CORPORATE PRESENTATION
French experiences PPP/Concessions
Agenda
1. Bouygues Construction Group
2. PUBLIC PRIVATE PARTNERSHIP – Main « keys » for a successful
project
3.” PPP-model –without demand (traffic) risk “L2, Marseille Bypass”
4.” PPP-model – with demand (traffic) risk “Concession of Zagreb Airport”
5. Comparative Traffic Risk Structure ( Airports: Cyprus vs. Iqaluit-
Canada)
6.Bouygues Construction – Some of our PPP/Concession References
WHO ARE WE?
1
Bouygues Construction Group
4
Bouygues Bâtiment International
5
Public Private Partnership- Main keys for a
successful project
2
Those countries which have a significant PPP
track record
7
 UK
 France
 Canada
 Australia
Those countries which have a less significant
PPP track record
8
 Belgium
 Germany
 Spain
 Italy
 Sweden
 Singapour
 Hong-Kong
Those countries which have already launched
or which are about to launch a PPP process
9
 USA
 South Africa
 New Zealand
 Bosnia and Herzegovina- Republic
of Srpska
 Croatia
 Cyprus
 Czech Republic
 Greece
 Hungary
 Poland
 Slovakia
 Egypt
 Turkey
 Central and South
 America Countries
10
Numerous countries are currently considering
enacting a new law on PPP and to start the
process of developing PPP schemes
11
Concessions and PPPs have been implemented globally by
numerous Governments across many different industry sectors
relating to public works including:
Education (schools, universities, academies)
Health (acute primary care hospitals, mental health facilities, local
health centre campuses, elderly care facilities)
Transport and Infrastructure (highways, heavy rail, light rail, ports,
shipping, airports)
Power and Energy
Water (wastewater, desalination, potable water)
Public Housing
Other social building projects (prisons, fire stations, police
headquarters, sports facilities, etc.)
12
 Increasing tendency for governments to use Concessions
and public private partnerships (PPPs)
 Private sector raises money then recoups the investment by
operating the asset over a long period and either charging
the users (Concession) or receiving payments from the
government (PPP/PFI)
 The main characteristic of a Concession/PPP project is that
the Public Sector can obtain a new infrastructure (i) without
paying for it during construction, (ii) transferring to the
Private Sector all the construction risks and, in turn, (iii)
granting the Private Sector with the right to operate the asset
and generate the necessary cash flow to repay the
investment
Concessions vs. PPP Model
13
Concession
 Private Sector can charge end users for the use of the
asset (e.g. a toll road, a commercial port, an airport, a
toll bridge, an underground parking)
 These projects involve a demand risk (revenues
depend on the use of the asset by end users). It is
revenue generating projects
14
PPP
 The asset itself cannot generate income directly from
charging the end-users but the government pays a
consideration for the availability of the asset which is
used for providing activities of public interest (hospitals,
schools, prisons, etc)
 These projects do not involve demand risk as the
payment from the government is not, or at least is in a
minimum part, linked with the use of the asset by end-
users. It is non-revenue generating projects.
The « main keys » for a successful project
15
 Strong political support
 Compliant legal frame
 Skilled – « Project Management team » on the
Concession grantor side (« the client »)
 Reputable/Experienced Transaction’s advisors
(legal/ financial/technical)
 Bankable contract/Market Practice
 Design development- allowing the Private Partner-to
propose the most functional and efficient design – in
order to optimize value for money (not too prescriptive)
Public Private Partnership model without
demand risk – “L2, Marseille Bypass”
3
ПРОЈЕКАТЛ2
ШПАНИЈА
A507
ИТАЛИЈА
СЕВЕР
Правац главног
транзита
Експресни пут-попречна веза,
Централна зона града Марсеја,
10 км између A7 и A50,
2 x 3 траке, 80 до 100 000 возила/дан,
Пола трасе испод земље.
L2 Est
ЗАШТОПППМОДЕЛ?
• Пројекат предвиђен
урбанистичким планом 1933
• Прве студије 1970 / 1980
• Почетак извођења 1993
• Привремени завршетак радова
Л2 Исток 2011г, након18 година,
без пуштања у саобраћај
• Инфраструктура :
• након толико времена
саобраћајница је изван
норми и стандарда
• повећани трошкови услед
захтева локалне заједнице
•Држава је претходно
уложила 600 МЕура (без
видљивог резултата),100%
државна инвестиција
•не отварање за саобраћај
од почетка радова!
ШТАОМОГУЋАВА ПРОЈЕКАТ ?
L2 Est
L2 Nord
Допринос функционалности
саобраћајница у центру града
Допринос побољшању квалитета
живота становника који живе у
деловима града кроз које пролази
пројекат
Допринос рaзвоју јавног превоза на
путевима који нису били у функцији као и
преко наткривеног дела Л2
EchangeurdesArnavaux
EchangeurdeFrais-Vallon
EchangeurdeSaint-Jérôme
SortieQueillau
EchangeurFlorian
V
A
T
A50
A7
1/2 EchangeurdeSaint-Julien
1/2 EchangeurdesCaillols
EchangeurdesFaïenciers
L2 Est
L2 Nord
ДУП Л2 Истok
Потписивање споразума између 4 ко-
финансијера да би се омогућили услови за
остваривање Јавно Приватног Партнерства
(ППП )
ДУП Л2 Север
Компетитивни дијалог- ППП
Финалне понуде
Потписивање уговора о Јавно Приватном
Партнерству 7.10.2013.
1992
2007
2010
2011
2012
2013
ГЛАВНИМОМЕНТИ
L2 Est2013
Почетак студија (Октобар (Т0))
2014
L2 Nord
2016
Пуштање у саобраћај Л2 Исток Јул (33 месеца)
Пуштање у саобраћај Л2 Север Октобар (48 месеци)
Почетак радова
Сектор Исток Јул (T0+9 месеци)
Почетак преусмеравања мреже Сектор Север
Август (T0+10 месеци)
2017
ПРРЕДВИЂЕНИ РОКОВИ
L2 Est
ПРЕДНОСТИПППМОДЕЛА
• Предвиђена динамика
радова је оптимизована и
непроменљива (високи пенали)
• Буџет је непроменљив,
одређен на самом почетку
пројекта
• Позитивне стране пројекта :
• уклапање у урбану
средину,
• искоришћење површине
