Jeff Manhardt | PMP
Fall 2016
Resource Capacity Planning
Resource Allocation
Resource Work Management
Resource Collaboration
Resource Task Management
Resource System Implementation
http://epmlive.com/project-management-tools-5-steps-resource-management/
Resource Capacity Planning
Identify
Generic
Roles
Determine
Estimated
Usage of
Each Role
Analyze
and Adjust
Resource
Plan
Finalize
Plan for
Resource
Allocation
Resource Allocation
Match
Potential
Candidates
w/ Needs
Assign
Names
Resources
Confirm
Project or
Work
Assignment
and Duration
Verify
Resource
Assignment
with
Necessary
Parties
Manage
Future Shifts
in Resource
Assignments
Resource Work Management
Manage
Work
Assignments
Track
Resource
Performance
Provide
Continuous
Feedback
and Status
Resolve
Issues and
Mitigate
Potential
Risks
Respond to
Changes
Resource Collaboration
Define
Shared Goals
& Objectives
Track Status
& Real Time
Updates
Provide
Teams
Efficient Tools
to Collaborate
Resource Task Management
Gather Work
Assignments
Provide Status
and Updates
Monitor Overall
Health of all
Work and
Dependencies
Resource System Implementation
Gather
Requirements
Determine
market
options
RFP
Develop
process
around the
system
Implement
Taken Together…
Identify Generic
Roles
Determine
Estimated Usage
of Each Role
Analyze and
Adjust Resource
Plan
Finalize Plan for
Resource
Allocation
Match Potential
Candidates w/
Needs
Assign Names
Resources
Confirm Project
or Work
Assignment and
Duration
Verify Resource
Assignment with
Necessary
Parties
Manage Future
Shifts in
Resource
Assignments
Manage Work
Assignments
Track
Resource
Performance
Provide
Continuous
Feedback and
Status
Resolve Issues
and Mitigate
Potential Risks
Respond to
Changes
Define
Shared Goals
& Objectives
Track Status
& Real Time
Updates
Provide
Teams
Efficient Tools
to Collaborate
Gather Work
Assignments
Provide Status and
Updates
Monitor Overall
Health of all Work
and Dependencies
Gather
Requirements
Determine
market
options
RFP
Develop
process
around the
system
Implement
• 1st attempt – Implement holistic resource management system
including:
• Project Task Management
• Cost Management
• Resource Management
• Artemis selected
• Technology-wide team included in implementation
• New Generic Roles created
• Process documented
• Training included
Utopia
Failed because organization wasn’t mature enough
• Resource Managers didn’t see value, only extra work
• Resource Managers & Project Managers didn’t collaborate on
resource needs
• RMs, PMs, team members – bad at estimating resource time
• Reports didn’t provide value because data entry was lackluster
or not accurate
Utopia
Identify Generic
Roles
Determine
Estimated Usage of
Each Role
Analyze and Adjust
Resource Plan
Finalize Plan for
Resource
Allocation
Match
Potential
Candidates w/
Needs
Assign Names
Resources
Confirm
Project or
Work
Assignment
and Duration
Verify
Resource
Assignment
with Necessary
Parties
Manage Future
Shifts in
Resource
Assignments
Manage Work
Assignments
Track
Resource
Performance
Provide
Continuous
Feedback and
Status
Resolve Issues
and Mitigate
Potential Risks
Respond to
Changes
Define Shared
Goals & Objectives
Track Status &
Real Time Updates
Provide Teams
Efficient Tools to
Collaborate
Gather Work
Assignments
Provide Status and
Updates
Monitor Overall
Health of all Work
and Dependencies
Gather
Requirements
Determine
market options
RFP
Develop
process
around the
system
Implement
After 2 years, old PMO disbanded, new PMO introduced
• Listened to complaints, concerns from RMs, PMs, management
• Retooled training
• Addressed software deficiencies
• Management top down focus
The Fix
Failed because software was still too difficult to use
• Wasn’t end-user friendly
• Report generation required BA & developer assistance
• Wasn’t upgraded over 8 years
• In the end, only used for time reporting of actuals, not resource
