Elimination of Rejection at OP80
because of Cross oil hole opn. missing in
Camshaft Line
Project Done By: Kamlashish Goswami
2 10/17/201
6
Ashok Leyland Presentation (PNR)
1) Select the process
1.1 Select the process for improvement
considering the priority
- Rejection at OP80 ( cross oil hole position out )
FY13-14 DEFECT Feedback
1.2 Setting up target :Elimination of
Rejection at OP80 ( cross oil hole
position out)
Correct Oil
Hole
Position
Oil Hole
Position
shift
2.15mm shift
OK
Not OK
3 10/17/201
6
Ashok Leyland Presentation (PNR)
2) System Analysis
2.1 Clarify own process step :
Process at Camshaft machining
2.2 Check Defect Step:
Op. No. Op. Name
10 Facing & centering
20 Straightening
30 Rough Turning
40 Finish Turning
50 Key-way milling
60 Cam Milling
70 Gundrilling
80 Oil hole drilling
90 H.P. Washing
100 Induction Hardening
110 Tempering
120 Straightening
130 Recentering
140 Journal grinding
150 Cam Lobe grinding
160 Deburring
170 Crack detector
180 Intermediate washing m/c
190 Accurate Inspection
200 Lobe Lapping m/c
210 Phosphating Plant
220 Journal Lapping
230 Washing +Oiling
Failure Process
that makes In
process Defect
Operation missing
(No Poka-Yoke available to
prevent the opn. missing part
to move on the next opn.)
4 10/17/201
6
Ashok Leyland Presentation (PNR)
2) System Analysis Contd…
2.3 Clarify Occurrence condition:
Appearance
OP70 Gun drilling operation
Problem : Opn. Completion signal given
to m/c by operator without inspection
Manufacturing
Defective Condition
4M
Man (X)
No SOP available to start the
m/c after any interruption
Machine N/A
Method
(X)
Operation missing
 No Poka-Yoke available for
human error
Material N/A
2.4 Root Cause Analysis:
Occurrence Side:
Cross oil hole
position out Pre Gun
drilling opn.
missing
Part location
shift during FE
drilling
because of
hitting in
Rapid
Opn. Completion
signal given to m/c
by operator
without inspection
2.5 Problem Summary :
No Poka-Yoke
available to
detect the opn.
Miss part
Root Cause:
5 10/17/201
6
Ashok Leyland Presentation (PNR)
3) Poka-Yoke implementation Plan
3.1 Create Idea 3.2 Check Document reflection
Poka-Yoke Item Description Target
To provide the mechanical
pin at OP75 to detect the
opn. Missing part
Before- No feedback from OP75 (Orientation station) about
the previous operation missing
Finished
After- Mechanical pin provided to ensure the operation
completion up to 60mm depth to avoid the rejection at Op80
Mistake proofing sheet1. To provide the mechanical pin at OP75
to detect the opn. Missing part
Control Plan & WIS
6 10/17/201
6
Ashok Leyland Presentation (PNR)
Machining position shift on OP80
due to gun drill opn. Miss.
Before Improvement After Improvement
Status Before Improvement: Status After Improvement:
Poka-yoke Pin provided to detect the Gun
drill operation miss on orientation station
OP75.
Poke
Yoke Pin
No Poke
Yoke
7 10/17/201
6
Ashok Leyland Presentation (PNR)
Sustenance:
8 10/17/201
6
Ashok Leyland Presentation (PNR)
4) Confirmation
4.1 Time Study 4.2 Compliance
No impact in Time
Evaluation Item
(Opn.no80 Cross oil hole
miss)
Effectiveness monitoring
TotalAp
l’1
4
Ma
y’
14
Ju
ne
’1
4
Ju
ly’
14
Au
g’
14
Se
p’
14
Oc
t’
14
No
v’
14
De
c’
14
Ja
n’
15
Fe
b’
15
Ma
rc
h’
15
Ap
l’1
5
Ma
y’
15
Ju
ne
’1
5
Ju
ly’
15
Au
g’
15
Se
p’
15
Elimination of
rejection at OP80 due
to OP70 opn. missing
0 0 0 0 0 0 0 0 0 0 0 0 0 0 Finished
0 –OK X-NGOpn. No Target Result Judge
80 100% 100% 0
9 10/17/201
6
Ashok Leyland Presentation (PNR)
Updated Control Plan
10 10/17/201
6
Ashok Leyland Presentation (PNR)
Thanks

Project for OP70 operation missing- Camshaft machining

  • 1.
