SlideShare a Scribd company logo
HR Function in Project-Oriented Organizations and the Problem
of
its Internal Consistency
Katarzyna Piwowar-Sulej
Wroclaw University of Economics, Wroclaw, Poland
[email protected]
Abstract: Nowadays, repetitive or routine activities are slowly
giving way to unique and complicated activities – i.e.
projects. Many enterprises implement the so-called management
by projects (MBP). The enterprises following such an
approach are referred to as project-oriented organizations
(PORORs). A project and an organization cannot exist without
appropriate human capital. This capital is developed in the
process of HR function fulfillment (R&S, training, HR
appraisal,
remuneration and HR flow). In every enterprise, which
implements MBP, HR function takes a two-way course: in an
organization-wide perspective (general HR function) and within
the framework of a particular project (HR function in
projects). The objective of the article is to answer the following
research questions: Q1: Should the same operational
schemes in both “courses” of HR function be used from the
perspective of an effective functioning of project-oriented
organizations? Q2: What kind of gaps occur in the area of HR
function internal consistency within the analyzed
organizations? The article presents the results of empirical
studies carried out in 2014 and 2015 in 100 project-oriented
organizations. The methodology for measuring HR function’s
internal consistency was proposed. Data triangulation was
applied in the research process. The conducted studies indicate
that the multidimensional consistency of the personnel
function results in an increased efficiency of not only projects,
but also the entire organization. The surveyed organizations
present higher general HR function consistency than the HR
function in projects. Moreover, some gaps in consistency
between both personnel function courses were indicated. The
presented results of empirical studies provide knowledge
about the specificity of project-oriented organizations. The
presented discussion can also become the foundation for
developing further research.
Keywords: HRM, HR function, project-oriented organization,
management challenges, management by projects
1. Introduction
A thesis can be put forward that since the 90s of the 20
th
century the interest in the way people function
within organizational structures has been increasing
continuously. Therefore, managing people (human
resources management, HRM) can be considered as the key
management area. Such management is identified
with personnel function (HR function), which covers tasks
related to attracting workers, adequate
development of their capital and taking advantage of it in the
course of any organization functioning. Currently
this function is focused on achieving organizational goals along
with meeting its employees’ needs. Its
development remains within the responsibility of human
resources department as a strategic partner.
The interest in project management issues is also continuously
growing. The analyses cover the application of
specific knowledge, skills and tools in terms of operations
performed in the course of carried out projects.
Nowadays, not only launching new products or services is
implemented in the form of projects. Project-
oriented approach, based on appointing interdisciplinary teams
and using tools typical for project
management, is extensively applied within the framework of
managing changes (Young, 2006). These
enterprises which take advantage of such approach are referred
to as project-oriented organizations. Among
them there are project-based organizations – in which project
implementation remains their core business –
and also organizations focused on repetitive actions (e.g. banks
or manufacturing companies) which, however,
implement projects.
Task-oriented organizational structure represents the factor
which differentiates the analyzed organizations
from the so-called traditional enterprises. In practice, pure
project-based structures – i.e. the ones within
which no other permanent units have been established – occur
very rarely. Therefore, the usual alternative to
this type of structure is the matrix structure, in which project
teams are formed and dissolved (Young, 2003).
In this case the complexity of personnel function is increasing.
HRM has a two-way course: on the one hand, in
the general organizational field, and on the other, within a given
project. The two ways of the HR function
have been respectively called the general personnel function
and the personnel function in project. In the
course of this function development in project-oriented
organizations, “new” subjects, absent in traditional
organizations, such as project managers gain more importance.
238
Katarzyna Piwowar-Sulej
As Huselid (2005) points out, a HRM system, based on
complementary practices, is the source of lasting
competitive advantage in an enterprise. The subject literature
presents various types of fit within the
framework of HRM. The problem of HRM consistency is
broadly discussed in the literature on traditional
organizations (e.g. Boon et al, 2007; Kepes and Delery, 2007;
Banks, 2014). Due to the two-way course of
personnel function in project-oriented organizations, internal fit
has been recognized as particularly important.
Even though the subject literature discussing project
management calls for the standardization of operations
in the subsequent projects in order to develop project
management maturity (Crawford, 2014), it seems,
however, that the consistency (fit) of activities taken up in
projects only, along with the existing discrepancies
between the practices applied in the general personnel function
