Feed-in tariffs – Design options and case studies for
                   developing countries

                   Leonardo Webinar 26 January 2012

                          Dr. des. David Jacobs
               Director Renewable Energy, IFOK GmbH




Course on Regulation and Sustainable Energy in Developing Countries – Session 4
www.leonardo-energy.org/course-regulation-and-sustainable-energy-developing-
                                 countries
Agenda

FIT design and case studies:


 Feed-in tariff calculation



 FIT financing



 Capacity caps



 Local content rules
FIT Countries 2010




 Countries with state FIT policy

 Countries with national FIT policy




                                      Source: REN21, Renewables 2010 Global Status Report


                                                                                            3
Basic feed-in tariff design

• Purchase obligation
   •   “Independent” from power demand

• Fixed tariff payment based on the actual power generation costs
   •   Price setting will be discussed in session 4

• Long duration of tariff payment
Tariff calculation
Tariff calculation methodology

 Early FITs (1970-1990s): Avoided costs



 Benchmark: cost for conventionally produced electricity



 Tariff level is only “right” coincidentally (under- or over-compensation)

   •   E.g. Nicaragua, Tanzania
Tariff calculation methodology

  •   Tariff calculation based on technology specific generation costs
      + “reasonable” rates of return

  • Don’t use “avoided costs” as point of reference

  • Cost factors:
             • Investment costs (material and capital costs); Grid-
               related and administrative costs (including grid
               connection, costs for licensing procedure; Operation
               and maintenance costs; Fuels costs (biomass and
               biogas)
Rate setting process

 Different jurisdictions use different methodologies for setting FIT rates.
 Recent research reviewed several models for rate setting, results
 indicate:
  • Most jurisdictions use similar approaches (even if inputs and
    assumptions vary):


         Discounted Cash Flow (DCF), after-tax analysis
             – Discounts to present value the estimated annual cash
               flows to equity investors
Building a feed-in tariff rate calculator

 Goal is to reach an appropriate rate that is high enough to spur
 renewable energy development while at the same time not so high as
 to provide windfall profits to project owners.


 Tradeoffs exist:
   • Ease of use vs. complexity
   • High-level representation vs. detailed analysis
   • Granularity vs. time investment
Tariff calculation methodology
  • Targeted IRR (Internal rate of return)
           • In the EU, feed-in tariffs target at an internal rate of
             return of 5-9 percent (certain jurisdictions use return on
             equity)
           • In developing countries, the targeted IRR usually
             needs to be higher (10-20 percent)
           • Public investment (monopolist, often without profit
             interest); or private IPPs (profitability important)?
           • Similar profitability for renewable energy projects
             needed as for convention energy market
Figure 4: Equity IRR expectation in developing countries:



      Equity IRR expectation in developing countries
25%




20%




15%




10%




 5%




 0%

        Infrastructure        Technology         Political risk   Reg. Risk, soft     Counterparty       Currency     Infrastructure

          investment         risk (missing                          political risk,          risk    safety cushion     investment

         (developed          track record)                         transparency,                                       (developing

              world)                                                       legal                                            world)

                                                                      framework




                    Source. Fulton et al. 2011
Tariff calculation methodology

• Assumed capital structure
        • Ratio of debt and equity (80 to 20 in Netherlands; 70 to 30 in
          Ontario (Canada))
        • Germany; different debt-equity ratio depending on each
          technology (reflecting their risk profile)
        • South Africa: 70:30
        • Higher equity share in other developing countries?
        • Interest rate for the debt? (international and national analysis
          needed)
        • Generally, debt term (duration) equals duration of feed-in tariff
          payment (average of 20 years)
Tariff calculation methodology

• Tax treatment
       • Pre-tax calculation (taking advantages and disadvantages from
         national taxation scheme into account)
        Post-tax: Germany, because not significant available tax benefits,
         and because tax liabilities vary across ownership and investor types
         and are difficult to generalize – also used in Malaysia
        Accelerated depreciation factored in (e.g. India)
Tariff calculation methodology

• Treatment of inflation (indexation)
        • Necessary because of long-term tariff payment (especially in
          developing countries with high inflation rates)
        • Usually applied to the investment share that is related to
          O&M costs
Tariff calculation – South Africa (2009 vs. 2011)
Tariff calculation assumptions – Malaysia (2010)




                         Source: Kettha 2010
Tariff calculation in Germany: Input data for wind energy

• Medium transparency in Germany


 Provision          of Equity share: 25%     Return on equity (100% -location): 12%
 capital               Share of debt: 75 %   Interest on debt: 5 % , or 5,5 %

 Time period in question                     20 years

 Inflation rate                              2% p.a.

