SlideShare a Scribd company logo
Elimination of Rejection at OP80
because of Cross oil hole opn. missing in
Camshaft Line
Project Done By: Kamlashish Goswami
2 10/17/201
6
Ashok Leyland Presentation (PNR)
1) Select the process
1.1 Select the process for improvement
considering the priority
- Rejection at OP80 ( cross oil hole position out )
FY13-14 DEFECT Feedback
1.2 Setting up target :Elimination of
Rejection at OP80 ( cross oil hole
position out)
Correct Oil
Hole
Position
Oil Hole
Position
shift
2.15mm shift
OK
Not OK
3 10/17/201
6
Ashok Leyland Presentation (PNR)
2) System Analysis
2.1 Clarify own process step :
Process at Camshaft machining
2.2 Check Defect Step:
Op. No. Op. Name
10 Facing & centering
20 Straightening
30 Rough Turning
40 Finish Turning
50 Key-way milling
60 Cam Milling
70 Gundrilling
80 Oil hole drilling
90 H.P. Washing
100 Induction Hardening
110 Tempering
120 Straightening
130 Recentering
140 Journal grinding
150 Cam Lobe grinding
160 Deburring
170 Crack detector
180 Intermediate washing m/c
190 Accurate Inspection
200 Lobe Lapping m/c
210 Phosphating Plant
220 Journal Lapping
230 Washing +Oiling
Failure Process
that makes In
process Defect
Operation missing
(No Poka-Yoke available to
prevent the opn. missing part
to move on the next opn.)
4 10/17/201
6
Ashok Leyland Presentation (PNR)
2) System Analysis Contd…
2.3 Clarify Occurrence condition:
Appearance
OP70 Gun drilling operation
Problem : Opn. Completion signal given
to m/c by operator without inspection
Manufacturing
Defective Condition
4M
Man (X)
No SOP available to start the
m/c after any interruption
Machine N/A
Method
(X)
Operation missing
 No Poka-Yoke available for
human error
Material N/A
2.4 Root Cause Analysis:
Occurrence Side:
Cross oil hole
position out Pre Gun
drilling opn.
missing
Part location
shift during FE
drilling
because of
hitting in
Rapid
Opn. Completion
signal given to m/c
by operator
without inspection
2.5 Problem Summary :
No Poka-Yoke
available to
detect the opn.
Miss part
Root Cause:
5 10/17/201
6
Ashok Leyland Presentation (PNR)
3) Poka-Yoke implementation Plan
3.1 Create Idea 3.2 Check Document reflection
Poka-Yoke Item Description Target
To provide the mechanical
pin at OP75 to detect the
opn. Missing part
Before- No feedback from OP75 (Orientation station) about
the previous operation missing
Finished
After- Mechanical pin provided to ensure the operation
completion up to 60mm depth to avoid the rejection at Op80
Mistake proofing sheet1. To provide the mechanical pin at OP75
to detect the opn. Missing part
Control Plan & WIS
6 10/17/201
6
Ashok Leyland Presentation (PNR)
Machining position shift on OP80
due to gun drill opn. Miss.
Before Improvement After Improvement
Status Before Improvement: Status After Improvement:
Poka-yoke Pin provided to detect the Gun
drill operation miss on orientation station
OP75.
Poke
Yoke Pin
No Poke
Yoke
7 10/17/201
6
Ashok Leyland Presentation (PNR)
Sustenance:
8 10/17/201
6
Ashok Leyland Presentation (PNR)
4) Confirmation
4.1 Time Study 4.2 Compliance
No impact in Time
Evaluation Item
(Opn.no80 Cross oil hole
miss)
Effectiveness monitoring
TotalAp
l’1
4
Ma
y’
14
Ju
ne
’1
4
Ju
ly’
14
Au
g’
14
Se
p’
14
Oc
t’
14
No
v’
14
De
c’
14
Ja
n’
15
Fe
b’
15
Ma
rc
h’
15
Ap
l’1
5
Ma
y’
15
Ju
ne
’1
5
Ju
ly’
15
Au
g’
15
Se
p’
15
Elimination of
rejection at OP80 due
to OP70 opn. missing
0 0 0 0 0 0 0 0 0 0 0 0 0 0 Finished
0 –OK X-NGOpn. No Target Result Judge
80 100% 100% 0
9 10/17/201
6
Ashok Leyland Presentation (PNR)
Updated Control Plan
10 10/17/201
6
Ashok Leyland Presentation (PNR)
Thanks

More Related Content

Viewers also liked

TERMINAL
TERMINALTERMINAL
2 water cycle
2 water cycle2 water cycle
2 water cycle
Elorrio
 
Media language - A2 Media
Media language - A2 MediaMedia language - A2 Media
Media language - A2 Media
MattLumley
 
ANIMALS NATURAL SCIENCE
ANIMALS NATURAL SCIENCEANIMALS NATURAL SCIENCE
ANIMALS NATURAL SCIENCE
LuciaAbalos
 
Sociology Chapter 8 culture
 Sociology Chapter 8  culture Sociology Chapter 8  culture
Sociology Chapter 8 culture
Liaqat Jogi .
 
