This document provides preliminary design submittal information for the redevelopment of Sewell Park in Cobb County, Georgia. It includes an overall site plan, individual site plans, grading plans, utility plans, architectural plans, and preliminary cost estimates totaling $244,231 for the project. Issues and questions are also listed regarding site elements, architectural components, and mechanical, electrical, and plumbing coordination.
This document lists projects executed for various clients including TAKREER, GASCO, ADGAS, ADCO, ADMA OPCO, ENOC, FERTIL, AL JABER, EMCO, JORD ENG, VELOCI, ZARCON, JGC, DEUTCH & BABCOOK, TECHNIP, BECHTEL, SNAMPROGETTI, FLUOR, SIDEM, CAMP RUWAIS, Foster Wheeler, Tyco, and SAIPEM. The projects include maintenance, inspection, fabrication and supply of various equipment such as heat exchangers, vessels, tanks, bundles, and other refinery components.
This document provides design plans for a slide correction project on State Road 250 located approximately at RP 68+00, 0.6 mile west of S.R. 156 in Posey Township, Switzerland County, Indiana. The project will involve full depth reconstruction and incidental construction along 0.09 miles of S.R. 250. Design plans include typical road sections, construction details, drainage details, and cross sections. Utility locations in the area are also noted.
This document contains information about various pool heating and cooling equipment, including:
1. An air/water heating/cooling pump that can extend the swim season and keep pool water comfortable year-round.
2. A G2 heat exchanger with a titanium tube bundle and stainless steel shell for efficient heat transfer between primary and secondary water circuits.
3. An Evolution electric pool heater that is fully equipped and easy to install for heating chlorinated pools.
The document describes the civil, structural and architectural works for various plant components. It discusses foundations for RCC structures like transformer yards and fencing. It also describes buildings like ESP control room, switchyard structures, intake water pump house, fire water pump house and tank foundations. Circulating water system involving sea water intake, pump houses, forebays and cooling water channels are also covered. Design criteria for RCC conduits for cooling water inlet and outlet is provided.
Type K Linear and Rotary Damper Actuators - RotorkCTi Controltech
The Type K Range offers rotary and linear pneumatic damper drives for utility power plants, refineries, powerhouse boilers, furnaces and process heaters that require precise combustion air and flue gas handling solutions. The damper drives are available in a wide range of configurations to meet the challenges of industrial applications. Some key features:
- A series offering drop-in-place retrofit, requiring no field engineering or fabrication.
- Improved reliability in high temperature environments
- Rated for 100% duty-cycle, continuous modulating service
- Highly accurate to 0.25% resolution
- Discrete contacts (O/C) and pneumatic, analog or bus network (MOD) communications
Lined Ball Valves Provide Corrosion ProtectionCTi Controltech
The document provides information on various lined ball valves and related products from Atomac/Flowserve including:
- AKH3 standard port and AKH2A full port lined ball valves that provide bubble-tight shutoff and low maintenance stem seals.
- V-port control valves and actuation options for precise throttling of corrosive media.
- Three-way AMP3 lined ball valves for corrosive diverter applications.
- Ceramic lined AKH5 valves for abrasive slurries and high temperature corrosives.
- Sampling valves, sight glasses, and check valves with corrosion resistant fluoropolymer linings for visual inspection and flow control of toxic chemicals
Victory Energy Firetube Boiler for extreme duty - Frontier SeriesCTi Controltech
By design, the Frontier® Series 3-pass and 4-pass wetback, and now dryback too, boilers are engineered and built for minimum maintenance and maximum output. Wall-to-wall super-structure and rifled tubes ensure years of extreme-duty performance.
Victory Energy utilizes the "latest" burner/control technology available to establish the most dependable operation needed for your specific application.
SunMaxx Installation Manual - StorMaxx Solar Hot Water Storage TanksSunMaxx Solar
This document provides an installation guide for StorMaxx CTEC Series water tanks. It includes requirements for the installation room and tank, descriptions of tank components like insulation, water casing, and electric heating elements. It also provides instructions for connecting a safety relief valve and technical specifications for various tank models.
This document lists projects executed for various clients including TAKREER, GASCO, ADGAS, ADCO, ADMA OPCO, ENOC, FERTIL, AL JABER, EMCO, JORD ENG, VELOCI, ZARCON, JGC, DEUTCH & BABCOOK, TECHNIP, BECHTEL, SNAMPROGETTI, FLUOR, SIDEM, CAMP RUWAIS, Foster Wheeler, Tyco, and SAIPEM. The projects include maintenance, inspection, fabrication and supply of various equipment such as heat exchangers, vessels, tanks, bundles, and other refinery components.
This document provides design plans for a slide correction project on State Road 250 located approximately at RP 68+00, 0.6 mile west of S.R. 156 in Posey Township, Switzerland County, Indiana. The project will involve full depth reconstruction and incidental construction along 0.09 miles of S.R. 250. Design plans include typical road sections, construction details, drainage details, and cross sections. Utility locations in the area are also noted.
This document contains information about various pool heating and cooling equipment, including:
1. An air/water heating/cooling pump that can extend the swim season and keep pool water comfortable year-round.
2. A G2 heat exchanger with a titanium tube bundle and stainless steel shell for efficient heat transfer between primary and secondary water circuits.
3. An Evolution electric pool heater that is fully equipped and easy to install for heating chlorinated pools.
The document describes the civil, structural and architectural works for various plant components. It discusses foundations for RCC structures like transformer yards and fencing. It also describes buildings like ESP control room, switchyard structures, intake water pump house, fire water pump house and tank foundations. Circulating water system involving sea water intake, pump houses, forebays and cooling water channels are also covered. Design criteria for RCC conduits for cooling water inlet and outlet is provided.
Type K Linear and Rotary Damper Actuators - RotorkCTi Controltech
The Type K Range offers rotary and linear pneumatic damper drives for utility power plants, refineries, powerhouse boilers, furnaces and process heaters that require precise combustion air and flue gas handling solutions. The damper drives are available in a wide range of configurations to meet the challenges of industrial applications. Some key features:
- A series offering drop-in-place retrofit, requiring no field engineering or fabrication.
- Improved reliability in high temperature environments
- Rated for 100% duty-cycle, continuous modulating service
- Highly accurate to 0.25% resolution
- Discrete contacts (O/C) and pneumatic, analog or bus network (MOD) communications
Lined Ball Valves Provide Corrosion ProtectionCTi Controltech
The document provides information on various lined ball valves and related products from Atomac/Flowserve including:
- AKH3 standard port and AKH2A full port lined ball valves that provide bubble-tight shutoff and low maintenance stem seals.
- V-port control valves and actuation options for precise throttling of corrosive media.
- Three-way AMP3 lined ball valves for corrosive diverter applications.
- Ceramic lined AKH5 valves for abrasive slurries and high temperature corrosives.
- Sampling valves, sight glasses, and check valves with corrosion resistant fluoropolymer linings for visual inspection and flow control of toxic chemicals
Victory Energy Firetube Boiler for extreme duty - Frontier SeriesCTi Controltech
By design, the Frontier® Series 3-pass and 4-pass wetback, and now dryback too, boilers are engineered and built for minimum maintenance and maximum output. Wall-to-wall super-structure and rifled tubes ensure years of extreme-duty performance.
Victory Energy utilizes the "latest" burner/control technology available to establish the most dependable operation needed for your specific application.
SunMaxx Installation Manual - StorMaxx Solar Hot Water Storage TanksSunMaxx Solar
This document provides an installation guide for StorMaxx CTEC Series water tanks. It includes requirements for the installation room and tank, descriptions of tank components like insulation, water casing, and electric heating elements. It also provides instructions for connecting a safety relief valve and technical specifications for various tank models.
