SlideShare a Scribd company logo
1 of 20
Download to read offline
Financial Management                                                                                    Unit 9 


Unit 9                                           Risk Analysis in Capital Budgeting 

Structure 


9.1  Introduction 
9.2  Types and sources of Risk in capital Budgeting 
9.3  Risk Adjusted Discount Rate 
9.4  Certainty Equivalent 
9.5  Sensitivity Analysis 
9.6  Probability Distribution Approach: 
9.7  Decision – tree approach 
9.8  Summary: 
      Terminal Questions 
      Answer to SAQs and TQs 


9.1  Introduction 
In the previous chapter on capital budgeting the project appraisal techniques were applied on the 
assumption that the project will generate a given set of cash flows. 
It is quite obvious that one of the limitations of DCF techniques is the difficulty in estimating  cash 
flows with certain degree of certainty.  Certain projects when taken up by the firm will change the 
business risk complexion of the firm. 
This business risk complexion of the firm influences the required rate of return of the investors. 
Suppliers of capital to the firm tend to be risk averse and the acceptance of a project that changes 
the risk profile of the firm may change their perception of required rates of return for investing in 
firm’s project. 
Generally the projects that generate high returns are risky.  This will naturally alter the business 
risk  of  the firm.   Because of  this high  risk perception  associated  with  the  new  project  a  firm is 
forced  to  asses  the  impact  of  the  risk  on  the  firm’s  cash  flows  and  the  discount  factor  to  be 
employed in the process of evaluation. 
Definition of Risk:  Risk may be defined  as the variation of actual cash flows from  the expected 
cash flows.  The term risk in capital budgeting decisions may be defined as the variability that is 
likely to occur in future between the estimated and the actual returns.  Risk exists on account of 
the inability of the firm to make perfect forecasts of cash flows.



Sikkim Manipal University                                                                                 147 
Financial Management                                                                                   Unit 9 

Risk arises in project evaluation because the firm cannot predict the occurrence of possible future 
events  with  certainty  and  hence,  cannot  make  any  correct  forecast  about  the  cash  flows.  The 
uncertain economic conditions are the sources of uncertainty in the cash flows. 
For  example,  a  company  wants  to  produce  and  market  a  new  product  to  their  prospective 
customers.  The demand is affected by the general economic conditions.  Demand may be very 
high if the country experiences higher economic growth.  On the other hand economic events like 
weakening of US dollar, sub prime crises may trigger economic slow down.  This may create a 
pessimistic demand drastically bringing down the estimate of cash flows. 
Risk is associated with the variability of future returns of a project.  The greater the variability of 
the expected returns, the riskier the project. 
Every business decision involves risk.  Risk arises out of the uncertain conditions under which a 
firm has to operate its activities.  Because of the inability of firms to forecast accurately cash flows 
of  future  operations  the firms face the  risks  of  operations.  The  capital budgeting  proposals  are 
not based on perfect forecast of costs and  revenues because the assumptions about the future 
behaviour of costs and revenue may change.  Decisions have to be made in advance assuming 
certain future economic conditions. 
There are Many factors that affect forecasts of investment, cost and revenue. 
1)  The business is affected by changes in political situations, monetary policies, taxation, interest 
    rates, policies of the central bank of the country on lending by banks etc. 
2)  Industry  specific  factors  influence  the  demand  for  the  products  of  the  industry  to  which  the 
    firm belongs. 
3)  Company  specific  factors  like  change  in  management,  wage  negotiations  with  the  workers, 
    strikes or lockouts affect company’s cost and revenue positions. 
Therefore,  risk  analysis  in  capital  budgeting  is  part  and  parcel  of  enterprise  risk  management. 
The best business decisions may not yield the desired results because the uncertain conditions 
likely to emerge in future can materially alter the fortunes of the company. 
Every  change  gives  birth  to  new  challenges.    New  challenges  are  the  source  of  new 
opportunities.  A proactive firm will convert every problem into successful enterprise opportunities. 
A firm which  avoids  new  opportunities for  the inherent  risk  associated with  it,  will  stagnate  and 
degenerate.  Successful firms have empirical history of successful management of risks. 
Therefore, analysing the risks of the project to reduce the element of uncertainty in execution has 
become an essential  aspect of today’s corporate project management.




Sikkim Manipal University                                                                                 148 
Financial Management                                                                                    Unit 9 

Learning Objectives: 

After studying this unit, you should be able to understand the following. 
1.  Define risk in capital budgeting. 
2.  Examine the importance of risk analysis in capital budgeting. 
3.  Methods of incorporating the risk factor in capital budgeting decision. 
4.  Understand the types and sources of risk in capital budgeting descision 


9.2 Types and sources of Risk in capital Budgeting 
Risks in a project are many.  It is possible to identify three separate and distinct types of risk in 
any project. 
1)  Stand – alone risk:  it is measured by the variability of expected returns of the project. 
2)  Portfolio risk:  A firm can be viewed as portfolio of projects having as certain degree of risk. 
    When new project added to the existing portfolio of project the risk profile the firm  will alter. 
    The degree of the change in the risk depend on the covariance of return from the new project 
    and the return from the existing portfolio of the projects. If the return from the new project is 
    negatively correlated with the return from portfolio, the risk of the firm will be further diversified 
    away. 
3)  Market or beta risk:  It is measured by the effect of the project on the beta of the firm.  The 
    market risk for a project is difficult to estimate. 
    Stand alone risk is the risk of a project when the project is considered in isolation.  Corporate 
    risk is the projects risks to the risk of the firm.  Market risk is systematic risk.  The market risk 
    is the most important risk because of the direct influence it has on stock prices. 
Sources of risk:  The sources of risks are 
1.  Project – specific risk 
2.  Competitive or Competition risk 
3.  Industry – specific risk 
4.  International risk 
5.  Market risk 
1.  Project – specific risk:  The sources of this risk could be traced to something quite specific 
    to  the  project.    Managerial  deficiencies  or  error  in  estimation of  cash flows  or  discount  rate 
    may lead to a situation of actual cash flows realised being less than that projected. 
2.  Competitive  risk  or  Competition  risk:  unanticipated  actions  of  a  firm’s  competitors  will 
    materially  affect  the  cash  flows  expected  from  a  project.    Because  of  this  the actual  cash 
    flows from a project will be less than that of the forecast.

Sikkim Manipal University                                                                                  149 
Financial Management                                                                                        Unit 9 

3.  Industry – specific:  industry – specific risks are those that affect all the firms in the industry. 
    It could be again grouped into technological risk, commodity risk and legal risk.  All these risks 
    will affect the earnings and cash flows of the project.  The changes in technology affect all the 
    firms not capable of adapting themselves to emerging new technology. 
The  best  example  is  the  case  of  firms  manufacturing  motor  cycles  with  two  strokes  engines. 
When technological innovations replaced the two stroke engines by the four stroke engines those 
firms which could not adapt to new technology had to shut down their operations. 
Commodity  risk  is  the  risk  arising  from  the  effect  of  price  –  changes  on  goods  produced  and 
marketed. 
Legal risk arises from changes in laws and regulations applicable to the industry to which the firm 
belongs.  The best example is the imposition of service tax on apartments by the Government of 
India  when  the  total  number  of  apartments  built  by  a  firm  engaged  in  that  industry  exceeds  a 
prescribed limit.  Similarly changes in Import – Export policy of the Government of India have led 
to the closure of some firms or sickness of some firms. 
4.  International Risk:  these types of risks are faced by firms whose business consists mainly 
    of  exports  or  those  who  procure  their  main  raw  material  from  international  markets.    For 
    example, rupee – dollar crisis affected the software and BPOs because it drastically reduced 
    their  profitability.    Another  best  example  is  that  of  the  textile  units  in  Tirupur  in  Tamilnadu, 
    exporting  their  major  part  of  the  garments  produced.  Rupee  gaining  and  dollar  Weakening 
    reduced  their  competitiveness  in  the  global  markets.    The  surging  Crude  oil  prices  coupled 
    with  the  governments  delay  in  taking  decision  on  pricing  of  petro  products  eroded  the 
    profitability of oil marketing Companies in public sector like Hindustan Petroleum Corporation 
    Limited.  Another example is the impact of US sub prime crisis on certain segments of Indian 
    economy. 
The changes in international political scenario also affect the operations of certain firms. 
5.  Market Risk:  Factors like inflation, changes in interest rates, and changing general economic 
    conditions affect all firms and all industries. 
Firms cannot diversify this risk in the normal course of business. 
Techniques used for incorporation of risk factor in capital budgeting decisions 
There  are  many  techniques  of  incorporation  of  risk  perceived  in  the  evaluation  of  capital 
budgeting  proposals.    They  differ  in  their  approach  and  methodology  so  far as incorporation of 
risk in the evaluation process is concerned. 
Conventional techniques 
Pay Back Period


Sikkim Manipal University                                                                                     150 
Financial Management                                                                                     Unit 9 

The  oldest  and  commonly used  method  of  recognising risk  associated  with  a  capital  budgeting 
proposal is pay back period.  Under this method, shorter pay back period is given preference to 
longer  ones.    Firms  establish  guidelines  for  acceptance  or  rejections  of  projects  based  on 
standards of pay back periods. 
Payback period prefers projects of short – term pay backs to that of long – term pay backs.  The 
emphasis is on the liquidity of the firm through recovery of capital.  Traditionally Indian business 
community employs this technique in evaluating projects with very high level of uncertainty. The 
changing trends in fashion make the fashion business, one of high risk and therefore, pay back 
period  has  been  endorsed  by  tradition  in  India  to  take  decisions  on  acceptance  or  rejection of 
such projects.  The usual risk in business is more concerned with the fore cast of cash flows.  It is 
the down side risk of lower cash flows arising from lower sales and higher costs of operation that 
matters in formulating standards of pay back. 
Pay back period ignores time value of many (cash flows).  For example, the following details are 
available in respect of two projects. 

                           Particulars          Project A (Rs)         Project B (Rs) 
                     Initial cash outlay       10 lakhs               10 lakhs 
                     Cash flows 
                     Year 1                    5 lakhs                2 lakhs 
                     Year 2                    3 lakhs                2 lakhs 
                     Year 3                    1 lakhs                3 lakhs 
                     Year 4                    1 lakhs                3 lakhs 

Both the projects have a pay back period of 4 years.  The project B is riskier than the Project A 
because Project A recovers 80% of initial cash outlay in the first two years of its operation where 
as  Project  B  generates  higher  Cash  inflows  only  in  the  latter  half  of  the  payback  period.    This 
undermines the utility of payback period as a technique of incorporating risk in project evaluation. 
This  method  considers  only  time  related  risks  and  ignores  all  other  risks  of  the  project  under 
consideration. 