management
The Fix
Identify Generic
Roles
Determine
Estimated Usage of
Each Role
Analyze and Adjust
Resource Plan
Finalize Plan for
Resource
Allocation
Match
Potential
Candidates w/
Needs
Assign Names
Resources
Confirm
Project or
Work
Assignment
and Duration
Verify
Resource
Assignment
with Necessary
Parties
Manage Future
Shifts in
Resource
Assignments
Manage Work
Assignments
Track
Resource
Performance
Provide
Continuous
Feedback and
Status
Resolve Issues
and Mitigate
Potential Risks
Respond to
Changes
Define Shared
Goals & Objectives
Track Status &
Real Time Updates
Provide Teams
Efficient Tools to
Collaborate
Gather Work
Assignments
Provide Status and
Updates
Monitor Overall
Health of all Work
and Dependencies
Gather
Requirements
Determine
market options
RFP
Develop
process
around the
system
Implement
It must be the tool!
• Artemis version was end of life
• Company moving from Novell to Microsoft
• MS EPM server software license low cost
• MS Project the de-facto desktop project management software
• 18 month project implemented MS EPM
• Customized with project status information and reporting
• Resource Management structured for PMs and RMs to
collaborate
• User interface already familiar
Failed because people weren’t incented
• Resource Managers weren’t incented to ensure consistent
resource estimation
• RMs & PMs were at odds for resource estimation
• RMs were incented to show all resources were fully allocated
• PMs were incented to show less resources than were used
to show reduced costs
• Reports didn’t provide value because data entry was constantly
shifting Identify Generic
Roles
Determine
Estimated Usage of
Each Role
Analyze and Adjust
Resource Plan
Finalize Plan for
Resource
Allocation
Match
Potential
Candidates w/
Needs
Assign Names
Resources
Confirm
Project or
Work
Assignment
and Duration
Verify
Resource
Assignment
with Necessary
Parties
Manage Future
Shifts in
Resource
Assignments
Manage Work
Assignments
Track
Resource
Performance
Provide
Continuous
Feedback and
Status
Resolve Issues
and Mitigate
Potential Risks
Respond to
Changes
Define Shared
Goals & Objectives
Track Status &
Real Time Updates
Provide Teams
Efficient Tools to
Collaborate
Gather Work
Assignments
Provide Status and
Updates
Monitor Overall
Health of all Work
and Dependencies
Gather
Requirements
Determine
market options
RFP
Develop
process
around the
system
Implement
Portfolio Management
It must be the tool!
• MS EPM didn’t provide for true portfolio management
• What-if technology investment scenarios needed
• Project business case, charter and selection criteria needed
• Focus on resource capacity & resource collaboration
• 24 month project
• Will it be successful?
It’s the Tool
Identify Generic
Roles
Determine
Estimated Usage of
Each Role
Analyze and Adjust
Resource Plan
Finalize Plan for
Resource
Allocation
Match
Potential
Candidates w/
Needs
Assign Names
Resources
Confirm
Project or
Work
Assignment
and Duration
Verify
Resource
Assignment
with Necessary
Parties
Manage Future
Shifts in
Resource
Assignments
Manage Work
Assignments
Track
Resource
Performance
Provide
Continuous
Feedback and
Status
Resolve Issues
and Mitigate
Potential Risks
Respond to
Changes
Define Shared
Goals & Objectives
Track Status &
Real Time Updates
Provide Teams
Efficient Tools to
Collaborate
Gather Work
Assignments
Provide Status and
Updates
Monitor Overall
Health of all Work
and Dependencies
Gather
Requirements
Determine
market options
RFP
Develop
process
around the
system
Implement
People do what they are incented to do
• Software needs to be user friendly & intuitive
• Process needs to be stream-lined and efficient
• Training needs to be on process & software; also why
• Resource management metrics are needed and be tied to
annual evaluations
We the People!
Learn from 3 Failed Attempts at Resource Management