Viking Universal Seal pumps are industrial-duty internal gear pumps that offer design flexibility and easy maintenance. They accommodate various sealing options, materials, port configurations and sizes to adapt to many applications. Key features include compatibility with all seal types, two-part design for efficiency, easy clearance adjustment, and a back pull-out seal design requiring no special tools. They are suitable for applications in chemicals, petroleum, transportation, machinery and more.
The document discusses Mitsubishi Electric's H2i line of hyper-heating inverter heat pumps. It provides details on their superior heating performance even in extreme cold, including 100% heating capacity down to 0°F outdoor ambient for R2-Series units. The document outlines residential M-Series and light commercial P-Series ductless split systems as well as larger commercial VRF R2-Series and Y-Series systems. It highlights features such as indoor unit options, controls, and heating performance advantages for cold climates.
Hobart Peelers: an hour of potatoes in three minutes.
Hobart Peeler
QUICK FACTS
Models can peel from 15 to 60 lbs. of potatoes in three minutes
Stainless steel housing for durability
Silicon, carbide-abrasive disk easily removed for cleaning
Stainless steel drive shaft
Heavy-duty hopper cover to monitor product
Heavy-duty motors for high volume, long life
FOOD PREP
Choppers/Grinders
Cutter Mixers
Food Cutters
Food Processors
Meat Saws
Mixers
Mixer/Grinders
Peelers
Power Drive Units
Tenderizers
Salad Dryers
Slicers
Accessories
This Webinar will also highlight our custom designed products that were specially manufactured per unique customer specifications. Learn about optional features that can be implemented into your designs for optimum functionality of the supports in your particular applications. Additionally, gain an overall understanding of pipe supports through a showcase of colorful photos and technical diagrams.
Updated Summary Lincoln Power Point PresentationDavid Page
The document provides an agenda and overview of Lincoln Associates, a manufacturer's representative specializing in HVAC&R equipment. It discusses Lincoln Associates' experience and the lines of equipment it represents, which include industrial heating, humidification, dehumidification, air handling units, and more. It also provides product specifications and details on various direct-fired, unit heater, refrigeration, infrared heating, and make-up air/ventilation system product lines such as air turnover units, evaporative coolers, and custom coils.
Specifically Designed for any industry that must obtain pressure or level transmitter readings on tanks and vessels. Valves are designed to ASME B16.34 and feature minimal dead space, preventing build-up. Purge ports and optional milled flats enable Clean In Place and drainage without process interruption.
Bolt pattern accommodates standard industry ANSI 150# flanged connections and retrofits to knife gate patterns. Hardware configuration allows separate bolting of valve to tank and transmitter to valve as an additional safety measure for hazardous media.
The document summarizes the Nordeast Nest, a custom eco home built in Minneapolis, MN from 2012-2014 that incorporates passive house principles and components. It achieved a very low annual heating demand of 32 kWh/m2 through an extremely well insulated and airtight building envelope. Key elements included walls with R-values of R-51 and R-39, a cold roof with R-70 insulation, high performance windows and doors, and an extremely tight air barrier that achieved an airtightness of 0.36 ACH50. HVAC systems included an energy recovery ventilator, air source heat pumps for heating and cooling, and a tankless water heater to provide heating, cooling, ventilation
The Raypak Digital gas pool heater has a microprocessor-controlled thermostat that allows the user to precisely set the pool and spa temperature. It has self-diagnostic controls to help with troubleshooting and notifies the user when the target temperature is reached. The heater is compatible with remote control systems and can monitor run time and cycles for maintenance purposes. It has a stainless steel burner system and pilot ignition for reliable heating.
The document discusses various techniques used in construction to improve energy efficiency and reduce waste, including:
- Diverting at least 85% of construction waste from the landfill by separating materials on-site for recycling
- Using a central cut area and storing wood off-cuts to reduce construction waste
- Implementing advanced framing techniques like insulated headers, 24" on-center wall spacing, and 2-stud corners to improve the home's insulation
The document describes Halo Eco-Twist compact fluorescent downlights. It discusses the new spiral twist CFL technology used in the Eco-Twist line and how the insulated housings prevent heat transfer between living areas and attics. The Eco-Twist system uses an electronic ballast that allows interchangeability between 16, 21, and 28 watt CFL lamps. The document provides details on the various 5" and 6" aperture housings, lamp features, compliance certifications, and compatible trim options.
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDYAgrima Garg
The document discusses services required for a business hotel including fire, HVAC, lifts, electrical, plumbing, and rainwater harvesting. It provides details on fire prevention measures like passive fire protection using non-combustible materials, fire exits, sprinkler systems, and firefighting shafts. HVAC services discussed include air handling units, cooling towers, supply/return air ducts, and equipment rooms. Lift services covered are types of elevators, lift planning and lobby designing. Electrical services summarized are emergency power backup systems and switchboards. Plumbing services note water consumption guidelines.
The document describes Viking Universal Seal pumps, which are heavy-duty internal gear pumps suitable for a wide range of applications up to 200 PSI pressure and temperatures from -120°F to 800°F. The pumps come in 13 sizes with flows up to 1,600 GPM and materials including cast iron, ductile iron, steel, and stainless steel. They have multiple sealing and port options. Larger N through RS sizes can be outfitted with a jacketed casing for temperature control applications requiring circulation of heat transfer fluids.
This document provides information on Viking heavy duty pumps series 125 and 4125, including:
- Standard features like revolvable casings, overpressure relief valves, and packed or mechanical seal construction.
- Specifications for unmounted pumps like port sizes, nominal pump ratings, maximum pressures and temperatures, viscosity ranges, and materials of construction.
- Details on optional helical gear reducer units for the pumps available in three sizes with various gear ratios to cover different flow rate ranges.
- Dimension drawings and performance data are referenced for additional technical specifications.
The document gives an overview of the construction, specifications, and options for Viking heavy duty rotary pumps to assist users in selecting the appropriate
Discover why choosing natural gas makes sense. Learn how you can get connected to natural gas in Ireland.
Natural gas has revolutionised the energy industry, playing an increasingly important role in our world today. In Ireland, natural gas accounts for almost a quarter of primary energy demand; fueling power plants, businesses and homes efficiently, cleanly
and reliably.
Natural gas is the fuel of choice for over 650,000 businesses and homes throughout Ireland. It is currently available in over 160 population centres across 19 counties.
Demand for natural gas has experienced phenomenal growth in recent years, with the number of natural gas users growing by almost 300,000 over the past ten years. More and more people are recognising the benefits of natural gas, in business, at home and, of course, for the environment.
Rheem Hot Water Brochure - The Heater ManBrendan Smith
The new Rheem hot water collection now available from The Heater Man in Sydney. Browse through this exciting range of Gas Storage Hot Water and Continuous Flow Gas Hot Water products.
The San Diego County Fire Authority document outlines standards for water storage tanks to provide fire protection where public water supply is unavailable. It provides tables specifying minimum water storage levels based on building size, as well as increased requirements when exposures are within 100 feet. The document also lists installation standards for water tanks, including that the tank must be higher than the fire department connection, supply pipes must be of an approved material, and the tank must be located between 50-150 feet from the structure.
GONKA, established as a limited company in 1986 in Ostim, Ankara, has become one of the leading firms in Heating - Cooling - Air Conditioning - Ventilating Installation, with the high performance and disciplined working mentality of Halil GONCU (Mechanical engineer, BS MS ITU, 1975) and Salih KADAYIFCIOGLU (Mechanical Engineer, BS GU, 1982) within more than 23 years for both manufacturing and contracting.