PROPAGANDA SERVIÇOS PSICOLÓGICOS PARA EMPRESAS
PROPAGANDA SERVIÇOS PSICOLÓGICOS PARA EMPRESASPROPAGANDA SERVIÇOS PSICOLÓGICOS PARA EMPRESAS
PROPAGANDA SERVIÇOS PSICOLÓGICOS PARA EMPRESAS
Jamyly da S. Rodrigues
 
Consumer behaviour
Consumer behaviourConsumer behaviour
Consumer behaviour
kapil kumar
 
What causes differences in compensation between employees
What causes differences in compensation between employeesWhat causes differences in compensation between employees
What causes differences in compensation between employees
GodioRK
 
Poster overview
Poster overviewPoster overview
Poster overview
10afrmal
 
Lesión cerebral
Lesión cerebralLesión cerebral
Lesión cerebral
Solange Calderon
 
Cox_Writing Sample
Cox_Writing SampleCox_Writing Sample
Cox_Writing SampleBrad Cox
 
Trastornos personalidad-narcisista
Trastornos personalidad-narcisistaTrastornos personalidad-narcisista
Trastornos personalidad-narcisista
alan dumrauf
 
Risk management - Controllo finanziario
Risk management - Controllo finanziario Risk management - Controllo finanziario
Risk management - Controllo finanziario
Manager.it
 
Variación de la intensidad del sonido
Variación de la intensidad del sonidoVariación de la intensidad del sonido
Variación de la intensidad del sonido
Jeaneth Molina
 

Viewers also liked (15)

TERMINAL
TERMINALTERMINAL
TERMINAL
 
2 water cycle
2 water cycle2 water cycle
2 water cycle
 
Media language - A2 Media
Media language - A2 MediaMedia language - A2 Media
Media language - A2 Media
 
ANIMALS NATURAL SCIENCE
ANIMALS NATURAL SCIENCEANIMALS NATURAL SCIENCE
ANIMALS NATURAL SCIENCE
 
Sociology Chapter 8 culture
 Sociology Chapter 8  culture Sociology Chapter 8  culture
Sociology Chapter 8 culture
 
PROPAGANDA SERVIÇOS PSICOLÓGICOS PARA EMPRESAS
PROPAGANDA SERVIÇOS PSICOLÓGICOS PARA EMPRESASPROPAGANDA SERVIÇOS PSICOLÓGICOS PARA EMPRESAS
PROPAGANDA SERVIÇOS PSICOLÓGICOS PARA EMPRESAS
 
Consumer behaviour
Consumer behaviourConsumer behaviour
Consumer behaviour
 
What causes differences in compensation between employees
What causes differences in compensation between employeesWhat causes differences in compensation between employees
What causes differences in compensation between employees
 
Poster overview
Poster overviewPoster overview
Poster overview
 
Lesión cerebral
Lesión cerebralLesión cerebral
Lesión cerebral
 
Cox_Writing Sample
Cox_Writing SampleCox_Writing Sample
Cox_Writing Sample
 
Ahmed Jawad CV
Ahmed Jawad CVAhmed Jawad CV
Ahmed Jawad CV
 
Trastornos personalidad-narcisista
Trastornos personalidad-narcisistaTrastornos personalidad-narcisista
Trastornos personalidad-narcisista
 
Risk management - Controllo finanziario
Risk management - Controllo finanziario Risk management - Controllo finanziario
Risk management - Controllo finanziario
 
Variación de la intensidad del sonido
Variación de la intensidad del sonidoVariación de la intensidad del sonido
Variación de la intensidad del sonido
 

Similar to Project for OP70 operation missing- Camshaft machining

001 QM Stage 1-7 ACME final
001 QM Stage 1-7 ACME final001 QM Stage 1-7 ACME final
001 QM Stage 1-7 ACME finalSachin Dhawale
 
Pt hpm half yearly presentation on may
Pt hpm half yearly presentation on mayPt hpm half yearly presentation on may
Pt hpm half yearly presentation on mayaristomy
 
Quality Innovation Plan
Quality Innovation PlanQuality Innovation Plan
Quality Innovation Plan
vinit chaudhary
 
Praveen Final Semester Viva Presentation.pptx
Praveen Final Semester Viva Presentation.pptxPraveen Final Semester Viva Presentation.pptx
Praveen Final Semester Viva Presentation.pptx
MohitNarwat1
 
