SlideShare a Scribd company logo
1 of 32
Download to read offline
Emerging Scenario with Renewable Energy in Sri Lanka.
Meeting the Challenges in Power System
Operations & Economic Consequences.
Lakshitha Weerasinghe
Ceylon Electricity Board
∗Basics of Power System Operations in
the Sri Lankan context.
∗Understanding the problem!
∗Solutions!
Contents
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Basics of Power System Operations
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Time Line of activitiesGenerationPlanning
Constructionof
GeneratingAssets
Constructionof
Transmission
Infrastructure
UnitCommitment
Freq.Control
Transmission
Planning
EconomicDispatch
Supply-Demand
Balancing
SecondsMinutesHrs./ Days
GovernorAction
Years
OperationsPlanning
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Time Line of activities
UnitCommitment
Freq.Control
EconomicDispatch
Supply-Demand
Balancing
SecondsMinutes
Hrs./ Days
GovernorAction
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
50Hz
51Hz49Hz
Demand Generation
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Supply-Demand Balancing
Supply-Demand
Balancing
Seconds
20:00
16:00
12:00
08:00
04:00
00:00
24:00
Intermediate load
Peak load
Load MW
Base Load
1400MW
1600MW
2000MW
900 MW
Understanding the Demand curve
© Lakshitha Weerasinghe Ceylon
Electricity Board 2014
Frequency (Hz)
Power (MW)
50Hz
100 MW
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Supply-Demand
Balancing
Seconds
GovernorAction
MinutesHrs./ Days
Frequency (Hz)
Power (MW)
50Hz
100 MW
49.5Hz
110 MW
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Supply-Demand
Balancing
Seconds
GovernorAction
MinutesHrs./ Days
Freq. Error
Without Governor Control
With Governor Control
Frequency
50 Hz Time
Disturbance (Generator Trips!)
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Supply-Demand
Balancing
Governor
Action
Frequency Control
Supply-Demand
Balancing
Seconds
GovernorAction
MinutesHrs./ Days
FrequencyControl
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Frequency
50 Hz
Freq. Error
With Frequency Control
Time
Disturbance (Generator Trips!)
With Governor Control
(Primary ALFC)
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Bringing Frequency back to 50Hz.
Hydro*
Thermal
CEB 1361 MW
•CEB 1164 MW
•IPP 771 MW
*Note :- Mini Hydro and wind not included
Understanding the Frequency Controller
0MW 67
Kothmale single unit maximum
capacity = 67MW
Eg.
50
49 51
5248
Hz
30 60
50Hz
51Hz49Hz
Demand Generation
50Hz
51Hz49Hz
Demand
Generation
50Hz
51Hz49Hz
Demand Generation
Any one of the following power
stations is assigned at any given time
to look after the system frequency.
1. Victoria (unit size = 71MWx3)
2. Kothmale (Unit size x 67 x 3)
3. New Laxapana (50MW x 2)
4. Samanala Wewa (60MW x 2)
© Lakshitha Weerasinghe Ceylon
Electricity Board 2014
Time Line of activities
UnitCommitment
Freq.Control
EconomicDispatch
Supply-Demand
Balancing
SecondsMinutes
Hrs./ Days
GovernorAction
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
∗Economic Dispatch – What load to be
kept on each machine that is already in
operation.
∗Unit Commitment – What are the
machines to start or stop to serve load
within a given period.
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Other Constraints/ Considerations
(1) Hydro Power comes last in the water
utilization Priority order
1. Water Service and Drainage
2. Environment
3. Irrigation
4. Power
(2) Pond balancing
(3) Reservoir Operations
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Annual Inflow 3500 GWh
Annual Hydro Generation 3500 GWh
Spill
MOL
Storage Capacity ≅ 1250 GWh
Reservoir1
Reservoir7
Understanding the problem.
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Resource Attributes that causes problems
to System Operations
Small Hydro Non Dispatchability.
Wind Non- Dispatchability and Intermittency.
