SlideShare a Scribd company logo
1 of 2
Document no: WGS ME-SOP-IN-25 Page 1 of 2 V1, June 2015
Apparel Manufacturing Excellence – Partnering for Continuous Process Efficiency Improvement
PROJECT CHARTER:Sewing_GTL2_Line-01
Project Name: Expected Benefit: Target Timeline:
Start & Estimated end
date
Date: Project
No.
Improve sewing
efficiency– 15%
Increase productivityper hour per person
(Current-1.88)
2.25%
Start –6 june,2016
End – 10 June, 2016
16-Jun-2016
01/ GTL
unit 2,
line 01
Reduce NVA (Current-23%) 3%
Improve Line Balancing% (current 74%) 86%
Increase production (Current-1000 pcs) 1200 pcs
Improve SMV (24.3) 23.3
What is the problem statement?
What havecustomers toldus is currentlya
problem and they want tochange? (Voiceof
Customer)
What is the project objective?
Objectives should beSpecific,Measurable, Achievable,
Relevant, Timely
On project completion what does ‘goodlook like’?
Measure Current Target
Increase higher efficiency to achieve more
volume business
Identify critical Operation and review
Method Analysisto improve efficiency
Efficiency 76% 91%
Eliminated NVA operation Reduce 2 NVA operation from the current
operationbreakdown
People Ratio( VA
:NNVA:NVA)
75:2:23 78:2:20
What is the scope of the project? (e.g. department, Categories, geographies)
In Scope Out of Scope
Unit 2, line 1 (Sewing) Unit 2 other linesand Cutting, Finishing
What are the project milestones?
Specify whenyou willbe reporting back to your sponsor / steering group, andDefine, Measure,Analyse,Improve, Controlend stage reviews ifappropriate
Description Planned
Complete date
Actual Complete
Date
Define (Current Assessment)—2 days 8 June,2016 8-June, 2016
Measured KPI-- (current)—2 days 11 June,2016 11-June, 2016
Analyse (Current vs. Future –variance)—2 days 13 June,2016 13-June, 2016
Improved (Action towards goals)---7 days 21 June,2016 21-June, 2016
Control—1 days 22 June,2016 22-June, 2016
What are the project deliverables?
Describe the expected outputs oftheproject,including whatcustomers / staffwould see new (e.g. Documents, presentation decks)
Description Planned date Actual Date
Use the current reports on productivity control and method study report.
As per requirement enhance to capture the required data to track the project report
Resources
Name, Position
Effort/Method/Notes What is the approximate project value?
See comment below Area Impacted:
Estimate Value:
USD/Local currency
Method/Notes:
Prepared by: ME Project leader ME Program Leader ME Champion ME Sponsor WMGS ME
Manufacturing
Excellence Team
Niroshana–IE
Kawsar- IE
Enamul – IE
Sofiq-Maintenance
Sohel- QC
Anik Hemantha Senake Al Bokor
Document no: WGS ME-SOP-IN-25 Page 2 of 2 V1, June 2015
Apparel Manufacturing Excellence – Partnering for Continuous Process Efficiency Improvement
Improvement - Action Points
Bottleneck operation identify based on set target 120 pcs/hr.
Attach Sleeve Tape/Gamble Method change.
Cuff turn Method change.
Cuff top stitch 1.4 method change & balancewith Hem cuff.
Side seam, cuff joint,BH operation method change.
Shoulder T/s operation method change & MachineRPM change.
Press waistbelt capacity increased by increasingfolder.
Loop mark operation eliminate by laser light.
Work on linebalancingbaseon capacity graph as increaselineefficiency
Excess Materials movement eliminateby layoutchange.
Box & cross stitch operation extra thread cutting time eliminate.
Button attach operation method change.
Care label tack atfront operation try adjustwith Sideseam.
Cuff squareMethod change & reduce 0.5.
Button attach on sleeve operator sleeve placketcut process balancewith sleeve placket mark.
**The purpose of this document is to help project managers communicate key projectinformation to their sponsors

More Related Content

What's hot

Productivity Improvement Study
Productivity Improvement StudyProductivity Improvement Study
Productivity Improvement Study
saranshshah
 
Ops 571 final exam questions and correct answers 100% guaranteed#
Ops 571 final exam questions and correct answers 100% guaranteed#Ops 571 final exam questions and correct answers 100% guaranteed#
Ops 571 final exam questions and correct answers 100% guaranteed#
siliverseyr
 
Job Description and Responsibility
Job Description and ResponsibilityJob Description and Responsibility
Job Description and Responsibility
Kannan Ramalingam
 
Just in-timeby stevespangler[1]
Just in-timeby stevespangler[1]Just in-timeby stevespangler[1]
Just in-timeby stevespangler[1]
Sunder Ram. M
 

What's hot (19)