 Specific investment costs                   60 and 80 % - location: 1.756 €/kW

                                             100 % location: 1,463 €/kW

                                             120% aand 150 % - location: 1, 336 €/kW

 Annual costs of operation                   Year 1-10: 2.19 ct/kWh

                                             Year 11-20: 2.49 ct/kWh


 Source: BMU 2011
Tools for tariff calculation

 RET Screen http://www.retscreen.net/


 CREST model from NREL
 https://financere.nrel.gov/finance/content/CREST-model


 Adoptation to national context is required (e.g. tax burdens and
 investment incentives)
Tools for tariff calculation – CREST from NREL (inputs)
Tools for tariff calculation – CREST from NREL (cash flow)
FIT financing
Financing mechanism - Germany

 Financing mechanism in liberalized electricity markets

 Financing trough “burden sharing” between all electricity consumers
Differences in emerging economies and developing countries

• low electricity costs
• little acceptance of electricity price increases




                                                     Artificially low
   Subsidies                  No interna-               electricity
      for                      lization of            prices = high
  conventional                  negative             cost difference
     power                   external costs                with
                                                       renewables
Combined financing – Taiwan

• Add additional financing to the national FIT fund (levy on producers from
  conventional electricity)
• Increase the retail electricity price by a certain share (after general elections
  next year)


     Conventional
                         Money
 electricity producers
                                                                           Payment for producers
                                 Renewable Energy Fund                     under the feed-in tariff
                                                                   Money
                                      (FIT Fund)                                  scheme

 Retail price increase
                         Money




                                            Source: David Jacobs
FIT financing in Malaysia – limited electricity price
increase




                          Source: Kettha 2010
FIT Fund in Malaysia
FIT financing cost in Germany (additional costs per kWh)




Source: BMU 2011
International FIT financing?
– The future of international climate talks?
                                    G TF fin c gflo s
                                     E IT an in w




     S u e: D C A "G TF ", A 2010
      o rc B C , E IT pril
Capacity caps
Capacity cap

 • Capacity cap might be necessary to control costs (limited number
 of project)

 • To control installed capacity (in line with central planning in
 monopolized electricity markets)

 • E.g. tariff payment for first 400 MW wind energy, first 100 MW
 geothermal, and first 50 MW solar PV

 • In this case: Project size should also be limited

 • Application process needs to be regulated (“first-come, first-
 served”)

 • Online application to avoid fraude? – Malaysia

Source: Mendonca et al. 2009
Capped feed-in tariff in Kenya (2009)

     • Tariff payment for 15 years
     • Rate setting based on generation costs
     • Support of least cost RES technologies


                                     Mainland Price
               Technology                             Capacity cap
                                        ($/kWh)

        Wind                             $0.09          150 MW
        Biomass (firm and non-          $0.045-         200 MW
        firm)                            0.07
        Hydro (firm and non             $0.06-          150 MW
        firm)                            0.12




31
Capped feed-in tariff in Ecuador

     • Tariff payment for 12 years
     • Rate setting based on generation costs
     • Cap: 2% of installed capacity



                  Technology                    Mainland Price ($/kWh)

      Wind                                              $0.09
      Photovoltaic                                      $0.52
      Biomass and biogas                                $0.10
      Geothermal                                        $0.09
      Small-hydro up to 5 MW                            $0.06
      Small-hydro 5 MW-10 MW                            $0.05



32
Annual Quota on RE Capacity in Malaysia (MW)

                                                                              Total per
    Year             Biomass   Biogas   Mini-Hydro   Solar PV   Solid Waste    Annum
    2011              110       20         60           9           20          219
    2012               40       15         50          11           30          146
    2013               50       15         60          13           40          178
    2014               60       25         60          15           50          210
    2015               70       25         60          17           60          232
    2016               80       25         60          19           40          224
    2017               90       30         50          21           40          231
    2018               100      30         40          24           30          224
    2019               100      30         30          28           30          218
    2020              100       25         20          33           20          198
      :                                                 :            :            :
    2030                                               280          2           282
      :                                                 :            :            :
    2040                                               850          2           852
      :                                                 :            :            :
    2050                                              1,350         2          1,352