над саобраћајницом,
• уређење зелених
површина,
• заштита животне
средине,
• стварање радних места
као и запошљавање
локалне радне снаге
L2 Est
L2 Nord
Пројекат експресног пута Л2
заснованог на моделу јавно приватног
партнерства подразумева :
пројектовање
изградњу
одржавање
тешко одржавање- реконструкцију
финансирање
Експлоатација и регулисање
саобраћаја ће се вршити од стране јавног
партнера .
МИСИЈЕ
КОНЗОРЦИЈУМ
4 ans
ОРГАНИЗАЦИОНА ШЕМАУГОВОРЕНИХ ОДНОСА
5 %
8 %
4 %
14 %
35 %
35 %
Меридиам
ЦДЦ Инфра
Филијале Буиг Грађевине
Колас Миди Медитеран
Спи Батињол
Ежис
АКЦИОНАРИКОНЦЕСИОНОГПРЕДУЗЕЋА
ФИНАНСИРАЊЕ
L2
Вредност Уговора 620 M€
Финансирање:
• 2/3 субвенција ( Држава + локална заједница)
• 1/3 приватно
Примена иновативног решења везано за финансирање
пројекта,приватно улагање у сарадњи са Алианц (165 M€).
Ново решење је омогућило смањивање висине годишњег
расположивог плаћања. Период отплате дуга је дужи,30 година, у
поређењу са периодом отплате код банака, највише 17-18 година.
Концесије и ППП у Инфраструктури
Буиг Грађевина, светски лидер у домену ППП-
а и концесија :
• 20 пројеката у 20 година
• 16 милијарди еура- вредност пројеката,
• Више од 1000 км путева и аутопутева
• 7 мостова или тунела урађених по моделу ППП-а
• Близу 200 км железничких пруга
• 7 пројеката у Француској
• 13 међународних пројеката ( Велика Британија, Немачка,
Мађарска, Хрватска, САД, Јамајка, Јужноафричка
Република, Обала Слоноваче, Јужна Кореја, Аустралија)
Public Private Partnership model with
demande risk – Concession of Zagreb Airport
4
A key player in airport concessions
30
Zagreb Airport
31
Zagreb Airport Concession Structure
32
CONCESSION GRANTOR
Ministry of Transportation
LENDERS
CONCESSIONAIRE (SPV)
« MZLZ »
SHAREHOLDERS
(Investors)
D&B CONTRACT
New facility
(Bouygues Croatia)
O&M CONTRACT
Existing/new facilities
(“MZLZ “& “ADP”)
Equity
Senior
debt
Facilitie
s
Direct
Agreement
33
 Concession Contract (CA) – risk allocation and concepts
different to other contracts
 Partnering « win-win » approach
 Basic principal – Concession Grantor grants to the
Concessionaire exclusive right to exploit/develop the
Airport in return of a concession fee (fix & variable)
 Risk allocated to the party best able to manage it
Contract Structure & key parties (1/2)
34
 CONCESSION GRANTOR
 Granting the concession
 Assume other obligations (e.g.. Expropriation, roads etc.)
>
 CONCESSIONAIRE
 Design, finance and build the Airport facilities
 Operate and maintain the airport Facilities
 Provide the Airport services
 Collect charges and other revenues
 OPERATOR
 Supporting Concessionaire in operation and maintaining the Airport Services
Contract Structure & key parties (2/2)
35
 LENDERS
 Finance via loan the investment
 Monitor project delivery (“LTA”)
 Control revenues
 LENDERS TECHNICAL ADVISORS (LTA) – are the lenders “eyes and
ears”
 CERTIFIERS
 Independent Engineer (IE) – construction works checking
 Dispute resolution –duty of care to both Concession Grantor &
Concessionaire)
Comparative risk Structure:
Cyprus (CONCESSION) vs. Iqaluit (PPP)
5
37
A key player in Airport Projects
38
Giving life to your next airport terminal
39
Cyprus (Concession) vs. Iqaluit Airport (PPP)
40
 Transferring Demand (Traffic) risk to the
Private Partner (Concession)
 Strong traffic potential _ possible to be
“sold” to the Lenders/Investors
 Outsourcing the Airport Management:
(Private Partner) for developing the
traffic, the commercial offer and
improving the passenger services
 Transfer of the personnel from the
Public to the Private Partner
 High expectations for the local
economical environment
 Demand (Traffic) Risk The Lenders
and the Investors will expect higher
return for their investments
 Credit Quality – depending on the
Private and the Public Partner
 Keeping Demand (Traffic) Risk of the
Public Partner (PPP)
 The Public Partner keeps the direct
control over the Airport Management
(Revenues, Airport Charges, Airlines
relationship)
 No social and political risk for
transferring the personnel
 New facility + improvement of the
passenger services through a D&B
Contract + management support by an
international reputable operator
 The Private Partner bears a lower risk
the development cost will be reduced
 No liquidity issue for raising the
project’s funding
 Credit Quality depending on the
Country Risk and ultimately on the
Public Partner
Some of our PPP / Concession
References
6
Larnaka Airport - Cyprus 2009
42
Asia World Expo – Hong Kong 2005
43
Arena Sports Centre – Hungary 2002
44
French Defense Ministry – France 2015
45
Paris Law Court Complex – France 2015
46
БУИГГРАЂЕВИНА
ИНФРАСТРУКТУРНИ САОБРАЋАЈНИ
ПРОЈЕКТИ УРАЂЕНИ ПО МОДЕЛУ ППП-а
Путеви и Аутопутеви:
• Аутопут M5 (3 Фазе) Мађарска
• Аутопут Истра (3 Фазе) Хрватска
• Национални Пут Н4 Јужноафричка Република
• Тунел Росток Немачка
• Аутопут 2000 (Х 2000) (3 Фазе) Јамајка
• Аутопут A28 Руан- Аленсон Француска
• Мост залив Масан Јужна Кореја
• Аутопут A41 Анси- Женева Француска
• Пут Тин Њукасл (2 фазе) Велика Британија
• Тунел Мајами САД
• Обилазница Виши Француска
• Мост Ривијера Маркори Абиџан Обала Слоноваче
• Експресни пут Л2 Марсеј Француска
• Девијација РД901 Француска
• Исток Запад веза Мелбурн Аустралија
Концесије и ППП у Инфраструктури
Тунел Мајами
ЖЕЛЕЗНИЧКИ ПРОЈЕКТИ
& ЛУКЕ:
• Метро Сиднеј Аустралија
• Трамвај Ранс Француска
• Пруга ГОТРАН Јужноафричка Република
• Лука Пусан Јужна Кореја
• Железничка обилазница Ним- Монпеље
Француска
Концесије и ППП у Инфраструктури
Трамвај Ранс
Thank you/ Хвала на пажњи…..
50
Victor STEFANESCU
S.E. Europe – Managing Director
0033 1 30 60 47 76
033 6 60 68 67 99
v.stefanescu@bouygues-construction .com
Mirko MEDIC
Head of Business Development- Balkan Area
0033 1 30 60 24 28
033 6 99 81 08 83
m.medic@bouygues-construction .com