More Related Content

What's hot

Edod 674 assignment 12 presentation
Edod 674 assignment 12 presentationEdod 674 assignment 12 presentation
Edod 674 assignment 12 presentationgsoffe
 
6 M&E - Monitoring and Evaluation of Aid Projects
6 M&E - Monitoring and Evaluation of Aid Projects6 M&E - Monitoring and Evaluation of Aid Projects
6 M&E - Monitoring and Evaluation of Aid ProjectsTony
 
Methods for evaluating project performance
Methods for evaluating project performanceMethods for evaluating project performance
Methods for evaluating project performanceliviu00
 
M& e slide share
M& e   slide shareM& e   slide share
M& e slide shareSelf
 
Monitoring and evaluation presentatios
Monitoring and evaluation presentatios Monitoring and evaluation presentatios
Monitoring and evaluation presentatios athanzeer
 
Monitoring and evaluation
Monitoring and evaluationMonitoring and evaluation
Monitoring and evaluationSudipta Barman
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
Tyler Moser Resume_Final
Tyler Moser Resume_FinalTyler Moser Resume_Final
Tyler Moser Resume_FinalTyler Moser
 
Monitoring and Evaluation for Project management.
Monitoring and Evaluation for Project management.Monitoring and Evaluation for Project management.
Monitoring and Evaluation for Project management.Muthuraj K
 
Agile project management SCRUM
Agile project management SCRUMAgile project management SCRUM
Agile project management SCRUMMarwa Salim
 
Module 8 presenter notes
Module 8 presenter notesModule 8 presenter notes
Module 8 presenter notesTony
 
Project management : Causal analysis and Resolution by iFour Technolab Pvt. ...
Project management :  Causal analysis and Resolution by iFour Technolab Pvt. ...Project management :  Causal analysis and Resolution by iFour Technolab Pvt. ...
Project management : Causal analysis and Resolution by iFour Technolab Pvt. ...iFour Institute - Sustainable Learning
 
Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)Vilimaka Foliaki
 
Project Evaluation, Recycling and Closing
Project Evaluation, Recycling and ClosingProject Evaluation, Recycling and Closing
Project Evaluation, Recycling and ClosingJo Balucanag - Bitonio
 
Monitoring And Evaluation Presentation
Monitoring And Evaluation PresentationMonitoring And Evaluation Presentation
Monitoring And Evaluation PresentationEquiGov Institute
 

What's hot (20)

Dr Brian Mutie on basics of Monitoring and Evaluation
Dr Brian Mutie on basics of Monitoring and EvaluationDr Brian Mutie on basics of Monitoring and Evaluation
Dr Brian Mutie on basics of Monitoring and Evaluation
 
Monitoring indicators
Monitoring indicatorsMonitoring indicators
Monitoring indicators
 
Edod 674 assignment 12 presentation
Edod 674 assignment 12 presentationEdod 674 assignment 12 presentation
Edod 674 assignment 12 presentation
 
6 M&E - Monitoring and Evaluation of Aid Projects
6 M&E - Monitoring and Evaluation of Aid Projects6 M&E - Monitoring and Evaluation of Aid Projects
6 M&E - Monitoring and Evaluation of Aid Projects
 
Methods for evaluating project performance
Methods for evaluating project performanceMethods for evaluating project performance
Methods for evaluating project performance
 
M& e slide share
M& e   slide shareM& e   slide share
M& e slide share
 
Monitoring and Evaluation
Monitoring and Evaluation Monitoring and Evaluation
Monitoring and Evaluation
 
Monitoring and evaluation presentatios
Monitoring and evaluation presentatios Monitoring and evaluation presentatios
Monitoring and evaluation presentatios
 
Monitoring and evaluation
Monitoring and evaluationMonitoring and evaluation
Monitoring and evaluation
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
Tyler Moser Resume_Final
Tyler Moser Resume_FinalTyler Moser Resume_Final
Tyler Moser Resume_Final
 
Monitoring and Evaluation for Project management.
Monitoring and Evaluation for Project management.Monitoring and Evaluation for Project management.
Monitoring and Evaluation for Project management.
 