Source: MBIPV 2010
Annual Quota on RE Capacity in Malaysia (MW)




         Source: MBIPV 2010
Capacity cap

• Disadvantages:
   •   “Stop-and-go” investment cycles – difficulty to establish a national
       industry (similar to tender)
   •   Unsustainable market development
Local content
 requirement
Local content requirement

  • Several countries have introduced local content requirements in
  national support mechanisms, i.e. obligations to produce a certain
  share of renewable energy equipment locally/nationally (e.g. Spain,
  China, India, Argentina - Chubut, Ontario - Canada, Malaysia, Italy)

  • These requirements can be implemented in national feed-in tariff
  mechanisms
        • Establish a national renewable energy industry
        • Take advantage of positive macro-economic effects

Source: Mendonca et al. 2009
Local content requirement Chubut

• Province in Argentina:
• Wind energy law 2005, Article 4, states:

• „... to enjoy this benefit, the wind mills installed have to comply with a timeline detailed
further below of including components made or assembled in the Province of Chubut:
a) As from 1 January 1999: 10%
b) As from 1 January 2001: 30%
c) As from 1 January 2003: 60%
d) As from 1 January 2005: 80%
e) As from 1 January 2007: 100%“

• Outcome: low incentive and rigid timeline impended wind power
development in Argentina
Local content requirement Ontario

• Local content wind: 25%; 50% in 2012

• Local content solar: 40-50%; 60% in 2011
Local content requirement Ontario

 • Complex definitions needed (Ontario): Solar PV

Designated Activity                                 Qualifying

                                                    Percentage

Silicon that has been used as input to solar           10%
photovoltaic cells manufactured in an Ontario
refinery.


Silicon ingots and wafer, where silicon ingots         12%
have been cast in Ontario and wafers have been
cut from the casting by a saw in Ontario.


The crystalline silicon solar photovoltaic cells,      10%
where there active photovoltaic layer(s) have
been formed in Ontario.
Local content requirement Ontario
 Solar photovoltaic modules (i.e. Panels), where      13%
 the electrical connections between the solar
 cells have been made in Ontario and the solar
 photovoltaic module materials have been
 encapsulated in Ontario.
 Inverter, where the assembly, final wiring and        9%
 testing has been done in Ontario.
 Mounting systems, where the structural                9%
 components of the fixed or moving mounting
 systems have been entirely machined or
 formed or cast in Ontario. ….



 Wiring and electrical hardware that is not part      10%
 of other Designated Activities (i.e. items 1, 2, 3
 and 5 of this table) sourced from an Ontario
 Supplier.
 All on-site and off-site labour and services. For    27%
 greater certainty, this Designated Activity shall
 apply in respect of all Contract Facilities.
 Total                                                100%
Local content requirement

• Problem: potential confliction with international trade rules (WTO)

• Malaysia: Adder for nationally produced equipment:
Malaysian tariff structure for solar PV




              Source: Kettha 2010
International “worst”
       practice
International “worst” practise

 • Low tariff = no tariff (e.g. Argentina: Premium tariff payment of 0.37
 €cent/kWh for wind energy)
    • Assessment report can help to correct tariff level

 • Unnecessary high tariffs
    • PV in Spain; PV in Czech Republic
    • High rates of return; attracts speculation; unsustainable market

       growth

 • Short payment durations (annual changes)
    • Germany until 1999; Spain until 2004, some Indian provinces

 •Size specific tariffs (huge differences in tariff levels)
    • Spain
Books on FIT design

                       The Evolution of FITs in
                      Germany, Spain and France
                      http://www.ashgate.com/default.aspx?pa
                      ge=637&title_id=11456&edition_id=1496
                                   0&calcTitle=1




                          The feed-in tariff
                             handbook
                      http://www.earthscan.co.uk/?tabi
                                 d=92822
Online policy advice: How to design good feed-in tariffs?


                                 Online policy advice:
                               Make your own FIT law
                                 www.futurepolicy.org
Thank you for your attention!!!