More Related Content

Similar to JPP Samit (NALED, Ekonomsko odeljenje Francuske Ambasade u Srbiji i Privredna Komora Srbije) - Bouygues Construction - građevinarstvo

Javno privatna partnerstva JPP
Javno privatna partnerstva JPPJavno privatna partnerstva JPP
Javno privatna partnerstva JPP
NALED Serbia
 
Smernice_za_izdavanje_municipalnih_obveznica
Smernice_za_izdavanje_municipalnih_obveznicaSmernice_za_izdavanje_municipalnih_obveznica
Smernice_za_izdavanje_municipalnih_obveznicaCulic
 
Vrste i vidovi saobracaja
Vrste i vidovi saobracajaVrste i vidovi saobracaja
Vrste i vidovi saobracaja
igoriv
 
Vrste i vidovi saobracaja
Vrste i vidovi saobracajaVrste i vidovi saobracaja
Vrste i vidovi saobracaja
igoriv
 
Prezentacija za sindikate
Prezentacija za sindikatePrezentacija za sindikate
Prezentacija za sindikate
Helleborus Odorus Waldst
 
SECEP's Tatjana Volarev
SECEP's Tatjana VolarevSECEP's Tatjana Volarev
18-574-epr_info-sesions_v1_300518_16x9.ppt
18-574-epr_info-sesions_v1_300518_16x9.ppt18-574-epr_info-sesions_v1_300518_16x9.ppt
18-574-epr_info-sesions_v1_300518_16x9.ppt
milenastokanovic
 
Agenda "Seminar on Introducing One Stop Shops in Serbia", 21 December 2017-Se...
Agenda "Seminar on Introducing One Stop Shops in Serbia", 21 December 2017-Se...Agenda "Seminar on Introducing One Stop Shops in Serbia", 21 December 2017-Se...
Agenda "Seminar on Introducing One Stop Shops in Serbia", 21 December 2017-Se...
Support for Improvement in Governance and Management SIGMA
 