Self Assessment Questions 2 
1.  _____________ is measured by the variability of expected returns of the project. 
2.  Market risk is measured by the effect of the project on the ____ of the firm. 
3.  Firms cannot ____ market risk in the normal course of business. 
4.  Impact  of  U.S  sub  prime  crisis  on  certain  segments  of  Indian  economy  is  and  example  of 
    _______________________.



Sikkim Manipal University                                                                                  151 
Financial Management                                                                                    Unit 9 

9.3 Risk Adjusted Discount Rate 
The basis of this approach is that there should be adequate reward in the form of return to firms 
which decide to execute risky business projects. Man by nature is risk­averse and tries to avoid 
risk.  To motivate firms to take up risky projects returns expected from the project shall have to be 
adequate, keeping in view the expectations of the investors. Therefore risk premium need to be 
incorporated in discount rate in the evaluation of risky project proposals. 
Therefore the discount rate for appraisal of projects has two components. 
Those components are 
1.  Risk – free rate and risk premium 
Risk Adjusted Discount rate = Risk free rate + Risk premium 
Risk free rate is computed based on the return on government securities. 
Risk  premium  is  the  additional  return  that  investors  require  as  compensation  for  assuming  the 
additional risk associated with the project to be taken up for execution. 
The  more  uncertain  the  returns  of  the  project  the  higher  the  risk.  Higher  the  risk  greater  the 
premium.    Therefore,  risk  adjusted  Discount  rate  is  a  composite  rate  of  risk  free  rate  and  risk 
premium of the project. 
Example:  An investment will have an initial outlay of Rs 100,000. It is expected to generate cash 
inflows as under: 
                                          Year      Cash in flows 
                                          1         40,000 
                                          2         50,000 
                                          3         15,000 
                                          4         30,000 

Risk free rate of interest is 10%.  Risk premium is 10% (the risk characterising the project) 
(a)     compute the NPV using risk free rate 
(b)     Compute NPV using risk – adjusted discount rate 
Solutions = (a) using risk – free rate 


       Year     Cash flows (inflows) Rs           PV Factor at 10%         PV of Cash flows (in flows) 
        1      40,000                          0.909                    36,360 
        2      50,000                          0.826                    41,300 
        3      15,000                          0.751                    11,265 
        4      30,000                          0.683                    20,490 
               PV of cash in flows                                      1,09,415


Sikkim Manipal University                                                                                  152 
Financial Management                                                                                   Unit 9 

             PV of Cash outflows                                       1,00,000 
             NPV                                                       9,415 


                 (b)  Using risk – adjusted discount rate 
         Year      Cash in flows Rs              PV factor at 20%          PV of cash inflows 
            1      40,000                        0.833                     33,320 
            2      50,000                        0.694                     34,700 
            3      15,000                        0.579                     8,685 
            4      30,000                        0.482                     14,460 
                   PV of Cash in flows                                     91,165 
                   PV of Cash out flows                                    100,000 
                   NPV                                                     (8,835) 


The project would be acceptable when no allowance is made for risk. 
But it will not be acceptable if risk premium is added to the risk free rate.  It moves from positive 
NPV to negative NPV. 
If the firm were to use the internal rate of return, then the project would be accepted when IRR is 
greater than the risk – adjusted discount rate. 
Evaluation of Risk – adjusted discount rate: 
 Advantages: 
1.  It is simple and easy to understand. 
2.  Risk premium takes care of the risk element in future cash flows. 
3.  It satisfies the businessmen who are risk – averse. 


Limitations: 
1.  There  are  no  objective  bases of  arriving  at  the  risk  premium.    In  this  process  the  premium 
    rates computed become arbitrary. 
2.  The assumption that investors are risk – averse may not be true in respect of certain investors 
    who are willing to take risks.  To such investors, as the level of risk increases, the discount 
    rate would be reduced. 
3.  Cash flows are not adapted to incorporate the risk adjustment for net cash in flows. 

Self Assessment Questions 2 

 1. Risk premium is the __________________ that the investors require as compensation for

Sikkim Manipal University                                                                                153 
Financial Management                                                                                   Unit 9 

        assumption of additional risks of project. 
     2. RADR is the sum of ______________ and ______________. 
     3. Higher the risk __________________ the premium. 
     4. Man by nature is risk­averse and tries to avoid risk. 


     9.4  Certainty Equivalent: 
     Under this method the risking uncertain, expected future cash flows are converted into cash flows 
     with  certainty.    Here  we  multiply  uncertain  future  cash  flows  by  the  certainty  –  equivalent 
     coefficient  to  convert  uncertain  cash  flows  into  certain  cash  flows.    The  certainty  equivalent 
     coefficient  is  also  known  as  the  risk  –  adjustment  factor.    Risk  adjustment  factor  is  normally 
     denoted by αt (Alpha).  It is the ratio of certain net cash flow to risky net cash flow 
              = Certainty Equivalent = Certain Cash flow 
                                          Risky Cash flow 


     The discount factor to be used is the risk free rate of interest.  Certainty equivalent coefficient is 
     between 0 and 1.  This risk – adjustment factor varies inversely with risk.  If risk is high a lower 
     value is used for risk adjustment.  If risk is low a higher coefficient of certainty equivalent is used 

     Illustration (Example) 
             A project costs Rs 50,000.  It is expected to generate cash inflows as under 
                          Year                      Cash in flows                Certainty Equivalent 
                           1                             32,000                            0.9 
                           2                             27,000                            0.6 
                           3                             20,000                            0.5 
                           4                             10,000                            0.3 


             Risk – free discount rate is 10% compute NPV 
             Answer: 
Year     Uncertain cash                  C E               Certain cash       PV Factor at  PV of certain cash 
              in flows                                         flows               10%                 inflows 
1        32,000                 0.9                       28,800              0.909            26,179 
2        27,000                 0.6                       16,200              0.826            13,381 
3        20,000                 0.5                       10,000              0.751            7,510 
4        10,000                 0.3                       3,000               0.683            2,049


     Sikkim Manipal University                                                                                154 
Financial Management                                                                                   Unit 9 

                          PV of certain cash in                                            49,119 
                          flows 
                          Initial cash out lay                                             50,000 
                          NPV                                                              (881) negative 


The project has a negative NPV. 
Therefore, it is rejected. 

If IRR is used the rate of discount at which NPV is equal to zero is computed and then compared 
with the minimum (required) risk free rate.  If IRR is greater than specified minimum risk free rate, 
the project is accepted, other wise rejected. 

Evaluation: 
It recognises risk.  Recognition of risk by risk – adjustment factor facilitates the conversion of risky 
cash flows into certain cash flows.  But there are chances of being inconsistent in the procedure 
employed from one project to another. 
When forecasts pass through many layers of management, original forecasts may become highly 
conservative. 
Because of high conservation in this process only good projects are likely to be cleared when this 
method is employed. 
Certainty –  equivalent approach is considered to be theoretically superior to the risk –  adjusted 
discount rate. 
Self Assessment Questions 3 
1. CE coefficient is the _______ . 
2. Discount factors to be used under CE approach is _____________. 
3. Because of high ______________ CE clears only good projects. 
4. ___________ is considered to be superior to RADR 
9.5  Sensitivity Analysis: 
There  are  many  variables  like  sales,  cost  of  sales,  investments,  tax  rates  etc  which  affect  the 
NPV  and  IRR  of a  project.    Analysing  the  change  in  the  project’s  NPV or  IRR  on  account  of a 
given change in one of the variables is called Sensitivity Analysis.  It is a technique that shows the 
change in NPV given a change in one of the variables that determine cash flows of a project.  It 
measures the sensitivity of NPV of a project in respect to a change in one of the input variables of 
NPV.



Sikkim Manipal University                                                                                 155 
Financial Management                                                                                      Unit 9 

The  reliability  of  the  NPV  depends  on  the  reliability  of  cash  flows.    If  fore  casts  go  wrong  on 
account  of  changes  in  assumed  economic  environments,  reliability  of  NPV  &  IRR  is  lost. 
Therefore, forecasts are made under different economic conditions viz pessimistic, expected and 
optimistic. NPV is arrived at for all the three assumptions. 
Following steps are involved in Sensitivity analysis: 
1.  Identification of variables that influence the NPV & IRR of the project. 
2.  Examining and defining the mathematical relationship between the variables. 
3.  Analysis of the effect of the change in each of the variables on the NPV of the project. 

Example:    A  company  has  two  mutually exclusive  projects  under  consideration viz  project  A  & 
project B. 
Each project requires an initial cash outlay of Rs 3,00,000 and has an effective life of 10 years. 
The  company’s  cost  of  capital  is  12%.    The  following  fore  cast  of  cash flows  are  made  by  the 
management. 


                Economic                        Project A                      Project B 
        Environment                     Annual cash inflows           Annual cash in flows 
        Pessimistic                     65,000                        25,000 
        Expected                        75,000                        75,000 
        Optimistic                      90,000                        1,00,000 


        What is the NPV of the project? 
        Which project should the management consider? 
        Given PVIFA = 5.650 
        Answer / Solutions 
        NPV of project A 


          Economic             Project              PVIFA          PV of cash in flows             NPV 
        Environment          cash inflows     at    12%      10 
                                              years 
        Pessimistic          65,000           5.650                3,67,250                   67,250 
        Expected             75,000           5.650                4,23,750                   1,23,750 
        Optimistic           90,000           5.650                5,08,500                   2,08,500




Sikkim Manipal University                                                                                   156 
Financial Management                                                                                     Unit 9 

        NPV of Project B 
        Pessimistic          25,000             5.650               1,41,250            (1,58,750) 
        Expected             75,000             5.650               4,23,750            1,23,750 
        Optimistic           1,00,000           5.650               5,65,000            2,65,000 


Decision 
1.  Under pessimistic conditions project A gives a positive NPV of Rs 67,250 and Project B has a 
    negative NPV of Rs 1,58,750 Project A is accepted. 
2.  Under  expected  conditions, both  gave  some  positive  NPV  of Rs  1,23,000.  Any  one  of  two 
    may be accepted. 
3.  Under optimistic conditions Project B has a higher NPV of Rs 2,65,000 compared to that  of 
    A’s NPV of Rs 2,08,500. 
4.  Difference  between  optimistic  and  pessimistic  NPV  for  Project  A  is  Rs  1,41,250  and  for 
    Project B the difference is Rs 4,23,750. 
5.  Project B is risky compared to Project A because the NPV range is of large differences. 
Statistical Techniques: 
Statistical techniques use analytical tools for assessing risks of investments. 

Self  Assessment Questions 4 

1. _____________ analysis the changes in the project NPV on account of a given change in one 
of the input variables of the project. 
2.  Examining  and  defining  the  mathematical  relation  between  the  variable  of  the  NPV  is 
_________________________. 
3. Forecasts under sensitivity analysis are made under __________. 