and a personnel function in project , shall
result in some organizational disorder. The latter, on the other
hand, has negative impact on the effectiveness
of the entire enterprise. Lundy and Crowling (2000) are of the
opinion that internal effectiveness in an
enterprise results from implementing and establishing
managerial mechanisms along with maintaining
consistency, harmony and feasibility
.
Consistency can be understood as harmony or compatibility, the
condition of cohering or holding together and
retaining form, solidity or firmness (Dictionary.com). Nadler
and Tushman (1980) define consistency or fit as
the level at which needs, requirements, goals, the construction
of one element remain in compliance with the
needs, requirements, goals, structure of another component.
It was observed that the discussion presented in subject
literature on human resources management in a
project-oriented organization persists, to some extent, “in
isolation” from the problem of organizational
structure. Furthermore, so far the issue of personnel function
consistency, in the specific functioning
conditions of project-oriented organizations, has not been
discussed. The purpose of the article was defined,
i.e. answering the following research questions:
Q1: Should the same operational schemes in both “courses” of
HR function be used from the
perspective of effective functioning of project-oriented
organizations?
Q2: What kind of gaps occur in the area of personnel function
internal consistency in the analyzed
organizations?
In order to carry out the purpose defined in this way the
relationships between the two courses of personnel
function were discussed. The theory referring to HRM
consistency was also explained. Finally, the results of the
empirical research were discussed. The above-mentioned
research constitutes the component of a broader
research project covering methods for personnel function
implementation in project-oriented organizations.
The research project was financed by The National Science
Centre Poland (DEC-2013/09/D/HS4/00566).
2. Literature Background
2.1 HR function in a traditional organization vs. HR function in
a project-oriented organization
The discussion on HRM has been going on in the subject
literature for many years. It is characterized by the
diversity of definitions referring to the problem of human
resources management, as well as a the broad
spectrum of activities which could be assigned to this concept.
It was adopted that every organization is
characterized by a certain set of basic physical functions,
indispensable in achieving its goals. One of them is a
personnel function which refers to all employees and covers the
tasks usually carried out by HR department.
As it has already been pointed out, its primary goal is to ensure
proper staffing in order to achieve the results
identified by an enterprise. In the 50s of the 20
th
century this function was still not perceived globally and no
need was observed to consider the relationships occurring
between its many components.
The author – having considered the relations occurring between
the particular HR function components –
suggests its presentation in the form illustrated in figure 1. It
was adopted that the recruitment and selection
of candidates (R&S) is not finalized while signing an
employment agreement or a civil contract. In practice the
so-called trial period agreements are frequently signed. During
such time an employee goes through a break-in
period and his/her practical competences are verified, therefore
he/she is still subject to the selection process.
The term of HR flow is understood as promotions (horizontal,
vertical), transfers (organizational unit changing
while remaining at the same or similar position), demotions and
layoffs. The feedbacks occurring between
personnel function components are marked by a dotted line. For
example, staff leaving implies the need for
239
Katarzyna Piwowar-Sulej
personnel recruitment. A dotted line on the figure below
illustrates that within the framework of R&S – and
specifically while breaking into work – adequate training are
provided. It refers to mandatory training
associated with signing employment agreements. (e.g. trainings
in occupational health and safety), but also
additional onboarding training.
Figure 1: Model presentation of a HR function in a traditional
organization
Source: Piwowar-Sulej (2016)
At this point it is worth emphasizing that the presented
perspective is a model oriented one. The result of HR
appraisal, either formal or informal, should imply offering
adequate training in terms of remuneration and
transfer.
On the basis of literature studies combining the problems of
project management and HRM two approaches to
personnel function presentation were identified. The dominating
practice is manifested in focusing on
personnel function only as representing the set of activities
addressed to project team members (see Clark and
Colling, 2005; Melnic and Puiu, 2011). The second and also
quite uncommon approach – which precursors are
Huemann and Keegan and Turner (2007) – consists in noticing
two courses of this function. The above-
mentioned authors prepared a graphic presentation of
differences occurring between personnel function in a
traditional organization (managed in a “classical” way, where
project-oriented approach is not applied) and a
project-oriented one (see figure 2).
Figure 2 shows that a project involves people already employed
in an organization. However, in business
practice both recruitment process and the selection of
candidates from an external labor market can be
arranged specifically for the needs of a particular project.