M & e indicators
M & e indicatorsM & e indicators
M & e indicators
 
Agile project management SCRUM
Agile project management SCRUMAgile project management SCRUM
Agile project management SCRUM
 
Module 8 presenter notes
Module 8 presenter notesModule 8 presenter notes
Module 8 presenter notes
 
Project management : Causal analysis and Resolution by iFour Technolab Pvt. ...
Project management :  Causal analysis and Resolution by iFour Technolab Pvt. ...Project management :  Causal analysis and Resolution by iFour Technolab Pvt. ...
Project management : Causal analysis and Resolution by iFour Technolab Pvt. ...
 
Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)
 
Project cycle
Project cycleProject cycle
Project cycle
 
Project Evaluation, Recycling and Closing
Project Evaluation, Recycling and ClosingProject Evaluation, Recycling and Closing
Project Evaluation, Recycling and Closing
 
Monitoring And Evaluation Presentation
Monitoring And Evaluation PresentationMonitoring And Evaluation Presentation
Monitoring And Evaluation Presentation
 

Viewers also liked

Presentación Encuesta Módulo II
Presentación Encuesta Módulo IIPresentación Encuesta Módulo II
Presentación Encuesta Módulo IIFondapCOES
 
S37 revue de presse kylia - semaine du 5 au 11 septembre 2016
S37   revue de presse kylia - semaine du 5 au 11 septembre 2016S37   revue de presse kylia - semaine du 5 au 11 septembre 2016
S37 revue de presse kylia - semaine du 5 au 11 septembre 2016KYLIA France
 
Derecho periodo prueba2016, diferente entidad
Derecho periodo prueba2016, diferente entidadDerecho periodo prueba2016, diferente entidad
Derecho periodo prueba2016, diferente entidadJesus Villa
 
Reducing energy consumption of computing
Reducing energy consumption of computing Reducing energy consumption of computing
Reducing energy consumption of computing NGUYEN VAN LUONG
 
India’s National Biometrics ID - Presented by Mr. Deepak Maheshwari
India’s National Biometrics ID - Presented by Mr. Deepak MaheshwariIndia’s National Biometrics ID - Presented by Mr. Deepak Maheshwari
India’s National Biometrics ID - Presented by Mr. Deepak Maheshwarivpnmentor
 
X Gripe A Grp5
X Gripe A Grp5X Gripe A Grp5
X Gripe A Grp5ap8cgrp5
 
On the Security of TLS-DHE in the Standard Model
On the Security of TLS-DHE in the Standard ModelOn the Security of TLS-DHE in the Standard Model
On the Security of TLS-DHE in the Standard Modelvpnmentor
 
ISO 9001_2015 Overview Presentation_Hawkeye
ISO 9001_2015 Overview Presentation_HawkeyeISO 9001_2015 Overview Presentation_Hawkeye
ISO 9001_2015 Overview Presentation_HawkeyeKatie Freeman
 
Reposicion evaluacion de desempeño
Reposicion evaluacion de desempeñoReposicion evaluacion de desempeño
Reposicion evaluacion de desempeñoJesus Villa
 
The influence of Deming's 14 points to ISO 9001:2015
The influence of Deming's 14 points to ISO 9001:2015The influence of Deming's 14 points to ISO 9001:2015
The influence of Deming's 14 points to ISO 9001:2015PECB
 
Abnormal uterine action
Abnormal uterine actionAbnormal uterine action
Abnormal uterine actionmagdy abdel
 
Etiqueta social diapositivas
Etiqueta social diapositivasEtiqueta social diapositivas
Etiqueta social diapositivasEliana Beltràn
 
La Encuesta
La EncuestaLa Encuesta
La EncuestaMgam
 
OBJETIVOS DE INVESTIGACION
OBJETIVOS DE INVESTIGACIONOBJETIVOS DE INVESTIGACION
OBJETIVOS DE INVESTIGACIONmasaco
 

Viewers also liked (20)

El cancer[1]
El cancer[1]El cancer[1]
El cancer[1]
 
Presentación Encuesta Módulo II
Presentación Encuesta Módulo IIPresentación Encuesta Módulo II
Presentación Encuesta Módulo II
 