Productivity Improvement Study
Productivity Improvement StudyProductivity Improvement Study
Productivity Improvement Study
 
Warwick Lean Agenda Aug Wk1 July 12 2010
Warwick Lean  Agenda Aug Wk1  July 12 2010Warwick Lean  Agenda Aug Wk1  July 12 2010
Warwick Lean Agenda Aug Wk1 July 12 2010
 
Ops 571 final exam questions and correct answers 100% guaranteed#
Ops 571 final exam questions and correct answers 100% guaranteed#Ops 571 final exam questions and correct answers 100% guaranteed#
Ops 571 final exam questions and correct answers 100% guaranteed#
 
Scope of Experience
Scope of ExperienceScope of Experience
Scope of Experience
 
different techniques to productivity improvement
different techniques to productivity improvementdifferent techniques to productivity improvement
different techniques to productivity improvement
 
Lean Manufacturing Cost Cutting Methods
Lean Manufacturing   Cost Cutting MethodsLean Manufacturing   Cost Cutting Methods
Lean Manufacturing Cost Cutting Methods
 
Implementing lean Six sigma
Implementing lean Six sigmaImplementing lean Six sigma
Implementing lean Six sigma
 
Value analysis
Value analysisValue analysis
Value analysis
 
UNIT 3 - PRODUCTION PLANNING AND PROCESS PLANNING
UNIT 3 - PRODUCTION PLANNING AND PROCESS PLANNINGUNIT 3 - PRODUCTION PLANNING AND PROCESS PLANNING
UNIT 3 - PRODUCTION PLANNING AND PROCESS PLANNING
 
Top 10 most important manufacturing performance indicators in 2019
Top 10 most important manufacturing performance indicators in 2019Top 10 most important manufacturing performance indicators in 2019
Top 10 most important manufacturing performance indicators in 2019
 
092 Productivity Improvement
092 Productivity Improvement092 Productivity Improvement
092 Productivity Improvement
 
Quality costing
Quality costingQuality costing
Quality costing
 
Production planning & control
Production planning & controlProduction planning & control
Production planning & control
 
Uop ops 571 final exam guide new 2017
Uop ops 571 final exam guide new 2017Uop ops 571 final exam guide new 2017
Uop ops 571 final exam guide new 2017
 
Uop ops 571 final exam guide new 2017
Uop ops 571 final exam guide new 2017Uop ops 571 final exam guide new 2017
Uop ops 571 final exam guide new 2017
 
Uop ops 571 final exam guide new 2017 (score 3030) new
Uop ops 571 final exam guide new 2017 (score 3030) newUop ops 571 final exam guide new 2017 (score 3030) new
Uop ops 571 final exam guide new 2017 (score 3030) new
 
Job Description and Responsibility
Job Description and ResponsibilityJob Description and Responsibility
Job Description and Responsibility
 
Just in-timeby stevespangler[1]
Just in-timeby stevespangler[1]Just in-timeby stevespangler[1]
Just in-timeby stevespangler[1]
 
CV_Dhage2
CV_Dhage2CV_Dhage2
CV_Dhage2
 

Viewers also liked (12)

HENRY VU-RESUME
HENRY VU-RESUMEHENRY VU-RESUME
HENRY VU-RESUME
 
Welzijnsindicatoren - stijgende belang van gedrag in de veiligheidscultuur
Welzijnsindicatoren - stijgende belang van gedrag in de veiligheidscultuurWelzijnsindicatoren - stijgende belang van gedrag in de veiligheidscultuur
Welzijnsindicatoren - stijgende belang van gedrag in de veiligheidscultuur
 
Unip instituições de direito - 110214 - aula 3
Unip   instituições de direito - 110214 - aula 3Unip   instituições de direito - 110214 - aula 3
Unip instituições de direito - 110214 - aula 3
 
Comunicat de presa activitati culturale luna aprilie
Comunicat de presa activitati culturale luna aprilieComunicat de presa activitati culturale luna aprilie
Comunicat de presa activitati culturale luna aprilie
 
Holguin
HolguinHolguin
Holguin
 
Supuesto no autocorrelación de análisis de regresion
Supuesto no autocorrelación de análisis de regresionSupuesto no autocorrelación de análisis de regresion
Supuesto no autocorrelación de análisis de regresion
 
Adf.ly bot 2016
Adf.ly bot 2016Adf.ly bot 2016
Adf.ly bot 2016
 
Spend one million_dollars_student_guide
Spend one million_dollars_student_guideSpend one million_dollars_student_guide
Spend one million_dollars_student_guide
 
12 superantígenos
12   superantígenos12   superantígenos
12 superantígenos
 
ãLvares de azevedo giovana 2º b
ãLvares de azevedo  giovana 2º bãLvares de azevedo  giovana 2º b
ãLvares de azevedo giovana 2º b
 