GONKA Company, has been continuing its activities, in its factory located in Sincan Organized Industrial Area, since 1996. GONKA manufactures its products related to Heating - Cooling - Air Conditioning - Ventilating Installation in its factory in an area of 10.000 m2 and equipped with the latest technology.
GONKA, which is continuing its activities through its technical and managerial staff in its modern Directorate General Building in Cetin Emec Boulevard, Ankara which it has moved in 2002, has been replaced "GONKA Air Conditioning Installation Construction and Trade Joint-Stock Company" by transforming into "joint-stock company" in 2003.
GONKA enforces its activity in Turkey By serving through its network consisted of Istanbul and Ankara Region Offices and maintenance-repair services firms. In regions other than these, GONKA offers contact and service through local offices and central maintenance-repair crews.
GONKA; has KnowHow, especially about the field of "Clean Room" technology, which requires sterility in operating theatres and air conditioning-ventilating systems of environments such as operas, theatres, auditorium buildings, television studios which require silence.
GONKA has created "model company" profile in air conditioning sector through both manufacturing or supply of devices and its disciplined approach in mechanical operations by succeeding a lot of projects within last 23 years. GONKA, which has focused on internto 32 countries and succeeded many projects in Middle-East, Asia and Africa countries by its powerful foreign trade departmentational projects in last 15 years, gave representations
O documento descreve a origem do Islã entre os povos da Arábia, como Maomé unificou politicamente a região sob um Estado teocrático e implantou o Islã como religião oficial. Explica também a expansão do Império Islâmico sob os califados Omíadas e Abássidas e as principais divisões no Islã entre Xiitas e Sunitas.
This document provides a marketing plan to increase student visitors to the ReStore, a reuse center, by 15%. It identifies the target audience as on-campus students who are unaware of the ReStore's local impact. The key insight is that students do not want to sacrifice their free time. The main message is that shopping at the ReStore benefits the community with no extra effort required. Various marketing tactics are proposed across print, digital, outdoor and social media to raise awareness among students.
Skype es una aplicación gratuita que permite realizar llamadas y videollamadas a otros usuarios de Skype en cualquier parte del mundo, así como llamadas a teléfonos fijos y móviles a tarifas económicas. Sus principales características incluyen llamadas de voz y video, mensajería instantánea, compartir archivos y conectarse a Internet desde puntos de acceso públicos. Skype también ofrece funciones para empresas como llamadas grupales gratuitas y herramientas para administrar cuentas y crédito.
El resumen describe el informe de gestión de la Asociación para la Integración de Juventudes Comunitarias para el año 2012. A pesar de que los ingresos superaron los de años anteriores, también lo hicieron los costos y gastos, lo que resultó en una pérdida al final del período. Los ingresos totales fueron de $197.978.182, un 43,83% más que el año anterior. Los costos aumentaron un 32,87% debido a inversiones iniciales en el mantenimiento de equipos y alquiler de equipos adic
Viking Universal Seal pumps are industrial-duty internal gear pumps that offer design flexibility and easy maintenance. They accommodate various sealing options, materials, port configurations and sizes to adapt to many applications. Key features include compatibility with all seal types, two-part design for efficiency, easy clearance adjustment, and a back pull-out seal design requiring no special tools. They are suitable for applications in chemicals, petroleum, transportation, machinery and more.
The document discusses Mitsubishi Electric's H2i line of hyper-heating inverter heat pumps. It provides details on their superior heating performance even in extreme cold, including 100% heating capacity down to 0°F outdoor ambient for R2-Series units. The document outlines residential M-Series and light commercial P-Series ductless split systems as well as larger commercial VRF R2-Series and Y-Series systems. It highlights features such as indoor unit options, controls, and heating performance advantages for cold climates.
Hobart Peelers: an hour of potatoes in three minutes.
Hobart Peeler
QUICK FACTS
Models can peel from 15 to 60 lbs. of potatoes in three minutes
Stainless steel housing for durability
Silicon, carbide-abrasive disk easily removed for cleaning
Stainless steel drive shaft
Heavy-duty hopper cover to monitor product
Heavy-duty motors for high volume, long life
FOOD PREP
Choppers/Grinders
Cutter Mixers
Food Cutters
Food Processors
Meat Saws
Mixers
Mixer/Grinders
Peelers
Power Drive Units
Tenderizers
Salad Dryers
Slicers
Accessories
This Webinar will also highlight our custom designed products that were specially manufactured per unique customer specifications. Learn about optional features that can be implemented into your designs for optimum functionality of the supports in your particular applications. Additionally, gain an overall understanding of pipe supports through a showcase of colorful photos and technical diagrams.
Updated Summary Lincoln Power Point PresentationDavid Page
The document provides an agenda and overview of Lincoln Associates, a manufacturer's representative specializing in HVAC&R equipment. It discusses Lincoln Associates' experience and the lines of equipment it represents, which include industrial heating, humidification, dehumidification, air handling units, and more. It also provides product specifications and details on various direct-fired, unit heater, refrigeration, infrared heating, and make-up air/ventilation system product lines such as air turnover units, evaporative coolers, and custom coils.
Specifically Designed for any industry that must obtain pressure or level transmitter readings on tanks and vessels. Valves are designed to ASME B16.34 and feature minimal dead space, preventing build-up. Purge ports and optional milled flats enable Clean In Place and drainage without process interruption.
Bolt pattern accommodates standard industry ANSI 150# flanged connections and retrofits to knife gate patterns. Hardware configuration allows separate bolting of valve to tank and transmitter to valve as an additional safety measure for hazardous media.
The document summarizes the Nordeast Nest, a custom eco home built in Minneapolis, MN from 2012-2014 that incorporates passive house principles and components. It achieved a very low annual heating demand of 32 kWh/m2 through an extremely well insulated and airtight building envelope. Key elements included walls with R-values of R-51 and R-39, a cold roof with R-70 insulation, high performance windows and doors, and an extremely tight air barrier that achieved an airtightness of 0.36 ACH50. HVAC systems included an energy recovery ventilator, air source heat pumps for heating and cooling, and a tankless water heater to provide heating, cooling, ventilation
The Raypak Digital gas pool heater has a microprocessor-controlled thermostat that allows the user to precisely set the pool and spa temperature. It has self-diagnostic controls to help with troubleshooting and notifies the user when the target temperature is reached. The heater is compatible with remote control systems and can monitor run time and cycles for maintenance purposes. It has a stainless steel burner system and pilot ignition for reliable heating.
The document discusses various techniques used in construction to improve energy efficiency and reduce waste, including:
- Diverting at least 85% of construction waste from the landfill by separating materials on-site for recycling
- Using a central cut area and storing wood off-cuts to reduce construction waste
- Implementing advanced framing techniques like insulated headers, 24" on-center wall spacing, and 2-stud corners to improve the home's insulation
The document describes Halo Eco-Twist compact fluorescent downlights. It discusses the new spiral twist CFL technology used in the Eco-Twist line and how the insulated housings prevent heat transfer between living areas and attics. The Eco-Twist system uses an electronic ballast that allows interchangeability between 16, 21, and 28 watt CFL lamps. The document provides details on the various 5" and 6" aperture housings, lamp features, compliance certifications, and compatible trim options.
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDYAgrima Garg
The document discusses services required for a business hotel including fire, HVAC, lifts, electrical, plumbing, and rainwater harvesting. It provides details on fire prevention measures like passive fire protection using non-combustible materials, fire exits, sprinkler systems, and firefighting shafts. HVAC services discussed include air handling units, cooling towers, supply/return air ducts, and equipment rooms. Lift services covered are types of elevators, lift planning and lobby designing. Electrical services summarized are emergency power backup systems and switchboards. Plumbing services note water consumption guidelines.
