1. Units 4, 5, 24, 31 - Task 3
Lauren Rosenfeld, Ben Karrass, Millie West, Ben Goldstone & Nikon Ahamed
Production
Schedule
Planned
date &
time
Whats planned
to be done &
where
Who's
responsible?
Resources needed Changes made & why Date completed
13.11.17 -
9:00
Initial meeting - 126 LR, MW, BK, BG,
NA
Computer, Google docs,
internet
13,11,17
13.11.17 -
9:00
Treatment LR, MW, BK, BG,
NA
Computer, Google docs,
internet
Edited, moved sentences to other
sections. Pictures added.
20.11.17
13.11.17 -
11:00
Budget LR, MW, BK, BG,
NA
Computer , Google
sheets
Changed colours as they were
not resembling the logo and it’s
colours.
Changed equipment and actors to
lower cost. Changed Nearly
everything to make it realistic to
what we will be actually using
20.11.17
17.11.17 Pitch Script LR, MW, BK, BG,
NA
Computer, Google docs,
internet
Changed layout and paragraphs
to match the treatment and
slideshow
20.11.17
14.11.17 - Pitch slideshow LR, MW, BK, BG, Computer. Google Changed budget costs 20.11.17
2. Units 4, 5, 24, 31 - Task 3
Lauren Rosenfeld, Ben Karrass, Millie West, Ben Goldstone & Nikon Ahamed
12:15 NA slides, internet
20,11,17 - Script LR, MW Computer, Google docs.
internet
28.11.17
28.11.17 -
8:56
Storyboard NA, Pencils, storyboard-
format pages, rubber,
pen
28.11.17 Location Scout Form BK Computer, Google docs,
internet
29.11.17
28.11.17 Site Plan BG. BK,MW Computer, Google docs.
internet
29.11.17
28.11.17 Risk Assessment BG, BK Computer, Google docs,
internet
28.11.17
28.11.17 Location Release
Form
BK Computer, Google docs.
internet
28.11.17
28.11.17 Talent Release Form BG, NA Computer, Google docs,
internet
28.11.17
13.11.17 Production schedule BG, NA,LR Computer, Google docs,
internet
20.11.17 Mock script LR Computer, Google docs,
internet
20/11/17
20.11.17 Script LR,MW Computer, Google docs,
internet
21.11.17
28.11.17 Shooting schedule BG. LR, Computer, Google docs,
internet
28.11.17
3. Units 4, 5, 24, 31 - Task 3
Lauren Rosenfeld, Ben Karrass, Millie West, Ben Goldstone & Nikon Ahamed
28.11.17 Call sheet BK. LR, Computer, Google docs,
internet
28.11.17
28.11.17 Meeting 2 LR,MW,BG,BK,N
A
Computer, Google docs,
internet
28.11.17
11.12.17 Meeting 3 LR,MW,BG,BK,N
A
Computer, Google docs,
internet
11.12.17