SlideShare a Scribd company logo
1 of 1
NSTX-U CPD DIAGNOSTIC IMPACTS, PF-1C BUS SUPPORT & D-SITE WATER SYSTEMS
Emmanuel O. Balogun, Kuishon A. Brown
Much Effort by: Neway Atnafu, Ron Bell, Andy Carpe, Robert Ellis, Steve Raftopoulos, Roger Raman, Matt Reinke, Filippo Scotti, Brent Stratton, John Winkelman, J. Mitchell, Stefan Gerhardt
Princeton Plasma Physics Laboratory, Princeton, NJ USA
INTRODUCTION
This presentation comprises three projects that were undertaken.
The Cryo-pump divertor (CPD) project is motivated by the need for a cryo-
pump and a re-design of the existing divertor in the NSTX-U. Port by port analysis
was done to see how the new CPD will affect respective diagnostics.
The second project is the D-Site Water Cooling System. Around Mid-July,
some contaminations were found in the water used for cooling the NSTX-U field
coils and thus we tracked down the cooling water system to find how the
contaminant might have been transported.
Finally, analysis work was done on the PF-1C Bus Support. The PF-1C Bus
Support is to provide support for the PF-1 Coils and preventing deflection of the
bus bars.
Final Presentation August 10th, 2016 • Princeton, NJ
SUMMARY TABLE OF FINDINGS
Analysis of Bays A & B viewing cones
CONCLUSION
Our work on the CPD diagnostics was instrumental in the success of the Conceptual Design review (CDR)
for the cryo-pumped divertor project. We were able to determine diagnostics that will be affected by the new
structure, and negotiate with physicists to redesign some structures to accommodate the new CPD.
Work on the D-Site water systems helped us create a flow diagram describing the water flow through a
central de-ionized make-up water system.
Structural analysis by hand calculations was done on the PF-1C bus flex cable support to test strengths in
both its parts and joints for anticipated loadings in the form of Torque, Shear, Tension, and Compression.
BAY DESCRIPTION FINDINGS
A PCHERS(Ron Bell), No interference with divertor detected so far.
Seems good.
B FIDA BKGRD(Deyoung Liu) No interference with divertor detected so far.
Seems good.
C U. Wash Bolometer; Dust Collector (Charles
Skinner/Raman)
Viewing cone of 70 degrees. Has extra-ion
outer shield, inner adapter, and lens is
straight up
D (Cryopump feedthroughs)
Future LD CP Feedthroughs
Not necessary; No interference
E EIES, VIPS (LLNL); Fast 1DCCD camera
(LLNL)
(Filippo Scotti)
Physicist will duplicate the specifications
from Bay H for this bay.
Interference is observed with the divertor and
the shield walls that are yet to be included in the
NSTX-U.
F QMB (Charles Skinner)
Elect. feedthroughs
Pending..
G UT-K Spectrometer, IR camera (Reinke) No interference with divertor detected so far.
Seems good.
H Visible fast camera(Filippo Scotti) Interference is observed with the divertor and
the shield walls that are yet to be included in the
NSTX-U.
I Elect. feedthroughs Not necessary.
J RF Probe (Bob Kaita)
Elect. feedthroughs
Okay. No interference detected.
K MAPP Probe, Elect. feedthroughs (Bob
Kaita)
Okay. No interference detected.
Bays A & B will continue to support the poloidal PCHERS
D-SITE WATER COOLING SYSTEMS FLOW CHART
Support is mounted to body of NSTX-U Machine
This work was made possible by funding from the Department of Energy for the Engineering Apprenticeship program.
PF1-C FLEX CABLES BUS SUPPORT
Above are pictures and drawings of the PF-1C Flex Cable Bus Supports. Hand calculations and
structural analysis was done to ensure it could withstand the forces caused by the turbulence of the
cables due to the presence of strong magnetic fields in NSTX-U. This structure is made almost
entirely out of stainless steel due to its insignificant magnetic permeability.
Tasked to identify the D-Site Water Systems Relationship with the
Facilities waters. Due to the fact that many drawings were either missing
or not up to date, extensive field work had to be undertaken.
Bays J and K Support Probe
• The present Bay I Upper
and Lower ports will support a
divertor resistive bolometer for
the FY17 & 18 runs.
• Elevated baffle top will
completely block the lower view.
• Need to assess the best path
forward after completing the CP
CDR.
– May involve a new
instrument at Bay I lower, tangential viewing bolometry,
viewing from the mid-plane.
Bay I Divertor Bolometer Is Severely Impacted by CP Design
Bays H & E Support Divertor Spectroscopy
• Evaluating the need to redesign the Bay H reentrant view and
shutter, given the raised divertor floor.
– Quite possible that the Bay E 1D CCD will need a similar
treatment.
• Must ensure lack of interference with divertor support structure.
Conceptual CAD model for diagnostic views
Above ore Images and picture of parts of the bus support
To the left is an image of hand
sketch-up of Bay G diagnostic
port views.
No pressing issues with views
were detected during sketch-up
Bay G
Above is an image of bay H port
showing diagnostic interference