The document describes Viking Universal Seal pumps, which are heavy-duty internal gear pumps suitable for a wide range of applications up to 200 PSI pressure and temperatures from -120°F to 800°F. The pumps come in 13 sizes with flows up to 1,600 GPM and materials including cast iron, ductile iron, steel, and stainless steel. They have multiple sealing and port options. Larger N through RS sizes can be outfitted with a jacketed casing for temperature control applications requiring circulation of heat transfer fluids.
This document provides information on Viking heavy duty pumps series 125 and 4125, including:
- Standard features like revolvable casings, overpressure relief valves, and packed or mechanical seal construction.
- Specifications for unmounted pumps like port sizes, nominal pump ratings, maximum pressures and temperatures, viscosity ranges, and materials of construction.
- Details on optional helical gear reducer units for the pumps available in three sizes with various gear ratios to cover different flow rate ranges.
- Dimension drawings and performance data are referenced for additional technical specifications.
The document gives an overview of the construction, specifications, and options for Viking heavy duty rotary pumps to assist users in selecting the appropriate
Discover why choosing natural gas makes sense. Learn how you can get connected to natural gas in Ireland.
Natural gas has revolutionised the energy industry, playing an increasingly important role in our world today. In Ireland, natural gas accounts for almost a quarter of primary energy demand; fueling power plants, businesses and homes efficiently, cleanly
and reliably.
Natural gas is the fuel of choice for over 650,000 businesses and homes throughout Ireland. It is currently available in over 160 population centres across 19 counties.
Demand for natural gas has experienced phenomenal growth in recent years, with the number of natural gas users growing by almost 300,000 over the past ten years. More and more people are recognising the benefits of natural gas, in business, at home and, of course, for the environment.
Rheem Hot Water Brochure - The Heater ManBrendan Smith
The new Rheem hot water collection now available from The Heater Man in Sydney. Browse through this exciting range of Gas Storage Hot Water and Continuous Flow Gas Hot Water products.
The San Diego County Fire Authority document outlines standards for water storage tanks to provide fire protection where public water supply is unavailable. It provides tables specifying minimum water storage levels based on building size, as well as increased requirements when exposures are within 100 feet. The document also lists installation standards for water tanks, including that the tank must be higher than the fire department connection, supply pipes must be of an approved material, and the tank must be located between 50-150 feet from the structure.
GONKA, established as a limited company in 1986 in Ostim, Ankara, has become one of the leading firms in Heating - Cooling - Air Conditioning - Ventilating Installation, with the high performance and disciplined working mentality of Halil GONCU (Mechanical engineer, BS MS ITU, 1975) and Salih KADAYIFCIOGLU (Mechanical Engineer, BS GU, 1982) within more than 23 years for both manufacturing and contracting.
GONKA Company, has been continuing its activities, in its factory located in Sincan Organized Industrial Area, since 1996. GONKA manufactures its products related to Heating - Cooling - Air Conditioning - Ventilating Installation in its factory in an area of 10.000 m2 and equipped with the latest technology.
GONKA, which is continuing its activities through its technical and managerial staff in its modern Directorate General Building in Cetin Emec Boulevard, Ankara which it has moved in 2002, has been replaced "GONKA Air Conditioning Installation Construction and Trade Joint-Stock Company" by transforming into "joint-stock company" in 2003.
GONKA enforces its activity in Turkey By serving through its network consisted of Istanbul and Ankara Region Offices and maintenance-repair services firms. In regions other than these, GONKA offers contact and service through local offices and central maintenance-repair crews.
GONKA; has KnowHow, especially about the field of "Clean Room" technology, which requires sterility in operating theatres and air conditioning-ventilating systems of environments such as operas, theatres, auditorium buildings, television studios which require silence.
GONKA has created "model company" profile in air conditioning sector through both manufacturing or supply of devices and its disciplined approach in mechanical operations by succeeding a lot of projects within last 23 years. GONKA, which has focused on internto 32 countries and succeeded many projects in Middle-East, Asia and Africa countries by its powerful foreign trade departmentational projects in last 15 years, gave representations
O documento descreve a origem do Islã entre os povos da Arábia, como Maomé unificou politicamente a região sob um Estado teocrático e implantou o Islã como religião oficial. Explica também a expansão do Império Islâmico sob os califados Omíadas e Abássidas e as principais divisões no Islã entre Xiitas e Sunitas.
This document provides a marketing plan to increase student visitors to the ReStore, a reuse center, by 15%. It identifies the target audience as on-campus students who are unaware of the ReStore's local impact. The key insight is that students do not want to sacrifice their free time. The main message is that shopping at the ReStore benefits the community with no extra effort required. Various marketing tactics are proposed across print, digital, outdoor and social media to raise awareness among students.
Skype es una aplicación gratuita que permite realizar llamadas y videollamadas a otros usuarios de Skype en cualquier parte del mundo, así como llamadas a teléfonos fijos y móviles a tarifas económicas. Sus principales características incluyen llamadas de voz y video, mensajería instantánea, compartir archivos y conectarse a Internet desde puntos de acceso públicos. Skype también ofrece funciones para empresas como llamadas grupales gratuitas y herramientas para administrar cuentas y crédito.
El resumen describe el informe de gestión de la Asociación para la Integración de Juventudes Comunitarias para el año 2012. A pesar de que los ingresos superaron los de años anteriores, también lo hicieron los costos y gastos, lo que resultó en una pérdida al final del período. Los ingresos totales fueron de $197.978.182, un 43,83% más que el año anterior. Los costos aumentaron un 32,87% debido a inversiones iniciales en el mantenimiento de equipos y alquiler de equipos adic
Xochiquetzal juró amor eterno a un guerrero mexica ausente en la guerra, pero un tlaxcalteca le mintió diciendo que su amado había muerto y la convenció de casarse con él. Cuando el guerrero mexica regresó, enfrentó al tlaxcalteca en una sangrienta lucha. Después, encontró a Xochiquetzal muerta de pena. El guerrero mexica lloró su muerte y sus lágrimas formaron las montañas nevadas de Iztaccihuatl y Popocatépet
El documento presenta el cronograma de actividades y evaluaciones para una capacitación que incluye temas de Excel y web 2.0. En marzo se enseñarán funciones de Excel y se construirá un blog colaborativo aplicando esos conocimientos. En abril habrá una entrega que incluye el blog y un proyecto en Excel. En mayo se realizará un segundo parcial y más adelante el examen final evaluará los contenidos vistos a lo largo del curso.
Este documento describe la creación de un programa en Eclipse para tomar una decisión basada en un número ingresado por el usuario. Incluye instrucciones para crear tres TextViews para pedir un número, mostrar instrucciones y mostrar el resultado, así como un botón para calcular. Explica que el programa funciona correctamente al mostrar la palabra "cero" cuando se ingresa 0.
Daniel Miles received the Wings of Hope Achievement Award for 2011/2012 in recognition of his efforts managing a project and raising funds that provided hope to underprivileged children around the world. The award was given by Mrs. Rajni Sdram and Dr. R Sri Ram, the co-founders of The Wings of Hope Children's Charity, in April 2012.
O documento descreve a lenda da Papisa Joana, que teria se disfarçado de homem para estudar e chegado ao papado no século IX. Também resume elementos fundamentais da sociedade feudal medieval, como a divisão em ordens, a estrutura dos feudos e as relações de vassalagem.
El documento describe tres modelos de impresoras multifunción de Epson con diferentes características y precios. La primera impresora es multifunción A3+ rápida y productiva con impresión, copia, escaneado y fax en A3 a un costo de $675.302. La segunda es compacta con cartuchos independientes y conectividad Wi-Fi por $227.488. La tercera es ultracompacta con Wi-Fi, pantalla LCD y capacidad de impresión y escaneado móviles a un costo de $251.434.