9.6  Probability Distribution Approach: 
When  we  incorporate the  chances  of occurrences  of various economic environments  computed 
NPV  becomes  more  reliable.    The  chances  of  occurrences  are  expressed  in  the  form  of 
probability.  Probability is the likelihood of occurrence of a particular economic environment.  After 
assigning probabilities to future cash flows expected net present value is computed. 

Illustration:    A  company  has  identified  a project  with  an  initial  cash  outlay  of  Rs  50,000.    The 
following distribution of cash flow is given below for the life of the project of 3 years.


Sikkim Manipal University                                                                                  157 
Financial Management                                                                                   Unit 9 

                 Year 1                            Year 2                             Year 3 
   Cash in flow        Probability    Cash in flow        Probability     Cash in flow       Probability 
   15,000              0.2            20,000              0.3             25,000             0.4 
   18,000              0.1            15,000              0.2             20,000             0.3 
   35,000              0.4            15,000              0.2             20,000             0.3 
   32,000              0.3            30,000              0.2             45,000             0.1 

                                         Discount rate is 10% 
        Year 1 
        = 15,000 x 0.2 + 18,000 x 0.1 + 35,000 x 0.4 + 32,000 x 0.300 
        3,000 + 1,800 + 14,000 + 9,600 = 28,400 
        Year 2 
        20,000 x 0.3 + 15,000 x 0.2 + 30,000 x 0.3 + 30,000 x 0.2 
        = 6,000 + 3,000 + 9,000 + 6,000 = 24,000 
        Year 3 
        25,000 x 0.4 + 20,000 x 0.3 + 40,000 x 0.2 + 5,000 x 0.1 = 
        10,000 + 6,000 + 8,000 + 4,500 == 28,500 


                                                                                    PV of expected 
         Year          Expected cash inflows              PV factor at 10% 
                                                                                     cash in flows 
           1       28,400                                        0.909                    25,816 
           2       24,000                                        0.826                    19,824 
           3       28,500                                        0.751                    21,403 
                   PV of expected cash in flows                                           67,043 
                   PV of initial cash out lay                                             50,000 
                   Expected NPV                                                           17,043 
Variance: 
A  study  of  dispersion  of  cash  flows  of  projects  will  help  the  management  in  assessing  the  risk 
associated  with  the  investment  proposal.    Dispersion  is  computed  by  variance  or  standard 
deviation.    Variance  measures  the  deviation  of  each  possible  cash  flow  from  the  expected. 
Square root of variance is standard deviation. 

Example:  Following details are available in respect of a project which requires an initial cost of 
Rs 5,00,000.


Sikkim Manipal University                                                                                 158 
Financial Management                                                                        Unit 9 

          Year    Economic Conditions         Cash flows       Probability 
             1    High growth                  2,00,000            0.3 
                  Average growth               1,50,000            0.6 
                  No growth                     40,000             0.1 
             2    High growth                   3,00,00            0.3 
                  Average growth               2,00,000            0.5 
                  No growth                    5,00,000            0.2 
             3    High growth                  4,00,000            0.2 
                  Average growth               2,50,000            0.6 
                  No growth                     30,000             0.2 


Discount rate is 10% 
Solution: 
Year 1 
Economic Condition           Cash in flow       Probability         Expected value of Cash in flow 
             1                     2                 3 
High growth                    2,00,000             0.3                         60,000 
Average growth                 1,50,000             0.6                         90,000 
No growth                        40,000             0.1                         4,000 
                                             Expected Value                    1,54,000 


Year 2 
Economic Condition           Cash in flow       Probability         Expected value of Cash in flow 
High growth                    3,00,000             0.3                         90,000 
Average growth                 2,00,000             0.5                        1,00,000 
No growth                        50,000             0.2                         10,000 
                                             Expected Value                    2,00,000 


Year 3 
Economic Condition           Cash in flow       Probability         Expected value of Cash in flow 
High growth                    4,00,000             0.2                         80,000 
Average growth                 2,50,000             0.6                        1,50,000 
No growth                        30,000             0.2                         6,000


Sikkim Manipal University                                                                     159 
Financial Management                                                                              Unit 9 

                                                   Expected Value of                     2,36,000 
                                                   Cash inflows 
                  1,54,000         2,00,000     2,36,000 
Expected NPV =  1.10               (1­10) 
                             +           2     +  (1.10) 
                                                        3        ­ 5,00,000

               = 1,40,000 + 1, 65, 289 + 1, 77, 310 – 5,00,000 = (17,401) negative NPV 


      Standard Deviation for I year 

                                                         2                           2 
       Cash in flow      Expected Value           (C – E)                     (C – E)  x prob 
             C                     E 
                                                         2               2 
         2,00,000             1,54,000           (46,000)        (46,000)  x 0.3 = 634800  000 
                                                         2                2 
         1,50,000             1,54,000           (­ 4000)        (­ 4,000)  x 0.3 = 9600  000 
                                                            2                2 
          40,000              1,54,000         ( ­ 1,14,000)     (­ 1,14,000)  x 0.3 = 12996 00 000 
                                                   Total                      1944  000 000 


      Standard deviation of Cash flows for I year = 44091 
           nd 
      For 2  year 
                                                         2                           2 
       Cash in flow      Expected Value           (C – E)                     (C – E)  x prob 
             C                     E 
                                                          2                2 
         3,00,000             2,00,000          (1,00,000)       (1,00,000)  x 0.3 = 3000 000  000 
                                                       2            2 
         2,00,000             2,00,000              (0)          (0)  x 0.5 = 0 
                                                            2                2 
          50,000              2,00,000         ( ­ 1,50,000)     (­ 1,50,000)  x 0.2 = 45 00 000 000 
                                                   Total                        7500 00 000 


                                  nd 
      Variance of Cash flows for 2  year = 7500 000 000 
                                            nd 
      Standard Deviation of cash flows for 2  year = 8660 
      For the third year 
                                                         2                           2 
       Cash in flow      Expected Value           (C – E)                     (C – E)  x prob 
             C                     E 
                                                          2                2 
         4,00,000             2,36,000          (1,64,000)       (1,64,000)  x 0.2 = 53792 00  000 
                                                         2               2 
         2,50,000             2,36,000           (14,000)        (14,000)  x 0.6 = 1176 00 000 
                                                            2                2 
          30,000              2,36,000         ( ­ 2,00,000)     (­ 2,00,000)  x 0.2 = 8000 000 000 
                                                   Total                       13496800 000 



      Sikkim Manipal University                                                                           160 
Financial Management                                                                                   Unit 9 

                            rd 
Variance of Cash flows for 3  year = 13496800 000 
                                      rd 
Standard Deviation of cash flows for 3  year = 116175 
Standard Deviation of NPV


                    2                  2                 2
            Ö(44091)             (8660)          (116175) 
 sNPV  =            2       +          4         +         6 
             Ö(1.10)             (1.10)              (1.10) 
        = Ö1606625026 + 51223004 + 7618496131 
        = Ö9276344161 
        = 96314 

        Here the assumption is that there is no relationship between cash flows from one period to 
        another. Under this assumption the standard deviation  of NPV  is Rs 96,314. 
        On  the  other  hand,  if  cash  flows  are  perfectly  correlated,  cash  flows  of  all  years  have 
        linear correlation to one another, then 


             44091                8660                116175 
 sNPV  =                    +  (1.10) 
                                     2           + (1.10) 
                                                         3 
              1.10 
        = 40083 + 7157 + 87284 = 134524 

        The  standard  deviation  of  NPV  when  cash  flows  are  perfectly  correlated  will  be  higher 
        than that under the situation of independent cash flows. 
Self Assessment Questions. 5 
1.  Probability  distribution  approach  incorporates  the  probability  of  occurrences  of  various 
economic environment, to make the NPV ________. 
2. _______ is likelihood of occurrence of a particular economic environment. 


9.7  Decision – tree approach: 
Many project decisions are complex investment decisions.  Such complex investment decisions 
involve a sequence of decisions over time.  Decisions tree can handle the sequential decisions of 
complex  investment  proposals.    The  decision  of  taking  up  an  investment  project  is  broken  into 
different stages.  At each stage the proposal is examined to decide whether to go ahead or not. 
The  multi  –  stages  approach  can  be  handled  effectively  with  the  help  of  decision  trees.    A 
decision tree presents graphically the relationship between a present decision and future events, 
future decisions and the consequences of such decisions.



Sikkim Manipal University                                                                                 161 
Financial Management                                                                                             Unit 9 

Example 
        R & D section of a company has developed an electric moped.  The firm is ready for pilot 
production and test  marketing.    This  will  cost  Rs  20  million and  take  six  months.    Management 
believes that there is a 70% chance that the pilot production and test marketing will be successful. 
        If successful the company can build a plant costing Rs 200 million. 
The plant will generate annual cash in flow of Rs 50 million for 20 years if the demand is high or 
an annual cash inflow or 20 million if the demand is low. 

High demand has a probability of 0.6 and low demand has a probability of 0.4.  Cost of capital is 
12%. 
Suggest  the  optimal  course  of  action  using  decision  tree  analysis  (Bangalore  University  MBA, 
adapted).                                                                                   High Demand 
                                                                                            Probability 0.6 
                                                                                             C21 
                                                            D21  Investment                     Annual Cash inflow 
                                                                  Rs.200 million                Rs.50 million 
                                                                                     C2 
 D11  Carry out pilot 
      Production                        C11  Success                                          Annual Cash inflow 
      And Market                                            D2                                Rs.20 million 
      test (20 million) 
                                            0.7                         D22  Stop           C22  Low Demand 
                           C1                                                                    Probability  0.4 

 D                                                            D3 
                                 C12    failure                                D31  Stop 
                                         Probability 0.3 

          D12  Do Nothing 

Working Notes:  From right hand side of the decision tree 
I  step:    Computation of Expected  Monetary  Value at point  C2.    Here EMV  represents expected 
NPV. 




         Cash in flow        Probability             Expected value of cash inflows 
                50                  0.6                                 30 
                20                  0.4                                  8 
                                   EMV                                  38 


Present Value of EMV = Expected value of cash inflow x PVIFA (12% 20) 
        38 x 7.469 = Rs 283.82 million 




Sikkim Manipal University                                                                                            162 
Financial Management                                                                                  Unit 9 

Step 2: 
Computation of EMV at decision point D2. 
Decision taken            Consequences                 The resulting EMV at this level 
        D2             Invest Rs 200 million             283.82 – 200 83.82 million 
       D22                       Stop                                    0 
Here the decision criterion is “select the EMV with the highest value”. 