Figure 2: HRM in the project-oriented company vs. HRM in the
classically managed (traditional) enterprise
Source: Huemann and Keegan and Turner (2007)
240
Katarzyna Piwowar-Sulej
As it has been indicated in the introduction to the study an
organizational structure determines the form of
personnel function. Personnel function in a project-oriented
organization takes a two-way course. Personnel
function in a project is made up of the same components as the
personnel function at the general
organizational level. There are mutual relations between the
particular components of a personnel function in
a project and a general personnel function, as shown in figure 3.
They are strictly connected with the problem
of internal HRM fit.
Figure 3: Two-way course of the personnel function in a
project-oriented organization
Source: Piwowar-Sulej (2014)
2.2 The problem of HRM internal consistency
Scientific literature distinguishes between four different types
of fit in terms of HRM, i.e. (Wood, 1999):
a) Strategic fit: the relationship between HRM system and
business strategy. It occurs when HRM practices
concentrate on stimulating people to meet organizational goals.
b) Internal fit: the relationship between various HRM practices
in the entire HRM system. Following this
approach HR system should remain internally consistent.
c) Organizational fit: the relationship between HRM system and
other systems in an organization (e.g.
technological, manufacturing, control systems).
d) Environmental fit: related to HRM system and external
environment. Following this logic, HRM system
should be fit to changes in the environment, as well as
principles and expectations of this environment
against an organization.
Within the framework of human resources strategic management
concept the need of so-called vertical
(strategic) integration is primarily emphasized. The author is of
the opinion that all of the above -mentioned
types of HRM fit are equally important. Due to the specific
nature of personnel function in a project-oriented
organization it was decided that the problem of horizontal
(internal) fit regarding HR practices is worth
discussing in more detail, i.e. having considered the
relationships marked with a dotted line in figure 3.
Recruitment and selection were recognized as major activities
carried out within the framework of personnel
function. It is justified by the fact that the decisions referring to
employment of a candidate presenting a
particular human capital remain fundamental for taking up
actions in the course of the subsequent HRM
stages.
A project team member can be recruited from either internal or
external labor market. In the first case a
temporary transfer of an employee from a permanent
organizational unit to a project takes place. The general
241
Katarzyna Piwowar-Sulej
personnel function stage, referred to as HR flow, provides
“resources” at the stage of staff recruitment for
project purposes.
Attracting project staff from external labor market can take the
same forms as in the case of recruiting
candidates for positions in an enterprise permanent structure. It
consists in applying appropriate R&S methods
or techniques. Moreover, when an employment agreement is
concluded – in the light of Polish labor law –
employee’s position in an organizational permanent unit has to
be defined. In this way the relationship
between recruiting people for organizations and attracting
project team members becomes visible.
After project completion the stage of team members’ transfer
takes place. They can be recruited to the next
project or return to their functional department. Once the
project is finalized an employee can be offered a
position in an organizational permanent structure.
The above presented examples illustrate objective relations
occurring between the stage of staff transfer in a
project and also R&S and HR flow stages in the general
organizational structure. Therefore, how should
internal consistency of the personnel function be approached in
the analyzed organizations? The problem of
interest for the author refers primarily to:
a. internal consistency within each course of the discussed
function,
b. consistency between both courses of the personnel function.
Internal consistency within a particular course takes the form of
making staff oriented decisions based on the
results of an employee appraisal. Training should result from
the needs defined in the course of periodical staff
appraisal. The consistency between personnel function courses
means, on the other hand, that the practices
applied within the framework of a general personnel function
and a personnel function in project remain
mutually fit. Not only are they linked by the relationships
presented in figure 3, but also use similar methods in
both courses within the particular stages of personnel functions
implementation. It is not about applying
exactly the same techniques e.g. candidates’ selection for work
on positions in an organizational permanent
structure and techniques for project members selection. It is
about the same rules applying in both identified
cases. For example, if the selection of candidates for the
positions in an enterprise permanent structure takes
advantage of recruitment addressed to a wide range of people,
the same rule should apply in case of projects.
It ensures order and the sense of justice. Furthermore – since
the organizational strategy is implemented
based on a project-oriented approach – the general personnel
function should support projects. Such
adjustment can take the form of e.g. checking at the stage of
selecting candidates’ suitability for project-
oriented work in an enterprise. These and other relationships