This document summarizes the details of two unused stainless steel evaporative condensers. Each unit is rated at 827 tons and was manufactured by Evapco with model ATW-207C. The units feature stainless steel construction, enclosed fan motors, quick connect piping, sloped access ladders, and elliptical coil designs. Additional details are provided on optional accessories and each unit's dimensions and electrical specifications.
This document summarizes 15 case studies presented in a webinar about pipe support and expansion joint field examples. The case studies covered a range of issues including designing custom spring supports, developing slide plates for high temperatures, replacing expansion joints and snubbers, and reducing lateral loads on piping systems. The webinar also discussed the company's engineering capabilities and value-added services for pipe support projects.
Service Center Solahart Pemanas Air Solar Water Heater Tenaga Matahari Solahart ahli
Dalam rangka untuk memastikan layanan terbaik dan saran, Solahart pemanas air tenaga surya dan sistem tenaga surya hanya tersedia melalui Expert Solahart lokal Anda. Dan dengan cakupan seluruh Australia ada satu tidak jauh dari Anda. Cari ahli terdekat Anda di sini.
Semua ahli kami dilatih dan memenuhi syarat untuk menilai rumah Anda atau bisnis dan penggunaan energi Anda. Konsultasi surya GRATIS kami menjamin Anda mendapatkan solusi terbaik mutlak surya untuk situasi Anda. Buku gratis di rumah surya kutipan di sini.
Tidak hanya installer sistem tenaga surya kita diakreditasi oleh Dewan Energi Bersih, mereka juga dilatih oleh Solahart untuk memastikan bahwa setiap instalasi dilakukan sesuai dengan standar instalasi kami yang ketat dan hanya komponen yang ditentukan oleh Solahart digunakan untuk memastikan kinerja dan keamanan sistem tenaga surya Solahart Anda.
In this Webinar we explore the details of actual case studies focusing on various signs that indicate if a particular support needs replaced or adjusted. The presentation also covers projects that brought on new standard designs and custom designs for specific applications. And lastly, it includes valuable additions and procedures that extend the typical life span of a pipe support.
In this Webinar we explore the details of actual case studies focusing on various signs that indicate if a particular support needs replaced or adjusted. The presentation also covers projects that brought on new standard designs and custom designs for specific applications. And lastly, it includes valuable additions and procedures that extend the typical life span of a pipe support. PT&P's field services division is available 24x7 in the case of an emergency situation or for a scheduled shut down.
The document discusses cathodic protection for above ground storage tanks (AGSTs). It introduces Elsyca and Audubon Companies, who provide software and services related to corrosion engineering. It then reviews the technical aspects of AGST cathodic protection, including the goals, complexities, and assumptions of current designs. Case studies are presented that measure and model the performance of different CP system designs. Recommendations are provided for improving new and existing AGST CP designs and construction to better achieve 30-year tank lifespan.
TA is an air-conditioning unit designed for horizontal or vertical installation in the residential, commercial and hotel sectors.
Cooling capacity: 4.5 ÷ 40 kW
Heating capacity: 14 ÷ 87.5 kW
Pipe Shields Inc. pioneered insulated pipe supports in 1971 to protect insulating fiberglass pipes from crushing under load points. They have since developed a large product line of insulated pipe supports using strong, insulating materials. This document provides selection guides to help customers choose the appropriate support for their pipe's size, material, temperature requirements, and needed load rating or movement allowance. It also lists other specialized products and services Pipe Shields offers.
What Constittutes a Cuality Commissioning jobjoseph william
This document provides an overview of commissioning services for a construction project. It discusses the importance of being involved early in the pre-construction phase to help define the owner's requirements. It also outlines the commissioning process, including conducting design reviews, developing checklists and test procedures, overseeing construction installation, performing functional testing, and providing owner training and documentation. The document emphasizes the importance of thorough documentation throughout the construction and acceptance phases to ensure all systems meet the specified requirements.
Válvula utilizada para la regulación del caudal en una tubería que contiene un elemento tipo disco móvil y un anillo estacionario en un cuerpo generalmente esférico.
Las válvulas de globo se llaman así por su cuerpo esférico y sus dos mitades separadas por una o varias pantallas internas. Éste tiene una apertura que forma un asiento donde un tapón movible puede ser roscado para cerrar la válvula.
Valve used for regulating the flow in piping that contains a mobile disk type element and a stationary ring in a generally spherical body.
Globe valves are so called due to their spherical body and their two halves separated by one or several internal screens.
Listen to in-depth explanations on how to choose the type of expansion joint that will best suit your system. Learn about the bellows movements throughout the piping system due to thermal changes of mechanical motion. Increase your understanding of the different types of expansion joints and value-added services offered by U.S. Bellows.
This document discusses and compares different HVAC system types for buildings including cold water systems, VRF systems, and package units. It provides details on system components, installation considerations, costs, energy efficiency, and maintenance requirements. Key points covered include that cold water systems have higher costs in Israel but longer lifespans, VRF systems are less costly but need space for outdoor units, and package units require ductwork to transport air to and from indoor units. Heat pump and heat recovery systems are also discussed.
This document provides the design basis for a class project to develop the optimum tie-back option for a third well drilled in the Red Hawk field within block GB 877. Three potential tie-back options are considered: 1) Tie back to the existing manifolds of the first two wells, 2) An independent flowline through a hazard mass directly to the riser, 3) Independent flowlines directly to the risers via the same route as the existing flowlines. Key parameters of the existing design basis for the first two wells and the third well location are presented. Deliverables for the project include an updated design basis, evaluation of options, recommended option details, diagrams and an equipment list.
The document discusses energy saving solutions from Powertech Solar, including solar thermal collectors and other renewable technologies. It provides details on their solar thermal collectors, including the benefits of evacuated tube collectors over flat plate collectors. It also describes how the solar thermal collectors can be installed in new or existing homes and integrated with other systems.
- A plate heat exchanger consists of thin metal plates arranged in a pack with spaces between the plates forming channels for two fluids to flow, enabling heat transfer between the fluids. It contains up to 700 thin plates that are compressed within a frame to form continuous manifolds for fluid flow.
- The heat transfer rate in a plate heat exchanger can be expressed by an equation involving the overall heat transfer coefficient, total plate area, and effective mean temperature difference. Dynamic modeling of the system derives transfer functions relating the temperature of one fluid to changes in the other.
- Process instrumentation like flow meters, temperature sensors, voltage amplifiers and control valves are required to monitor and regulate the plate heat exchanger process. Orif
This document provides product data on Carrier rooftop air conditioning units. It includes details on:
- Features and benefits of the units such as ease of installation, maintenance, and use
- Model number nomenclature explaining the coding system
- Available factory-installed options and field-installed accessories such as economizers, motors, controls, coils, and curbs
- Performance data including cooling and heating capacity tables, sound levels, dimensions, and electrical information
The document provides specification sheets, engineering details, and selection information for Carrier 48TC packaged rooftop air conditioning units for heating, cooling, and ventilation applications.
In this Webinar we explore the details of actual case studies focusing on various signs that indicate if a particular support needs replaced or adjusted. The presentation also covers projects that brought on new standard designs and custom designs for specific applications. And lastly, it includes valuable additions and procedures that extend the typical life span of a pipe support.