Futuro Television - EBE Madrid
Futuro Television - EBE MadridFuturo Television - EBE Madrid
Futuro Television - EBE Madrid
 
Brucellosis
BrucellosisBrucellosis
Brucellosis
 

Similar to Project Charter GTL2 _Sewing_6_June_ 2016

IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
Karina Islam
 
System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011
ExerciseLeanLLC
 
Submission of mba spring 2012
Submission of mba spring 2012Submission of mba spring 2012
Submission of mba spring 2012
Shraddha Singh
 
Project Charter GTL_Sewing DHU_ 24_ August 2016
Project Charter GTL_Sewing DHU_ 24_ August 2016Project Charter GTL_Sewing DHU_ 24_ August 2016
Project Charter GTL_Sewing DHU_ 24_ August 2016
Anik Mazumdar
 
Mb0044 production and operation management..
Mb0044   production and operation management..Mb0044   production and operation management..
Mb0044 production and operation management..
smumbahelp
 

Similar to Project Charter GTL2 _Sewing_6_June_ 2016 (20)

IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
Software Solution for Production Planning and Scheduling
Software Solution for Production Planning and SchedulingSoftware Solution for Production Planning and Scheduling
Software Solution for Production Planning and Scheduling
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
 
System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011
 
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
 
ASQ CSSBB Affidavit Example
ASQ CSSBB Affidavit ExampleASQ CSSBB Affidavit Example
ASQ CSSBB Affidavit Example
 
Submission of mba spring 2012
Submission of mba spring 2012Submission of mba spring 2012
Submission of mba spring 2012
 
Project Charter GTL_Sewing DHU_ 24_ August 2016
Project Charter GTL_Sewing DHU_ 24_ August 2016Project Charter GTL_Sewing DHU_ 24_ August 2016
Project Charter GTL_Sewing DHU_ 24_ August 2016
 
Iss 9
Iss 9Iss 9
Iss 9
 
Quality Function Deployment in Construction Industry
Quality Function Deployment in Construction IndustryQuality Function Deployment in Construction Industry
Quality Function Deployment in Construction Industry
 
Strategic Cost Management
Strategic Cost ManagementStrategic Cost Management
Strategic Cost Management
 
VSM – Current & Future
VSM – Current & FutureVSM – Current & Future
VSM – Current & Future
 
Zero Tolerancev
Zero TolerancevZero Tolerancev
Zero Tolerancev
 
Manish Gujarathi - Copy
Manish Gujarathi  - CopyManish Gujarathi  - Copy
Manish Gujarathi - Copy
 
About Production Planning Process of a RMG !!!
About Production Planning Process of a RMG !!!About Production Planning Process of a RMG !!!
About Production Planning Process of a RMG !!!
 
Mb0044 production and operation management..
Mb0044   production and operation management..Mb0044   production and operation management..
Mb0044 production and operation management..
 
PRODUCTION CYCLE
PRODUCTION CYCLE PRODUCTION CYCLE
PRODUCTION CYCLE
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryManufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
 

More from Anik Mazumdar

Friends foundation Certificate
Friends foundation CertificateFriends foundation Certificate
Friends foundation Certificate
Anik Mazumdar
 
White Belt Certification-Anik Mazumdar
White Belt Certification-Anik MazumdarWhite Belt Certification-Anik Mazumdar
White Belt Certification-Anik Mazumdar
Anik Mazumdar
 
Six Sigma Yellow Belt -Anik Mazumdar
Six Sigma Yellow Belt -Anik MazumdarSix Sigma Yellow Belt -Anik Mazumdar
Six Sigma Yellow Belt -Anik Mazumdar
Anik Mazumdar
 
Manufacturing Excellence Line- Efficiency Improvement Project
Manufacturing Excellence Line- Efficiency Improvement ProjectManufacturing Excellence Line- Efficiency Improvement Project
Manufacturing Excellence Line- Efficiency Improvement Project
Anik Mazumdar
 
Six Sigma Yellow Belt -Anik Mazumdar
Six Sigma Yellow Belt -Anik MazumdarSix Sigma Yellow Belt -Anik Mazumdar
Six Sigma Yellow Belt -Anik Mazumdar
Anik Mazumdar
 
White Belt Certification-Anik Mazumdar
White Belt Certification-Anik MazumdarWhite Belt Certification-Anik Mazumdar
White Belt Certification-Anik Mazumdar
Anik Mazumdar
 

More from Anik Mazumdar (7)

BSC Certificate (1)
BSC Certificate (1)BSC Certificate (1)
BSC Certificate (1)
 
Friends foundation Certificate
Friends foundation CertificateFriends foundation Certificate
Friends foundation Certificate
 
White Belt Certification-Anik Mazumdar
White Belt Certification-Anik MazumdarWhite Belt Certification-Anik Mazumdar
White Belt Certification-Anik Mazumdar
 