Stage 3: 
Therefore EMV with Rs 83.82 million will be considered therefore; we select the decision taken at 
D2, 
Stage 4: 
        Computation of EMV at the point C, 
                               EMV        Probability       Expected Value 
                               83.82            0.7              58.67 
                                 0              0.3                 0 
                                         EMV at this stage                        58.67 


Step 5: 
        Compute EMV at decisions point D, 
               Decision taken                   Consequences              The resulting Em at this 
                                                                                   level 
        D11 carry out pilot                Invest                    58.67 – 20 = Rs 38.67 Million 
        production and market test         20 million 
        D12 Do nothing                     0                         0 
                                           EMV at this stage         38.67 Million 
                                                                     (Apply the EMV criterion) i.e 
                                                                     select the EMV with the 
                                                                     highest value 


Therefore optimal strategy is 
1.  Carry out pilot production and market test. 
2.  If  the  result  of pilot production  and  market  test  is  successful,  go  ahead  with  the investment 
    decision of Rs 200 million in establishing a plant. 
3.  If the result of pilot production and market test is future, stop.


Sikkim Manipal University                                                                                163 
Financial Management                                                                                  Unit 9 

Evaluation of Decision tree approach: 
1.  It portrays inter – related, sequential  and critical multi dimensional elements of major project 
    decisions. 
2.  Adequate attention is given to the critical aspects in an investment decision which spread over 
    a time sequence. 
3.  Complex  projects  involve  huge  out  lay  and  hence  risky.    There  is  the  need  to  define  and 
    evaluate  scientifically  the  complex  managerial  problems  arising  out  of  the  sequence  of 
    interrelated decisions with consequential outcomes of high risk.  It is effectively answered by 
    decision tree approach. 
4.  Structuring a  complex project  decision  with  many  sequential investment  decisions demands 
    effective project risk management.  This is possible only with the help of an analytical tool like 
    decision tree approach. 
5.  Able  to  eliminate unprofitable outcomes  and helps  in  arriving  at  optimum decision stages in 
    time sequence. 


Self Assessment Questions 6 
1. Decision tree can handle the _____________ of complex investment proposals. 
2. _____ portrays inter­related, sequential and critical multi dimensional elements of major project 
decisions. 
3.  Adequate  attention  is  given  to  the  ______  in  an  investment  decision  under  decision  tree 
approach’s. 
4. ____________ are effectively handled by decision tree approach’s . 


9.8 Summary 
Risk in project evaluation arises on account of the inability of the firm to predict  the performance 
of the firm  with  certainty.  Risk in capital budgeting  decision  may  be  defined  as  the variability of 
actual  returns  from  the  expected.  There  are  many  factors  that  affect  forecasts  of  investment, 
costs and revenues of a project. It is possible to identify three type of risk in any project, viz stand­ 
alone risk, corporate risk and market risk. The sources of risks are: 
a.  Project 
b.  Competition 
c.  Industry 
d.  International factors and 
e.  Market


Sikkim Manipal University                                                                               164 
Financial Management                                                                                 Unit 9 

The techniques for incorporation of risk factor in capital budgeting decision could be grouped into 
conventional techniques and statistical techniques. 


Terminal Questions 
1.  Define risk. Examine the need for assessing the risks in a project. 
2.  Examine the type and sources of risk in capital budgeting . 
3.  Examine  risk  adjusted  discount  rate  as  a  technique  of  incorporating  risk  factor  in  capital 
    budgeting. 
4.  Examine the steps involved in sensitivity analysis. 
5.  Examine the features of Decision­tree approaches. 


Answer for Self Assessment Questions 
Self Assessment Questions 1 
1.  Stand­alone risk. 
2.  Beta 
3.  Diversify 
4.  International risk 


Self Assessment Question 2 
1.  Additional return 
2.  Risk free rate, risk premium. 
3.  Greater. 


Self Assessment Question 3 
1.  Risk­ adjustment factor 
2.  Risk free rate of interest. 
3.  Conservation. 
4.  CE 


Self Assessment Question 4 
1.  Sensitivity analysis 
2.  One of the steps of sensitivity analysis 
3.  Different economic conditions




Sikkim Manipal University                                                                              165 
Financial Management             Unit 9 

Self Assessment Question 5 
1.  More reliable 
2.  Probability 


Self Assessment Question 6 
1.  Sequential decisions 
2.  Decision tree. 
3.  Critical aspects 
4.  Complex projects. 


Answer for Terminal Questions 
1.  Refer to units 9.1 
2.  Refer to units 9. 2 
3.  Refer to units 9.3 
4.  Refer to unit 9.5 
5.  Refer to unit 9.7




Sikkim Manipal University          166 

More Related Content

What's hot

Measurement of Risk and Calculation of Portfolio Risk
Measurement of Risk and Calculation of Portfolio RiskMeasurement of Risk and Calculation of Portfolio Risk
Measurement of Risk and Calculation of Portfolio RiskDhrumil Shah
 
Corporate valuation
Corporate valuation Corporate valuation
Corporate valuation RudreshSamant
 
Investment Banking
Investment BankingInvestment Banking
Investment BankingIshan Jain
 
Management of interest rate risk
Management of interest rate riskManagement of interest rate risk
Management of interest rate riskSonam Basia
 
Introduction to risk management and insurance
Introduction to risk management and insuranceIntroduction to risk management and insurance
Introduction to risk management and insuranceVipul Kumar
 
Chapter 2 Financial Institutions, Financial Intermediaries and Asset Manageme...
Chapter 2 Financial Institutions, Financial Intermediaries and Asset Manageme...Chapter 2 Financial Institutions, Financial Intermediaries and Asset Manageme...
Chapter 2 Financial Institutions, Financial Intermediaries and Asset Manageme...Nardin A
 
financial restructuring
financial restructuringfinancial restructuring
financial restructuringsangeeta saini
 
Financial risk management ppt @ mba finance
Financial risk management  ppt @ mba financeFinancial risk management  ppt @ mba finance
Financial risk management ppt @ mba financeBabasab Patil
 
All About Fixed Income Instruments
All About Fixed Income InstrumentsAll About Fixed Income Instruments
All About Fixed Income Instrumentsguest241aa3
 
Interest Rate Risk
Interest Rate Risk Interest Rate Risk
Interest Rate Risk nikatmalik
 
Credit Risk Management
Credit Risk  ManagementCredit Risk  Management
Credit Risk ManagementFarouk Nasser
 
Chapter 08 risk management in banks
Chapter 08    risk management in banksChapter 08    risk management in banks
Chapter 08 risk management in banksiipmff2
 
Risk and Return Analysis
Risk and Return AnalysisRisk and Return Analysis
Risk and Return AnalysisRamziya Begam
 
Risk Management in Banking Sectors.
Risk Management in Banking Sectors.Risk Management in Banking Sectors.
Risk Management in Banking Sectors.Rupesh neupane
 
What is venture capital & venture capital in india
What is venture capital & venture capital in indiaWhat is venture capital & venture capital in india
What is venture capital & venture capital in indiaSandeep Mane
 
Dividend policy theories
Dividend policy theoriesDividend policy theories
Dividend policy theoriesSameera Khan
 

What's hot (20)

Measurement of Risk and Calculation of Portfolio Risk
Measurement of Risk and Calculation of Portfolio RiskMeasurement of Risk and Calculation of Portfolio Risk
Measurement of Risk and Calculation of Portfolio Risk
 
Corporate valuation
Corporate valuation Corporate valuation
Corporate valuation
 
Investment Banking
Investment BankingInvestment Banking
Investment Banking
 
Management of interest rate risk
Management of interest rate riskManagement of interest rate risk
Management of interest rate risk
 
Introduction to risk management and insurance
Introduction to risk management and insuranceIntroduction to risk management and insurance
Introduction to risk management and insurance
 
Chapter 2 Financial Institutions, Financial Intermediaries and Asset Manageme...
Chapter 2 Financial Institutions, Financial Intermediaries and Asset Manageme...Chapter 2 Financial Institutions, Financial Intermediaries and Asset Manageme...
Chapter 2 Financial Institutions, Financial Intermediaries and Asset Manageme...
 
Value at risk
Value at riskValue at risk
Value at risk
 
financial restructuring
financial restructuringfinancial restructuring
financial restructuring
 
Financial risk management ppt @ mba finance
Financial risk management  ppt @ mba financeFinancial risk management  ppt @ mba finance
Financial risk management ppt @ mba finance
 
All About Fixed Income Instruments
All About Fixed Income InstrumentsAll About Fixed Income Instruments
All About Fixed Income Instruments
 
Interest Rate Risk
Interest Rate Risk Interest Rate Risk
Interest Rate Risk
 
Credit Risk Management
Credit Risk  ManagementCredit Risk  Management
Credit Risk Management
 
risk and return
risk and returnrisk and return
risk and return
 
Risk types
Risk  typesRisk  types
Risk types
 
Chapter 08 risk management in banks
Chapter 08    risk management in banksChapter 08    risk management in banks
Chapter 08 risk management in banks
 
Risk and Return Analysis
Risk and Return AnalysisRisk and Return Analysis
Risk and Return Analysis
 
Risk Management in Banking Sectors.
Risk Management in Banking Sectors.Risk Management in Banking Sectors.
Risk Management in Banking Sectors.
 
What is venture capital & venture capital in india
What is venture capital & venture capital in indiaWhat is venture capital & venture capital in india
What is venture capital & venture capital in india
 
Dividend policy theories
Dividend policy theoriesDividend policy theories
Dividend policy theories
 
bond and its types
bond and its typesbond and its types
bond and its types
 

Similar to Risk analysis in capital bugeting

Capital budgeting and risk ii
Capital budgeting and risk   iiCapital budgeting and risk   ii
Capital budgeting and risk iiUzma Yzaii
 
Mark Weber-GFMI Presentation-Final-v1
Mark Weber-GFMI Presentation-Final-v1Mark Weber-GFMI Presentation-Final-v1
Mark Weber-GFMI Presentation-Final-v1Mark Weber
 
Risk analysis by raviteja & pranshul (26th august)
Risk analysis by raviteja & pranshul (26th august)Risk analysis by raviteja & pranshul (26th august)
Risk analysis by raviteja & pranshul (26th august)rtejj
 
Measuring risk in investments
Measuring risk in investmentsMeasuring risk in investments
Measuring risk in investmentsBabasab Patil
 
AgendaComprehending risk when modeling investment (project) de.docx
AgendaComprehending risk when modeling investment (project) de.docxAgendaComprehending risk when modeling investment (project) de.docx
AgendaComprehending risk when modeling investment (project) de.docxgalerussel59292
 
An Assignment On Risks In Public Private Partnership
An Assignment On Risks In Public Private PartnershipAn Assignment On Risks In Public Private Partnership
An Assignment On Risks In Public Private PartnershipStephen Faucher
 
Financial Management - An overview
Financial Management - An overviewFinancial Management - An overview
Financial Management - An overviewTanmay Rajpurkar
 