AmSan Now Carries a Complete MRO Building Maintenance Supplies Product Offering.Steve Kolesar
AmSan has introduced a complete MRO Building Maintenance Supplies product offering:
appliances, electrical maintenance, lighting fixtures, bulbs and fluorescent lamps, HVAC
units and maintenance items, plumbing fixtures, plumbing repair and maintenance items,
bath accessories, hardware, tools, access control, and door hardware. Streamlining and
simplifying your ordering processes by offering both Janitorial and MRO products is
another step in our process to decrease your operating expense and improve your bottomline. With just a single purchase order, AmSan can fulfill all your facility maintenance needs.
Need a proven solution to remove surface runoff? Contech's Slotted Drain™ has over 100-years of proven in the ground performance and can remove over 50% more surface runoff than alternative inlet solutions.
This document summarizes information about the Ivanpah Solar Thermal Project, including:
1. The project organization involving Solar Partners Holdco, LLC and three individual solar thermal plants with power purchase agreements with PG&E and SCE.
2. Environmental considerations like protecting desert tortoises and managing weeds, as well as water and air emissions.
3. Site details like the 3,500 acre footprint and layout of the three solar units with towers up to 459 feet tall.
4. How the heliostat mirrors focus sunlight to generate thermal energy and produce steam to power turbines and generate electricity in an environmentally friendly manner.
Similar to Preliminary design submittal presentation (20)
1. 1275 Shiloh Road • Suite 2560
Kennesaw, GA 30144
770.794.7012
brewerengineering.com
Preliminary Design Submittal
Professional Design and Construction
Administration Services for:
Sewell Park Redevelopment
Cobb County Parks, Recreational, and
Cultural Affairs Department
April 19, 2013
2. Submittal Contents
Preliminary Base Sheets
Overall Site Plan
Site Plans
Grading Plans
Utility Plans
Architectural Plans
Architectural Elevations
Issues Lists
Updated Schedule
Permit Required List
Preliminary Cost Estimates
24. 5855 Jimmy Carter Boulevard Suite 218 Norcross, Georgia 30071 770.729.8433 fax 770.729.8466
SEWELL PARK PRELIMINARY NOTES AND QUESTIONS
Notes
1. The asbestos report notes the tan tile has asbestos and will need to be remediated. Our
understanding is that this will be handled by the client before we begin demolition.
2. Geo Hydro recommends that the demolition contractor make a specific composite sample of
the demolition debris for the Concession/Restroom building and a combined sample from the
Field 3 Dugouts for Toxic Characteristic (TC) analysis for lead. According to their findings they do
not believe that they test will come back showing a high level of lead content. This test will cost
approximately $50.00 and is up to the owner. Please advise is you want to have us include this
in the specifications.
3. We will note in the specifications the recommendations for the fluorescent light fixtures.
Architectural:
1. The schematic notes added a door from the concession storage (was Youth Closet) to the
concession room. Is an exterior door needed for concession storage.
2. If a exterior door is needed to concession storage does it need to be 4'-0"?
3. In expanding the dugouts at field 3 to the requested size the two poles next to (and attached)
the existing dugouts will need to be relocated or demolished. Please advise.
4. There are wooded baseball bat holders at each of the dugout areas. Are those to be saved?
5. If the wooded bat holders are to be saved are they to be repainted?
6. According to Addendum 1 the dugouts at field 3 are to be brought up to grade. We are
currently showing that situation. if this is incorrect please let us know.
7. We are currently showing a 4' gate on one side of the Field 3 building by one of the redesigned
dugouts for access to the condenser in between the building and the field. If this is not
acceptable or you would like different access please advise.
8. The current benches have backs. We are current showing new benches without backs. Is that
acceptable.
9. We have provided a shelf in the dugouts in field 3 for helmets. Please advise if this is not
acceptable.
Plumbing:
1. In an attempt at meeting the latest State adopted water conservation requirements (i.e. use of
high-efficiency plumbing fixtures), it appears that the standard push-button styles typically used
do not meet the minimum ADA push requirements, therefore we are proposing use of hydraulic
flushometers for the water closets and urinals (see Attachments 1 & 2 for products by Sloan).
They can be ordered with accessories for metal push buttons in lieu of the plastic buttons
shown, and elbows for top-spud connections in lieu of the back-spud shown). Please advise if
acceptable.
2. For the 3-compartment sink a drop-in stainless steel fixture will be specified. To meet
requirements of Cobb Food Service Code where each compartment “shall be large enough to
accommodate immersion of the largest equipment and utensils” what are the minimum
compartment dimensions required.
25. 5855 Jimmy Carter Boulevard Suite 218 Norcross, Georgia 30071 770.729.8433 fax 770.729.8466
HVAC:
1. For concession area we are providing a ductless split heat pump unit with programmable thermostat,
however, there is concern about concession storage room being hot during the summer months. To
solve this problem, In lieu of ductless split unit, we could put a floor mounted unit in the Concession
storage and duct this unit to serve both concession storage and concession room. Please advise.
2. In case it was decided not to provide any air-conditioning for concession storage, we can ventilate this
room along with baseball storage room by means of a roof mounted exhaust fan. The fan will be
controlled by means of wall mounted thermostat at Concession storage room. Please advise.
3. For Ventilation of restrooms, we plan to control the roof mounted exhaust fan serving the restrooms by
means of both programmed timer and motion sensor, that is, in the summer months; we program the
fan to run continuously on certain days and certain hours, and during the cold months, we let the fan to
be controlled by motion sensor. This way, we can lower the space temperature during the summer
months. Please advise.
ELECTRICAL:
1. Are we to provide any power or EC to the scoreboards? Notes indicate that this will be done under a
separate contract but the electrical will need to be coordinated.
2. Is any EC or power needed for sound systems?
3. Need direction on how to control the field lighting. Notes indicate a remote control and time clock.
What is needed for the remote connection for lighting controls?
4. Do we need any dedicated power outside the concessions building for fryers or will they be propane?
28. 1275 Shiloh Road
Suite 2560
Kennesaw, GA 30144
Preliminary Design Questions/Issues
1. What playground surface and equipment is desired for the Commons Area? What age group should this area
be designed for?
2. Do we have as-builts or design drawings for the irrigation system recently installed for Fields 5A 5B?
3. Do we know where the existing septic field and tank is located for the existing concession stand?
4. Will the existing score keepers structure be retained for both Fields 1 2?
5. We have had several discussions with Cobb Stormwater to develop ways to incorporate the scope of the
project desired without requiring water quality measures ponds. We are attempting to develop a plan that
will not generate an increase in stormwater runoff and thereby not require detention ponds or water quality
ponds. Paving scope will be a possible issue with water quality.