Dr. des. David Jacobs I Director Renewable Energy
IFOK GmbH
Reinhardtstraße 58
10117 Berlin


Tel.: +49 30 536077-27
E-Mail: david.jacobs@ifok.de
David.jacobs@gmx.de
www.ifok.de




© 2010, IFOK GmbH
IFOK behält sich alle Urheber-, Marken-, Leistungsschutz- sowie sonstigen Rechte an den Inhalten der Präsentation vor. Ohne schriftliche
Einwilligung durch IFOK dürfen diese Inhalte oder Teile davon weder bearbeitet oder verwertet noch Dritten zugänglich gemacht werden.
Titel

Seite 48

Course on Regulation and Sustainable Energy in Developing Countries - Session 4

  • 1.
    Feed-in tariffs –Design options and case studies for developing countries Leonardo Webinar 26 January 2012 Dr. des. David Jacobs Director Renewable Energy, IFOK GmbH Course on Regulation and Sustainable Energy in Developing Countries – Session 4 www.leonardo-energy.org/course-regulation-and-sustainable-energy-developing- countries
  • 2.
    Agenda FIT design andcase studies: Feed-in tariff calculation FIT financing Capacity caps Local content rules
  • 3.
    FIT Countries 2010 Countries with state FIT policy Countries with national FIT policy Source: REN21, Renewables 2010 Global Status Report 3
  • 4.
    Basic feed-in tariffdesign • Purchase obligation • “Independent” from power demand • Fixed tariff payment based on the actual power generation costs • Price setting will be discussed in session 4 • Long duration of tariff payment
  • 5.
  • 6.
    Tariff calculation methodology Early FITs (1970-1990s): Avoided costs Benchmark: cost for conventionally produced electricity Tariff level is only “right” coincidentally (under- or over-compensation) • E.g. Nicaragua, Tanzania
  • 7.
    Tariff calculation methodology • Tariff calculation based on technology specific generation costs + “reasonable” rates of return • Don’t use “avoided costs” as point of reference • Cost factors: • Investment costs (material and capital costs); Grid- related and administrative costs (including grid connection, costs for licensing procedure; Operation and maintenance costs; Fuels costs (biomass and biogas)
  • 8.
    Rate setting process Different jurisdictions use different methodologies for setting FIT rates. Recent research reviewed several models for rate setting, results indicate: • Most jurisdictions use similar approaches (even if inputs and assumptions vary):  Discounted Cash Flow (DCF), after-tax analysis – Discounts to present value the estimated annual cash flows to equity investors
  • 9.
    Building a feed-intariff rate calculator Goal is to reach an appropriate rate that is high enough to spur renewable energy development while at the same time not so high as to provide windfall profits to project owners. Tradeoffs exist: • Ease of use vs. complexity • High-level representation vs. detailed analysis • Granularity vs. time investment
  • 10.
    Tariff calculation methodology • Targeted IRR (Internal rate of return) • In the EU, feed-in tariffs target at an internal rate of return of 5-9 percent (certain jurisdictions use return on equity) • In developing countries, the targeted IRR usually needs to be higher (10-20 percent) • Public investment (monopolist, often without profit interest); or private IPPs (profitability important)? • Similar profitability for renewable energy projects needed as for convention energy market
  • 11.
    Figure 4: EquityIRR expectation in developing countries: Equity IRR expectation in developing countries 25% 20% 15% 10% 5% 0% Infrastructure Technology Political risk Reg. Risk, soft Counterparty Currency Infrastructure investment risk (missing political risk, risk safety cushion investment (developed track record) transparency, (developing world) legal world) framework Source. Fulton et al. 2011
  • 12.
    Tariff calculation methodology •Assumed capital structure • Ratio of debt and equity (80 to 20 in Netherlands; 70 to 30 in Ontario (Canada)) • Germany; different debt-equity ratio depending on each technology (reflecting their risk profile) • South Africa: 70:30 • Higher equity share in other developing countries? • Interest rate for the debt? (international and national analysis needed) • Generally, debt term (duration) equals duration of feed-in tariff payment (average of 20 years)
  • 13.