More Related Content

What's hot

Bodem Breed 2011 - Potential of Aquifer Storage and Recovery (ASR) for a clim...
Bodem Breed 2011 - Potential of Aquifer Storage and Recovery (ASR) for a clim...Bodem Breed 2011 - Potential of Aquifer Storage and Recovery (ASR) for a clim...
Bodem Breed 2011 - Potential of Aquifer Storage and Recovery (ASR) for a clim...Koen_Zuurbier
 
Hydrology and hydraulics for design design
Hydrology and hydraulics for design designHydrology and hydraulics for design design
Hydrology and hydraulics for design designavirup naskar
 
ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002William Godwin
 
Floodplain Mapping for Design Professionals_RIFMA2016
Floodplain Mapping for Design Professionals_RIFMA2016Floodplain Mapping for Design Professionals_RIFMA2016
Floodplain Mapping for Design Professionals_RIFMA2016RI_FMA
 
TERS Presentation
TERS PresentationTERS Presentation
TERS Presentationhtgcd
 
pump test for linkedin
pump test for linkedinpump test for linkedin
pump test for linkedinSean Haugen
 
Desired Future Condition (DFC) Presentation
Desired Future Condition (DFC) PresentationDesired Future Condition (DFC) Presentation
Desired Future Condition (DFC) Presentationhtgcd
 
Hisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsHisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsSarah El Akkad
 
SSA_flyer 2011revised_june
SSA_flyer 2011revised_juneSSA_flyer 2011revised_june
SSA_flyer 2011revised_juneThomas Stump
 
Nwp rov and sonar briefing mar 2014
Nwp rov and sonar briefing mar 2014Nwp rov and sonar briefing mar 2014
Nwp rov and sonar briefing mar 2014Rick Benoit
 
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2syed abdul wahab
 
1976 floating breakwater performance
1976  floating breakwater performance1976  floating breakwater performance
1976 floating breakwater performanceApoorva Appi
 
Hydrodynamic Analysis of Baral river
Hydrodynamic Analysis of Baral riverHydrodynamic Analysis of Baral river
Hydrodynamic Analysis of Baral riverKhushnuma Wasim
 
CE-235 EH Coursepack 2010
CE-235 EH Coursepack 2010CE-235 EH Coursepack 2010
CE-235 EH Coursepack 2010Sajjad Ahmad
 
DSD-INT 2014 - OpenMI Symposium - Integrated Environmental Modelling, Andrew ...
DSD-INT 2014 - OpenMI Symposium - Integrated Environmental Modelling, Andrew ...DSD-INT 2014 - OpenMI Symposium - Integrated Environmental Modelling, Andrew ...
DSD-INT 2014 - OpenMI Symposium - Integrated Environmental Modelling, Andrew ...Deltares
 
Field methods final project
Field methods final projectField methods final project
Field methods final projectQisKIA
 

What's hot (20)

Bodem Breed 2011 - Potential of Aquifer Storage and Recovery (ASR) for a clim...
Bodem Breed 2011 - Potential of Aquifer Storage and Recovery (ASR) for a clim...Bodem Breed 2011 - Potential of Aquifer Storage and Recovery (ASR) for a clim...
Bodem Breed 2011 - Potential of Aquifer Storage and Recovery (ASR) for a clim...
 
Hydrology and hydraulics for design design
Hydrology and hydraulics for design designHydrology and hydraulics for design design
Hydrology and hydraulics for design design
 
INIO2014 Presentation
INIO2014 PresentationINIO2014 Presentation
INIO2014 Presentation
 
ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002
 
Floodplain Mapping for Design Professionals_RIFMA2016
Floodplain Mapping for Design Professionals_RIFMA2016Floodplain Mapping for Design Professionals_RIFMA2016
Floodplain Mapping for Design Professionals_RIFMA2016
 
TERS Presentation
TERS PresentationTERS Presentation
TERS Presentation
 
pump test for linkedin
pump test for linkedinpump test for linkedin
pump test for linkedin
 
Desired Future Condition (DFC) Presentation
Desired Future Condition (DFC) PresentationDesired Future Condition (DFC) Presentation
Desired Future Condition (DFC) Presentation
 
Hisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsHisham hajaj, stanley consultants
Hisham hajaj, stanley consultants
 
SSA_flyer 2011revised_june
SSA_flyer 2011revised_juneSSA_flyer 2011revised_june
SSA_flyer 2011revised_june
 
Nwp rov and sonar briefing mar 2014
Nwp rov and sonar briefing mar 2014Nwp rov and sonar briefing mar 2014
Nwp rov and sonar briefing mar 2014
 
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
 
1976 floating breakwater performance
1976  floating breakwater performance1976  floating breakwater performance
1976 floating breakwater performance
 
Medição
MediçãoMedição
Medição
 
Hydrodynamic Analysis of Baral river
Hydrodynamic Analysis of Baral riverHydrodynamic Analysis of Baral river
Hydrodynamic Analysis of Baral river
 
CE-235 EH Coursepack 2010
CE-235 EH Coursepack 2010CE-235 EH Coursepack 2010
CE-235 EH Coursepack 2010
 
Nebraska
NebraskaNebraska
Nebraska
 
DSD-INT 2014 - OpenMI Symposium - Integrated Environmental Modelling, Andrew ...
DSD-INT 2014 - OpenMI Symposium - Integrated Environmental Modelling, Andrew ...DSD-INT 2014 - OpenMI Symposium - Integrated Environmental Modelling, Andrew ...
DSD-INT 2014 - OpenMI Symposium - Integrated Environmental Modelling, Andrew ...
 
Field methods final project
Field methods final projectField methods final project
Field methods final project
 
Al Burj Abstract
Al Burj AbstractAl Burj Abstract
Al Burj Abstract
 

Viewers also liked

Planeaciones mate. sec 13(1)
Planeaciones mate. sec 13(1)Planeaciones mate. sec 13(1)
Planeaciones mate. sec 13(1)Kevin Andrid
 
קורס עיצוב פנים חדש נפתח במעלה אדומים
קורס עיצוב פנים חדש נפתח במעלה אדומיםקורס עיצוב פנים חדש נפתח במעלה אדומים
קורס עיצוב פנים חדש נפתח במעלה אדומיםטנא עיצובים
 
Farai CILT(UK) Diploma in Logistics and Trspt-1
Farai CILT(UK) Diploma in Logistics and Trspt-1Farai CILT(UK) Diploma in Logistics and Trspt-1
Farai CILT(UK) Diploma in Logistics and Trspt-1fmpasi
 
CIPS Level 5 - certificate AR.PDF
CIPS Level 5 - certificate AR.PDFCIPS Level 5 - certificate AR.PDF
CIPS Level 5 - certificate AR.PDFAntonio Ramirez
 

Viewers also liked (8)

Portfolio
PortfolioPortfolio
Portfolio
 
Planeaciones mate. sec 13(1)
Planeaciones mate. sec 13(1)Planeaciones mate. sec 13(1)
Planeaciones mate. sec 13(1)
 
AR award Gold
AR award GoldAR award Gold
AR award Gold
 
קורס עיצוב פנים חדש נפתח במעלה אדומים
קורס עיצוב פנים חדש נפתח במעלה אדומיםקורס עיצוב פנים חדש נפתח במעלה אדומים
קורס עיצוב פנים חדש נפתח במעלה אדומים
 
Alimentacion en preescolares
Alimentacion en preescolaresAlimentacion en preescolares
Alimentacion en preescolares
 
Farai CILT(UK) Diploma in Logistics and Trspt-1
Farai CILT(UK) Diploma in Logistics and Trspt-1Farai CILT(UK) Diploma in Logistics and Trspt-1
Farai CILT(UK) Diploma in Logistics and Trspt-1
 
CIPS Level 5 - certificate AR.PDF
CIPS Level 5 - certificate AR.PDFCIPS Level 5 - certificate AR.PDF
CIPS Level 5 - certificate AR.PDF
 
Corporate Identity Programme
Corporate Identity ProgrammeCorporate Identity Programme
Corporate Identity Programme
 

Similar to NSTX-U CPD Diagnostic Impacts & Water System Analysis

“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”IRJET Journal
 
THIẾT KẾ ĐƯỜNG ỐNG
THIẾT KẾ ĐƯỜNG ỐNGTHIẾT KẾ ĐƯỜNG ỐNG
THIẾT KẾ ĐƯỜNG ỐNGhieudk53
 
Well logging summary and Interpretation
Well logging summary and InterpretationWell logging summary and Interpretation
Well logging summary and InterpretationPE Mahmoud Jad
 