S37 revue de presse kylia - semaine du 5 au 11 septembre 2016
S37   revue de presse kylia - semaine du 5 au 11 septembre 2016S37   revue de presse kylia - semaine du 5 au 11 septembre 2016
S37 revue de presse kylia - semaine du 5 au 11 septembre 2016
 
Derecho periodo prueba2016, diferente entidad
Derecho periodo prueba2016, diferente entidadDerecho periodo prueba2016, diferente entidad
Derecho periodo prueba2016, diferente entidad
 
Reducing energy consumption of computing
Reducing energy consumption of computing Reducing energy consumption of computing
Reducing energy consumption of computing
 
India’s National Biometrics ID - Presented by Mr. Deepak Maheshwari
India’s National Biometrics ID - Presented by Mr. Deepak MaheshwariIndia’s National Biometrics ID - Presented by Mr. Deepak Maheshwari
India’s National Biometrics ID - Presented by Mr. Deepak Maheshwari
 
portfolio2016
portfolio2016portfolio2016
portfolio2016
 
X Gripe A Grp5
X Gripe A Grp5X Gripe A Grp5
X Gripe A Grp5
 
Sesión2 publicación.doc
Sesión2 publicación.docSesión2 publicación.doc
Sesión2 publicación.doc
 
On the Security of TLS-DHE in the Standard Model
On the Security of TLS-DHE in the Standard ModelOn the Security of TLS-DHE in the Standard Model
On the Security of TLS-DHE in the Standard Model
 
Reacusación
ReacusaciónReacusación
Reacusación
 
ISO 9001_2015 Overview Presentation_Hawkeye
ISO 9001_2015 Overview Presentation_HawkeyeISO 9001_2015 Overview Presentation_Hawkeye
ISO 9001_2015 Overview Presentation_Hawkeye
 
Reposicion evaluacion de desempeño
Reposicion evaluacion de desempeñoReposicion evaluacion de desempeño
Reposicion evaluacion de desempeño
 
Boletin nº 02
Boletin nº 02Boletin nº 02
Boletin nº 02
 
The influence of Deming's 14 points to ISO 9001:2015
The influence of Deming's 14 points to ISO 9001:2015The influence of Deming's 14 points to ISO 9001:2015
The influence of Deming's 14 points to ISO 9001:2015
 
Abnormal uterine action
Abnormal uterine actionAbnormal uterine action
Abnormal uterine action
 
Encuesta
EncuestaEncuesta
Encuesta
 
Etiqueta social diapositivas
Etiqueta social diapositivasEtiqueta social diapositivas
Etiqueta social diapositivas
 
La Encuesta
La EncuestaLa Encuesta
La Encuesta
 
OBJETIVOS DE INVESTIGACION
OBJETIVOS DE INVESTIGACIONOBJETIVOS DE INVESTIGACION
OBJETIVOS DE INVESTIGACION
 

Similar to Learn from 3 Failed Attempts at Resource Management

Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change TutorialSanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorialguesta83e9d
 
Change Management for Technology Projects 4
Change Management for Technology Projects 4Change Management for Technology Projects 4
Change Management for Technology Projects 4dmdk12
 
Vikram - Resume
Vikram - ResumeVikram - Resume
Vikram - ResumeVikram Rao
 
Resource Management General Practice Itvamp 2006
Resource Management General Practice Itvamp 2006Resource Management General Practice Itvamp 2006
Resource Management General Practice Itvamp 2006ITVAMP, LLC
 
Program Evaluation & Planning System
Program Evaluation & Planning SystemProgram Evaluation & Planning System
Program Evaluation & Planning Systemnavinbkraj
 
Advanced program management resource, content and knowledge management
Advanced program management   resource, content and knowledge managementAdvanced program management   resource, content and knowledge management
Advanced program management resource, content and knowledge managementMarcus Vannini
 
Critical Success Factors along ERP life-cycle in Small medium enterprises
Critical Success Factors along ERP life-cycle in Small medium enterprises Critical Success Factors along ERP life-cycle in Small medium enterprises
Critical Success Factors along ERP life-cycle in Small medium enterprises Moutasm Tamimi
 
