SlideShare a Scribd company logo
1 of 22
Download to read offline
Proper Concrete
Design Methodology
          Roger Faulkner, PE
   Director of Engineering & Promotion
             Ohio Concrete
Overview
   TYPES OF PAVEMENT

 ASSOCIATED DESIGN METHODS

 PARKING LOT DESIGN

 PAVING – “The New Realities”
TYPES OF PAVEMENT

   Highways
     Design Speed: 55 mph and greater
     High Frequency of Heavy Truck Loads

 Streets and Local Roads
      Design Speed: 25 mph to 45 mph
      Low to Medium Frequency of Heavy Truck Loads

 Parking Lots and Drives
      Design Speed: Typically Less than 15 mph
      Minimal (or None) to Low Frequency of Heavy Truck Loads
DESIGN METHODS

   Highways
    Linear Pavement – 2 or more lanes wide
    Transverse Joints - Dowels
    Edge Support – Tied Shoulders
    Concrete Design Thickness – 9” or greater
 AASHTO 1993 Highway Design Guide
    ODOT Pavement Design Manual
    ACPA “WinPAS” Software
DESIGN METHODS

   Streets and Local Roads
    Linear Pavement – 2 or more lanes wide
    Transverse Joints – Dowels if Needed
    Edge Support – Curb and Gutter or widened lane
    Concrete Design Thickness – 6” to 8”
 ACPA
     “StreetPave” Software
DESIGN METHODS

   Parking Lots and Drives
    Complex Area Pavement – Width Varies
    Joints – Square Panels or Length to Width <1.25
    Edge Support – Integral Curb or Thickened Edge
    Concrete Design Thickness – 4” to 8”
 American Concrete Institute
    ACI 330R-08 – “Guide for the Design and
     Construction of Concrete Parking Lots”
PARKING LOT DESIGN
 ACI 330R-08
 Section 3.6 –
 “Thickness Design”
 Plain Concrete
 Pavement
PARKING LOT DESIGN
 ACI 330R-08, Section 3.6
 Traffic Categories
PARKING LOT DESIGN
 Subgrade Support
   Typ. K=100 psi/in.
 Concrete Flexural Strength
   MOR (psi) = 10 x Square Root of f’c
   For f’c= 3500 to 5000 psi
    MOR = 600 to 670 psi
 Table 3.4, Recommended 20 Year
 Design Thicknesses, with no dowels
PARKING LOT DESIGN
PARKING LOT DESIGN
 Steel Reinforcement
   Per 3.8.1 – “The use of distributed steel
   reinforcement will not add to the load-carrying
   capacity of the pavement and should not be
   used in anticipation of poor construction
   practices.”
   Replaced with Shorter Joint Spacings
PARKING LOT DESIGN
 Joint Spacing
   Per Section 3.7
    Joint Patterns should be approx. square
    Length Not > than 125% of Width
    Spacing = 2 x thickness in Feet
   Jointing Pattern can be used to delineate
   parking lanes and parking stalls
PARKING LOT DESIGN
 Tie-Bars
  Per 3.8.3 – Tie only the first longitudinal joint
  from the pavement edge to keep the outside slab
  from separating
  Tie Centerline Joints of Entrance Drives
 No. 4, ½” dia. – Typ. 24” long (See Table 3.7)
   30” spacing
PARKING LOT DESIGN

 Dowels
  Per 3.8.2 – Dowels generally not needed for
  parking lots
  Per Table 3.4 – Category D Thickness can be
  reduced 1” to 7”, if dowels are used
PARKING LOT DESIGN
 Table 3.4 of ACI 330R-08
  Developed using
  ACPA“StreetPave” Computer
  Program MC003

 It is a pavement design tool for
  low volume roads (streets &
  local roads)

 It is based on the PCA’s
  pavement thickness design
  methodology

 PCA assesses adequacy of
  concrete thickness using both
  fatigue and erosion criteria
PARKING LOT DESIGN