between the particular personnel function
components were subject to empirical verification.
3. Research methodology
As it has already been mentioned in the introduction to the
study, so far no scientific debate has been going on
regarding personnel function consistency in project-oriented
organizations. On the other hand, the research
on HRM consistency in traditional organizations has, so far,
been mainly applying quantitative methods such
as: reliability analysis, factor and cluster analysis, multiple
regression analysis, sequence analysis (Boon, 2008).
An alternative approach to research methods in this area of
knowledge was recognized as desirable.
Within the framework of empirical research an idiographic
approach, based on purposive sample, was used
(for more see: Piwowar-Sulej, 2016). It covered 100 enterprises
based in Poland and applying a project-
oriented approach. The research sample was balanced, i.e.
covered an equal number of project-based
enterprises (with projects as their core business) and the other
ones which conduct projects. In the process of
the research sample construction it was considered that while a
defined number of project-based enterprises
is operating on the market, it is difficult to identify the other
organizations which apply a project-oriented
approach. There are no objective registers to define the entire
population of project-oriented organizations
and enable representative sampling. The study covered
enterprises offering a position or a function (role) of a
project manager. An additional condition to include an
enterprise in a research sample was HR department
presence in an enterprise structure. Thus, medium and large
enterprises participated in the research.
242
Katarzyna Piwowar-Sulej
Having considered the above-mentioned problems in obtaining a
representative sample, along with an
intention to ensure higher quality of the conducted research,
data triangulation was used in the research
process. Structured interview (using PAPI method) with a
project manager, project executor and HR specialist
was performed in each enterprise.
Research tools were developed in the form of structured
interview questionnaires. The questionnaires
addressed to each group of respondents contained 300
questions. Due to size limitations of the article and its
purpose, the author decided to focus on the research part which
referred directly to the problem of personnel
function consistency. 24 questions/statements (see table 1) were
addressed to each group of respondents,
which referred directly to internal consistency of the personnel
function. The respondents had to choose the
answer (“yes” or “now”). Kruskal-Wallis test was applied to
check the convergence level of the answers
provided by representatives of various respondent groups. It
turned out that in case of 17 out of 24 questions
the level of significance was less than 0,05, which indicates that
the respondents were providing significantly
different answers to a particular question. It became a reason
for the use in the research process additionally
in-depth interview method. The answers to research questions
will be provided in the next part of the study.
Table 1: Hypothesis test summary (Kruskal-Wallis test for
independent samples)
No. Null hypothesis Significance Decision
1.
A project team member is brought into operation in a planned
manner (formal information
about the project objective, project implementation
methodology, methods of work, duties).
,007 Reject null
hypothesis
2.
During staff employment in an enterprise their suitability for
project-oriented work is taken into
account.
0,804 Accept null
hypothesis
3.
The system of periodical appraisal, taking project-oriented work
into account, functions in an
enterprise.
,174 Accept null
hypothesis
4.
Decisions about employees’ remuneration result from periodical
appraisals in an enterprise. ,000 Reject null
hypothesis
5.
Decisions about training result from periodical appraisals in an
enterprise. ,000 Reject null
hypothesis
6.
Decisions about employee promotions result from periodical
appraisals in an enterprise. ,386 Accept null
hypothesis
7.
Decisions about moving an employee from an organizational
structure to a project result from
periodical appraisals in an enterprise.
,000 Reject null
hypothesis
8.
Training offered in the workplace is necessary for the
successful implementation of a particular
project.
,013 Reject null
hypothesis
9.
During a long-term project the decision is made about a team
member training based on
his/her work appraisal.
,893 Accept null
hypothesis
10.
Project-oriented training is organized in the workplace. ,000
Reject null
hypothesis
11.
The analysis of training needs in the company is based on
employee appraisal. ,014 Reject null
hypothesis
12.
After finalizing training its effectiveness is analyzed. ,006
Reject null
hypothesis
13.
Base salary level (including e.g. pay rise) depends on the
variety of roles performed by a
particular employee.
,046 Reject null
hypothesis
14.
Base salary level (including e.g. pay rise) depends on
employee’s achievements in projects. ,000 Reject null
hypothesis
15.
Career paths in the enterprise take into account project-oriented
career (offer opportunities
not only for climbing the career ladder from an administration
clerk position to a department
manager, but also for taking the position/function of a project
manager or specialist in project
management office).
,006 Reject null
hypothesis
16.
Success in projects is taken into account while making decisions
about an internal promotion in
a department where an employee works on a daily basis.
,093 Accept null
hypothesis
17.