Solar Non-Dispatchability and Intermittency.
Problems associated with Non
Conventional Renewable Technologies.
Over 260 MW of Small NCRE generators are connected to the Distribution network.
They appear as “Negative Loads” to system operators.
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Issues due to Non
Dispatchability.
20:00
16:00
12:00
08:00
04:00
00:00
24:00
Load MW
Minimum Demand
© Lakshitha Weerasinghe Ceylon
Electricity Board 2014
Issues due to non Dispatchable nature
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Issues due to non Dispatchable nature
20:00
16:00
12:00
08:00
04:00
00:00
24:00
Load MW
© Lakshitha Weerasinghe Ceylon
Electricity Board 2014
Issues due to non Dispatchable nature
3 Base Load Coal plants. Minimum stable load is
180MW.
Base Load Thermals such as Sapugaskanda HFO
plant, CC plants.
Frequency Controlling Hydro Plant
Plants providing (Up/Down) Operating Reserves.
“Must Run” Hydro plants
Hydro plants operated to balance ponds.
360MW of non dispatchable small renewable
plants.
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Issues due to Intermittency
Technical
• Violation of operating frequency
limits. (±1%)
• Operation of Under Frequency Load
Shedding (starting from 48.75Hz).
• Severe Frequency instabilities leading
to cascaded total collapse.
Economical
• Cost of maintaining high spinning
reserve.
• Underutilization of energy from other
sources which may be cheaper or at
zero cost (such as from Run-of-the-
river plants that are spilling).
• Cycling of base load thermal plants.
How Intermittent is Wind SPEED ?
0.00
2.00
4.00
6.00
8.00
10.00
12.00
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Velocitym/s
Seasonal Variation of Wind Velocity
8.80
9.00
9.20
9.40
9.60
9.80
10.00
10.20
10.40
1 2 3 4 5 6 7 8 9 101112131415161718192021222324
velocitym/s
Diurnal Variation of Wind Velocity
0
1
2
3
4
5
6
7
8
9
10
0 50 100 150 200 250 300 350 400 450 500
Source: SEA
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
How Intermittent is Wind Power ?
Minute to Minute variation of out put (MW) of a wind Farm over
3 hour period.
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
How Intermittent is Solar?
Perfect Solar Day Pre-monsoon Clouds Passing Over
Source - SEA
Cost of Spinning Reserves.
Gradient = Incremental cost Rs/kWh
Generation
Cost per
hour
Output (MW)
No Load
Cost per
hour
Plant No Load Cost per Hour
(Rs million)
(September 2014)
Kalanitissa CCP (Diesel) 1.17
AES CCP 1.3
Kerawalapitiya Yougadanavi 1.6
Victoria 10 m3 /s (25% of full load )
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Cost of Cycling
Plant Start/Stop Cost (Rs million)
Hot (<8 h) Warm
(8<h<48)
Cold
(48<h)
Kalanithissa CC
(Diesel)
3.9 4.6 5.3
AES CC 3.3 8.6 10.5
Kerawalapitiya
Yougadanavi
5.9 7.1 9.5
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Solutions
© Lakshitha Weerasinghe Ceylon Electricity Board 2014
Solutions
Supply Side Solutions
• Maintaining larger spinning reserve to do Load-Frequency Control on supply side.
• Operating intermittent sources (such as Wind) below capable output and utilize the balance
capacity to cushion out fluctuations at the source itself.
• Group Control & AGC at Load dispatch Centre.
• Secondary Automatic Load-Frequency regulation using Integral Controllers.
Demand Side Solutions
• Valley Filling measures to improve Low demand period
• Introducing variable loads to be called upon low demand periods.
• Changing Customer demand using smart Grid options.
• Introducing local loads such as Hydrogen, Compressed Air and Battery technologies to utilize
part of the generation to cushion out intermittency/variability at the terminal.
Other Solutions
• Forecasting Wind speeds to do improved Operations Planning.
• Interconnect with neighboring Grids.
• Geographical scattering of Wind and Solar park locations.

