- Rikert applied for a building permit to construct a detached garage but was told he needed to apply for a minor zoning variance, adding 7-10 weeks to the project timeline. This delay threatened his ability to complete the project on time.
- Rikert took the next two days to review the project and determine if it was still feasible given the additional time required.
- The project involved building a detached double garage for the new owner of his home as part of the sale agreement. Rikert needed to complete the garage construction within the 18 week timeline before title transfer.