Aman ,FMS BHU
Aman ,FMS BHUAman ,FMS BHU
Aman ,FMS BHUvijukrish
 
Chapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital BudgetingChapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital BudgetingFiaz Ahmad
 
Chapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital BudgetingChapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital BudgetingInocentshuja Ahmad
 
MBA 640 Final Project Milestone Two Guidelines and Rubric .docx
MBA 640 Final Project Milestone Two Guidelines and Rubric  .docxMBA 640 Final Project Milestone Two Guidelines and Rubric  .docx
MBA 640 Final Project Milestone Two Guidelines and Rubric .docxARIV4
 
Project Management- Managerial Appraisal
Project Management- Managerial AppraisalProject Management- Managerial Appraisal
Project Management- Managerial AppraisalAhmedCOC
 
Operation risk management in Private Equity firms
Operation risk management in Private Equity firmsOperation risk management in Private Equity firms
Operation risk management in Private Equity firmsJoseph Kariuki
 
1RUNNING HEAD Genesis Energy Capital Plan Report2Genesi.docx
1RUNNING HEAD Genesis Energy Capital Plan Report2Genesi.docx1RUNNING HEAD Genesis Energy Capital Plan Report2Genesi.docx
1RUNNING HEAD Genesis Energy Capital Plan Report2Genesi.docxeugeniadean34240
 
ADV. FINANCIAL MANAGEMENT ASSIGNMENT
ADV. FINANCIAL MANAGEMENT ASSIGNMENTADV. FINANCIAL MANAGEMENT ASSIGNMENT
ADV. FINANCIAL MANAGEMENT ASSIGNMENTRutuja Chudnaik
 

Similar to Risk analysis in capital bugeting (20)

Capital rationing
Capital rationingCapital rationing
Capital rationing
 
Capital budgeting and risk ii
Capital budgeting and risk   iiCapital budgeting and risk   ii
Capital budgeting and risk ii
 
Mark Weber-GFMI Presentation-Final-v1
Mark Weber-GFMI Presentation-Final-v1Mark Weber-GFMI Presentation-Final-v1
Mark Weber-GFMI Presentation-Final-v1
 
Risk analysis by raviteja & pranshul (26th august)
Risk analysis by raviteja & pranshul (26th august)Risk analysis by raviteja & pranshul (26th august)
Risk analysis by raviteja & pranshul (26th august)
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Measuring risk in investments
Measuring risk in investmentsMeasuring risk in investments
Measuring risk in investments
 
AgendaComprehending risk when modeling investment (project) de.docx
AgendaComprehending risk when modeling investment (project) de.docxAgendaComprehending risk when modeling investment (project) de.docx
AgendaComprehending risk when modeling investment (project) de.docx
 
An Assignment On Risks In Public Private Partnership
An Assignment On Risks In Public Private PartnershipAn Assignment On Risks In Public Private Partnership
An Assignment On Risks In Public Private Partnership
 
Financial Management - An overview
Financial Management - An overviewFinancial Management - An overview
Financial Management - An overview
 
Project finance
Project financeProject finance
Project finance
 
Aman ,FMS BHU
Aman ,FMS BHUAman ,FMS BHU
Aman ,FMS BHU
 
Chapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital BudgetingChapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital Budgeting
 
Chapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital BudgetingChapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital Budgeting
 
MBA 640 Final Project Milestone Two Guidelines and Rubric .docx
MBA 640 Final Project Milestone Two Guidelines and Rubric  .docxMBA 640 Final Project Milestone Two Guidelines and Rubric  .docx
MBA 640 Final Project Milestone Two Guidelines and Rubric .docx
 
Project Management- Managerial Appraisal
Project Management- Managerial AppraisalProject Management- Managerial Appraisal
Project Management- Managerial Appraisal
 
Risk management
Risk managementRisk management
Risk management
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Operation risk management in Private Equity firms
Operation risk management in Private Equity firmsOperation risk management in Private Equity firms
Operation risk management in Private Equity firms
 
1RUNNING HEAD Genesis Energy Capital Plan Report2Genesi.docx
1RUNNING HEAD Genesis Energy Capital Plan Report2Genesi.docx1RUNNING HEAD Genesis Energy Capital Plan Report2Genesi.docx
1RUNNING HEAD Genesis Energy Capital Plan Report2Genesi.docx
 
ADV. FINANCIAL MANAGEMENT ASSIGNMENT
ADV. FINANCIAL MANAGEMENT ASSIGNMENTADV. FINANCIAL MANAGEMENT ASSIGNMENT
ADV. FINANCIAL MANAGEMENT ASSIGNMENT
 

More from Dr. Ravneet Kaur

Stages of consumer buying behaviour
Stages of consumer buying behaviourStages of consumer buying behaviour
Stages of consumer buying behaviourDr. Ravneet Kaur
 
MARKET, MARKETING & ITS FEATURES
MARKET, MARKETING & ITS FEATURESMARKET, MARKETING & ITS FEATURES
MARKET, MARKETING & ITS FEATURESDr. Ravneet Kaur
 
Meaning of management accounting & it objectives
Meaning of management accounting & it objectivesMeaning of management accounting & it objectives
Meaning of management accounting & it objectivesDr. Ravneet Kaur
 
Installation of management accounting system
Installation of management accounting system Installation of management accounting system
Installation of management accounting system Dr. Ravneet Kaur
 
General principles of good reporting systems
General principles of good reporting systemsGeneral principles of good reporting systems
General principles of good reporting systemsDr. Ravneet Kaur
 
Features of management accounting
Features of management accountingFeatures of management accounting
Features of management accountingDr. Ravneet Kaur
 
IMPORTANCE OF INTERNATIONAL BUSINESS
IMPORTANCE OF INTERNATIONAL BUSINESSIMPORTANCE OF INTERNATIONAL BUSINESS
IMPORTANCE OF INTERNATIONAL BUSINESSDr. Ravneet Kaur
 
STAGES OF INTERNATIONAL BUSINESS
STAGES OF INTERNATIONAL BUSINESSSTAGES OF INTERNATIONAL BUSINESS
STAGES OF INTERNATIONAL BUSINESSDr. Ravneet Kaur
 
Advantages and disadvantages of INTERNATIONAL BUSINESS
Advantages and disadvantages of INTERNATIONAL BUSINESSAdvantages and disadvantages of INTERNATIONAL BUSINESS
Advantages and disadvantages of INTERNATIONAL BUSINESSDr. Ravneet Kaur
 
Centralisation & decentralisation
Centralisation & decentralisationCentralisation & decentralisation
Centralisation & decentralisationDr. Ravneet Kaur
 
Division of work and authority & responsibility
Division of work and authority & responsibilityDivision of work and authority & responsibility
Division of work and authority & responsibilityDr. Ravneet Kaur
 
Discipline ; unity of command
Discipline ; unity of commandDiscipline ; unity of command
Discipline ; unity of commandDr. Ravneet Kaur
 
Henri fayol's principles of management
Henri fayol's principles of managementHenri fayol's principles of management
Henri fayol's principles of managementDr. Ravneet Kaur
 

More from Dr. Ravneet Kaur (20)

Stages of consumer buying behaviour
Stages of consumer buying behaviourStages of consumer buying behaviour
Stages of consumer buying behaviour
 
Direct taxes
Direct taxesDirect taxes
Direct taxes
 
Consumer behaviour
Consumer behaviourConsumer behaviour
Consumer behaviour
 
MARKET, MARKETING & ITS FEATURES
MARKET, MARKETING & ITS FEATURESMARKET, MARKETING & ITS FEATURES
MARKET, MARKETING & ITS FEATURES
 
Meaning of management accounting & it objectives
Meaning of management accounting & it objectivesMeaning of management accounting & it objectives
Meaning of management accounting & it objectives
 
Management reporting
Management reportingManagement reporting
Management reporting
 
Installation of management accounting system
Installation of management accounting system Installation of management accounting system
Installation of management accounting system
 
General principles of good reporting systems
General principles of good reporting systemsGeneral principles of good reporting systems
General principles of good reporting systems
 
Consumer behaviour
Consumer behaviourConsumer behaviour
Consumer behaviour
 
Features of management accounting
Features of management accountingFeatures of management accounting
Features of management accounting
 
IMPORTANCE OF INTERNATIONAL BUSINESS
IMPORTANCE OF INTERNATIONAL BUSINESSIMPORTANCE OF INTERNATIONAL BUSINESS
IMPORTANCE OF INTERNATIONAL BUSINESS
 
STAGES OF INTERNATIONAL BUSINESS
STAGES OF INTERNATIONAL BUSINESSSTAGES OF INTERNATIONAL BUSINESS
STAGES OF INTERNATIONAL BUSINESS
 
Features of globalisation
Features of globalisationFeatures of globalisation
Features of globalisation
 
Advantages and disadvantages of INTERNATIONAL BUSINESS
Advantages and disadvantages of INTERNATIONAL BUSINESSAdvantages and disadvantages of INTERNATIONAL BUSINESS
Advantages and disadvantages of INTERNATIONAL BUSINESS
 
Ud & si
Ud & siUd & si
Ud & si
 
Centralisation & decentralisation
Centralisation & decentralisationCentralisation & decentralisation
Centralisation & decentralisation
 
Division of work and authority & responsibility
Division of work and authority & responsibilityDivision of work and authority & responsibility
Division of work and authority & responsibility
 
Discipline ; unity of command
Discipline ; unity of commandDiscipline ; unity of command
Discipline ; unity of command
 
Prof ravneet kaur
Prof ravneet kaurProf ravneet kaur
Prof ravneet kaur
 
Henri fayol's principles of management
Henri fayol's principles of managementHenri fayol's principles of management
Henri fayol's principles of management
 