Recruitment to the enterprise and project team members’
recruitment follows the same
general principles.
,003 Reject null
hypothesis
18.
The selection of candidates for enterprise employees and the
selection of project team
members is performed based on the same professional methods.
,000 Reject null
hypothesis
19.
A new employee and a new project team member breaks into
work in a planned manner (there
is a formal onboarding process).
,173 Accept null
hypothesis
20.
New employees representing different departments are informed
about the possibility of
participation in projects.
,017 Reject null
hypothesis
21.
Formal appraisal system for projects is applied based on the
same methods used in the
appraisal system in permanent organizational units (e.g.
appraisal based on competencies,
management by objectives, 360 degree feedback).
,000 Reject null
hypothesis
22.
Decisions about salaries, training and promotions result from
periodical appraisals in an
enterprise.
,001 Reject null
hypothesis
243
Katarzyna Piwowar-Sulej
23.
Decisions about project team members’ salaries and role
changes result from periodical HR
appraisals in a particular project.
,280 Accept null
hypothesis
24.
All employees have access to information about the principles
of participation in projects. ,001 Reject null
hypothesis
The presentation of asymptomatic significance. The level of
significance is ,05.
Source: author’s research project
4. The results of empirical studies with reference to the research
questions
Q1: Should the same operational schemes in both “courses” of
personnel function be used from the
perspective of an effective functioning of project-oriented
organizations?
Having taken into account the first research question (Q1) the
author distinguished two detailed areas of
organizational effectiveness, i.e.:
A database of common answers provided by all groups of
respondents was established for the purposes of the
conducted analysis. Respondents from 88% of the studied
organizations stated unanimously that
multidimensional consistency increases the effectiveness of the
entire organization (see table 2). Internal
personnel function consistency increases the effectiveness of
personnel function fulfillment and project
success probability in opinion of respondents from 85% of the
organizations.
Table 2: The impact areas of personnel function internal
consistency
Number of enterprises
(n=100)
Statement
Total
(n=100)
Internal personnel function consistency increases project
success probability.
85 (85%)
Internal personnel function consistency increases the
effectiveness of personnel function fulfillment.
85 (85%)
Internal personnel function consistency increases the entire
organization effectiveness.
88 (88%)
Source: author’s research project
Q2: What kind of gaps occur in the area of the personnel
function internal consistency in the analyzed
organizations?
The survey consisted of 24 questions focused exclusively on
diagnosing internal consistency level of the
personnel function. The maximum number of positive responses
was thus 24 (24 questions to which the
respondents answered unanimously “yes”). The highest possible
level of personnel function consistency – in
accordance with the provided responses – was not achieved in
any of the analyzed organizations. The
arithmetic mean was 8,74, at standard deviation of 4,87. The
median was set at the level of 9, lower quartile –
5, upper quartile – 12. Based on the statistical measures one can
state that the personnel function is not
consistent in the majority of organizations. Moreover, in-depth
data analysis confirmed:
a. higher internal consistency of the general personnel function
than the project-oriented personnel
function,
b. some shortcomings in the consistency of both personnel
function courses (see table 3).
244
Katarzyna Piwowar-Sulej
Table 3: Main shortcomings in the personnel function internal
consistency – summary of the empirical
research results
Stage of HR function Revealed shortcomings
Recruitment and selection
(R&S)
There are certain discrepancies in the area of recruitment
between both personnel function courses.
Recruitment to permanent structures – whether internal or
external – takes an open form, whereas
project-oriented recruitment is usually based on addressing the
offer for project participation to the
individuals selected from an internal labor market. It often
happens that project managers do not
decide about the composition of their team, whereas line unit
managers recruit staff for their projects
themselves.
Competence profiles are used in the process of selecting
candidates for permanent organizational
units, whereas it is not applied in the course of project-oriented
selection. The criteria for getting a job
in the first case are of substantive nature. In recruiting project
team members, however, availability
remains the crucial attribute of a candidate. While selecting
candidates for permanent structures their
project oriented competencies are not verified.
Personnel appraisal The appraisals – but rather the
organization-wide ones – result in the decisions about salaries,
transfers and trainings.
Rewarding The project staff doesn’t know the rewarding system
which is used in projects.
Training and development The so-called “hard training”, related
to project-oriented topics, are mainly organized. The
effectiveness of trainings is subject to verification.
Source: author’s research project
In the responding organizations the general personnel function
remains internally consistent. It, however,
cannot be decided whether it supports personnel function
fulfillment in a project. It results, e.g. in the absence
of individuals, in an organization, featuring the human capital