Similar to JPP Samit (NALED, Ekonomsko odeljenje Francuske Ambasade u Srbiji i Privredna Komora Srbije) - Bouygues Construction - građevinarstvo (8)

Javno privatna partnerstva JPP
Javno privatna partnerstva JPPJavno privatna partnerstva JPP
Javno privatna partnerstva JPP
 
Smernice_za_izdavanje_municipalnih_obveznica
Smernice_za_izdavanje_municipalnih_obveznicaSmernice_za_izdavanje_municipalnih_obveznica
Smernice_za_izdavanje_municipalnih_obveznica
 
Vrste i vidovi saobracaja
Vrste i vidovi saobracajaVrste i vidovi saobracaja
Vrste i vidovi saobracaja
 
Vrste i vidovi saobracaja
Vrste i vidovi saobracajaVrste i vidovi saobracaja
Vrste i vidovi saobracaja
 
Prezentacija za sindikate
Prezentacija za sindikatePrezentacija za sindikate
Prezentacija za sindikate
 
SECEP's Tatjana Volarev
SECEP's Tatjana VolarevSECEP's Tatjana Volarev
SECEP's Tatjana Volarev
 
18-574-epr_info-sesions_v1_300518_16x9.ppt
18-574-epr_info-sesions_v1_300518_16x9.ppt18-574-epr_info-sesions_v1_300518_16x9.ppt
18-574-epr_info-sesions_v1_300518_16x9.ppt
 
Agenda "Seminar on Introducing One Stop Shops in Serbia", 21 December 2017-Se...
Agenda "Seminar on Introducing One Stop Shops in Serbia", 21 December 2017-Se...Agenda "Seminar on Introducing One Stop Shops in Serbia", 21 December 2017-Se...
Agenda "Seminar on Introducing One Stop Shops in Serbia", 21 December 2017-Se...
 

More from NALED Serbia

NALED results and activities - 2020 Assembly
NALED results and activities - 2020 AssemblyNALED results and activities - 2020 Assembly
NALED results and activities - 2020 Assembly
NALED Serbia
 
Rezultati i aktivnosti NALED-a 2019/20
Rezultati i aktivnosti NALED-a 2019/20Rezultati i aktivnosti NALED-a 2019/20
Rezultati i aktivnosti NALED-a 2019/20
NALED Serbia
 
Istraživanje stavova građana o sivoj ekonomiji, maj 2018
Istraživanje stavova građana o sivoj ekonomiji, maj 2018Istraživanje stavova građana o sivoj ekonomiji, maj 2018
Istraživanje stavova građana o sivoj ekonomiji, maj 2018
NALED Serbia
 
Sektorska analiza tržišta maloprodaje u Srbiji, maj 2018.
Sektorska analiza tržišta maloprodaje u Srbiji, maj 2018.Sektorska analiza tržišta maloprodaje u Srbiji, maj 2018.
Sektorska analiza tržišta maloprodaje u Srbiji, maj 2018.
NALED Serbia
 
Istraživanje kapaciteta za lokalni ekonomski razvoj u Srbiji
Istraživanje kapaciteta za lokalni ekonomski razvoj u SrbijiIstraživanje kapaciteta za lokalni ekonomski razvoj u Srbiji
Istraživanje kapaciteta za lokalni ekonomski razvoj u Srbiji
NALED Serbia
 
Pravilnik o odštetnim zahtevima usled ujeda napuštenih pasa
Pravilnik o odštetnim zahtevima usled ujeda napuštenih pasaPravilnik o odštetnim zahtevima usled ujeda napuštenih pasa
Pravilnik o odštetnim zahtevima usled ujeda napuštenih pasa
NALED Serbia
 
Grey Book 10 - Recommendations for Eliminating Administrative Obstacles to Do...
Grey Book 10 - Recommendations for Eliminating Administrative Obstacles to Do...Grey Book 10 - Recommendations for Eliminating Administrative Obstacles to Do...
Grey Book 10 - Recommendations for Eliminating Administrative Obstacles to Do...
NALED Serbia
 
Siva knjiga 10 - Preporuke za ukidanje administrativnih preporuka poslovanju ...
Siva knjiga 10 - Preporuke za ukidanje administrativnih preporuka poslovanju ...Siva knjiga 10 - Preporuke za ukidanje administrativnih preporuka poslovanju ...
Siva knjiga 10 - Preporuke za ukidanje administrativnih preporuka poslovanju ...
NALED Serbia
 
Studija: Siva ekonomija u Srbiji 2017. - karakteristike i obim
Studija: Siva ekonomija u Srbiji 2017. - karakteristike i obimStudija: Siva ekonomija u Srbiji 2017. - karakteristike i obim
Studija: Siva ekonomija u Srbiji 2017. - karakteristike i obim
NALED Serbia
 
Upravljanje bezbednosti saobraćaja u lokalnim samoupravama kroz digitalizacij...
Upravljanje bezbednosti saobraćaja u lokalnim samoupravama kroz digitalizacij...Upravljanje bezbednosti saobraćaja u lokalnim samoupravama kroz digitalizacij...
Upravljanje bezbednosti saobraćaja u lokalnim samoupravama kroz digitalizacij...
NALED Serbia
 