29. Sewell Park Project Schedule
Notice to Proceed 2-25-13
Begin Field Survey 3-04-13
Project Team Site Visit 3-04-13
Kick-off Meeting 2-25-13
Survey Completed 3-16-13
Schematic/Preliminary Design 4-19-13
Formal Presentation to County 4-26-13
Design Development Submittal 5-17-13
90% CD Submittal 6-26-13
100% CD Submittal 7-17-13
Submit for LDP 7-24-13
LDP Permit 9-02-13
Submit for Building Permit 9-02-13
Submit to Purchasing-Bid Set 9-18-13
Building Permit 9-30-13
Issue for Bid 9-27-13
Pre-Bid Meeting 10-08-13
Bid Date 10-24-13
BOC Award 11-12-13
Construction Begins 1-02-14
Sod Installed 5-08-14
Construction Completion 8-01-14
30. Permits Required
Land Disturbance Permit- Cobb County
Marietta Water Sewer Marietta Power Approvals
Building Permit-Cobb County
NPDES Permit
31. Units Qty Unit Rate Sub Total Total
244,231.00$
‐$
LS 1 30,000.00$ 30,000.00$
LS 1 123,000.00$ 123,000.00$
LS 1 35,000.00$ 35,000.00$
LS 1 19,000.00$ 19,000.00$
LS 1 36,000.00$ 36,000.00$
243,000.00$
SF 25600 0.25$ 6,400.00$
CY 75 15.00$ 1,125.00$
LF 686 5.00$ 3,430.00$
SF 400 2.00$ 800.00$
LS 2 3,000.00$ 6,000.00$
CY 200 12.00$ 2,400.00$
CY 500 15.00$ 7,500.00$
SF 30000 0.10$ 3,000.00$
SF 30000 0.10$ 3,000.00$
SF 30000 0.10$ 3,000.00$
Re‐Development of Sewell Park
Cobb County Parks, Recreation, Cultural Affairs
Preliminary Cost Estimate ‐ 4‐19‐13
Laser Grading Filling
Laser Grading before sod
Project Budget for Redevelopment of Fields #1, #2, #3, #4, Common
Area Between Field 3 and 5A 5B
Preliminary Cost Estimate‐ Baseball Concession/RR Bldg
Strip Haul off sod
Demolition of existing building
New Concession Building
Electrical
HVAC
Plumbing
Field #1
Hazardous Material Abatement (
Total Preliminary Estimated Cost Concession/RR Bldg
$ 977,500.00
Item ‐ Description
Project Budget for Baseball Concession/Restroom Building
Demolition‐Field 1
Remove existing infield mix
Remove existing fencing posts
Remove existing concrete
Remove existing dugouts
Grading Field 1
Import fill
Import topsoil
Laser Grading Subgrade
32. Sewell Park Preliminary Cost Estimate 2
Units Qty Unit Rate Sub Total Total
TN 120 110.00$ 13,200.00$
TN 35 85.00$ 2,975.00$
TN 300 30.00$ 9,000.00$
‐$
‐$
‐$
‐$
EA 1 1,750.00$ 1,750.00$
LF 700 4.00$ 2,800.00$
EA 1 400.00$ 400.00$
SF 10000 0.25$ 2,500.00$
‐$
SF 26500 0.50$ 13,250.00$
EA 1 1,250.00$ 1,250.00$
EA 1 400.00$ 400.00$
EA 8 300.00$ 2,400.00$
EA 2 200.00$ 400.00$
EA 28 75.00$ 2,100.00$
EA 1 3,000.00$ 3,000.00$
LF 400 15.00$ 6,000.00$
LF 400 12.00$ 4,800.00$
LF 200 10.00$ 2,000.00$
LF 200 10.00$ 2,000.00$
‐$
‐$
EA 1 3,000.00$ 3,000.00$
‐$
‐$
2 Irrigation Meter
2 PVC
1.5 PVC
1.25 PVC
1 PVC
Main Shut Off Valve
Scrubber Valves
Quick Coupling Valve
Falcon 6504
Controller
Grassing
Landscaping Irrigation Field 1
Sod
Backflow Preventer
Erosion Field 1
Temoporary construction entrance
Silt Fence
Inlet Protection
Sand
Existing Septic Field Removal
Infield Mix
Warning Track Mix
Item ‐ Description
33. Sewell Park Preliminary Cost Estimate 3
Units Qty Unit Rate Sub Total Total
SF 650 5.00$ 3,250.00$
LF 500 15.00$ 7,500.00$
LF 135 25.00$ 3,375.00$
LF 60 75.00$ 4,500.00$
LF ‐$
EA 1 1,750.00$ 1,750.00$
EA 4 300.00$ 1,200.00$
LF 300 3.00$ 900.00$
LS 1 1,000.00$ 1,000.00$
‐$
EA 2 1,250.00$ 2,500.00$
LF 300 2.00$ 600.00$
‐$
EA 2 250.00$ 500.00$
EA 3 150.00$ 450.00$
LS 2 15,000.00$ 30,000.00$
‐$
LS 1 70,000.00$ 70,000.00$
EA 1 2,000.00$ 2,000.00$
EA 1 2,000.00$ 2,000.00$
SY 365 25.00$ 9,125.00$
SF 180 50.00$ 9,000.00$
‐$
LF 50 35.00$ 1,750.00$
LF 40.00$ ‐$
LF 250 35.00$ 8,750.00$
LS 1 15,000.00$ 15,000.00$
285,030.00$
Storm drainage
Fence Windscreen
Heavy Duty Rubber Backstop Netting
Outfield Distance Markers
Dugouts
4 FT Gate
Yellow Fence Capping
Homeplate Bases
Pitching Mound
Foul Poles
6 FT Chain Link Fencing
Underground Power Service to Fields 1 2 to replace overhead
Total Preliminary Estimated Costs ‐ Field #1
Concrete Retaining Wall
Utilities Field 1
Water
Sanitary Sewer
Scoreboards
New Wiring for Light Poles
New wiring for Pitching Machines
Power to Pitching Mound
Asphalt Drive
10 FT Chain Link Fencing
20 FT Chain Link Fencing
24 FT Chain Link Fencing
12 FT Gate
Item ‐ Description
Site Improvements Field 1
Concrete Pad
34. Sewell Park Preliminary Cost Estimate 4
Units Qty Unit Rate Sub Total Total
SF 15500 0.25$ 3,875.00$
CY 100 15.00$ 1,500.00$
LF 498 5.00$ 2,490.00$
EA 2 3,000.00$ 6,000.00$
‐$
CY 500 15.00$ 7,500.00$
SF 20000 0.10$ 2,000.00$
SF 20000 0.20$ 4,000.00$
TN 120 110.00$ 13,200.00$
TN 20 85.00$ 1,700.00$
TN 150 30.00$ 4,500.00$
EA 1 1,750.00$ 1,750.00$
LF 600 4.00$ 2,400.00$
‐$
SF 10000 0.25$ 2,500.00$
SF 16000 0.50$ 8,000.00$
EA 1 800.00$ 800.00$
EA 1 400.00$ 400.00$
EA 6 300.00$ 1,800.00$
EA 2 200.00$ 400.00$
EA 20 75.00$ 1,500.00$
EA 1 1,200.00$ 1,200.00$
LF 400 10.00$ 4,000.00$
LF 300 10.00$ 3,000.00$
LF 150 10.00$ 1,500.00$
LF 150 10.00$ 1,500.00$
‐$
1.25 PVC
1 PVC
Quick Coupling Valve
Falcon 6504
Controller
2 PVC
1.5 PVC
Landscaping Irrigation Field 2
Sod
Backflow Preventer
Main Shut Off Valve
Scrubber Valves
Erosion Field 2
Temoporary construction entrance
Silt Fence
Inlet Protection
Grassing
Laser Grading Subgrade
Laser Grading Filling before sod
Infield Mix
Warning Track Mix
Sand
Remove existing fencing posts
Demo and remove existing dugout
Grading Field 2
Import fill
Import topsoil
Item ‐ Description
Field #2
Demolition Field 2
Strip Haul off sod
Remove existing infield mix
35. Sewell Park Preliminary Cost Estimate 5
Units Qty Unit Rate Sub Total Total
SF 650 5.00$ 3,250.00$