required for work in interdisciplinary teams.
However, the disorder revealed in a project-oriented personnel
function – manifested by the absence of clear
principles – results in the sense of injustice. It mainly refers to
the selection process of project team members.
The above presented observations can result from the lack of
HR specialists involvement in projects.
Moreover, as O. Zwikael and E. Unger-Aviram (2010)
indicated, the absence of an appropriate training remains
one of the main reasons of the underutilization of project team
management tools.
5. Conclusions and directions for further research
In the modern economic reality factors such as rapid changes in
the environment require, e.g. such
organizational structure adjustment which ensures immediate
reaction to the occurring opportunities. In these
conditions flexible organizational structures, including matrix
ones, function very well, whereas organizational
changes are implemented in the form of projects.
The discussed situation is implied by the two-way course of the
personnel function. This particular function, in
accordance with the theory of management and empirical
studies presented in the article, should remain
internally consistent. Such consistency should be analyzed in
terms of practices applied in the area of each
functional course and with regard to mutual relations between
both personnel function courses. Moreover,
the conducted empirical research leads to the conclusion that
the general personnel function is characterized
by higher consistency than a project-oriented one. The analyzed
organizations revealed numerous consistency
gaps between the two personnel function courses.
The practical significance of this research project consists in
supplying HR departments and those involved in
project management with information in how many dimensions
should the personnel function be analyzed
and how should its particular components be arranged to
facilitate an effective project implementation and
increase the effectiveness of the entire organization.
HRM is a complex and multi-dimensional object of academic
studies. The organizational structures in current
enterprises are more and more complicated. There are
organizations which also implement so called process-
oriented approach and process manager positions. If permanent
units (departments) coexist not only with
projects (project teams) but also with well-described and
formalized cross-functional processes, the
complexity of HR function increases even more. This issue
seems nowadays to be an interesting research
problem.
References
Banks, G.C. (2015), “The influence of internal HRM activity fit
on the dynamics within the “black box”“, Human Resource
Management Review, Vo. 25, Issue 4, pp 352-367.
245
Katarzyna Piwowar-Sulej
Boon, C. et al (2007), “MEASURING STRATEGIC AND
INTERNAL FIT IN HRM: AN ALTERNATIVE APPROACH”,
Academy Of
Management Proceedings, August 1, pp 1-6.
Boon, C. (2008), HRM and fit. Survival of the fittest?, Erasmus
University, Rotterdam.
Clark, I. and Colling, T. (2005), “The management of human
resources in project management-led organizations”, Personnel
Review, Vol. 34 No. 2, pp 178-191.
Crawford, J.K. (2014), Project Management Maturity Model.
Third Edition, CRC Press, Boca Raton.
Dictionary.com, Unabridged. [online], Random House, Inc.
http://dictionary.reference.com/browse/consistency.
Huemann, M. and Keegan, A. and Turner, J.R. (2007), “Human
Resources Management in the project-oriented company. A
Review”, International Journal of Project Management, No. 25,
pp 315-323.
Huselid, M.A. (2005), “The impact of human resource
management practices on turnover, productivity, and corporate
financial performance”, Academy of Management Journal, No.
38(3), pp 635-672.
Kepes, S. and Delery, J.E. (2007), HRM Systems and the
Problem of Internal Fit, in: The Oxford Handbook of Human
Resource Management, Boxall Peter F., Purcell John, Wrigh
Patrick M. (eds.), Oxford University Press, New York, pp
385-405.
Lundy, O. and Crowling, A. (2000), Strategiczne zarządzanie
zasobami ludzkimi [Strategic human resources management],
Oficyna Ekonomiczna, Kraków.
Melnic, A.-S. and Puiu, T. (2011), “The Management of Human
Resources within Projects: the Structures of Project Team,
the Responsibility Assignment Matrix”, Economy
Transdisciplinarity Cognition, Vol. XIV, Issue 1, pp 476-484.
Nadler, D.A. and Tushman, M.L. (1980), “A model for
diagnosing organizational behavior”, Organizational Dynamics,
No.
9(2), pp 35-51.
Piwowar-Sulej, K. (2014), “Personnel function in a project-
oriented organization - its form and a matter of consistency”,
International Journal of Academic Research, Part B; No. 6(2),
pp 249-253.
Piwowar-Sulej, K. (2016), Zarządzanie ludźmi w organizacji
zorientowanej na projekty [People Management in a Project-
Oriented Organization], Difin, Warszawa.
Wood, S. (1999), “Getting a measure of the transformed high-
performance organization”, British Journal of Industrial
Relations, No. 37(3), pp. 391-417.
Young, D. (2003), Eit Industrial Review. For the Fundamentals
of Engineering Exam, Engineering Press, Austin.
Zwikael, O. and Unger-Aviram, E. (2010), “HRM in project
groups: The effect on project duration on team development
effectiveness”, International Journal of Project Management,
No. 28 (5), pp 413-421.
246
Copyright of Proceedings of the European Conference on
Intellectual Capital is the property
of Academic Conferences & Publishing International Ltd. and
its content may not be copied
or emailed to multiple sites or posted to a listserv without the
copyright holder's express
written permission. However, users may print, download, or
email articles for individual use.

