This letter from INEOS Chemicals Grangemouth Ltd thanks Engenda DTEC for their work on a turnaround project at the Grangemouth site. The project involved work on columns, safety valves, vessels and pipework and was completed successfully within the planned 20,000 man-hours scope and budget. An additional 250 hours of unplanned work was also completed without going over the agreed manning levels. The letter praises the proactive workforce and notes Engenda DTEC may be considered for even larger future projects at the Grangemouth site.