Project management
Project managementProject management
Project managementNitin KR
 
NCA Residency Session 8 April 5 2017
NCA Residency Session 8 April 5 2017NCA Residency Session 8 April 5 2017
NCA Residency Session 8 April 5 2017CHC Connecticut
 
Assignment 2 Designing a Training ProgramDue Week 8 and worth 3.docx
Assignment 2 Designing a Training ProgramDue Week 8 and worth 3.docxAssignment 2 Designing a Training ProgramDue Week 8 and worth 3.docx
Assignment 2 Designing a Training ProgramDue Week 8 and worth 3.docxsherni1
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance StructureSaurabh Sardesai
 
Planning And Controlling
Planning And ControllingPlanning And Controlling
Planning And ControllingManuel Ardales
 
Planning And Controlling
Planning And ControllingPlanning And Controlling
Planning And Controllingguestead93f3
 
Performance Appraisalsfor Prof Staff.Ppt
Performance Appraisalsfor Prof Staff.PptPerformance Appraisalsfor Prof Staff.Ppt
Performance Appraisalsfor Prof Staff.Pptsatyam mishra
 
PMO Proposal For Global Sales Operations
PMO Proposal For Global Sales OperationsPMO Proposal For Global Sales Operations
PMO Proposal For Global Sales Operationstonyhinojosa
 
Addressing strategicsourcingchallenges
Addressing strategicsourcingchallengesAddressing strategicsourcingchallenges
Addressing strategicsourcingchallengesJoshua Kaiman
 
How to assess and continuously improve the maturity of health information sys...
How to assess and continuously improve the maturity of health information sys...How to assess and continuously improve the maturity of health information sys...
How to assess and continuously improve the maturity of health information sys...MEASURE Evaluation
 
Monitoring & evaluation presentation[1]
Monitoring & evaluation presentation[1]Monitoring & evaluation presentation[1]
Monitoring & evaluation presentation[1]skzarif
 

Similar to Learn from 3 Failed Attempts at Resource Management (20)

Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change TutorialSanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
 
Change Management for Technology Projects 4
Change Management for Technology Projects 4Change Management for Technology Projects 4
Change Management for Technology Projects 4
 
Hm 418 harris ch10 ppt
Hm 418 harris ch10 pptHm 418 harris ch10 ppt
Hm 418 harris ch10 ppt
 
Vikram - Resume
Vikram - ResumeVikram - Resume
Vikram - Resume
 
Resource Management General Practice Itvamp 2006
Resource Management General Practice Itvamp 2006Resource Management General Practice Itvamp 2006
Resource Management General Practice Itvamp 2006
 
Program Evaluation & Planning System
Program Evaluation & Planning SystemProgram Evaluation & Planning System
Program Evaluation & Planning System
 
Advanced program management resource, content and knowledge management
Advanced program management   resource, content and knowledge managementAdvanced program management   resource, content and knowledge management
Advanced program management resource, content and knowledge management
 
Critical Success Factors along ERP life-cycle in Small medium enterprises
Critical Success Factors along ERP life-cycle in Small medium enterprises Critical Success Factors along ERP life-cycle in Small medium enterprises
Critical Success Factors along ERP life-cycle in Small medium enterprises
 
Project management
Project managementProject management
Project management
 
NCA Residency Session 8 April 5 2017
NCA Residency Session 8 April 5 2017NCA Residency Session 8 April 5 2017
NCA Residency Session 8 April 5 2017
 
Assignment 2 Designing a Training ProgramDue Week 8 and worth 3.docx
Assignment 2 Designing a Training ProgramDue Week 8 and worth 3.docxAssignment 2 Designing a Training ProgramDue Week 8 and worth 3.docx
Assignment 2 Designing a Training ProgramDue Week 8 and worth 3.docx
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance Structure
 
Planning And Controlling
Planning And ControllingPlanning And Controlling
Planning And Controlling
 
Planning And Controlling
Planning And ControllingPlanning And Controlling
Planning And Controlling
 