More Related Content

Similar to lakshitha weerasinghe

Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Kachinga-Wankunda Phiri
 
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATIONCOST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATIONRajeev Kumar
 
Review of journal articles of wave energy converters and their impact on powe...
Review of journal articles of wave energy converters and their impact on powe...Review of journal articles of wave energy converters and their impact on powe...
Review of journal articles of wave energy converters and their impact on powe...Nuwan Dinusha
 
Applicability of pressure retarded osmosis power generation
Applicability of pressure retarded osmosis power generationApplicability of pressure retarded osmosis power generation
Applicability of pressure retarded osmosis power generationRajani Kanth
 
Presentation by Dr. Shrikrishna Sane- Hydro Kinetic Renewable Energy Resource
Presentation by Dr. Shrikrishna Sane- Hydro Kinetic Renewable Energy ResourcePresentation by Dr. Shrikrishna Sane- Hydro Kinetic Renewable Energy Resource
Presentation by Dr. Shrikrishna Sane- Hydro Kinetic Renewable Energy ResourceIITBAA
 
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distributionDay-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distributionIPPAI
 
Sam latz-se tu-p-solar-energy-transformation-program-setup
Sam latz-se tu-p-solar-energy-transformation-program-setupSam latz-se tu-p-solar-energy-transformation-program-setup
Sam latz-se tu-p-solar-energy-transformation-program-setupjames hamilton
 
Ips connect 2015 francisco gafaro
Ips connect 2015 francisco gafaroIps connect 2015 francisco gafaro
Ips connect 2015 francisco gafarojames_hamilton
 
The Insufficent Power Situation Due to Low Lake Levels 2016
The Insufficent  Power Situation Due to Low Lake Levels 2016The Insufficent  Power Situation Due to Low Lake Levels 2016
The Insufficent Power Situation Due to Low Lake Levels 2016Fabiano Thulu
 
The role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAEThe role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAEReedExhibitionsMiddl
 
Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016Roy Robinson
 
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...Celestial Light
 
Power system operation corporation ltd (posoco)
Power system operation corporation ltd (posoco)Power system operation corporation ltd (posoco)
Power system operation corporation ltd (posoco)Dhruv Agarwal
 
Guest Lecture at University of Mataram (UNRAM).pdf
Guest Lecture at University of Mataram (UNRAM).pdfGuest Lecture at University of Mataram (UNRAM).pdf
Guest Lecture at University of Mataram (UNRAM).pdfParyantoDS
 
Load Research Concept and Approach _Kolkata.pptx
Load Research Concept and Approach  _Kolkata.pptxLoad Research Concept and Approach  _Kolkata.pptx
Load Research Concept and Approach _Kolkata.pptxRAMAPANDA6
 

Similar to lakshitha weerasinghe (20)

Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16Fixing Our Power Crisis - EAZ v2 28.10.16
Fixing Our Power Crisis - EAZ v2 28.10.16
 
EirGrid NATIONAL CONTROL CENTRE
EirGrid NATIONAL CONTROL CENTREEirGrid NATIONAL CONTROL CENTRE
EirGrid NATIONAL CONTROL CENTRE
 
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATIONCOST ESTIMATION OF SMALL HYDRO POWER GENERATION
COST ESTIMATION OF SMALL HYDRO POWER GENERATION
 
REPORT-NHPC
REPORT-NHPCREPORT-NHPC
REPORT-NHPC
 
Review of journal articles of wave energy converters and their impact on powe...
Review of journal articles of wave energy converters and their impact on powe...Review of journal articles of wave energy converters and their impact on powe...
Review of journal articles of wave energy converters and their impact on powe...
 
Applicability of pressure retarded osmosis power generation
Applicability of pressure retarded osmosis power generationApplicability of pressure retarded osmosis power generation
Applicability of pressure retarded osmosis power generation
 
Presentation by Dr. Shrikrishna Sane- Hydro Kinetic Renewable Energy Resource
Presentation by Dr. Shrikrishna Sane- Hydro Kinetic Renewable Energy ResourcePresentation by Dr. Shrikrishna Sane- Hydro Kinetic Renewable Energy Resource
Presentation by Dr. Shrikrishna Sane- Hydro Kinetic Renewable Energy Resource
 
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distributionDay-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
 
Sam latz-se tu-p-solar-energy-transformation-program-setup
Sam latz-se tu-p-solar-energy-transformation-program-setupSam latz-se tu-p-solar-energy-transformation-program-setup
Sam latz-se tu-p-solar-energy-transformation-program-setup
 
Ips connect 2015 francisco gafaro
Ips connect 2015 francisco gafaroIps connect 2015 francisco gafaro
Ips connect 2015 francisco gafaro
 
The Insufficent Power Situation Due to Low Lake Levels 2016
The Insufficent  Power Situation Due to Low Lake Levels 2016The Insufficent  Power Situation Due to Low Lake Levels 2016
The Insufficent Power Situation Due to Low Lake Levels 2016
 
The role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAEThe role of energy storage in planning our energy needs in the UAE
The role of energy storage in planning our energy needs in the UAE
 
Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016
 
Tidal Energy
Tidal EnergyTidal Energy
Tidal Energy
 
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...
 