Six Sigma Yellow Belt -Anik Mazumdar
Six Sigma Yellow Belt -Anik MazumdarSix Sigma Yellow Belt -Anik Mazumdar
Six Sigma Yellow Belt -Anik Mazumdar
 
Manufacturing Excellence Line- Efficiency Improvement Project
Manufacturing Excellence Line- Efficiency Improvement ProjectManufacturing Excellence Line- Efficiency Improvement Project
Manufacturing Excellence Line- Efficiency Improvement Project
 
Six Sigma Yellow Belt -Anik Mazumdar
Six Sigma Yellow Belt -Anik MazumdarSix Sigma Yellow Belt -Anik Mazumdar
Six Sigma Yellow Belt -Anik Mazumdar
 
White Belt Certification-Anik Mazumdar
White Belt Certification-Anik MazumdarWhite Belt Certification-Anik Mazumdar
White Belt Certification-Anik Mazumdar
 

Project Charter GTL2 _Sewing_6_June_ 2016

  • 1. Document no: WGS ME-SOP-IN-25 Page 1 of 2 V1, June 2015 Apparel Manufacturing Excellence – Partnering for Continuous Process Efficiency Improvement PROJECT CHARTER:Sewing_GTL2_Line-01 Project Name: Expected Benefit: Target Timeline: Start & Estimated end date Date: Project No. Improve sewing efficiency– 15% Increase productivityper hour per person (Current-1.88) 2.25% Start –6 june,2016 End – 10 June, 2016 16-Jun-2016 01/ GTL unit 2, line 01 Reduce NVA (Current-23%) 3% Improve Line Balancing% (current 74%) 86% Increase production (Current-1000 pcs) 1200 pcs Improve SMV (24.3) 23.3 What is the problem statement? What havecustomers toldus is currentlya problem and they want tochange? (Voiceof Customer) What is the project objective? Objectives should beSpecific,Measurable, Achievable, Relevant, Timely On project completion what does ‘goodlook like’? Measure Current Target Increase higher efficiency to achieve more volume business Identify critical Operation and review Method Analysisto improve efficiency Efficiency 76% 91% Eliminated NVA operation Reduce 2 NVA operation from the current operationbreakdown People Ratio( VA :NNVA:NVA) 75:2:23 78:2:20 What is the scope of the project? (e.g. department, Categories, geographies) In Scope Out of Scope Unit 2, line 1 (Sewing) Unit 2 other linesand Cutting, Finishing What are the project milestones? Specify whenyou willbe reporting back to your sponsor / steering group, andDefine, Measure,Analyse,Improve, Controlend stage reviews ifappropriate Description Planned Complete date Actual Complete Date Define (Current Assessment)—2 days 8 June,2016 8-June, 2016 Measured KPI-- (current)—2 days 11 June,2016 11-June, 2016 Analyse (Current vs. Future –variance)—2 days 13 June,2016 13-June, 2016 Improved (Action towards goals)---7 days 21 June,2016 21-June, 2016 Control—1 days 22 June,2016 22-June, 2016 What are the project deliverables? Describe the expected outputs oftheproject,including whatcustomers / staffwould see new (e.g. Documents, presentation decks) Description Planned date Actual Date Use the current reports on productivity control and method study report. As per requirement enhance to capture the required data to track the project report Resources Name, Position Effort/Method/Notes What is the approximate project value? See comment below Area Impacted: Estimate Value: USD/Local currency Method/Notes: Prepared by: ME Project leader ME Program Leader ME Champion ME Sponsor WMGS ME Manufacturing Excellence Team Niroshana–IE Kawsar- IE Enamul – IE Sofiq-Maintenance Sohel- QC Anik Hemantha Senake Al Bokor
  • 2. Document no: WGS ME-SOP-IN-25 Page 2 of 2 V1, June 2015 Apparel Manufacturing Excellence – Partnering for Continuous Process Efficiency Improvement Improvement - Action Points Bottleneck operation identify based on set target 120 pcs/hr. Attach Sleeve Tape/Gamble Method change. Cuff turn Method change. Cuff top stitch 1.4 method change & balancewith Hem cuff. Side seam, cuff joint,BH operation method change. Shoulder T/s operation method change & MachineRPM change. Press waistbelt capacity increased by increasingfolder. Loop mark operation eliminate by laser light. Work on linebalancingbaseon capacity graph as increaselineefficiency Excess Materials movement eliminateby layoutchange. Box & cross stitch operation extra thread cutting time eliminate. Button attach operation method change. Care label tack atfront operation try adjustwith Sideseam. Cuff squareMethod change & reduce 0.5. Button attach on sleeve operator sleeve placketcut process balancewith sleeve placket mark. **The purpose of this document is to help project managers communicate key projectinformation to their sponsors