Risk analysis in capital bugeting

  • 1. Financial Management  Unit 9  Unit 9  Risk Analysis in Capital Budgeting  Structure  9.1  Introduction  9.2  Types and sources of Risk in capital Budgeting  9.3  Risk Adjusted Discount Rate  9.4  Certainty Equivalent  9.5  Sensitivity Analysis  9.6  Probability Distribution Approach:  9.7  Decision – tree approach  9.8  Summary:  Terminal Questions  Answer to SAQs and TQs  9.1  Introduction  In the previous chapter on capital budgeting the project appraisal techniques were applied on the  assumption that the project will generate a given set of cash flows.  It is quite obvious that one of the limitations of DCF techniques is the difficulty in estimating  cash  flows with certain degree of certainty.  Certain projects when taken up by the firm will change the  business risk complexion of the firm.  This business risk complexion of the firm influences the required rate of return of the investors.  Suppliers of capital to the firm tend to be risk averse and the acceptance of a project that changes  the risk profile of the firm may change their perception of required rates of return for investing in  firm’s project.  Generally the projects that generate high returns are risky.  This will naturally alter the business  risk  of  the firm.   Because of  this high  risk perception  associated  with  the  new  project  a  firm is  forced  to  asses  the  impact  of  the  risk  on  the  firm’s  cash  flows  and  the  discount  factor  to  be  employed in the process of evaluation.  Definition of Risk:  Risk may be defined  as the variation of actual cash flows from  the expected  cash flows.  The term risk in capital budgeting decisions may be defined as the variability that is  likely to occur in future between the estimated and the actual returns.  Risk exists on account of  the inability of the firm to make perfect forecasts of cash flows. Sikkim Manipal University  147 
  • 2. Financial Management  Unit 9  Risk arises in project evaluation because the firm cannot predict the occurrence of possible future  events  with  certainty  and  hence,  cannot  make  any  correct  forecast  about  the  cash  flows.  The  uncertain economic conditions are the sources of uncertainty in the cash flows.  For  example,  a  company  wants  to  produce  and  market  a  new  product  to  their  prospective  customers.  The demand is affected by the general economic conditions.  Demand may be very  high if the country experiences higher economic growth.  On the other hand economic events like  weakening of US dollar, sub prime crises may trigger economic slow down.  This may create a  pessimistic demand drastically bringing down the estimate of cash flows.  Risk is associated with the variability of future returns of a project.  The greater the variability of  the expected returns, the riskier the project.  Every business decision involves risk.  Risk arises out of the uncertain conditions under which a  firm has to operate its activities.  Because of the inability of firms to forecast accurately cash flows  of  future  operations  the firms face the  risks  of  operations.  The  capital budgeting  proposals  are  not based on perfect forecast of costs and  revenues because the assumptions about the future  behaviour of costs and revenue may change.  Decisions have to be made in advance assuming  certain future economic conditions.  There are Many factors that affect forecasts of investment, cost and revenue.  1)  The business is affected by changes in political situations, monetary policies, taxation, interest  rates, policies of the central bank of the country on lending by banks etc.  2)  Industry  specific  factors  influence  the  demand  for  the  products  of  the  industry  to  which  the  firm belongs.  3)  Company  specific  factors  like  change  in  management,  wage  negotiations  with  the  workers,  strikes or lockouts affect company’s cost and revenue positions.  Therefore,  risk  analysis  in  capital  budgeting  is  part  and  parcel  of  enterprise  risk  management.  The best business decisions may not yield the desired results because the uncertain conditions  likely to emerge in future can materially alter the fortunes of the company.  Every  change  gives  birth  to  new  challenges.    New  challenges  are  the  source  of  new  opportunities.  A proactive firm will convert every problem into successful enterprise opportunities.  A firm which  avoids  new  opportunities for  the inherent  risk  associated with  it,  will  stagnate  and  degenerate.  Successful firms have empirical history of successful management of risks.  Therefore, analysing the risks of the project to reduce the element of uncertainty in execution has  become an essential  aspect of today’s corporate project management. Sikkim Manipal University  148 
  • 3. Financial Management  Unit 9  Learning Objectives:  After studying this unit, you should be able to understand the following.  1.  Define risk in capital budgeting.  2.  Examine the importance of risk analysis in capital budgeting.  3.  Methods of incorporating the risk factor in capital budgeting decision.  4.  Understand the types and sources of risk in capital budgeting descision  9.2 Types and sources of Risk in capital Budgeting  Risks in a project are many.  It is possible to identify three separate and distinct types of risk in  any project.  1)  Stand – alone risk:  it is measured by the variability of expected returns of the project.  2)  Portfolio risk:  A firm can be viewed as portfolio of projects having as certain degree of risk.  When new project added to the existing portfolio of project the risk profile the firm  will alter.  The degree of the change in the risk depend on the covariance of return from the new project  and the return from the existing portfolio of the projects. If the return from the new project is  negatively correlated with the return from portfolio, the risk of the firm will be further diversified  away.  3)  Market or beta risk:  It is measured by the effect of the project on the beta of the firm.  The  market risk for a project is difficult to estimate.  Stand alone risk is the risk of a project when the project is considered in isolation.  Corporate  risk is the projects risks to the risk of the firm.  Market risk is systematic risk.  The market risk  is the most important risk because of the direct influence it has on stock prices.  Sources of risk:  The sources of risks are  1.  Project – specific risk  2.  Competitive or Competition risk  3.  Industry – specific risk  4.  International risk  5.  Market risk  1.  Project – specific risk:  The sources of this risk could be traced to something quite specific  to  the  project.    Managerial  deficiencies  or  error  in  estimation of  cash flows  or  discount  rate  may lead to a situation of actual cash flows realised being less than that projected.  2.  Competitive  risk  or  Competition  risk:  unanticipated  actions  of  a  firm’s  competitors  will  materially  affect  the  cash  flows  expected  from  a  project.    Because  of  this  the actual  cash  flows from a project will be less than that of the forecast. Sikkim Manipal University  149 
  • 4. Financial Management  Unit 9  3.  Industry – specific:  industry – specific risks are those that affect all the firms in the industry.  It could be again grouped into technological risk, commodity risk and legal risk.  All these risks  will affect the earnings and cash flows of the project.  The changes in technology affect all the  firms not capable of adapting themselves to emerging new technology.  The  best  example  is  the  case  of  firms  manufacturing  motor  cycles  with  two  strokes  engines.  When technological innovations replaced the two stroke engines by the four stroke engines those  firms which could not adapt to new technology had to shut down their operations.  Commodity  risk  is  the  risk  arising  from  the  effect  of  price  –  changes  on  goods  produced  and  marketed.  Legal risk arises from changes in laws and regulations applicable to the industry to which the firm  belongs.  The best example is the imposition of service tax on apartments by the Government of  India  when  the  total  number  of  apartments  built  by  a  firm  engaged  in  that  industry  exceeds  a  prescribed limit.  Similarly changes in Import – Export policy of the Government of India have led  to the closure of some firms or sickness of some firms.  4.  International Risk:  these types of risks are faced by firms whose business consists mainly  of  exports  or  those  who  procure  their  main  raw  material  from  international  markets.    For  example, rupee – dollar crisis affected the software and BPOs because it drastically reduced  their  profitability.    Another  best  example  is  that  of  the  textile  units  in  Tirupur  in  Tamilnadu,  exporting  their  major  part  of  the  garments  produced.  Rupee  gaining  and  dollar  Weakening  reduced  their  competitiveness  in  the  global  markets.    The  surging  Crude  oil  prices  coupled  with  the  governments  delay  in  taking  decision  on  pricing  of  petro  products  eroded  the  profitability of oil marketing Companies in public sector like Hindustan Petroleum Corporation  Limited.  Another example is the impact of US sub prime crisis on certain segments of Indian  economy.  The changes in international political scenario also affect the operations of certain firms.  5.  Market Risk:  Factors like inflation, changes in interest rates, and changing general economic  conditions affect all firms and all industries.  Firms cannot diversify this risk in the normal course of business.  Techniques used for incorporation of risk factor in capital budgeting decisions  There  are  many  techniques  of  incorporation  of  risk  perceived  in  the  evaluation  of  capital  budgeting  proposals.    They  differ  in  their  approach  and  methodology  so  far as incorporation of  risk in the evaluation process is concerned.  Conventional techniques  Pay Back Period Sikkim Manipal University  150 
  • 5. Financial Management  Unit 9  The  oldest  and  commonly used  method  of  recognising risk  associated  with  a  capital  budgeting  proposal is pay back period.  Under this method, shorter pay back period is given preference to  longer  ones.    Firms  establish  guidelines  for  acceptance  or  rejections  of  projects  based  on  standards of pay back periods.  Payback period prefers projects of short – term pay backs to that of long – term pay backs.  The  emphasis is on the liquidity of the firm through recovery of capital.  Traditionally Indian business  community employs this technique in evaluating projects with very high level of uncertainty. The  changing trends in fashion make the fashion business, one of high risk and therefore, pay back  period  has  been  endorsed  by  tradition  in  India  to  take  decisions  on  acceptance  or  rejection of  such projects.  The usual risk in business is more concerned with the fore cast of cash flows.  It is  the down side risk of lower cash flows arising from lower sales and higher costs of operation that  matters in formulating standards of pay back.  Pay back period ignores time value of many (cash flows).  For example, the following details are  available in respect of two projects.  Particulars  Project A (Rs)  Project B (Rs)  Initial cash outlay  10 lakhs  10 lakhs  Cash flows  Year 1  5 lakhs  2 lakhs  Year 2  3 lakhs  2 lakhs  Year 3  1 lakhs  3 lakhs  Year 4  1 lakhs  3 lakhs  Both the projects have a pay back period of 4 years.  The project B is riskier than the Project A  because Project A recovers 80% of initial cash outlay in the first two years of its operation where  as  Project  B  generates  higher  Cash  inflows  only  in  the  latter  half  of  the  payback  period.    This  undermines the utility of payback period as a technique of incorporating risk in project evaluation.  This  method  considers  only  time  related  risks  and  ignores  all  other  risks  of  the  project  under  consideration.  Self Assessment Questions 2  1.  _____________ is measured by the variability of expected returns of the project.  2.  Market risk is measured by the effect of the project on the ____ of the firm.  3.  Firms cannot ____ market risk in the normal course of business.  4.  Impact  of  U.S  sub  prime  crisis  on  certain  segments  of  Indian  economy  is  and  example  of  _______________________. Sikkim Manipal University  151 