Nacrt Zakona o putevima
Nacrt Zakona o putevimaNacrt Zakona o putevima
Nacrt Zakona o putevima
NALED Serbia
 
Opstina Vrbas kao primer upravljanja bezbednosti saobraćaja kroz digitalizaci...
Opstina Vrbas kao primer upravljanja bezbednosti saobraćaja kroz digitalizaci...Opstina Vrbas kao primer upravljanja bezbednosti saobraćaja kroz digitalizaci...
Opstina Vrbas kao primer upravljanja bezbednosti saobraćaja kroz digitalizaci...
NALED Serbia
 
Izmene Zakona o bezbednosti saobraćaja
Izmene Zakona o bezbednosti saobraćajaIzmene Zakona o bezbednosti saobraćaja
Izmene Zakona o bezbednosti saobraćaja
NALED Serbia
 
Analiza rada lokalnih saveta i bezbednosti saobraćaja na lokalu
Analiza rada lokalnih saveta i bezbednosti saobraćaja na lokaluAnaliza rada lokalnih saveta i bezbednosti saobraćaja na lokalu
Analiza rada lokalnih saveta i bezbednosti saobraćaja na lokalu
NALED Serbia
 
Cashless students
Cashless studentsCashless students
Cashless students
NALED Serbia
 
Cashless Case Challenge 2017 - Umrežavanje
Cashless Case Challenge 2017 - UmrežavanjeCashless Case Challenge 2017 - Umrežavanje
Cashless Case Challenge 2017 - Umrežavanje
NALED Serbia
 
Cashless Case Challenge 2017 - Triple A
Cashless Case Challenge 2017 - Triple ACashless Case Challenge 2017 - Triple A
Cashless Case Challenge 2017 - Triple A
NALED Serbia
 
Cashless Case Challenge 2017 - 24h
Cashless Case Challenge 2017 - 24hCashless Case Challenge 2017 - 24h
Cashless Case Challenge 2017 - 24h
NALED Serbia
 
Cashless Case Challenge 2017 - Štediše
Cashless Case Challenge 2017 - ŠtedišeCashless Case Challenge 2017 - Štediše
Cashless Case Challenge 2017 - Štediše
NALED Serbia
 
Cashless Case Challenge 2017 - S-Gen
Cashless Case Challenge 2017 - S-GenCashless Case Challenge 2017 - S-Gen
Cashless Case Challenge 2017 - S-Gen
NALED Serbia
 

More from NALED Serbia (20)

NALED results and activities - 2020 Assembly
NALED results and activities - 2020 AssemblyNALED results and activities - 2020 Assembly
NALED results and activities - 2020 Assembly
 
Rezultati i aktivnosti NALED-a 2019/20
Rezultati i aktivnosti NALED-a 2019/20Rezultati i aktivnosti NALED-a 2019/20
Rezultati i aktivnosti NALED-a 2019/20
 
Istraživanje stavova građana o sivoj ekonomiji, maj 2018
Istraživanje stavova građana o sivoj ekonomiji, maj 2018Istraživanje stavova građana o sivoj ekonomiji, maj 2018
Istraživanje stavova građana o sivoj ekonomiji, maj 2018
 
Sektorska analiza tržišta maloprodaje u Srbiji, maj 2018.
Sektorska analiza tržišta maloprodaje u Srbiji, maj 2018.Sektorska analiza tržišta maloprodaje u Srbiji, maj 2018.
Sektorska analiza tržišta maloprodaje u Srbiji, maj 2018.
 
Istraživanje kapaciteta za lokalni ekonomski razvoj u Srbiji
Istraživanje kapaciteta za lokalni ekonomski razvoj u SrbijiIstraživanje kapaciteta za lokalni ekonomski razvoj u Srbiji
Istraživanje kapaciteta za lokalni ekonomski razvoj u Srbiji
 
Pravilnik o odštetnim zahtevima usled ujeda napuštenih pasa
Pravilnik o odštetnim zahtevima usled ujeda napuštenih pasaPravilnik o odštetnim zahtevima usled ujeda napuštenih pasa
Pravilnik o odštetnim zahtevima usled ujeda napuštenih pasa
 
Grey Book 10 - Recommendations for Eliminating Administrative Obstacles to Do...
Grey Book 10 - Recommendations for Eliminating Administrative Obstacles to Do...Grey Book 10 - Recommendations for Eliminating Administrative Obstacles to Do...
Grey Book 10 - Recommendations for Eliminating Administrative Obstacles to Do...
 
Siva knjiga 10 - Preporuke za ukidanje administrativnih preporuka poslovanju ...
Siva knjiga 10 - Preporuke za ukidanje administrativnih preporuka poslovanju ...Siva knjiga 10 - Preporuke za ukidanje administrativnih preporuka poslovanju ...
Siva knjiga 10 - Preporuke za ukidanje administrativnih preporuka poslovanju ...
 