   Engineering Services Center “ESC”
     CAD parking lot and intersection layout
    Concrete Mix Design
    Pavement Thickness and Joint Spacing


 FREE Service!
Paving - “The New Realities”

 Concrete and Asphalt have reached parity on
 Initial Cost
 ODOT Initiated Alternate Pavement Bids
 Those Projects Yielded HUGE Cost Savings
ODOT Alternate Bid Projects

 5 Projects Bid in 2009 w/ Alternate Pavement Bids
 State’s Estimate for the 5 Projects - $405 Million
 Total Award for the 5 Projects - $345 Million
 $60 Million Cost Savings or approx. 15%
 Non-Alternate Bid Projects
   3 Asphalt Only - $170 M Est., $157 M Award
   $13 Million Savings – Ave. 7% Cost Savings
 Alternate Bids Yield TWICE the Costs Savings!
ODOT Alternate Bid Projects

 Key Aspects of Alternate Bid Process
   Increased Competition
     More bidders
     Plus, competition between Asphalt and Concrete Industries
   No Material Price Adjustments
     ODOT Proposal Note 115, Price Adjustment Exclusions
  Contractor Required to Submit Prices for Both
    ODOT chooses the alternate
ODOT Drafts New Policy

 Projects require an LCCA for both concrete and
 asphalt pavement alternates
  If LCCA’s >10%
    Alternate with Lower LCCA is selected alternate
    An Updated LCCA Required before Final Tracings
       • If LCCA’s still >10% - project bid with original alternate
       • If LCCA’s <10% - plans modified to bid with both concrete and
         asphalt pavement alternates
  If LCCA’s <10%
    Plans developed to bid for both concrete and asphalt alternates
Questions?
Proper Concrete
Design Methodology

   THANK YOU !

More Related Content

What's hot

Tysons Boulevard and Galleria Drive Pedestrian Access Improvements
Tysons Boulevard and Galleria Drive Pedestrian Access ImprovementsTysons Boulevard and Galleria Drive Pedestrian Access Improvements
Tysons Boulevard and Galleria Drive Pedestrian Access ImprovementsFairfax County
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2Crosstown TO
 
Torrey pines road corridor study final
Torrey pines road corridor study finalTorrey pines road corridor study final
Torrey pines road corridor study finalkday1
 
Keelesdale station open house
Keelesdale station open houseKeelesdale station open house
Keelesdale station open houseCrosstown TO
 
Science centre station open house
Science centre station open houseScience centre station open house
Science centre station open houseCrosstown TO
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open HouseCrosstown TO
 
The District at Leander Overview 8/3/17
The District at Leander Overview 8/3/17The District at Leander Overview 8/3/17
The District at Leander Overview 8/3/17City of Leander
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationCrosstown TO
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house Crosstown TO
 
Jonathan Danos Valuable Experience and Works
Jonathan Danos Valuable Experience and WorksJonathan Danos Valuable Experience and Works
Jonathan Danos Valuable Experience and WorksJonathan Danos
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open houseCrosstown TO
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house Crosstown TO
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Crosstown TO
 
Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017melissanatech
 

What's hot (20)

Tysons Boulevard and Galleria Drive Pedestrian Access Improvements
Tysons Boulevard and Galleria Drive Pedestrian Access ImprovementsTysons Boulevard and Galleria Drive Pedestrian Access Improvements
Tysons Boulevard and Galleria Drive Pedestrian Access Improvements
 
King Street Pilot Public Meeting
King Street Pilot Public MeetingKing Street Pilot Public Meeting
King Street Pilot Public Meeting
 
2016 master slides
2016 master slides2016 master slides
2016 master slides
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Torrey pines road corridor study final
Torrey pines road corridor study finalTorrey pines road corridor study final
Torrey pines road corridor study final
 
Keelesdale station open house
Keelesdale station open houseKeelesdale station open house
Keelesdale station open house
 
Science centre station open house
Science centre station open houseScience centre station open house
Science centre station open house
 
Eglinton Park
Eglinton ParkEglinton Park
Eglinton Park
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open House
 