Update on ERCOT Activities
Update on ERCOT ActivitiesUpdate on ERCOT Activities
Update on ERCOT Activities
 
Power system operation corporation ltd (posoco)
Power system operation corporation ltd (posoco)Power system operation corporation ltd (posoco)
Power system operation corporation ltd (posoco)
 
Guest Lecture at University of Mataram (UNRAM).pdf
Guest Lecture at University of Mataram (UNRAM).pdfGuest Lecture at University of Mataram (UNRAM).pdf
Guest Lecture at University of Mataram (UNRAM).pdf
 
Load Research Concept and Approach _Kolkata.pptx
Load Research Concept and Approach  _Kolkata.pptxLoad Research Concept and Approach  _Kolkata.pptx
Load Research Concept and Approach _Kolkata.pptx
 
Training report
Training reportTraining report
Training report
 

lakshitha weerasinghe

  • 1. Emerging Scenario with Renewable Energy in Sri Lanka. Meeting the Challenges in Power System Operations & Economic Consequences. Lakshitha Weerasinghe Ceylon Electricity Board
  • 2. ∗Basics of Power System Operations in the Sri Lankan context. ∗Understanding the problem! ∗Solutions! Contents © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 3. Basics of Power System Operations © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 4. Time Line of activitiesGenerationPlanning Constructionof GeneratingAssets Constructionof Transmission Infrastructure UnitCommitment Freq.Control Transmission Planning EconomicDispatch Supply-Demand Balancing SecondsMinutesHrs./ Days GovernorAction Years OperationsPlanning © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 5. Time Line of activities UnitCommitment Freq.Control EconomicDispatch Supply-Demand Balancing SecondsMinutes Hrs./ Days GovernorAction © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 6. 50Hz 51Hz49Hz Demand Generation © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Supply-Demand Balancing Supply-Demand Balancing Seconds
  • 7. 20:00 16:00 12:00 08:00 04:00 00:00 24:00 Intermediate load Peak load Load MW Base Load 1400MW 1600MW 2000MW 900 MW Understanding the Demand curve © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 8. Frequency (Hz) Power (MW) 50Hz 100 MW © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Supply-Demand Balancing Seconds GovernorAction MinutesHrs./ Days
  • 9. Frequency (Hz) Power (MW) 50Hz 100 MW 49.5Hz 110 MW © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Supply-Demand Balancing Seconds GovernorAction MinutesHrs./ Days
  • 10. Freq. Error Without Governor Control With Governor Control Frequency 50 Hz Time Disturbance (Generator Trips!) © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Supply-Demand Balancing Governor Action
  • 12. Frequency 50 Hz Freq. Error With Frequency Control Time Disturbance (Generator Trips!) With Governor Control (Primary ALFC) © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 13. Bringing Frequency back to 50Hz. Hydro* Thermal CEB 1361 MW •CEB 1164 MW •IPP 771 MW *Note :- Mini Hydro and wind not included
  • 14. Understanding the Frequency Controller 0MW 67 Kothmale single unit maximum capacity = 67MW Eg. 50 49 51 5248 Hz 30 60 50Hz 51Hz49Hz Demand Generation 50Hz 51Hz49Hz Demand Generation 50Hz 51Hz49Hz Demand Generation Any one of the following power stations is assigned at any given time to look after the system frequency. 1. Victoria (unit size = 71MWx3) 2. Kothmale (Unit size x 67 x 3) 3. New Laxapana (50MW x 2) 4. Samanala Wewa (60MW x 2) © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 15. Time Line of activities UnitCommitment Freq.Control EconomicDispatch Supply-Demand Balancing SecondsMinutes Hrs./ Days GovernorAction © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 16. ∗Economic Dispatch – What load to be kept on each machine that is already in operation. ∗Unit Commitment – What are the machines to start or stop to serve load within a given period. © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 17. Other Constraints/ Considerations (1) Hydro Power comes last in the water utilization Priority order 1. Water Service and Drainage 2. Environment 3. Irrigation 4. Power (2) Pond balancing (3) Reservoir Operations © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 18. Annual Inflow 3500 GWh Annual Hydro Generation 3500 GWh Spill MOL Storage Capacity ≅ 1250 GWh Reservoir1 Reservoir7