To Study the power supply of the Assembly Shop
To Study the power supply of the Assembly ShopTo Study the power supply of the Assembly Shop
To Study the power supply of the Assembly Shop
Abhishek Roy
 
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
sbradsha1
 
Lean six sigma green belt project improvement
Lean six sigma  green belt project improvementLean six sigma  green belt project improvement
Lean six sigma green belt project improvement
AnkurSharma820
 
Lean green belt project improvement
Lean   green belt project improvementLean   green belt project improvement
Lean green belt project improvement
AnkurSharma820
 
Forward revrese pressure not ok
Forward revrese pressure not okForward revrese pressure not ok
Forward revrese pressure not okJeetin Agrawal
 
Va.ve approach
Va.ve approachVa.ve approach
Va.ve approachAnujKSingh
 
Updated cycle time_reduction_on_valve_body_ih_
Updated cycle time_reduction_on_valve_body_ih_Updated cycle time_reduction_on_valve_body_ih_
Updated cycle time_reduction_on_valve_body_ih_Shalini Rai
 
Medium artillery ammunition(MAA) Factory (1)
Medium artillery ammunition(MAA) Factory (1)Medium artillery ammunition(MAA) Factory (1)
Medium artillery ammunition(MAA) Factory (1)Malik Raheel
 
New Microsoft PowerPoint Presentation
New Microsoft PowerPoint PresentationNew Microsoft PowerPoint Presentation
New Microsoft PowerPoint Presentationebbin daniel
 
4r75w Ford instalaciones diagramas sonn
4r75w  Ford instalaciones diagramas sonn4r75w  Ford instalaciones diagramas sonn
4r75w Ford instalaciones diagramas sonn
ErickCabezas11
 
Project Presentation PQM
Project Presentation PQMProject Presentation PQM
Project Presentation PQMSaif Ul Islam
 
Atlas Internship report
Atlas Internship reportAtlas Internship report
Atlas Internship report
M Nadeem
 
Coining QCC R1.pptx
Coining QCC R1.pptxCoining QCC R1.pptx
Coining QCC R1.pptx
PhaniKishore15
 

Similar to Project for OP70 operation missing- Camshaft machining (20)

001 QM Stage 1-7 ACME final
001 QM Stage 1-7 ACME final001 QM Stage 1-7 ACME final
001 QM Stage 1-7 ACME final
 
FINAL REVIEW
FINAL REVIEWFINAL REVIEW
FINAL REVIEW
 
Pt hpm half yearly presentation on may
Pt hpm half yearly presentation on mayPt hpm half yearly presentation on may
Pt hpm half yearly presentation on may
 
Quality Innovation Plan
Quality Innovation PlanQuality Innovation Plan
Quality Innovation Plan
 
project ppt
project pptproject ppt
project ppt
 
Praveen Final Semester Viva Presentation.pptx
Praveen Final Semester Viva Presentation.pptxPraveen Final Semester Viva Presentation.pptx
Praveen Final Semester Viva Presentation.pptx
 
To Study the power supply of the Assembly Shop
To Study the power supply of the Assembly ShopTo Study the power supply of the Assembly Shop
To Study the power supply of the Assembly Shop
 
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
Modification Of Bb1 Pump Vibration Characteristics To Meet ISO 13709 2nd Edit...
 
Lean six sigma green belt project improvement
Lean six sigma  green belt project improvementLean six sigma  green belt project improvement
Lean six sigma green belt project improvement
 
Lean green belt project improvement
Lean   green belt project improvementLean   green belt project improvement
Lean green belt project improvement
 
Forward revrese pressure not ok
Forward revrese pressure not okForward revrese pressure not ok
Forward revrese pressure not ok
 
Va.ve approach
Va.ve approachVa.ve approach
Va.ve approach
 
Updated cycle time_reduction_on_valve_body_ih_
Updated cycle time_reduction_on_valve_body_ih_Updated cycle time_reduction_on_valve_body_ih_
Updated cycle time_reduction_on_valve_body_ih_
 
Medium artillery ammunition(MAA) Factory (1)
Medium artillery ammunition(MAA) Factory (1)Medium artillery ammunition(MAA) Factory (1)
Medium artillery ammunition(MAA) Factory (1)
 
New Microsoft PowerPoint Presentation
New Microsoft PowerPoint PresentationNew Microsoft PowerPoint Presentation
New Microsoft PowerPoint Presentation
 
4r75w Ford instalaciones diagramas sonn
4r75w  Ford instalaciones diagramas sonn4r75w  Ford instalaciones diagramas sonn
4r75w Ford instalaciones diagramas sonn
 