    Tariff calculation methodology •Tax treatment • Pre-tax calculation (taking advantages and disadvantages from national taxation scheme into account)  Post-tax: Germany, because not significant available tax benefits, and because tax liabilities vary across ownership and investor types and are difficult to generalize – also used in Malaysia  Accelerated depreciation factored in (e.g. India)
  • 14.
    Tariff calculation methodology •Treatment of inflation (indexation) • Necessary because of long-term tariff payment (especially in developing countries with high inflation rates) • Usually applied to the investment share that is related to O&M costs
  • 15.
    Tariff calculation –South Africa (2009 vs. 2011)
  • 16.
    Tariff calculation assumptions– Malaysia (2010) Source: Kettha 2010
  • 17.
    Tariff calculation inGermany: Input data for wind energy • Medium transparency in Germany Provision of Equity share: 25% Return on equity (100% -location): 12% capital Share of debt: 75 % Interest on debt: 5 % , or 5,5 % Time period in question 20 years Inflation rate 2% p.a. Specific investment costs 60 and 80 % - location: 1.756 €/kW 100 % location: 1,463 €/kW 120% aand 150 % - location: 1, 336 €/kW Annual costs of operation Year 1-10: 2.19 ct/kWh Year 11-20: 2.49 ct/kWh Source: BMU 2011
  • 18.
    Tools for tariffcalculation RET Screen http://www.retscreen.net/ CREST model from NREL https://financere.nrel.gov/finance/content/CREST-model Adoptation to national context is required (e.g. tax burdens and investment incentives)
  • 19.
    Tools for tariffcalculation – CREST from NREL (inputs)
  • 20.
    Tools for tariffcalculation – CREST from NREL (cash flow)
  • 21.
  • 22.
    Financing mechanism -Germany Financing mechanism in liberalized electricity markets Financing trough “burden sharing” between all electricity consumers
  • 23.
    Differences in emergingeconomies and developing countries • low electricity costs • little acceptance of electricity price increases Artificially low Subsidies No interna- electricity for lization of prices = high conventional negative cost difference power external costs with renewables
  • 24.
    Combined financing –Taiwan • Add additional financing to the national FIT fund (levy on producers from conventional electricity) • Increase the retail electricity price by a certain share (after general elections next year) Conventional Money electricity producers Payment for producers Renewable Energy Fund under the feed-in tariff Money (FIT Fund) scheme Retail price increase Money Source: David Jacobs
  • 25.
    FIT financing inMalaysia – limited electricity price increase Source: Kettha 2010
  • 26.
    FIT Fund inMalaysia
  • 27.
    FIT financing costin Germany (additional costs per kWh) Source: BMU 2011
  • 28.
    International FIT financing? –The future of international climate talks? G TF fin c gflo s E IT an in w S u e: D C A "G TF ", A 2010 o rc B C , E IT pril
  • 29.
  • 30.
    Capacity cap •Capacity cap might be necessary to control costs (limited number of project) • To control installed capacity (in line with central planning in monopolized electricity markets) • E.g. tariff payment for first 400 MW wind energy, first 100 MW geothermal, and first 50 MW solar PV • In this case: Project size should also be limited • Application process needs to be regulated (“first-come, first- served”) • Online application to avoid fraude? – Malaysia Source: Mendonca et al. 2009
  • 31.
    Capped feed-in tariffin Kenya (2009) • Tariff payment for 15 years • Rate setting based on generation costs • Support of least cost RES technologies Mainland Price Technology Capacity cap ($/kWh) Wind $0.09 150 MW Biomass (firm and non- $0.045- 200 MW firm) 0.07 Hydro (firm and non $0.06- 150 MW firm) 0.12 31
  • 32.
    Capped feed-in tariffin Ecuador • Tariff payment for 12 years • Rate setting based on generation costs • Cap: 2% of installed capacity Technology Mainland Price ($/kWh) Wind $0.09 Photovoltaic $0.52 Biomass and biogas $0.10 Geothermal $0.09 Small-hydro up to 5 MW $0.06 Small-hydro 5 MW-10 MW $0.05 32
  • 33.
    Annual Quota onRE Capacity in Malaysia (MW) Total per Year Biomass Biogas Mini-Hydro Solar PV Solid Waste Annum 2011 110 20 60 9 20 219 2012 40 15 50 11 30 146 2013 50 15 60 13 40 178 2014 60 25 60 15 50 210 2015 70 25 60 17 60 232 2016 80 25 60 19 40 224 2017 90 30 50 21 40 231 2018 100 30 40 24 30 224 2019 100 30 30 28 30 218 2020 100 25 20 33 20 198 : : : : 2030 280 2 282 : : : : 2040 850 2 852 : : : : 2050 1,350 2 1,352 Source: MBIPV 2010
