Based on the column structure of the old concrete parking deck, we built a new one with Additive Floors from Thyssen Krupp Hoesch. Final completion exactly according to plan, despite the delay incurred by the main contractor. The whole structure was built during normal store opening hours. Metro Group chose to skip the coating on the top floor and have it installed later.