26. @marciosete
Lead Time 42 days or less were required to complete 85% of items
WIP 148 work items are currently in progress
Stability
Current Week (Week 21) Last Week (Week 20) Last Week (Week 17)
Arrival Rate / week 2 26
Throughput / week 2 27 67
Avg. WIP / week 42 76 18
WIP Age 147 154 245
Avg. Lead Time 42 76 18
Avg. Flow Efficiency 22.6% 28.2% 33.5%
% of Value Demand 14.8%
% of Failure Demand 100.0% 85.2% 100.0%
Discard - count 3
Discard - # Days 76
Discard - # days cumulative 110 110 34
Service Delivery Performance