The District at Leander Overview 8/3/17
The District at Leander Overview 8/3/17The District at Leander Overview 8/3/17
The District at Leander Overview 8/3/17
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting Presentation
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house
 
sr 90 sw 8th street at sw 87 avenue pd&e study
sr 90 sw 8th street at sw 87 avenue pd&e studysr 90 sw 8th street at sw 87 avenue pd&e study
sr 90 sw 8th street at sw 87 avenue pd&e study
 
Public Workshop #1
Public Workshop #1Public Workshop #1
Public Workshop #1
 
Jonathan Danos Valuable Experience and Works
Jonathan Danos Valuable Experience and WorksJonathan Danos Valuable Experience and Works
Jonathan Danos Valuable Experience and Works
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open house
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house
 
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015
 
Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017
 

Viewers also liked

Ingredients and mixing concrete
Ingredients and mixing concreteIngredients and mixing concrete
Ingredients and mixing concreteJustin Myint
 
Ingredients and mixing concrete
Ingredients and mixing concreteIngredients and mixing concrete
Ingredients and mixing concreteJustin Myint
 
ROADS/PAVEMENT & TYPES OF ROAD BY ENGR SAAD ULLAH WEC
ROADS/PAVEMENT  &  TYPES OF ROAD BY ENGR SAAD ULLAH WECROADS/PAVEMENT  &  TYPES OF ROAD BY ENGR SAAD ULLAH WEC
ROADS/PAVEMENT & TYPES OF ROAD BY ENGR SAAD ULLAH WECSAAD ULLAH
 
Introduction to Pharmacoepidemiology
Introduction to PharmacoepidemiologyIntroduction to Pharmacoepidemiology
Introduction to PharmacoepidemiologyPerficient
 
PAVEMENT DESIGN (Group 9)
PAVEMENT DESIGN (Group 9)PAVEMENT DESIGN (Group 9)
PAVEMENT DESIGN (Group 9)eddie fonte
 
Pharmacoepidemiology
PharmacoepidemiologyPharmacoepidemiology
Pharmacoepidemiologylateef khan
 
Ideas for pharmacy students on final year project : Possible Research Fields
Ideas for pharmacy students on final year project : Possible Research FieldsIdeas for pharmacy students on final year project : Possible Research Fields
Ideas for pharmacy students on final year project : Possible Research FieldsTareq ✅
 
Studies of vaccine safety (Pharmacoepidemiology) V PharmD
Studies of vaccine safety (Pharmacoepidemiology)  V PharmDStudies of vaccine safety (Pharmacoepidemiology)  V PharmD
Studies of vaccine safety (Pharmacoepidemiology) V PharmDDr.Sohel Memon
 
Rigid pavement distress
Rigid pavement distress Rigid pavement distress
Rigid pavement distress Ankit Sarkar
 
PHARMACOEPIDEMIOLOGY
PHARMACOEPIDEMIOLOGYPHARMACOEPIDEMIOLOGY
PHARMACOEPIDEMIOLOGYAISHASID
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 
Concrete design mix (ss)
Concrete design mix (ss)Concrete design mix (ss)
Concrete design mix (ss)Kezar Ali. Shah
 
Mix Design of Concrete
Mix Design of ConcreteMix Design of Concrete
Mix Design of ConcreteVivek Das
 
Process of manufacture of concrete
Process of manufacture of  concreteProcess of manufacture of  concrete
Process of manufacture of concreteManpreet Singh
 

Viewers also liked (20)

Concrete pavement design
Concrete pavement designConcrete pavement design
Concrete pavement design
 
Ingredients and mixing concrete
Ingredients and mixing concreteIngredients and mixing concrete
Ingredients and mixing concrete
 
Pavement design
Pavement designPavement design
Pavement design
 
Ingredients and mixing concrete
Ingredients and mixing concreteIngredients and mixing concrete
Ingredients and mixing concrete
 