  • 34.
    Annual Quota onRE Capacity in Malaysia (MW) Source: MBIPV 2010
  • 35.
    Capacity cap • Disadvantages: • “Stop-and-go” investment cycles – difficulty to establish a national industry (similar to tender) • Unsustainable market development
  • 36.
  • 37.
    Local content requirement • Several countries have introduced local content requirements in national support mechanisms, i.e. obligations to produce a certain share of renewable energy equipment locally/nationally (e.g. Spain, China, India, Argentina - Chubut, Ontario - Canada, Malaysia, Italy) • These requirements can be implemented in national feed-in tariff mechanisms • Establish a national renewable energy industry • Take advantage of positive macro-economic effects Source: Mendonca et al. 2009
  • 38.
    Local content requirementChubut • Province in Argentina: • Wind energy law 2005, Article 4, states: • „... to enjoy this benefit, the wind mills installed have to comply with a timeline detailed further below of including components made or assembled in the Province of Chubut: a) As from 1 January 1999: 10% b) As from 1 January 2001: 30% c) As from 1 January 2003: 60% d) As from 1 January 2005: 80% e) As from 1 January 2007: 100%“ • Outcome: low incentive and rigid timeline impended wind power development in Argentina
  • 39.
    Local content requirementOntario • Local content wind: 25%; 50% in 2012 • Local content solar: 40-50%; 60% in 2011
  • 40.
    Local content requirementOntario • Complex definitions needed (Ontario): Solar PV Designated Activity Qualifying Percentage Silicon that has been used as input to solar 10% photovoltaic cells manufactured in an Ontario refinery. Silicon ingots and wafer, where silicon ingots 12% have been cast in Ontario and wafers have been cut from the casting by a saw in Ontario. The crystalline silicon solar photovoltaic cells, 10% where there active photovoltaic layer(s) have been formed in Ontario.
  • 41.
    Local content requirementOntario Solar photovoltaic modules (i.e. Panels), where 13% the electrical connections between the solar cells have been made in Ontario and the solar photovoltaic module materials have been encapsulated in Ontario. Inverter, where the assembly, final wiring and 9% testing has been done in Ontario. Mounting systems, where the structural 9% components of the fixed or moving mounting systems have been entirely machined or formed or cast in Ontario. …. Wiring and electrical hardware that is not part 10% of other Designated Activities (i.e. items 1, 2, 3 and 5 of this table) sourced from an Ontario Supplier. All on-site and off-site labour and services. For 27% greater certainty, this Designated Activity shall apply in respect of all Contract Facilities. Total 100%
  • 42.
    Local content requirement •Problem: potential confliction with international trade rules (WTO) • Malaysia: Adder for nationally produced equipment:
  • 43.
    Malaysian tariff structurefor solar PV Source: Kettha 2010
  • 44.
  • 45.
    International “worst” practise • Low tariff = no tariff (e.g. Argentina: Premium tariff payment of 0.37 €cent/kWh for wind energy) • Assessment report can help to correct tariff level • Unnecessary high tariffs • PV in Spain; PV in Czech Republic • High rates of return; attracts speculation; unsustainable market growth • Short payment durations (annual changes) • Germany until 1999; Spain until 2004, some Indian provinces •Size specific tariffs (huge differences in tariff levels) • Spain
  • 46.
    Books on FITdesign The Evolution of FITs in Germany, Spain and France http://www.ashgate.com/default.aspx?pa ge=637&title_id=11456&edition_id=1496 0&calcTitle=1 The feed-in tariff handbook http://www.earthscan.co.uk/?tabi d=92822
  • 47.
    Online policy advice:How to design good feed-in tariffs? Online policy advice: Make your own FIT law www.futurepolicy.org
  • 48.
    Thank you foryour attention!!! Dr. des. David Jacobs I Director Renewable Energy IFOK GmbH Reinhardtstraße 58 10117 Berlin Tel.: +49 30 536077-27 E-Mail: david.jacobs@ifok.de David.jacobs@gmx.de www.ifok.de © 2010, IFOK GmbH IFOK behält sich alle Urheber-, Marken-, Leistungsschutz- sowie sonstigen Rechte an den Inhalten der Präsentation vor. Ohne schriftliche Einwilligung durch IFOK dürfen diese Inhalte oder Teile davon weder bearbeitet oder verwertet noch Dritten zugänglich gemacht werden. Titel Seite 48