    Elimination of Rejectionat OP80 because of Cross oil hole opn. missing in Camshaft Line Project Done By: Kamlashish Goswami
  • 2.
    2 10/17/201 6 Ashok LeylandPresentation (PNR) 1) Select the process 1.1 Select the process for improvement considering the priority - Rejection at OP80 ( cross oil hole position out ) FY13-14 DEFECT Feedback 1.2 Setting up target :Elimination of Rejection at OP80 ( cross oil hole position out) Correct Oil Hole Position Oil Hole Position shift 2.15mm shift OK Not OK
  • 3.
    3 10/17/201 6 Ashok LeylandPresentation (PNR) 2) System Analysis 2.1 Clarify own process step : Process at Camshaft machining 2.2 Check Defect Step: Op. No. Op. Name 10 Facing & centering 20 Straightening 30 Rough Turning 40 Finish Turning 50 Key-way milling 60 Cam Milling 70 Gundrilling 80 Oil hole drilling 90 H.P. Washing 100 Induction Hardening 110 Tempering 120 Straightening 130 Recentering 140 Journal grinding 150 Cam Lobe grinding 160 Deburring 170 Crack detector 180 Intermediate washing m/c 190 Accurate Inspection 200 Lobe Lapping m/c 210 Phosphating Plant 220 Journal Lapping 230 Washing +Oiling Failure Process that makes In process Defect Operation missing (No Poka-Yoke available to prevent the opn. missing part to move on the next opn.)
  • 4.
    4 10/17/201 6 Ashok LeylandPresentation (PNR) 2) System Analysis Contd… 2.3 Clarify Occurrence condition: Appearance OP70 Gun drilling operation Problem : Opn. Completion signal given to m/c by operator without inspection Manufacturing Defective Condition 4M Man (X) No SOP available to start the m/c after any interruption Machine N/A Method (X) Operation missing  No Poka-Yoke available for human error Material N/A 2.4 Root Cause Analysis: Occurrence Side: Cross oil hole position out Pre Gun drilling opn. missing Part location shift during FE drilling because of hitting in Rapid Opn. Completion signal given to m/c by operator without inspection 2.5 Problem Summary : No Poka-Yoke available to detect the opn. Miss part Root Cause:
  • 5.
    5 10/17/201 6 Ashok LeylandPresentation (PNR) 3) Poka-Yoke implementation Plan 3.1 Create Idea 3.2 Check Document reflection Poka-Yoke Item Description Target To provide the mechanical pin at OP75 to detect the opn. Missing part Before- No feedback from OP75 (Orientation station) about the previous operation missing Finished After- Mechanical pin provided to ensure the operation completion up to 60mm depth to avoid the rejection at Op80 Mistake proofing sheet1. To provide the mechanical pin at OP75 to detect the opn. Missing part Control Plan & WIS
  • 6.
    6 10/17/201 6 Ashok LeylandPresentation (PNR) Machining position shift on OP80 due to gun drill opn. Miss. Before Improvement After Improvement Status Before Improvement: Status After Improvement: Poka-yoke Pin provided to detect the Gun drill operation miss on orientation station OP75. Poke Yoke Pin No Poke Yoke
  • 7.
    7 10/17/201 6 Ashok LeylandPresentation (PNR) Sustenance:
  • 8.
    8 10/17/201 6 Ashok LeylandPresentation (PNR) 4) Confirmation 4.1 Time Study 4.2 Compliance No impact in Time Evaluation Item (Opn.no80 Cross oil hole miss) Effectiveness monitoring TotalAp l’1 4 Ma y’ 14 Ju ne ’1 4 Ju ly’ 14 Au g’ 14 Se p’ 14 Oc t’ 14 No v’ 14 De c’ 14 Ja n’ 15 Fe b’ 15 Ma rc h’ 15 Ap l’1 5 Ma y’ 15 Ju ne ’1 5 Ju ly’ 15 Au g’ 15 Se p’ 15 Elimination of rejection at OP80 due to OP70 opn. missing 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Finished 0 –OK X-NGOpn. No Target Result Judge 80 100% 100% 0
  • 9.
    9 10/17/201 6 Ashok LeylandPresentation (PNR) Updated Control Plan
  • 10.
    10 10/17/201 6 Ashok LeylandPresentation (PNR) Thanks