LF 435 15.00$ 6,525.00$
LF 120 25.00$ 3,000.00$
LF 65 75.00$ 4,875.00$
LF ‐$
EA 1 1,750.00$ 1,750.00$
EA 4 300.00$ 1,200.00$
LF 250 3.00$ 750.00$
EA 1 1,000.00$ 1,000.00$
‐$
EA 2 1,250.00$ 2,500.00$
LF 250 2.00$ 500.00$
‐$
EA 2 250.00$ 500.00$
EA 3 150.00$ 450.00$
EA 2 15,000.00$ 30,000.00$
‐$
LS 1 70,000.00$ 70,000.00$
LS 1 2,000.00$ 2,000.00$
‐$
‐$
‐$
LF 350 50.00$ 17,500.00$
‐$
223,315.00$ Total Preliminary Estimated Costs ‐ Field #2
Water
Sanitary Sewer
Storm drainage
Scoreboards
New Wiring for Light Poles
New wiring for Pitching Machines
Utilities Field 2
Fence Windscreen
Heavy Duty Rubber Backstop Netting
Outfield Distance Markers
Dugouts
4 FT Gate
Yellow Fence Capping
Homeplate Bases
Pitching Mound
Foul Poles
6 FT Chain Link Fencing
10 FT Chain Link Fencing
20 FT Chain Link Fencing
24 FT Chain Link Fencing
12 FT Gate
Item ‐ Description
Site Improvements Field 2
Concrete Sidewalks
36. Sewell Park Preliminary Cost Estimate 6
Units Qty Unit Rate Sub Total Total
‐$
‐$
‐$
LS 2 6,000.00$ 12,000.00$
‐$
‐$
‐$
‐$
LS 2 25,000.00$ 50,000.00$
‐$
‐$
‐$
‐$
62,000.00$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
Total Preliminary Estimated Costs ‐ Field #3
New Dugout
Field #3
Demolition Field 3
Demolition of existing Dugout
Item ‐ Description
37. Sewell Park Preliminary Cost Estimate 7
Units Qty Unit Rate Sub Total Total
‐$
SF 55600 0.25$ 13,900.00$
CY 300 15.00$ 4,500.00$
LF 1000 5.00$ 5,000.00$
SF 600 2.00$ 1,200.00$
EA 6 1,600.00$ 9,600.00$
EA 2 3,000.00$ 6,000.00$
EA 6 400.00$ 2,400.00$
CY 2000 12.00$ 24,000.00$
CY 900 15.00$ 13,500.00$
EA 1 5,000.00$ 5,000.00$
EA 1 6,000.00$ 6,000.00$
TN 300 110.00$ 33,000.00$
LS 1 5,000.00$ 5,000.00$
TN 80 85.00$ 6,800.00$
TN 600 30.00$ 18,000.00$
‐$
EA 1 3,000.00$ 3,000.00$
SF 1500 4.00$ 6,000.00$
EA 3 400.00$ 1,200.00$
SF 43000 0.25$ 10,750.00$
‐$
LF ‐$
LF ‐$
LF 600 50.00$ 30,000.00$
Utilities Field 4
Water
Sanitary Sewer
Storm drainage
Erosion Field 4
Temoporary construction entrance
Silt Fence
Inlet Protection
Grassing
Laser Grading Filling before sod
Infield Mix
Clear Grub
Warning Track Mix
Sand
Selective Tree Removal
Grading Field 4
Earthwork
Import topsoil
Laser Grading Subgrade
Remove existing infield mix
Remove existing fencing posts
Remove existing concrete
Remove and dispose of existing light poles
Demo and remove existing dugout
Item ‐ Description
Field #4
Demolition Field 4
Strip Haul off sod
38. Sewell Park Preliminary Cost Estimate 8
Units Qty Unit Rate Sub Total Total
Landscaping Irrigation Field 4
Sod SF 58000 0.50$ 29,000.00$
Backflow Preventer EA 1 1,200.00$ 1,200.00$
Main Shut Off Valve EA 1 400.00$ 400.00$
Scrubber Valves EA 14 300.00$ 4,200.00$
Quick Coupling Valve EA 4 200.00$ 800.00$
Falcon 6504 EA 40 75.00$ 3,000.00$
Controller EA 1 3,000.00$ 3,000.00$
2 PVC EA 800 10.00$ 8,000.00$
1.5 PVC LF 600 10.00$ 6,000.00$
1.25 PVC LF 300 10.00$ 3,000.00$
1 PVC LF 300 10.00$ 3,000.00$
‐$
‐$
Irrigation Meter EA 1 3,000.00$ 3,000.00$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
Item ‐ Description
39. Sewell Park Preliminary Cost Estimate 9
Units Qty Unit Rate Sub Total Total
SF 650 5.00$ 3,250.00$
LF 580 15.00$ 8,700.00$
LF 120 25.00$ 3,000.00$
LF 180 75.00$ 13,500.00$
LF 120 125.00$ 15,000.00$
EA 2 1,750.00$ 3,500.00$
EA 4 300.00$ 1,200.00$
LF 275 3.00$ 825.00$
EA 1 1,000.00$ 1,000.00$
‐$
EA 2 1,250.00$ 2,500.00$
SF 120 2.00$ 240.00$
‐$
EA 3 250.00$ 750.00$
EA 3 250.00$ 750.00$
EA 2 15,000.00$ 30,000.00$
‐$
‐$
LS 1 25,000.00$ 25,000.00$
EA 6 20,000.00$ 120,000.00$
LS 1 2,000.00$ 2,000.00$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
500,665.00$
Item ‐ Description
Site Improvements Field 4
Concrete Sidewalks
6 FT Chain Link Fencing
10 FT Chain Link Fencing
20 FT Chain Link Fencing
30 FT Chain Link Fencing
12 FT Gate
4 FT Gate
Yellow Fence Capping
Homeplate Bases
Pitching Mound
Foul Poles
Fence Windscreen
Heavy Duty Rubber Backstop Netting
Outfield Distance Markers
Dugouts
Scoreboards
Lighting Distribution Modifications Allowance
New Light Pole Fixtures ( Assuming Musco direct burial pole)
Power to Pitching Mound
Total Preliminary Estimated Costs ‐ Field #4
40. Sewell Park Preliminary Cost Estimate 10
Units Qty Unit Rate Sub Total Total
‐$
‐$
‐$
EA 10 450.00$ 4,500.00$
EA 9 190.00$ 1,710.00$
EA 9 175.00$ 1,575.00$
EA 25 45.00$ 1,125.00$
EA 25 25.00$ 625.00$
EA 25 15.00$ 375.00$
EA 21 16.00$ 336.00$
‐$
TN 50 50.00$ 2,500.00$
TN 2 225.00$ 450.00$
SF 1000 10.00$ 10,000.00$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
‐$
23,196.00$
Item ‐ Description
Common Area Between Field #3 #5A/5B
Large Trees
Evergreen Tree
Small Flowering Trees
Large Shrubs
Small Shrubs
Ground Cover
Oerebbuaks.Native Grasses
Slate Dust
Boulders
Play Surface
Total Preliminary Estimated Costs‐ Common Area
41. Sewell Park Preliminary Cost Estimate 11
Units Qty Unit Rate Sub Total Total
‐$
244,231.00$
SY 1200 16.00$ 19,200.00$
SY 1200 8.00$ 9,600.00$
‐$
‐$
‐$
LF 420 10.00$ 4,200.00$
LS 1 2,500.00$ 2,500.00$
‐$
‐$
LS 1 8,000.00$ 8,000.00$
‐$
‐$
SY 8000 24.00$ 192,000.00$
‐$
‐$
‐$
235,500.00$
‐$
1 20,000.00$ 20,000.00$
1 4,000.00$ 4,000.00$
‐$
‐$
‐$
‐$
‐$
24,000.00$
Item ‐ Description
Project Budget for Paving
Site Paving
Soil Cement Stabilization
2 Asphalt Topping
Storm Sewer
Curb Gutter
Traffic Striping
Removal and Disposal of gravel
Landscaping
Additional Available for Site Paving (8,000 sy‐ 72,000 sf)
Total Preliminary Estimated Costs ‐ Site Paving
Alternates
Storage Shed
Electrical for Shed
Total Preliminary Estimated Costs‐ Storage Shed