Performance Appraisalsfor Prof Staff.Ppt
Performance Appraisalsfor Prof Staff.PptPerformance Appraisalsfor Prof Staff.Ppt
Performance Appraisalsfor Prof Staff.Ppt
 
PMO Proposal For Global Sales Operations
PMO Proposal For Global Sales OperationsPMO Proposal For Global Sales Operations
PMO Proposal For Global Sales Operations
 
Addressing strategicsourcingchallenges
Addressing strategicsourcingchallengesAddressing strategicsourcingchallenges
Addressing strategicsourcingchallenges
 
How to assess and continuously improve the maturity of health information sys...
How to assess and continuously improve the maturity of health information sys...How to assess and continuously improve the maturity of health information sys...
How to assess and continuously improve the maturity of health information sys...
 
Monitoring & evaluation presentation[1]
Monitoring & evaluation presentation[1]Monitoring & evaluation presentation[1]
Monitoring & evaluation presentation[1]
 
PMRolesResponsibilities.ppt
PMRolesResponsibilities.pptPMRolesResponsibilities.ppt
PMRolesResponsibilities.ppt
 

Learn from 3 Failed Attempts at Resource Management

  • 1. Learn from 3 Failed Attempts at Resource Management Jeff Manhardt | PMP Fall 2016
  • 2. Resource Capacity Planning Resource Allocation Resource Work Management Resource Collaboration Resource Task Management Resource System Implementation http://epmlive.com/project-management-tools-5-steps-resource-management/
  • 3. Resource Capacity Planning Identify Generic Roles Determine Estimated Usage of Each Role Analyze and Adjust Resource Plan Finalize Plan for Resource Allocation
  • 4. Resource Allocation Match Potential Candidates w/ Needs Assign Names Resources Confirm Project or Work Assignment and Duration Verify Resource Assignment with Necessary Parties Manage Future Shifts in Resource Assignments
  • 5. Resource Work Management Manage Work Assignments Track Resource Performance Provide Continuous Feedback and Status Resolve Issues and Mitigate Potential Risks Respond to Changes
  • 6. Resource Collaboration Define Shared Goals & Objectives Track Status & Real Time Updates Provide Teams Efficient Tools to Collaborate
  • 7. Resource Task Management Gather Work Assignments Provide Status and Updates Monitor Overall Health of all Work and Dependencies
  • 9. Taken Together… Identify Generic Roles Determine Estimated Usage of Each Role Analyze and Adjust Resource Plan Finalize Plan for Resource Allocation Match Potential Candidates w/ Needs Assign Names Resources Confirm Project or Work Assignment and Duration Verify Resource Assignment with Necessary Parties Manage Future Shifts in Resource Assignments Manage Work Assignments Track Resource Performance Provide Continuous Feedback and Status Resolve Issues and Mitigate Potential Risks Respond to Changes Define Shared Goals & Objectives Track Status & Real Time Updates Provide Teams Efficient Tools to Collaborate Gather Work Assignments Provide Status and Updates Monitor Overall Health of all Work and Dependencies Gather Requirements Determine market options RFP Develop process around the system Implement
  • 10.
  • 11. • 1st attempt – Implement holistic resource management system including: • Project Task Management • Cost Management • Resource Management • Artemis selected • Technology-wide team included in implementation • New Generic Roles created • Process documented • Training included Utopia
  • 12. Failed because organization wasn’t mature enough • Resource Managers didn’t see value, only extra work • Resource Managers & Project Managers didn’t collaborate on resource needs • RMs, PMs, team members – bad at estimating resource time • Reports didn’t provide value because data entry was lackluster or not accurate Utopia Identify Generic Roles Determine Estimated Usage of Each Role Analyze and Adjust Resource Plan Finalize Plan for Resource Allocation Match Potential Candidates w/ Needs Assign Names Resources Confirm Project or Work Assignment and Duration Verify Resource Assignment with Necessary Parties Manage Future Shifts in Resource Assignments Manage Work Assignments Track Resource Performance Provide Continuous Feedback and Status Resolve Issues and Mitigate Potential Risks Respond to Changes Define Shared Goals & Objectives Track Status & Real Time Updates Provide Teams Efficient Tools to Collaborate Gather Work Assignments Provide Status and Updates Monitor Overall Health of all Work and Dependencies Gather Requirements Determine market options RFP Develop process around the system Implement