  • 6. Financial Management  Unit 9  9.3 Risk Adjusted Discount Rate  The basis of this approach is that there should be adequate reward in the form of return to firms  which decide to execute risky business projects. Man by nature is risk­averse and tries to avoid  risk.  To motivate firms to take up risky projects returns expected from the project shall have to be  adequate, keeping in view the expectations of the investors. Therefore risk premium need to be  incorporated in discount rate in the evaluation of risky project proposals.  Therefore the discount rate for appraisal of projects has two components.  Those components are  1.  Risk – free rate and risk premium  Risk Adjusted Discount rate = Risk free rate + Risk premium  Risk free rate is computed based on the return on government securities.  Risk  premium  is  the  additional  return  that  investors  require  as  compensation  for  assuming  the  additional risk associated with the project to be taken up for execution.  The  more  uncertain  the  returns  of  the  project  the  higher  the  risk.  Higher  the  risk  greater  the  premium.    Therefore,  risk  adjusted  Discount  rate  is  a  composite  rate  of  risk  free  rate  and  risk  premium of the project.  Example:  An investment will have an initial outlay of Rs 100,000. It is expected to generate cash  inflows as under:  Year  Cash in flows  1  40,000  2  50,000  3  15,000  4  30,000  Risk free rate of interest is 10%.  Risk premium is 10% (the risk characterising the project)  (a)  compute the NPV using risk free rate  (b)  Compute NPV using risk – adjusted discount rate  Solutions = (a) using risk – free rate  Year  Cash flows (inflows) Rs  PV Factor at 10%  PV of Cash flows (in flows)  1  40,000  0.909  36,360  2  50,000  0.826  41,300  3  15,000  0.751  11,265  4  30,000  0.683  20,490  PV of cash in flows  1,09,415 Sikkim Manipal University  152 
  • 7. Financial Management  Unit 9  PV of Cash outflows  1,00,000  NPV  9,415  (b)  Using risk – adjusted discount rate  Year  Cash in flows Rs  PV factor at 20%  PV of cash inflows  1  40,000  0.833  33,320  2  50,000  0.694  34,700  3  15,000  0.579  8,685  4  30,000  0.482  14,460  PV of Cash in flows  91,165  PV of Cash out flows  100,000  NPV  (8,835)  The project would be acceptable when no allowance is made for risk.  But it will not be acceptable if risk premium is added to the risk free rate.  It moves from positive  NPV to negative NPV.  If the firm were to use the internal rate of return, then the project would be accepted when IRR is  greater than the risk – adjusted discount rate.  Evaluation of Risk – adjusted discount rate:  Advantages:  1.  It is simple and easy to understand.  2.  Risk premium takes care of the risk element in future cash flows.  3.  It satisfies the businessmen who are risk – averse.  Limitations:  1.  There  are  no  objective  bases of  arriving  at  the  risk  premium.    In  this  process  the  premium  rates computed become arbitrary.  2.  The assumption that investors are risk – averse may not be true in respect of certain investors  who are willing to take risks.  To such investors, as the level of risk increases, the discount  rate would be reduced.  3.  Cash flows are not adapted to incorporate the risk adjustment for net cash in flows.  Self Assessment Questions 2  1. Risk premium is the __________________ that the investors require as compensation for Sikkim Manipal University  153 
  • 8. Financial Management  Unit 9  assumption of additional risks of project.  2. RADR is the sum of ______________ and ______________.  3. Higher the risk __________________ the premium.  4. Man by nature is risk­averse and tries to avoid risk.  9.4  Certainty Equivalent:  Under this method the risking uncertain, expected future cash flows are converted into cash flows  with  certainty.    Here  we  multiply  uncertain  future  cash  flows  by  the  certainty  –  equivalent  coefficient  to  convert  uncertain  cash  flows  into  certain  cash  flows.    The  certainty  equivalent  coefficient  is  also  known  as  the  risk  –  adjustment  factor.    Risk  adjustment  factor  is  normally  denoted by αt (Alpha).  It is the ratio of certain net cash flow to risky net cash flow  = Certainty Equivalent = Certain Cash flow  Risky Cash flow  The discount factor to be used is the risk free rate of interest.  Certainty equivalent coefficient is  between 0 and 1.  This risk – adjustment factor varies inversely with risk.  If risk is high a lower  value is used for risk adjustment.  If risk is low a higher coefficient of certainty equivalent is used  Illustration (Example)  A project costs Rs 50,000.  It is expected to generate cash inflows as under  Year  Cash in flows  Certainty Equivalent  1  32,000  0.9  2  27,000  0.6  3  20,000  0.5  4  10,000  0.3  Risk – free discount rate is 10% compute NPV  Answer:  Year  Uncertain cash  C E  Certain cash  PV Factor at  PV of certain cash  in flows  flows  10%  inflows  1  32,000  0.9  28,800  0.909  26,179  2  27,000  0.6  16,200  0.826  13,381  3  20,000  0.5  10,000  0.751  7,510  4  10,000  0.3  3,000  0.683  2,049 Sikkim Manipal University  154 
  • 9. Financial Management  Unit 9  PV of certain cash in  49,119  flows  Initial cash out lay  50,000  NPV  (881) negative  The project has a negative NPV.  Therefore, it is rejected.  If IRR is used the rate of discount at which NPV is equal to zero is computed and then compared  with the minimum (required) risk free rate.  If IRR is greater than specified minimum risk free rate,  the project is accepted, other wise rejected.  Evaluation:  It recognises risk.  Recognition of risk by risk – adjustment factor facilitates the conversion of risky  cash flows into certain cash flows.  But there are chances of being inconsistent in the procedure  employed from one project to another.  When forecasts pass through many layers of management, original forecasts may become highly  conservative.  Because of high conservation in this process only good projects are likely to be cleared when this  method is employed.  Certainty –  equivalent approach is considered to be theoretically superior to the risk –  adjusted  discount rate.  Self Assessment Questions 3  1. CE coefficient is the _______ .  2. Discount factors to be used under CE approach is _____________.  3. Because of high ______________ CE clears only good projects.  4. ___________ is considered to be superior to RADR  9.5  Sensitivity Analysis:  There  are  many  variables  like  sales,  cost  of  sales,  investments,  tax  rates  etc  which  affect  the  NPV  and  IRR  of a  project.    Analysing  the  change  in  the  project’s  NPV or  IRR  on  account  of a  given change in one of the variables is called Sensitivity Analysis.  It is a technique that shows the  change in NPV given a change in one of the variables that determine cash flows of a project.  It  measures the sensitivity of NPV of a project in respect to a change in one of the input variables of  NPV. Sikkim Manipal University  155 
  • 10. Financial Management  Unit 9  The  reliability  of  the  NPV  depends  on  the  reliability  of  cash  flows.    If  fore  casts  go  wrong  on  account  of  changes  in  assumed  economic  environments,  reliability  of  NPV  &  IRR  is  lost.  Therefore, forecasts are made under different economic conditions viz pessimistic, expected and  optimistic. NPV is arrived at for all the three assumptions.  Following steps are involved in Sensitivity analysis:  1.  Identification of variables that influence the NPV & IRR of the project.  2.  Examining and defining the mathematical relationship between the variables.  3.  Analysis of the effect of the change in each of the variables on the NPV of the project.  Example:    A  company  has  two  mutually exclusive  projects  under  consideration viz  project  A  &  project B.  Each project requires an initial cash outlay of Rs 3,00,000 and has an effective life of 10 years.  The  company’s  cost  of  capital  is  12%.    The  following  fore  cast  of  cash flows  are  made  by  the  management.  Economic  Project A  Project B  Environment  Annual cash inflows  Annual cash in flows  Pessimistic  65,000  25,000  Expected  75,000  75,000  Optimistic  90,000  1,00,000  What is the NPV of the project?  Which project should the management consider?  Given PVIFA = 5.650  Answer / Solutions  NPV of project A  Economic  Project  PVIFA  PV of cash in flows  NPV  Environment  cash inflows  at  12%  10  years  Pessimistic  65,000  5.650  3,67,250  67,250  Expected  75,000  5.650  4,23,750  1,23,750  Optimistic  90,000  5.650  5,08,500  2,08,500 Sikkim Manipal University  156 
  • 11. Financial Management  Unit 9  NPV of Project B  Pessimistic  25,000  5.650  1,41,250  (1,58,750)  Expected  75,000  5.650  4,23,750  1,23,750  Optimistic  1,00,000  5.650  5,65,000  2,65,000  Decision  1.  Under pessimistic conditions project A gives a positive NPV of Rs 67,250 and Project B has a  negative NPV of Rs 1,58,750 Project A is accepted.  2.  Under  expected  conditions, both  gave  some  positive  NPV  of Rs  1,23,000.  Any  one  of  two  may be accepted.  3.  Under optimistic conditions Project B has a higher NPV of Rs 2,65,000 compared to that  of  A’s NPV of Rs 2,08,500.  4.  Difference  between  optimistic  and  pessimistic  NPV  for  Project  A  is  Rs  1,41,250  and  for  Project B the difference is Rs 4,23,750.  5.  Project B is risky compared to Project A because the NPV range is of large differences.  Statistical Techniques:  Statistical techniques use analytical tools for assessing risks of investments.  Self  Assessment Questions 4  1. _____________ analysis the changes in the project NPV on account of a given change in one  of the input variables of the project.  2.  Examining  and  defining  the  mathematical  relation  between  the  variable  of  the  NPV  is  _________________________.  3. Forecasts under sensitivity analysis are made under __________.  9.6  Probability Distribution Approach:  When  we  incorporate the  chances  of occurrences  of various economic environments  computed  NPV  becomes  more  reliable.    The  chances  of  occurrences  are  expressed  in  the  form  of  probability.  Probability is the likelihood of occurrence of a particular economic environment.  After  assigning probabilities to future cash flows expected net present value is computed.  Illustration:    A  company  has  identified  a project  with  an  initial  cash  outlay  of  Rs  50,000.    The  following distribution of cash flow is given below for the life of the project of 3 years. Sikkim Manipal University  157 