Fib2010 article269 june 2008 eq case study_rev_a
Fib2010 article269 june 2008 eq case study_rev_aFib2010 article269 june 2008 eq case study_rev_a
Fib2010 article269 june 2008 eq case study_rev_agefyra-rion
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16Leo Youngman
 
FYP Presentation v2.0
FYP Presentation v2.0FYP Presentation v2.0
FYP Presentation v2.0Bianchi Dy
 
There are several documentaries about the engineering disasters assoc.pdf
 There are several documentaries about the engineering disasters assoc.pdf There are several documentaries about the engineering disasters assoc.pdf
There are several documentaries about the engineering disasters assoc.pdfanshuanil26
 
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Stephen Flood
 
Gowanus Canal Survey Report - Single Beam Echo Sounders
Gowanus Canal Survey Report - Single Beam Echo SoundersGowanus Canal Survey Report - Single Beam Echo Sounders
Gowanus Canal Survey Report - Single Beam Echo SoundersSyQwest Inc.
 
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docxMTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docxgilpinleeanna
 
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...MD.Suresh Kumar
 
Modeling analyses for fort lewis jblm drinking water system, aspect 2009
Modeling analyses for fort lewis jblm drinking water system, aspect 2009Modeling analyses for fort lewis jblm drinking water system, aspect 2009
Modeling analyses for fort lewis jblm drinking water system, aspect 2009Sequalitchew Creek Watershed Council
 

Similar to NSTX-U CPD Diagnostic Impacts & Water System Analysis (20)

SOFT Poster 2016
SOFT Poster 2016SOFT Poster 2016
SOFT Poster 2016
 
SOFE Poster 2013
SOFE Poster 2013SOFE Poster 2013
SOFE Poster 2013
 
John Hart TAC Paper
John Hart TAC PaperJohn Hart TAC Paper
John Hart TAC Paper
 
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
 
Hawaii Pacific GIS Conference 2012: Disaster Management and Emergency Respons...
Hawaii Pacific GIS Conference 2012: Disaster Management and Emergency Respons...Hawaii Pacific GIS Conference 2012: Disaster Management and Emergency Respons...
Hawaii Pacific GIS Conference 2012: Disaster Management and Emergency Respons...
 
TOFE 2016
TOFE 2016TOFE 2016
TOFE 2016
 
S0029801814004545.PDF
S0029801814004545.PDFS0029801814004545.PDF
S0029801814004545.PDF
 
putnam engineering geophysics 2007
putnam engineering geophysics 2007putnam engineering geophysics 2007
putnam engineering geophysics 2007
 
THIẾT KẾ ĐƯỜNG ỐNG
THIẾT KẾ ĐƯỜNG ỐNGTHIẾT KẾ ĐƯỜNG ỐNG
THIẾT KẾ ĐƯỜNG ỐNG
 
Well logging summary and Interpretation
Well logging summary and InterpretationWell logging summary and Interpretation
Well logging summary and Interpretation
 
Fib2010 article269 june 2008 eq case study_rev_a
Fib2010 article269 june 2008 eq case study_rev_aFib2010 article269 june 2008 eq case study_rev_a
Fib2010 article269 june 2008 eq case study_rev_a
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
 
FYP Presentation v2.0
FYP Presentation v2.0FYP Presentation v2.0
FYP Presentation v2.0
 
There are several documentaries about the engineering disasters assoc.pdf
 There are several documentaries about the engineering disasters assoc.pdf There are several documentaries about the engineering disasters assoc.pdf
There are several documentaries about the engineering disasters assoc.pdf
 
epa600-s-96-001
epa600-s-96-001epa600-s-96-001
epa600-s-96-001
 
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
 
Gowanus Canal Survey Report - Single Beam Echo Sounders
Gowanus Canal Survey Report - Single Beam Echo SoundersGowanus Canal Survey Report - Single Beam Echo Sounders
Gowanus Canal Survey Report - Single Beam Echo Sounders
 
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docxMTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
 
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
 
Modeling analyses for fort lewis jblm drinking water system, aspect 2009
Modeling analyses for fort lewis jblm drinking water system, aspect 2009Modeling analyses for fort lewis jblm drinking water system, aspect 2009
Modeling analyses for fort lewis jblm drinking water system, aspect 2009
 