ROADS/PAVEMENT & TYPES OF ROAD BY ENGR SAAD ULLAH WEC
ROADS/PAVEMENT  &  TYPES OF ROAD BY ENGR SAAD ULLAH WECROADS/PAVEMENT  &  TYPES OF ROAD BY ENGR SAAD ULLAH WEC
ROADS/PAVEMENT & TYPES OF ROAD BY ENGR SAAD ULLAH WEC
 
Introduction to Pharmacoepidemiology
Introduction to PharmacoepidemiologyIntroduction to Pharmacoepidemiology
Introduction to Pharmacoepidemiology
 
PAVEMENT DESIGN (Group 9)
PAVEMENT DESIGN (Group 9)PAVEMENT DESIGN (Group 9)
PAVEMENT DESIGN (Group 9)
 
Pharmacoepidemiology
PharmacoepidemiologyPharmacoepidemiology
Pharmacoepidemiology
 
Ideas for pharmacy students on final year project : Possible Research Fields
Ideas for pharmacy students on final year project : Possible Research FieldsIdeas for pharmacy students on final year project : Possible Research Fields
Ideas for pharmacy students on final year project : Possible Research Fields
 
Studies of vaccine safety (Pharmacoepidemiology) V PharmD
Studies of vaccine safety (Pharmacoepidemiology)  V PharmDStudies of vaccine safety (Pharmacoepidemiology)  V PharmD
Studies of vaccine safety (Pharmacoepidemiology) V PharmD
 
Pharmacoepidemiology
PharmacoepidemiologyPharmacoepidemiology
Pharmacoepidemiology
 
Rigid pavement distress
Rigid pavement distress Rigid pavement distress
Rigid pavement distress
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
 
PHARMACOEPIDEMIOLOGY
PHARMACOEPIDEMIOLOGYPHARMACOEPIDEMIOLOGY
PHARMACOEPIDEMIOLOGY
 
Concrete test on site
Concrete test on siteConcrete test on site
Concrete test on site
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
Concrete design mix (ss)
Concrete design mix (ss)Concrete design mix (ss)
Concrete design mix (ss)
 
Pavement design
Pavement designPavement design
Pavement design
 
Mix Design of Concrete
Mix Design of ConcreteMix Design of Concrete
Mix Design of Concrete
 
Process of manufacture of concrete
Process of manufacture of  concreteProcess of manufacture of  concrete
Process of manufacture of concrete
 

Similar to Proper Concrete Design Methodology

S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...R C Patil Patil
 
141221_CebePortfolio_LR
141221_CebePortfolio_LR141221_CebePortfolio_LR
141221_CebePortfolio_LRJack Cebe, PLA
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Malyar Talash
 
Reading and Analyzing of Non-Newtonian speed Bumps (speed breakers)
Reading and Analyzing of Non-Newtonian speed Bumps (speed breakers)Reading and Analyzing of Non-Newtonian speed Bumps (speed breakers)
Reading and Analyzing of Non-Newtonian speed Bumps (speed breakers)IRJET Journal
 
GTA West Corridor - Project Proposal - Ryerson University Capstone 2021
GTA West Corridor - Project Proposal - Ryerson University Capstone 2021GTA West Corridor - Project Proposal - Ryerson University Capstone 2021
GTA West Corridor - Project Proposal - Ryerson University Capstone 2021Neha Patel
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking pptPatel Tapan
 
Seafarer's Center Parking Lot
Seafarer's Center Parking LotSeafarer's Center Parking Lot
Seafarer's Center Parking LotMaha Al Soufi
 
Economics of upgrading a gravel road to Otta seal surface
Economics of upgrading a gravel road to Otta seal surfaceEconomics of upgrading a gravel road to Otta seal surface
Economics of upgrading a gravel road to Otta seal surfaceAliNahvi
 
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...Hossam Shafiq I
 
Pavement Design_IRC-37-2018.pptx
Pavement Design_IRC-37-2018.pptxPavement Design_IRC-37-2018.pptx
Pavement Design_IRC-37-2018.pptxJignesh patel
 
Value engineering and application
Value engineering and applicationValue engineering and application
Value engineering and applicationSourish ghosh
 