  • 19. Understanding the problem. © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 20. Resource Attributes that causes problems to System Operations Small Hydro Non Dispatchability. Wind Non- Dispatchability and Intermittency. Solar Non-Dispatchability and Intermittency. Problems associated with Non Conventional Renewable Technologies. Over 260 MW of Small NCRE generators are connected to the Distribution network. They appear as “Negative Loads” to system operators. © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 21. © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Issues due to Non Dispatchability.
  • 22. 20:00 16:00 12:00 08:00 04:00 00:00 24:00 Load MW Minimum Demand © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Issues due to non Dispatchable nature
  • 23. © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Issues due to non Dispatchable nature
  • 24. 20:00 16:00 12:00 08:00 04:00 00:00 24:00 Load MW © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Issues due to non Dispatchable nature 3 Base Load Coal plants. Minimum stable load is 180MW. Base Load Thermals such as Sapugaskanda HFO plant, CC plants. Frequency Controlling Hydro Plant Plants providing (Up/Down) Operating Reserves. “Must Run” Hydro plants Hydro plants operated to balance ponds. 360MW of non dispatchable small renewable plants.
  • 25. © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Issues due to Intermittency Technical • Violation of operating frequency limits. (±1%) • Operation of Under Frequency Load Shedding (starting from 48.75Hz). • Severe Frequency instabilities leading to cascaded total collapse. Economical • Cost of maintaining high spinning reserve. • Underutilization of energy from other sources which may be cheaper or at zero cost (such as from Run-of-the- river plants that are spilling). • Cycling of base load thermal plants.
  • 26. How Intermittent is Wind SPEED ? 0.00 2.00 4.00 6.00 8.00 10.00 12.00 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Velocitym/s Seasonal Variation of Wind Velocity 8.80 9.00 9.20 9.40 9.60 9.80 10.00 10.20 10.40 1 2 3 4 5 6 7 8 9 101112131415161718192021222324 velocitym/s Diurnal Variation of Wind Velocity 0 1 2 3 4 5 6 7 8 9 10 0 50 100 150 200 250 300 350 400 450 500 Source: SEA
  • 27. © Lakshitha Weerasinghe Ceylon Electricity Board 2014 How Intermittent is Wind Power ? Minute to Minute variation of out put (MW) of a wind Farm over 3 hour period.
  • 28. © Lakshitha Weerasinghe Ceylon Electricity Board 2014 How Intermittent is Solar? Perfect Solar Day Pre-monsoon Clouds Passing Over Source - SEA
  • 29. Cost of Spinning Reserves. Gradient = Incremental cost Rs/kWh Generation Cost per hour Output (MW) No Load Cost per hour Plant No Load Cost per Hour (Rs million) (September 2014) Kalanitissa CCP (Diesel) 1.17 AES CCP 1.3 Kerawalapitiya Yougadanavi 1.6 Victoria 10 m3 /s (25% of full load ) © Lakshitha Weerasinghe Ceylon Electricity Board 2014
  • 30. © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Cost of Cycling Plant Start/Stop Cost (Rs million) Hot (<8 h) Warm (8<h<48) Cold (48<h) Kalanithissa CC (Diesel) 3.9 4.6 5.3 AES CC 3.3 8.6 10.5 Kerawalapitiya Yougadanavi 5.9 7.1 9.5
  • 31. © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Solutions
  • 32. © Lakshitha Weerasinghe Ceylon Electricity Board 2014 Solutions Supply Side Solutions • Maintaining larger spinning reserve to do Load-Frequency Control on supply side. • Operating intermittent sources (such as Wind) below capable output and utilize the balance capacity to cushion out fluctuations at the source itself. • Group Control & AGC at Load dispatch Centre. • Secondary Automatic Load-Frequency regulation using Integral Controllers. Demand Side Solutions • Valley Filling measures to improve Low demand period • Introducing variable loads to be called upon low demand periods. • Changing Customer demand using smart Grid options. • Introducing local loads such as Hydrogen, Compressed Air and Battery technologies to utilize part of the generation to cushion out intermittency/variability at the terminal. Other Solutions • Forecasting Wind speeds to do improved Operations Planning. • Interconnect with neighboring Grids. • Geographical scattering of Wind and Solar park locations.