NSTX-U CPD Diagnostic Impacts & Water System Analysis

  • 1. NSTX-U CPD DIAGNOSTIC IMPACTS, PF-1C BUS SUPPORT & D-SITE WATER SYSTEMS Emmanuel O. Balogun, Kuishon A. Brown Much Effort by: Neway Atnafu, Ron Bell, Andy Carpe, Robert Ellis, Steve Raftopoulos, Roger Raman, Matt Reinke, Filippo Scotti, Brent Stratton, John Winkelman, J. Mitchell, Stefan Gerhardt Princeton Plasma Physics Laboratory, Princeton, NJ USA INTRODUCTION This presentation comprises three projects that were undertaken. The Cryo-pump divertor (CPD) project is motivated by the need for a cryo- pump and a re-design of the existing divertor in the NSTX-U. Port by port analysis was done to see how the new CPD will affect respective diagnostics. The second project is the D-Site Water Cooling System. Around Mid-July, some contaminations were found in the water used for cooling the NSTX-U field coils and thus we tracked down the cooling water system to find how the contaminant might have been transported. Finally, analysis work was done on the PF-1C Bus Support. The PF-1C Bus Support is to provide support for the PF-1 Coils and preventing deflection of the bus bars. Final Presentation August 10th, 2016 • Princeton, NJ SUMMARY TABLE OF FINDINGS Analysis of Bays A & B viewing cones CONCLUSION Our work on the CPD diagnostics was instrumental in the success of the Conceptual Design review (CDR) for the cryo-pumped divertor project. We were able to determine diagnostics that will be affected by the new structure, and negotiate with physicists to redesign some structures to accommodate the new CPD. Work on the D-Site water systems helped us create a flow diagram describing the water flow through a central de-ionized make-up water system. Structural analysis by hand calculations was done on the PF-1C bus flex cable support to test strengths in both its parts and joints for anticipated loadings in the form of Torque, Shear, Tension, and Compression. BAY DESCRIPTION FINDINGS A PCHERS(Ron Bell), No interference with divertor detected so far. Seems good. B FIDA BKGRD(Deyoung Liu) No interference with divertor detected so far. Seems good. C U. Wash Bolometer; Dust Collector (Charles Skinner/Raman) Viewing cone of 70 degrees. Has extra-ion outer shield, inner adapter, and lens is straight up D (Cryopump feedthroughs) Future LD CP Feedthroughs Not necessary; No interference E EIES, VIPS (LLNL); Fast 1DCCD camera (LLNL) (Filippo Scotti) Physicist will duplicate the specifications from Bay H for this bay. Interference is observed with the divertor and the shield walls that are yet to be included in the NSTX-U. F QMB (Charles Skinner) Elect. feedthroughs Pending.. G UT-K Spectrometer, IR camera (Reinke) No interference with divertor detected so far. Seems good. H Visible fast camera(Filippo Scotti) Interference is observed with the divertor and the shield walls that are yet to be included in the NSTX-U. I Elect. feedthroughs Not necessary. J RF Probe (Bob Kaita) Elect. feedthroughs Okay. No interference detected. K MAPP Probe, Elect. feedthroughs (Bob Kaita) Okay. No interference detected. Bays A & B will continue to support the poloidal PCHERS D-SITE WATER COOLING SYSTEMS FLOW CHART Support is mounted to body of NSTX-U Machine This work was made possible by funding from the Department of Energy for the Engineering Apprenticeship program. PF1-C FLEX CABLES BUS SUPPORT Above are pictures and drawings of the PF-1C Flex Cable Bus Supports. Hand calculations and structural analysis was done to ensure it could withstand the forces caused by the turbulence of the cables due to the presence of strong magnetic fields in NSTX-U. This structure is made almost entirely out of stainless steel due to its insignificant magnetic permeability. Tasked to identify the D-Site Water Systems Relationship with the Facilities waters. Due to the fact that many drawings were either missing or not up to date, extensive field work had to be undertaken. Bays J and K Support Probe • The present Bay I Upper and Lower ports will support a divertor resistive bolometer for the FY17 & 18 runs. • Elevated baffle top will completely block the lower view. • Need to assess the best path forward after completing the CP CDR. – May involve a new instrument at Bay I lower, tangential viewing bolometry, viewing from the mid-plane. Bay I Divertor Bolometer Is Severely Impacted by CP Design Bays H & E Support Divertor Spectroscopy • Evaluating the need to redesign the Bay H reentrant view and shutter, given the raised divertor floor. – Quite possible that the Bay E 1D CCD will need a similar treatment. • Must ensure lack of interference with divertor support structure. Conceptual CAD model for diagnostic views Above ore Images and picture of parts of the bus support To the left is an image of hand sketch-up of Bay G diagnostic port views. No pressing issues with views were detected during sketch-up Bay G Above is an image of bay H port showing diagnostic interference