Studija: Siva ekonomija u Srbiji 2017. - karakteristike i obim
Studija: Siva ekonomija u Srbiji 2017. - karakteristike i obimStudija: Siva ekonomija u Srbiji 2017. - karakteristike i obim
Studija: Siva ekonomija u Srbiji 2017. - karakteristike i obim
 
Upravljanje bezbednosti saobraćaja u lokalnim samoupravama kroz digitalizacij...
Upravljanje bezbednosti saobraćaja u lokalnim samoupravama kroz digitalizacij...Upravljanje bezbednosti saobraćaja u lokalnim samoupravama kroz digitalizacij...
Upravljanje bezbednosti saobraćaja u lokalnim samoupravama kroz digitalizacij...
 
Nacrt Zakona o putevima
Nacrt Zakona o putevimaNacrt Zakona o putevima
Nacrt Zakona o putevima
 
Opstina Vrbas kao primer upravljanja bezbednosti saobraćaja kroz digitalizaci...
Opstina Vrbas kao primer upravljanja bezbednosti saobraćaja kroz digitalizaci...Opstina Vrbas kao primer upravljanja bezbednosti saobraćaja kroz digitalizaci...
Opstina Vrbas kao primer upravljanja bezbednosti saobraćaja kroz digitalizaci...
 
Izmene Zakona o bezbednosti saobraćaja
Izmene Zakona o bezbednosti saobraćajaIzmene Zakona o bezbednosti saobraćaja
Izmene Zakona o bezbednosti saobraćaja
 
Analiza rada lokalnih saveta i bezbednosti saobraćaja na lokalu
Analiza rada lokalnih saveta i bezbednosti saobraćaja na lokaluAnaliza rada lokalnih saveta i bezbednosti saobraćaja na lokalu
Analiza rada lokalnih saveta i bezbednosti saobraćaja na lokalu
 
Cashless students
Cashless studentsCashless students
Cashless students
 
Cashless Case Challenge 2017 - Umrežavanje
Cashless Case Challenge 2017 - UmrežavanjeCashless Case Challenge 2017 - Umrežavanje
Cashless Case Challenge 2017 - Umrežavanje
 
Cashless Case Challenge 2017 - Triple A
Cashless Case Challenge 2017 - Triple ACashless Case Challenge 2017 - Triple A
Cashless Case Challenge 2017 - Triple A
 
Cashless Case Challenge 2017 - 24h
Cashless Case Challenge 2017 - 24hCashless Case Challenge 2017 - 24h
Cashless Case Challenge 2017 - 24h
 
Cashless Case Challenge 2017 - Štediše
Cashless Case Challenge 2017 - ŠtedišeCashless Case Challenge 2017 - Štediše
Cashless Case Challenge 2017 - Štediše
 
Cashless Case Challenge 2017 - S-Gen
Cashless Case Challenge 2017 - S-GenCashless Case Challenge 2017 - S-Gen
Cashless Case Challenge 2017 - S-Gen
 

JPP Samit (NALED, Ekonomsko odeljenje Francuske Ambasade u Srbiji i Privredna Komora Srbije) - Bouygues Construction - građevinarstvo

