SlideShare a Scribd company logo
Risk of Occurrence %        x     Impact of Occurrence $            =      Risk Exposure

                                           Risk Exposure
   Rick of Occurrence       =
                                        Impact of Occurrence

                                            Pessimistic + 4(Most Likely) + Optimstic
        PERT Estimate       =
                                                              6

Schedule Network Analysis Diagram:
                    ES             EF                          ------>
                            DU
                    LS             LF                          <------

                           TF =   LF - EF
                           FF =   ES (Suc) - EF (Pre)


       Communications       =                 n (n-1)
          Channel                                2

Earned Value Management:
   Planned Value (PV)       =     Time Value of Work Completed % x BAC

   Earned Value (EV)        =     Amount of Work Done % x BAC

   Cost Variance (CV)       =     EV - AC                      +1 = under budget

             CPI            =     EV / AC

Schedule Variance (SV)      =     EV - PV

             SPI            =     EV / PV                      + 1 = ahead of schedule

Est to Complete (ETC)       =     BAC - EV                     past not = to future performance

Est to Complete (ETC)       =     (BAC - EV) / CPI             past = future performance

Est @ Complete (EAC)        =     AC + ETC                     past not = to future performance

Est @ Complete (EAC)        =     AC + BAC - EV                past = future performance

Est @ Complete (EAC)        =     AC + ((BAC - EV) / CPI)      past = future performance

Est @ Complete (EAC)        =     BAC / CPI                    past = future performance

TCPI based on BAC           =     (BAC - EV) / (BAC - AC)

TCPI based on EAC           =     (BAC - EV) / (EAC - AC)

TSPI                        =     (BAC - EV) / (BAC - PV)

More Related Content

Viewers also liked

Presentacionluisdaniel
PresentacionluisdanielPresentacionluisdaniel
Presentacionluisdanielluisdaniel2211
 
577555 369240686473654 1008293425_n
577555 369240686473654 1008293425_n577555 369240686473654 1008293425_n
577555 369240686473654 1008293425_nmatthew_fabian
 
Combinado ciudad con playa blanca resort
Combinado ciudad con playa blanca resortCombinado ciudad con playa blanca resort
Combinado ciudad con playa blanca resortprestigio-mayorista
 
Logo banner url
Logo banner urlLogo banner url
Presentación para el blog
Presentación para el blogPresentación para el blog
Presentación para el bloggibtaoni14
 

Viewers also liked (11)

Presentacionluisdaniel
PresentacionluisdanielPresentacionluisdaniel
Presentacionluisdaniel
 
577555 369240686473654 1008293425_n
577555 369240686473654 1008293425_n577555 369240686473654 1008293425_n
577555 369240686473654 1008293425_n
 
27
2727
27
 
On The Spot Award
On The Spot AwardOn The Spot Award
On The Spot Award
 
43
4343
43
 
Ensayo
EnsayoEnsayo
Ensayo
 
Combinado ciudad con playa blanca resort
Combinado ciudad con playa blanca resortCombinado ciudad con playa blanca resort
Combinado ciudad con playa blanca resort
 
Logo banner url
Logo banner urlLogo banner url
Logo banner url
 
Presentación para el blog
Presentación para el blogPresentación para el blog
Presentación para el blog
 
Las tics
Las ticsLas tics
Las tics
 
Las tecnologìas
Las tecnologìasLas tecnologìas
Las tecnologìas
 

Similar to PMP Formulas

Pmp formulas v5
Pmp formulas v5Pmp formulas v5
Pmp formulas v5
Dr Ezzat Mansour
 
Pmp formulas pmbok6
Pmp formulas pmbok6Pmp formulas pmbok6
Pmp formulas pmbok6
Mohammed Dissouky
 
Pmp formulas pmbok5
Pmp formulas pmbok5Pmp formulas pmbok5
Pmp formulas pmbok5
Khanh Dinh Duy
 
PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam Formulas
Amr Miqdadi
 
Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
Poonam Anand
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
Nabeel Ahmad
 
Formulas for pmp exam
Formulas for pmp examFormulas for pmp exam
Formulas for pmp exam
Ibrahem Faheem
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
KhalidMahmood253
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
Dr Ezzat Mansour
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
Jamil Faraj , PMP
 
Formula pocket guide
Formula pocket guideFormula pocket guide
Formula pocket guide
Vicky Maly
 
PMP - Math Formulas
PMP - Math FormulasPMP - Math Formulas
PMP - Math Formulas
gijoeusa
 
PMP Exam Formulas To Know
PMP Exam Formulas To KnowPMP Exam Formulas To Know
PMP Exam Formulas To Know
Joanne Greene-Blose
 
Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
FARISH V M
 
7.4 Forecasting Techniques
7.4 Forecasting Techniques7.4 Forecasting Techniques
7.4 Forecasting Techniques
DavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
DavidMcLachlan1
 

Similar to PMP Formulas (17)

Pmp formulas v5
Pmp formulas v5Pmp formulas v5
Pmp formulas v5
 
Pmp formulas pmbok6
Pmp formulas pmbok6Pmp formulas pmbok6
Pmp formulas pmbok6
 
Pmp formulas pmbok5
Pmp formulas pmbok5Pmp formulas pmbok5
Pmp formulas pmbok5
 
PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam Formulas
 
Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Formulas for pmp exam
Formulas for pmp examFormulas for pmp exam
Formulas for pmp exam
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
Formula pocket guide
Formula pocket guideFormula pocket guide
Formula pocket guide
 
PMP - Math Formulas
PMP - Math FormulasPMP - Math Formulas
PMP - Math Formulas
 
PMP Exam Formulas To Know
PMP Exam Formulas To KnowPMP Exam Formulas To Know
PMP Exam Formulas To Know
 
Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
 
7.4 Forecasting Techniques
7.4 Forecasting Techniques7.4 Forecasting Techniques
7.4 Forecasting Techniques
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Ec 2-simulation-lab
Ec 2-simulation-labEc 2-simulation-lab
Ec 2-simulation-lab
 

PMP Formulas

  • 1. Risk of Occurrence % x Impact of Occurrence $ = Risk Exposure Risk Exposure Rick of Occurrence = Impact of Occurrence Pessimistic + 4(Most Likely) + Optimstic PERT Estimate = 6 Schedule Network Analysis Diagram: ES EF ------> DU LS LF <------ TF = LF - EF FF = ES (Suc) - EF (Pre) Communications = n (n-1) Channel 2 Earned Value Management: Planned Value (PV) = Time Value of Work Completed % x BAC Earned Value (EV) = Amount of Work Done % x BAC Cost Variance (CV) = EV - AC +1 = under budget CPI = EV / AC Schedule Variance (SV) = EV - PV SPI = EV / PV + 1 = ahead of schedule Est to Complete (ETC) = BAC - EV past not = to future performance Est to Complete (ETC) = (BAC - EV) / CPI past = future performance Est @ Complete (EAC) = AC + ETC past not = to future performance Est @ Complete (EAC) = AC + BAC - EV past = future performance Est @ Complete (EAC) = AC + ((BAC - EV) / CPI) past = future performance Est @ Complete (EAC) = BAC / CPI past = future performance TCPI based on BAC = (BAC - EV) / (BAC - AC) TCPI based on EAC = (BAC - EV) / (EAC - AC) TSPI = (BAC - EV) / (BAC - PV)