Project Presentation PQM
Project Presentation PQMProject Presentation PQM
Project Presentation PQM
 
Notes for scft
Notes for scftNotes for scft
Notes for scft
 
Atlas Internship report
Atlas Internship reportAtlas Internship report
Atlas Internship report
 
Coining QCC R1.pptx
Coining QCC R1.pptxCoining QCC R1.pptx
Coining QCC R1.pptx
 

Project for OP70 operation missing- Camshaft machining

  • 1. Elimination of Rejection at OP80 because of Cross oil hole opn. missing in Camshaft Line Project Done By: Kamlashish Goswami
  • 2. 2 10/17/201 6 Ashok Leyland Presentation (PNR) 1) Select the process 1.1 Select the process for improvement considering the priority - Rejection at OP80 ( cross oil hole position out ) FY13-14 DEFECT Feedback 1.2 Setting up target :Elimination of Rejection at OP80 ( cross oil hole position out) Correct Oil Hole Position Oil Hole Position shift 2.15mm shift OK Not OK
  • 3. 3 10/17/201 6 Ashok Leyland Presentation (PNR) 2) System Analysis 2.1 Clarify own process step : Process at Camshaft machining 2.2 Check Defect Step: Op. No. Op. Name 10 Facing & centering 20 Straightening 30 Rough Turning 40 Finish Turning 50 Key-way milling 60 Cam Milling 70 Gundrilling 80 Oil hole drilling 90 H.P. Washing 100 Induction Hardening 110 Tempering 120 Straightening 130 Recentering 140 Journal grinding 150 Cam Lobe grinding 160 Deburring 170 Crack detector 180 Intermediate washing m/c 190 Accurate Inspection 200 Lobe Lapping m/c 210 Phosphating Plant 220 Journal Lapping 230 Washing +Oiling Failure Process that makes In process Defect Operation missing (No Poka-Yoke available to prevent the opn. missing part to move on the next opn.)
  • 4. 4 10/17/201 6 Ashok Leyland Presentation (PNR) 2) System Analysis Contd… 2.3 Clarify Occurrence condition: Appearance OP70 Gun drilling operation Problem : Opn. Completion signal given to m/c by operator without inspection Manufacturing Defective Condition 4M Man (X) No SOP available to start the m/c after any interruption Machine N/A Method (X) Operation missing  No Poka-Yoke available for human error Material N/A 2.4 Root Cause Analysis: Occurrence Side: Cross oil hole position out Pre Gun drilling opn. missing Part location shift during FE drilling because of hitting in Rapid Opn. Completion signal given to m/c by operator without inspection 2.5 Problem Summary : No Poka-Yoke available to detect the opn. Miss part Root Cause:
  • 5. 5 10/17/201 6 Ashok Leyland Presentation (PNR) 3) Poka-Yoke implementation Plan 3.1 Create Idea 3.2 Check Document reflection Poka-Yoke Item Description Target To provide the mechanical pin at OP75 to detect the opn. Missing part Before- No feedback from OP75 (Orientation station) about the previous operation missing Finished After- Mechanical pin provided to ensure the operation completion up to 60mm depth to avoid the rejection at Op80 Mistake proofing sheet1. To provide the mechanical pin at OP75 to detect the opn. Missing part Control Plan & WIS
  • 6. 6 10/17/201 6 Ashok Leyland Presentation (PNR) Machining position shift on OP80 due to gun drill opn. Miss. Before Improvement After Improvement Status Before Improvement: Status After Improvement: Poka-yoke Pin provided to detect the Gun drill operation miss on orientation station OP75. Poke Yoke Pin No Poke Yoke
  • 7. 7 10/17/201 6 Ashok Leyland Presentation (PNR) Sustenance:
  • 8. 8 10/17/201 6 Ashok Leyland Presentation (PNR) 4) Confirmation 4.1 Time Study 4.2 Compliance No impact in Time Evaluation Item (Opn.no80 Cross oil hole miss) Effectiveness monitoring TotalAp l’1 4 Ma y’ 14 Ju ne ’1 4 Ju ly’ 14 Au g’ 14 Se p’ 14 Oc t’ 14 No v’ 14 De c’ 14 Ja n’ 15 Fe b’ 15 Ma rc h’ 15 Ap l’1 5 Ma y’ 15 Ju ne ’1 5 Ju ly’ 15 Au g’ 15 Se p’ 15 Elimination of rejection at OP80 due to OP70 opn. missing 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Finished 0 –OK X-NGOpn. No Target Result Judge 80 100% 100% 0
  • 9. 9 10/17/201 6 Ashok Leyland Presentation (PNR) Updated Control Plan
  • 10. 10 10/17/201 6 Ashok Leyland Presentation (PNR) Thanks