  • 13.
  • 14. After 2 years, old PMO disbanded, new PMO introduced • Listened to complaints, concerns from RMs, PMs, management • Retooled training • Addressed software deficiencies • Management top down focus The Fix
  • 15. Failed because software was still too difficult to use • Wasn’t end-user friendly • Report generation required BA & developer assistance • Wasn’t upgraded over 8 years • In the end, only used for time reporting of actuals, not resource management The Fix Identify Generic Roles Determine Estimated Usage of Each Role Analyze and Adjust Resource Plan Finalize Plan for Resource Allocation Match Potential Candidates w/ Needs Assign Names Resources Confirm Project or Work Assignment and Duration Verify Resource Assignment with Necessary Parties Manage Future Shifts in Resource Assignments Manage Work Assignments Track Resource Performance Provide Continuous Feedback and Status Resolve Issues and Mitigate Potential Risks Respond to Changes Define Shared Goals & Objectives Track Status & Real Time Updates Provide Teams Efficient Tools to Collaborate Gather Work Assignments Provide Status and Updates Monitor Overall Health of all Work and Dependencies Gather Requirements Determine market options RFP Develop process around the system Implement
  • 16.
  • 17.
  • 18. It must be the tool! • Artemis version was end of life • Company moving from Novell to Microsoft • MS EPM server software license low cost • MS Project the de-facto desktop project management software • 18 month project implemented MS EPM • Customized with project status information and reporting • Resource Management structured for PMs and RMs to collaborate • User interface already familiar
  • 19. Failed because people weren’t incented • Resource Managers weren’t incented to ensure consistent resource estimation • RMs & PMs were at odds for resource estimation • RMs were incented to show all resources were fully allocated • PMs were incented to show less resources than were used to show reduced costs • Reports didn’t provide value because data entry was constantly shifting Identify Generic Roles Determine Estimated Usage of Each Role Analyze and Adjust Resource Plan Finalize Plan for Resource Allocation Match Potential Candidates w/ Needs Assign Names Resources Confirm Project or Work Assignment and Duration Verify Resource Assignment with Necessary Parties Manage Future Shifts in Resource Assignments Manage Work Assignments Track Resource Performance Provide Continuous Feedback and Status Resolve Issues and Mitigate Potential Risks Respond to Changes Define Shared Goals & Objectives Track Status & Real Time Updates Provide Teams Efficient Tools to Collaborate Gather Work Assignments Provide Status and Updates Monitor Overall Health of all Work and Dependencies Gather Requirements Determine market options RFP Develop process around the system Implement
  • 21.
  • 22. It must be the tool! • MS EPM didn’t provide for true portfolio management • What-if technology investment scenarios needed • Project business case, charter and selection criteria needed • Focus on resource capacity & resource collaboration • 24 month project • Will it be successful? It’s the Tool Identify Generic Roles Determine Estimated Usage of Each Role Analyze and Adjust Resource Plan Finalize Plan for Resource Allocation Match Potential Candidates w/ Needs Assign Names Resources Confirm Project or Work Assignment and Duration Verify Resource Assignment with Necessary Parties Manage Future Shifts in Resource Assignments Manage Work Assignments Track Resource Performance Provide Continuous Feedback and Status Resolve Issues and Mitigate Potential Risks Respond to Changes Define Shared Goals & Objectives Track Status & Real Time Updates Provide Teams Efficient Tools to Collaborate Gather Work Assignments Provide Status and Updates Monitor Overall Health of all Work and Dependencies Gather Requirements Determine market options RFP Develop process around the system Implement
  • 23.
  • 24. People do what they are incented to do • Software needs to be user friendly & intuitive • Process needs to be stream-lined and efficient • Training needs to be on process & software; also why • Resource management metrics are needed and be tied to annual evaluations We the People!