of the problem investigation and will prepare findings report. In
addition, if there is a need PowerPoint presentation could be prepared also to summarize the findings report.
Make suggestions – Based on the findings results and literature review the intern will make to the best of her knowledge
suggestions to make improvements in the area of appointment scheduling system.
Project Wrap-up – The intern will review the project and prepare a summary report with lessons learned and will get
feedback from project stakeholders.
Project Charter v 1.0
Prepared by Mariana Sabeva Page 4 of 7
5. Scheduling System Optimization Project – Project Charter
D. Scope
1) In-Scope
a) Project Scope
The current effort for the project is to find out reasons for the inability of patients to be
seen in a timely manner
The project will:
Summarize reasons for the problem
Investigate and research other Phoenix area based Family Medicine Residency
programs and their experience with “open-access” scheduling system
Perform a literature search to assess effectiveness and feasibility of implementation
of an “open-access” system at St. Joseph’s Family Medicine Residency program
b) Organizational Scope
St. Joseph’s Family Medicine Residency Program
2) Out of Scope
a) Project Scope
Post-implementation survey – administration, results analysis
NCQA Patient Centered Medical Home Certification compliance
b) Organizational Scope
Other Family Medicine Residency Programs
E. Timeline
1) Key Business Dates
Target Completion is end of May.
2) High Level Schedule
Overall Project Timeline – Using World Date Format
Project Framework Estimated Estimated
Phase Start Date End Date
Define 02/22/2011 03/07/2011
Analyze 03/10/2011 05/27/2011
Summarize Findings 05/28/2011 06/27/2011
Make Suggestions 06/28/2011 07/08/2011
Project Wrap-up 06/28/2011 07/15/2011
F. Benefits
1) Expected Benefits
Find the reasons why patients are not seen in a timely manner.
Help to formulate suggestions to make improvement in the scheduling system.
Project Charter v 1.0
Prepared by Mariana Sabeva Page 5 of 7
6. Scheduling System Optimization Project – Project Charter
3. Project Organization
A. Organizational Structure
Stakeholders Organization Role
Dr. M. Baldwin W.P. Carey Graduate School of Faculty Advisor
Business, MHSM
Dr. R. Garcia St. Joseph’s Family Medicine Site Supervisor
Residency Program
Dr. C.J. O’Connor W.P. Carey Graduate School of Internship Coordinator
Business, MHSM
B. Project Roles and Phase End Approvers
Name Dept Project Role
Define Analyze Summarize Make Project
Phase Phase Findings Suggestions Wrap-up
Phase Phase Phase
Dr. M. Baldwin W.P. Carey, x x x x x
MHSM Faculty Advisor
Dr. R. Garcia St. Joseph’s x x x x x
Family
Medicine Site Supervisor
Residency
Program
Nida Torres, RN St. Joseph’s x x
Family
Subject Matter
Medicine
Expert
Residency
Program
Project Charter v 1.0
Prepared by Mariana Sabeva Page 6 of 7
7. Scheduling System Optimization Project – Project Charter
4. Major Assumptions, Risks and Dependencies
Type Assumptions/ Mitigation/Contingency Mechanisms
Risks/Dependencies
People Support of the graduate They are signers on this project and will
student at the internship site is be informed in the weekly status
key to the success of this communication via email.
project
The project is completed on There is project schedule which will be
time signed and agreed upon project start.
Only deliverables existing in Scope will be signed and reviewed from
the project charter will be major project stakeholders.
delivered upon project
completion
Project Charter v 1.0
Prepared by Mariana Sabeva Page 7 of 7