Similar to Proper Concrete Design Methodology (20)

S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
 
141221_CebePortfolio_LR
141221_CebePortfolio_LR141221_CebePortfolio_LR
141221_CebePortfolio_LR
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
 
Reading and Analyzing of Non-Newtonian speed Bumps (speed breakers)
Reading and Analyzing of Non-Newtonian speed Bumps (speed breakers)Reading and Analyzing of Non-Newtonian speed Bumps (speed breakers)
Reading and Analyzing of Non-Newtonian speed Bumps (speed breakers)
 
#41 Times Change, People Change, Transportation Needs Change - LaPlante
#41 Times Change, People Change, Transportation Needs Change - LaPlante#41 Times Change, People Change, Transportation Needs Change - LaPlante
#41 Times Change, People Change, Transportation Needs Change - LaPlante
 
GTA West Corridor - Project Proposal - Ryerson University Capstone 2021
GTA West Corridor - Project Proposal - Ryerson University Capstone 2021GTA West Corridor - Project Proposal - Ryerson University Capstone 2021
GTA West Corridor - Project Proposal - Ryerson University Capstone 2021
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Project For Transportation Reform Lunch
Project For Transportation Reform LunchProject For Transportation Reform Lunch
Project For Transportation Reform Lunch
 
Public Workshop #3
Public Workshop #3Public Workshop #3
Public Workshop #3
 
Public Workshop #3
Public Workshop #3Public Workshop #3
Public Workshop #3
 
Seafarer's Center Parking Lot
Seafarer's Center Parking LotSeafarer's Center Parking Lot
Seafarer's Center Parking Lot
 
V35119123
V35119123V35119123
V35119123
 
Economics of upgrading a gravel road to Otta seal surface
Economics of upgrading a gravel road to Otta seal surfaceEconomics of upgrading a gravel road to Otta seal surface
Economics of upgrading a gravel road to Otta seal surface
 
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...
 
Designing the highway
Designing the highwayDesigning the highway
Designing the highway
 
Parking geometry
Parking geometryParking geometry
Parking geometry
 
Roads & bridges
Roads & bridgesRoads & bridges
Roads & bridges
 
Pavement Design_IRC-37-2018.pptx
Pavement Design_IRC-37-2018.pptxPavement Design_IRC-37-2018.pptx
Pavement Design_IRC-37-2018.pptx
 
Asphalt Parking Lot Construction Best Practices
Asphalt Parking Lot Construction Best PracticesAsphalt Parking Lot Construction Best Practices
Asphalt Parking Lot Construction Best Practices
 
Value engineering and application
Value engineering and applicationValue engineering and application
Value engineering and application
 