  • 2. Agenda 1. Bouygues Construction Group 2. PUBLIC PRIVATE PARTNERSHIP – Main « keys » for a successful project 3.” PPP-model –without demand (traffic) risk “L2, Marseille Bypass” 4.” PPP-model – with demand (traffic) risk “Concession of Zagreb Airport” 5. Comparative Traffic Risk Structure ( Airports: Cyprus vs. Iqaluit- Canada) 6.Bouygues Construction – Some of our PPP/Concession References
  • 6. Public Private Partnership- Main keys for a successful project 2
  • 7. Those countries which have a significant PPP track record 7  UK  France  Canada  Australia
  • 8. Those countries which have a less significant PPP track record 8  Belgium  Germany  Spain  Italy  Sweden  Singapour  Hong-Kong
  • 9. Those countries which have already launched or which are about to launch a PPP process 9  USA  South Africa  New Zealand  Bosnia and Herzegovina- Republic of Srpska  Croatia  Cyprus  Czech Republic  Greece  Hungary  Poland  Slovakia  Egypt  Turkey  Central and South  America Countries
  • 10. 10 Numerous countries are currently considering enacting a new law on PPP and to start the process of developing PPP schemes
  • 11. 11 Concessions and PPPs have been implemented globally by numerous Governments across many different industry sectors relating to public works including: Education (schools, universities, academies) Health (acute primary care hospitals, mental health facilities, local health centre campuses, elderly care facilities) Transport and Infrastructure (highways, heavy rail, light rail, ports, shipping, airports) Power and Energy Water (wastewater, desalination, potable water) Public Housing Other social building projects (prisons, fire stations, police headquarters, sports facilities, etc.)
  • 12. 12  Increasing tendency for governments to use Concessions and public private partnerships (PPPs)  Private sector raises money then recoups the investment by operating the asset over a long period and either charging the users (Concession) or receiving payments from the government (PPP/PFI)  The main characteristic of a Concession/PPP project is that the Public Sector can obtain a new infrastructure (i) without paying for it during construction, (ii) transferring to the Private Sector all the construction risks and, in turn, (iii) granting the Private Sector with the right to operate the asset and generate the necessary cash flow to repay the investment
  • 13. Concessions vs. PPP Model 13 Concession  Private Sector can charge end users for the use of the asset (e.g. a toll road, a commercial port, an airport, a toll bridge, an underground parking)  These projects involve a demand risk (revenues depend on the use of the asset by end users). It is revenue generating projects
  • 14. 14 PPP  The asset itself cannot generate income directly from charging the end-users but the government pays a consideration for the availability of the asset which is used for providing activities of public interest (hospitals, schools, prisons, etc)  These projects do not involve demand risk as the payment from the government is not, or at least is in a minimum part, linked with the use of the asset by end- users. It is non-revenue generating projects.
  • 15. The « main keys » for a successful project 15  Strong political support  Compliant legal frame  Skilled – « Project Management team » on the Concession grantor side (« the client »)  Reputable/Experienced Transaction’s advisors (legal/ financial/technical)  Bankable contract/Market Practice  Design development- allowing the Private Partner-to propose the most functional and efficient design – in order to optimize value for money (not too prescriptive)
  • 16. Public Private Partnership model without demand risk – “L2, Marseille Bypass” 3
  • 17. ПРОЈЕКАТЛ2 ШПАНИЈА A507 ИТАЛИЈА СЕВЕР Правац главног транзита Експресни пут-попречна веза, Централна зона града Марсеја, 10 км између A7 и A50, 2 x 3 траке, 80 до 100 000 возила/дан, Пола трасе испод земље.
  • 18. L2 Est ЗАШТОПППМОДЕЛ? • Пројекат предвиђен урбанистичким планом 1933 • Прве студије 1970 / 1980 • Почетак извођења 1993 • Привремени завршетак радова Л2 Исток 2011г, након18 година, без пуштања у саобраћај • Инфраструктура : • након толико времена саобраћајница је изван норми и стандарда • повећани трошкови услед захтева локалне заједнице •Држава је претходно уложила 600 МЕура (без видљивог резултата),100% државна инвестиција •не отварање за саобраћај од почетка радова!
  • 19. ШТАОМОГУЋАВА ПРОЈЕКАТ ? L2 Est L2 Nord Допринос функционалности саобраћајница у центру града Допринос побољшању квалитета живота становника који живе у деловима града кроз које пролази пројекат Допринос рaзвоју јавног превоза на путевима који нису били у функцији као и преко наткривеног дела Л2 EchangeurdesArnavaux EchangeurdeFrais-Vallon EchangeurdeSaint-Jérôme SortieQueillau EchangeurFlorian V A T A50 A7 1/2 EchangeurdeSaint-Julien 1/2 EchangeurdesCaillols EchangeurdesFaïenciers
  • 20. L2 Est L2 Nord ДУП Л2 Истok Потписивање споразума између 4 ко- финансијера да би се омогућили услови за остваривање Јавно Приватног Партнерства (ППП ) ДУП Л2 Север Компетитивни дијалог- ППП Финалне понуде Потписивање уговора о Јавно Приватном Партнерству 7.10.2013. 1992 2007 2010 2011 2012 2013 ГЛАВНИМОМЕНТИ
  • 21. L2 Est2013 Почетак студија (Октобар (Т0)) 2014 L2 Nord 2016 Пуштање у саобраћај Л2 Исток Јул (33 месеца) Пуштање у саобраћај Л2 Север Октобар (48 месеци) Почетак радова Сектор Исток Јул (T0+9 месеци) Почетак преусмеравања мреже Сектор Север Август (T0+10 месеци) 2017 ПРРЕДВИЂЕНИ РОКОВИ
  • 22. L2 Est ПРЕДНОСТИПППМОДЕЛА • Предвиђена динамика радова је оптимизована и непроменљива (високи пенали) • Буџет је непроменљив, одређен на самом почетку пројекта • Позитивне стране пројекта : • уклапање у урбану средину, • искоришћење површине над саобраћајницом, • уређење зелених површина, • заштита животне средине, • стварање радних места као и запошљавање локалне радне снаге