  • 12. Financial Management  Unit 9  Year 1  Year 2  Year 3  Cash in flow  Probability  Cash in flow  Probability  Cash in flow  Probability  15,000  0.2  20,000  0.3  25,000  0.4  18,000  0.1  15,000  0.2  20,000  0.3  35,000  0.4  15,000  0.2  20,000  0.3  32,000  0.3  30,000  0.2  45,000  0.1  Discount rate is 10%  Year 1  = 15,000 x 0.2 + 18,000 x 0.1 + 35,000 x 0.4 + 32,000 x 0.300  3,000 + 1,800 + 14,000 + 9,600 = 28,400  Year 2  20,000 x 0.3 + 15,000 x 0.2 + 30,000 x 0.3 + 30,000 x 0.2  = 6,000 + 3,000 + 9,000 + 6,000 = 24,000  Year 3  25,000 x 0.4 + 20,000 x 0.3 + 40,000 x 0.2 + 5,000 x 0.1 =  10,000 + 6,000 + 8,000 + 4,500 == 28,500  PV of expected  Year  Expected cash inflows  PV factor at 10%  cash in flows  1  28,400  0.909  25,816  2  24,000  0.826  19,824  3  28,500  0.751  21,403  PV of expected cash in flows  67,043  PV of initial cash out lay  50,000  Expected NPV  17,043  Variance:  A  study  of  dispersion  of  cash  flows  of  projects  will  help  the  management  in  assessing  the  risk  associated  with  the  investment  proposal.    Dispersion  is  computed  by  variance  or  standard  deviation.    Variance  measures  the  deviation  of  each  possible  cash  flow  from  the  expected.  Square root of variance is standard deviation.  Example:  Following details are available in respect of a project which requires an initial cost of  Rs 5,00,000. Sikkim Manipal University  158 
  • 13. Financial Management  Unit 9  Year  Economic Conditions  Cash flows  Probability  1  High growth  2,00,000  0.3  Average growth  1,50,000  0.6  No growth  40,000  0.1  2  High growth  3,00,00  0.3  Average growth  2,00,000  0.5  No growth  5,00,000  0.2  3  High growth  4,00,000  0.2  Average growth  2,50,000  0.6  No growth  30,000  0.2  Discount rate is 10%  Solution:  Year 1  Economic Condition  Cash in flow  Probability  Expected value of Cash in flow  1  2  3  High growth  2,00,000  0.3  60,000  Average growth  1,50,000  0.6  90,000  No growth  40,000  0.1  4,000  Expected Value  1,54,000  Year 2  Economic Condition  Cash in flow  Probability  Expected value of Cash in flow  High growth  3,00,000  0.3  90,000  Average growth  2,00,000  0.5  1,00,000  No growth  50,000  0.2  10,000  Expected Value  2,00,000  Year 3  Economic Condition  Cash in flow  Probability  Expected value of Cash in flow  High growth  4,00,000  0.2  80,000  Average growth  2,50,000  0.6  1,50,000  No growth  30,000  0.2  6,000 Sikkim Manipal University  159 
  • 14. Financial Management  Unit 9  Expected Value of  2,36,000  Cash inflows  1,54,000         2,00,000  2,36,000  Expected NPV =  1.10               (1­10)  +  2  +  (1.10)  3  ­ 5,00,000 = 1,40,000 + 1, 65, 289 + 1, 77, 310 – 5,00,000 = (17,401) negative NPV  Standard Deviation for I year  2  2  Cash in flow  Expected Value  (C – E)  (C – E)  x prob  C  E  2  2  2,00,000  1,54,000  (46,000)  (46,000)  x 0.3 = 634800  000  2  2  1,50,000  1,54,000  (­ 4000)  (­ 4,000)  x 0.3 = 9600  000  2  2  40,000  1,54,000  ( ­ 1,14,000)  (­ 1,14,000)  x 0.3 = 12996 00 000  Total  1944  000 000  Standard deviation of Cash flows for I year = 44091  nd  For 2  year  2  2  Cash in flow  Expected Value  (C – E)  (C – E)  x prob  C  E  2  2  3,00,000  2,00,000  (1,00,000)  (1,00,000)  x 0.3 = 3000 000  000  2  2  2,00,000  2,00,000  (0)  (0)  x 0.5 = 0  2  2  50,000  2,00,000  ( ­ 1,50,000)  (­ 1,50,000)  x 0.2 = 45 00 000 000  Total  7500 00 000  nd  Variance of Cash flows for 2  year = 7500 000 000  nd  Standard Deviation of cash flows for 2  year = 8660  For the third year  2  2  Cash in flow  Expected Value  (C – E)  (C – E)  x prob  C  E  2  2  4,00,000  2,36,000  (1,64,000)  (1,64,000)  x 0.2 = 53792 00  000  2  2  2,50,000  2,36,000  (14,000)  (14,000)  x 0.6 = 1176 00 000  2  2  30,000  2,36,000  ( ­ 2,00,000)  (­ 2,00,000)  x 0.2 = 8000 000 000  Total  13496800 000  Sikkim Manipal University  160 
  • 15. Financial Management  Unit 9  rd  Variance of Cash flows for 3  year = 13496800 000  rd  Standard Deviation of cash flows for 3  year = 116175  Standard Deviation of NPV 2  2  2 Ö(44091)  (8660)  (116175)  sNPV  =  2  +  4  + 6  Ö(1.10)  (1.10)  (1.10)  = Ö1606625026 + 51223004 + 7618496131  = Ö9276344161  = 96314  Here the assumption is that there is no relationship between cash flows from one period to  another. Under this assumption the standard deviation  of NPV  is Rs 96,314.  On  the  other  hand,  if  cash  flows  are  perfectly  correlated,  cash  flows  of  all  years  have  linear correlation to one another, then  44091                8660                116175  sNPV  =  +  (1.10)  2  + (1.10)  3  1.10  = 40083 + 7157 + 87284 = 134524  The  standard  deviation  of  NPV  when  cash  flows  are  perfectly  correlated  will  be  higher  than that under the situation of independent cash flows.  Self Assessment Questions. 5  1.  Probability  distribution  approach  incorporates  the  probability  of  occurrences  of  various  economic environment, to make the NPV ________.  2. _______ is likelihood of occurrence of a particular economic environment.  9.7  Decision – tree approach:  Many project decisions are complex investment decisions.  Such complex investment decisions  involve a sequence of decisions over time.  Decisions tree can handle the sequential decisions of  complex  investment  proposals.    The  decision  of  taking  up  an  investment  project  is  broken  into  different stages.  At each stage the proposal is examined to decide whether to go ahead or not.  The  multi  –  stages  approach  can  be  handled  effectively  with  the  help  of  decision  trees.    A  decision tree presents graphically the relationship between a present decision and future events,  future decisions and the consequences of such decisions. Sikkim Manipal University  161 
  • 16. Financial Management  Unit 9  Example  R & D section of a company has developed an electric moped.  The firm is ready for pilot  production and test  marketing.    This  will  cost  Rs  20  million and  take  six  months.    Management  believes that there is a 70% chance that the pilot production and test marketing will be successful.  If successful the company can build a plant costing Rs 200 million.  The plant will generate annual cash in flow of Rs 50 million for 20 years if the demand is high or  an annual cash inflow or 20 million if the demand is low.  High demand has a probability of 0.6 and low demand has a probability of 0.4.  Cost of capital is  12%.  Suggest  the  optimal  course  of  action  using  decision  tree  analysis  (Bangalore  University  MBA,  adapted).  High Demand  Probability 0.6  C21  D21  Investment  Annual Cash inflow  Rs.200 million  Rs.50 million  C2  D11  Carry out pilot  Production  C11  Success  Annual Cash inflow  And Market  D2  Rs.20 million  test (20 million)  0.7 D22  Stop  C22  Low Demand  C1  Probability  0.4  D  D3  C12  failure  D31  Stop  Probability 0.3  D12  Do Nothing  Working Notes:  From right hand side of the decision tree  I  step:    Computation of Expected  Monetary  Value at point  C2.    Here EMV  represents expected  NPV.  Cash in flow  Probability  Expected value of cash inflows  50  0.6  30  20  0.4  8  EMV  38  Present Value of EMV = Expected value of cash inflow x PVIFA (12% 20)  38 x 7.469 = Rs 283.82 million  Sikkim Manipal University  162 
  • 17. Financial Management  Unit 9  Step 2:  Computation of EMV at decision point D2.  Decision taken  Consequences  The resulting EMV at this level  D2  Invest Rs 200 million  283.82 – 200 83.82 million  D22  Stop  0  Here the decision criterion is “select the EMV with the highest value”.  Stage 3:  Therefore EMV with Rs 83.82 million will be considered therefore; we select the decision taken at  D2,  Stage 4:  Computation of EMV at the point C,  EMV  Probability  Expected Value  83.82  0.7  58.67  0  0.3  0  EMV at this stage  58.67  Step 5:  Compute EMV at decisions point D,  Decision taken  Consequences  The resulting Em at this  level  D11 carry out pilot  Invest  58.67 – 20 = Rs 38.67 Million  production and market test  20 million  D12 Do nothing  0  0  EMV at this stage  38.67 Million  (Apply the EMV criterion) i.e  select the EMV with the  highest value  Therefore optimal strategy is  1.  Carry out pilot production and market test.  2.  If  the  result  of pilot production  and  market  test  is  successful,  go  ahead  with  the investment  decision of Rs 200 million in establishing a plant.  3.  If the result of pilot production and market test is future, stop. Sikkim Manipal University  163 
  • 18. Financial Management  Unit 9  Evaluation of Decision tree approach:  1.  It portrays inter – related, sequential  and critical multi dimensional elements of major project  decisions.  2.  Adequate attention is given to the critical aspects in an investment decision which spread over  a time sequence.  3.  Complex  projects  involve  huge  out  lay  and  hence  risky.    There  is  the  need  to  define  and  evaluate  scientifically  the  complex  managerial  problems  arising  out  of  the  sequence  of  interrelated decisions with consequential outcomes of high risk.  It is effectively answered by  decision tree approach.  4.  Structuring a  complex project  decision  with  many  sequential investment  decisions demands  effective project risk management.  This is possible only with the help of an analytical tool like  decision tree approach.  5.  Able  to  eliminate unprofitable outcomes  and helps  in  arriving  at  optimum decision stages in  time sequence.  Self Assessment Questions 6  1. Decision tree can handle the _____________ of complex investment proposals.  2. _____ portrays inter­related, sequential and critical multi dimensional elements of major project  decisions.  3.  Adequate  attention  is  given  to  the  ______  in  an  investment  decision  under  decision  tree  approach’s.  4. ____________ are effectively handled by decision tree approach’s .  9.8 Summary  Risk in project evaluation arises on account of the inability of the firm to predict  the performance  of the firm  with  certainty.  Risk in capital budgeting  decision  may  be  defined  as  the variability of  actual  returns  from  the  expected.  There  are  many  factors  that  affect  forecasts  of  investment,  costs and revenues of a project. It is possible to identify three type of risk in any project, viz stand­  alone risk, corporate risk and market risk. The sources of risks are:  a.  Project  b.  Competition  c.  Industry  d.  International factors and  e.  Market Sikkim Manipal University  164 
  • 19. Financial Management  Unit 9  The techniques for incorporation of risk factor in capital budgeting decision could be grouped into  conventional techniques and statistical techniques.  Terminal Questions  1.  Define risk. Examine the need for assessing the risks in a project.  2.  Examine the type and sources of risk in capital budgeting .  3.  Examine  risk  adjusted  discount  rate  as  a  technique  of  incorporating  risk  factor  in  capital  budgeting.  4.  Examine the steps involved in sensitivity analysis.  5.  Examine the features of Decision­tree approaches.  Answer for Self Assessment Questions  Self Assessment Questions 1  1.  Stand­alone risk.  2.  Beta  3.  Diversify  4.  International risk  Self Assessment Question 2  1.  Additional return  2.  Risk free rate, risk premium.  3.  Greater.  Self Assessment Question 3  1.  Risk­ adjustment factor  2.  Risk free rate of interest.  3.  Conservation.  4.  CE  Self Assessment Question 4  1.  Sensitivity analysis  2.  One of the steps of sensitivity analysis  3.  Different economic conditions Sikkim Manipal University  165 
  • 20. Financial Management  Unit 9  Self Assessment Question 5  1.  More reliable  2.  Probability  Self Assessment Question 6  1.  Sequential decisions  2.  Decision tree.  3.  Critical aspects  4.  Complex projects.  Answer for Terminal Questions  1.  Refer to units 9.1  2.  Refer to units 9. 2  3.  Refer to units 9.3  4.  Refer to unit 9.5  5.  Refer to unit 9.7 Sikkim Manipal University  166