Proper Concrete Design Methodology

  • 1. Proper Concrete Design Methodology Roger Faulkner, PE Director of Engineering & Promotion Ohio Concrete
  • 2. Overview  TYPES OF PAVEMENT  ASSOCIATED DESIGN METHODS  PARKING LOT DESIGN  PAVING – “The New Realities”
  • 3. TYPES OF PAVEMENT  Highways Design Speed: 55 mph and greater High Frequency of Heavy Truck Loads  Streets and Local Roads Design Speed: 25 mph to 45 mph Low to Medium Frequency of Heavy Truck Loads  Parking Lots and Drives Design Speed: Typically Less than 15 mph Minimal (or None) to Low Frequency of Heavy Truck Loads
  • 4. DESIGN METHODS  Highways Linear Pavement – 2 or more lanes wide Transverse Joints - Dowels Edge Support – Tied Shoulders Concrete Design Thickness – 9” or greater  AASHTO 1993 Highway Design Guide ODOT Pavement Design Manual ACPA “WinPAS” Software
  • 5. DESIGN METHODS  Streets and Local Roads Linear Pavement – 2 or more lanes wide Transverse Joints – Dowels if Needed Edge Support – Curb and Gutter or widened lane Concrete Design Thickness – 6” to 8”  ACPA  “StreetPave” Software
  • 6. DESIGN METHODS  Parking Lots and Drives Complex Area Pavement – Width Varies Joints – Square Panels or Length to Width <1.25 Edge Support – Integral Curb or Thickened Edge Concrete Design Thickness – 4” to 8”  American Concrete Institute ACI 330R-08 – “Guide for the Design and Construction of Concrete Parking Lots”
  • 7. PARKING LOT DESIGN  ACI 330R-08  Section 3.6 – “Thickness Design”  Plain Concrete Pavement
  • 8. PARKING LOT DESIGN  ACI 330R-08, Section 3.6  Traffic Categories
  • 9. PARKING LOT DESIGN  Subgrade Support  Typ. K=100 psi/in.  Concrete Flexural Strength  MOR (psi) = 10 x Square Root of f’c  For f’c= 3500 to 5000 psi MOR = 600 to 670 psi  Table 3.4, Recommended 20 Year Design Thicknesses, with no dowels
  • 11. PARKING LOT DESIGN  Steel Reinforcement  Per 3.8.1 – “The use of distributed steel reinforcement will not add to the load-carrying capacity of the pavement and should not be used in anticipation of poor construction practices.”  Replaced with Shorter Joint Spacings
  • 12. PARKING LOT DESIGN  Joint Spacing  Per Section 3.7 Joint Patterns should be approx. square Length Not > than 125% of Width Spacing = 2 x thickness in Feet  Jointing Pattern can be used to delineate parking lanes and parking stalls
  • 13. PARKING LOT DESIGN  Tie-Bars  Per 3.8.3 – Tie only the first longitudinal joint from the pavement edge to keep the outside slab from separating  Tie Centerline Joints of Entrance Drives No. 4, ½” dia. – Typ. 24” long (See Table 3.7) 30” spacing
  • 14. PARKING LOT DESIGN  Dowels  Per 3.8.2 – Dowels generally not needed for parking lots  Per Table 3.4 – Category D Thickness can be reduced 1” to 7”, if dowels are used
  • 15. PARKING LOT DESIGN  Table 3.4 of ACI 330R-08 Developed using ACPA“StreetPave” Computer Program MC003  It is a pavement design tool for low volume roads (streets & local roads)  It is based on the PCA’s pavement thickness design methodology  PCA assesses adequacy of concrete thickness using both fatigue and erosion criteria
  • 16. PARKING LOT DESIGN  Engineering Services Center “ESC”  CAD parking lot and intersection layout Concrete Mix Design Pavement Thickness and Joint Spacing  FREE Service!
  • 17. Paving - “The New Realities”  Concrete and Asphalt have reached parity on Initial Cost  ODOT Initiated Alternate Pavement Bids  Those Projects Yielded HUGE Cost Savings
  • 18. ODOT Alternate Bid Projects  5 Projects Bid in 2009 w/ Alternate Pavement Bids  State’s Estimate for the 5 Projects - $405 Million  Total Award for the 5 Projects - $345 Million  $60 Million Cost Savings or approx. 15%  Non-Alternate Bid Projects  3 Asphalt Only - $170 M Est., $157 M Award  $13 Million Savings – Ave. 7% Cost Savings  Alternate Bids Yield TWICE the Costs Savings!
  • 19. ODOT Alternate Bid Projects  Key Aspects of Alternate Bid Process  Increased Competition  More bidders  Plus, competition between Asphalt and Concrete Industries  No Material Price Adjustments  ODOT Proposal Note 115, Price Adjustment Exclusions  Contractor Required to Submit Prices for Both ODOT chooses the alternate
  • 20. ODOT Drafts New Policy  Projects require an LCCA for both concrete and asphalt pavement alternates If LCCA’s >10% Alternate with Lower LCCA is selected alternate An Updated LCCA Required before Final Tracings • If LCCA’s still >10% - project bid with original alternate • If LCCA’s <10% - plans modified to bid with both concrete and asphalt pavement alternates If LCCA’s <10% Plans developed to bid for both concrete and asphalt alternates