  • 23. L2 Est L2 Nord Пројекат експресног пута Л2 заснованог на моделу јавно приватног партнерства подразумева : пројектовање изградњу одржавање тешко одржавање- реконструкцију финансирање Експлоатација и регулисање саобраћаја ће се вршити од стране јавног партнера . МИСИЈЕ
  • 26. 5 % 8 % 4 % 14 % 35 % 35 % Меридиам ЦДЦ Инфра Филијале Буиг Грађевине Колас Миди Медитеран Спи Батињол Ежис АКЦИОНАРИКОНЦЕСИОНОГПРЕДУЗЕЋА
  • 27. ФИНАНСИРАЊЕ L2 Вредност Уговора 620 M€ Финансирање: • 2/3 субвенција ( Држава + локална заједница) • 1/3 приватно Примена иновативног решења везано за финансирање пројекта,приватно улагање у сарадњи са Алианц (165 M€). Ново решење је омогућило смањивање висине годишњег расположивог плаћања. Период отплате дуга је дужи,30 година, у поређењу са периодом отплате код банака, највише 17-18 година.
  • 28. Концесије и ППП у Инфраструктури Буиг Грађевина, светски лидер у домену ППП- а и концесија : • 20 пројеката у 20 година • 16 милијарди еура- вредност пројеката, • Више од 1000 км путева и аутопутева • 7 мостова или тунела урађених по моделу ППП-а • Близу 200 км железничких пруга • 7 пројеката у Француској • 13 међународних пројеката ( Велика Британија, Немачка, Мађарска, Хрватска, САД, Јамајка, Јужноафричка Република, Обала Слоноваче, Јужна Кореја, Аустралија)
  • 29. Public Private Partnership model with demande risk – Concession of Zagreb Airport 4
  • 30. A key player in airport concessions 30
  • 32. Zagreb Airport Concession Structure 32 CONCESSION GRANTOR Ministry of Transportation LENDERS CONCESSIONAIRE (SPV) « MZLZ » SHAREHOLDERS (Investors) D&B CONTRACT New facility (Bouygues Croatia) O&M CONTRACT Existing/new facilities (“MZLZ “& “ADP”) Equity Senior debt Facilitie s Direct Agreement
  • 33. 33  Concession Contract (CA) – risk allocation and concepts different to other contracts  Partnering « win-win » approach  Basic principal – Concession Grantor grants to the Concessionaire exclusive right to exploit/develop the Airport in return of a concession fee (fix & variable)  Risk allocated to the party best able to manage it
  • 34. Contract Structure & key parties (1/2) 34  CONCESSION GRANTOR  Granting the concession  Assume other obligations (e.g.. Expropriation, roads etc.) >  CONCESSIONAIRE  Design, finance and build the Airport facilities  Operate and maintain the airport Facilities  Provide the Airport services  Collect charges and other revenues  OPERATOR  Supporting Concessionaire in operation and maintaining the Airport Services
  • 35. Contract Structure & key parties (2/2) 35  LENDERS  Finance via loan the investment  Monitor project delivery (“LTA”)  Control revenues  LENDERS TECHNICAL ADVISORS (LTA) – are the lenders “eyes and ears”  CERTIFIERS  Independent Engineer (IE) – construction works checking  Dispute resolution –duty of care to both Concession Grantor & Concessionaire)
  • 36. Comparative risk Structure: Cyprus (CONCESSION) vs. Iqaluit (PPP) 5
  • 37. 37
  • 38. A key player in Airport Projects 38
  • 39. Giving life to your next airport terminal 39
  • 40. Cyprus (Concession) vs. Iqaluit Airport (PPP) 40  Transferring Demand (Traffic) risk to the Private Partner (Concession)  Strong traffic potential _ possible to be “sold” to the Lenders/Investors  Outsourcing the Airport Management: (Private Partner) for developing the traffic, the commercial offer and improving the passenger services  Transfer of the personnel from the Public to the Private Partner  High expectations for the local economical environment  Demand (Traffic) Risk The Lenders and the Investors will expect higher return for their investments  Credit Quality – depending on the Private and the Public Partner  Keeping Demand (Traffic) Risk of the Public Partner (PPP)  The Public Partner keeps the direct control over the Airport Management (Revenues, Airport Charges, Airlines relationship)  No social and political risk for transferring the personnel  New facility + improvement of the passenger services through a D&B Contract + management support by an international reputable operator  The Private Partner bears a lower risk the development cost will be reduced  No liquidity issue for raising the project’s funding  Credit Quality depending on the Country Risk and ultimately on the Public Partner
  • 41. Some of our PPP / Concession References 6
  • 42. Larnaka Airport - Cyprus 2009 42
  • 43. Asia World Expo – Hong Kong 2005 43
  • 44. Arena Sports Centre – Hungary 2002 44
  • 45. French Defense Ministry – France 2015 45
  • 46. Paris Law Court Complex – France 2015 46
  • 48. Путеви и Аутопутеви: • Аутопут M5 (3 Фазе) Мађарска • Аутопут Истра (3 Фазе) Хрватска • Национални Пут Н4 Јужноафричка Република • Тунел Росток Немачка • Аутопут 2000 (Х 2000) (3 Фазе) Јамајка • Аутопут A28 Руан- Аленсон Француска • Мост залив Масан Јужна Кореја • Аутопут A41 Анси- Женева Француска • Пут Тин Њукасл (2 фазе) Велика Британија • Тунел Мајами САД • Обилазница Виши Француска • Мост Ривијера Маркори Абиџан Обала Слоноваче • Експресни пут Л2 Марсеј Француска • Девијација РД901 Француска • Исток Запад веза Мелбурн Аустралија Концесије и ППП у Инфраструктури Тунел Мајами
  • 49. ЖЕЛЕЗНИЧКИ ПРОЈЕКТИ & ЛУКЕ: • Метро Сиднеј Аустралија • Трамвај Ранс Француска • Пруга ГОТРАН Јужноафричка Република • Лука Пусан Јужна Кореја • Железничка обилазница Ним- Монпеље Француска Концесије и ППП у Инфраструктури Трамвај Ранс
  • 50. Thank you/ Хвала на пажњи….. 50 Victor STEFANESCU S.E. Europe – Managing Director 0033 1 30 60 47 76 033 6 60 68 67 99 v.stefanescu@bouygues-construction .com Mirko MEDIC Head of Business Development- Balkan Area 0033 1 30 60 24 28 033 6 99 81 08 83 m.medic@bouygues-construction .com