More Related Content

Similar to HR Function in Project-Oriented Organizations and the Problem .docx

IRJET- The Strength of Human Resources in Organization
IRJET-  	  The Strength of Human Resources in OrganizationIRJET-  	  The Strength of Human Resources in Organization
IRJET- The Strength of Human Resources in Organization
IRJET Journal
 
Running Head THE RESEARCH PROPOSAL BUS8115 – BUS8120 THE RE.docx
Running Head THE RESEARCH PROPOSAL BUS8115 – BUS8120   THE RE.docxRunning Head THE RESEARCH PROPOSAL BUS8115 – BUS8120   THE RE.docx
Running Head THE RESEARCH PROPOSAL BUS8115 – BUS8120 THE RE.docx
WilheminaRossi174
 
Deliverables towards hr sustainability
Deliverables towards hr sustainabilityDeliverables towards hr sustainability
Deliverables towards hr sustainability
Alexander Decker
 
11.the impact of leadership on project performance
11.the impact of leadership on project performance11.the impact of leadership on project performance
11.the impact of leadership on project performance
Alexander Decker
 
The Factors Influencing to Job Satisfaction with Work Motivation as Moderator
The Factors Influencing to Job Satisfaction with Work Motivation as ModeratorThe Factors Influencing to Job Satisfaction with Work Motivation as Moderator
The Factors Influencing to Job Satisfaction with Work Motivation as Moderator
inventionjournals
 
Organizational citizenship Behavior as Attitude Integrity in Measurement of I...
Organizational citizenship Behavior as Attitude Integrity in Measurement of I...Organizational citizenship Behavior as Attitude Integrity in Measurement of I...
Organizational citizenship Behavior as Attitude Integrity in Measurement of I...
IOSR Journals
 
distinguishing various management levels
distinguishing various management levelsdistinguishing various management levels
distinguishing various management levels
Simiyu Yu
 
Reflection Paper 1Reflection Paper 2Reflection Paper.docx
Reflection Paper 1Reflection Paper 2Reflection Paper.docxReflection Paper 1Reflection Paper 2Reflection Paper.docx
Reflection Paper 1Reflection Paper 2Reflection Paper.docx
sodhi3
 
Hr human resource competencies an empirical study on the hr
Hr human resource competencies an empirical study on the hrHr human resource competencies an empirical study on the hr
Hr human resource competencies an empirical study on the hr
Marcus Vannini
 
2 6-66-722
2 6-66-7222 6-66-722
2 6-66-722
babloocps
 
12
1212
SWA_HR_AFTA issues
SWA_HR_AFTA issuesSWA_HR_AFTA issues
SWA_HR_AFTA issues
Wijayanto NM
 
Business Function Human Resources.pptx
Business Function Human Resources.pptxBusiness Function Human Resources.pptx
Business Function Human Resources.pptx
Shivani. Naik
 
Hrm
HrmHrm
Eng class 12 project Article.docx
Eng class 12 project Article.docxEng class 12 project Article.docx
Eng class 12 project Article.docx
ManavDhorajiya
 
Implementing and Monitoring the HR Operating Plan: A Conceptual Framework for...
Implementing and Monitoring the HR Operating Plan: A Conceptual Framework for...Implementing and Monitoring the HR Operating Plan: A Conceptual Framework for...
Implementing and Monitoring the HR Operating Plan: A Conceptual Framework for...
The International Journal of Business Management and Technology
 
Organizational problem in the company and performance management appraisal
Organizational problem in the company and performance management appraisalOrganizational problem in the company and performance management appraisal
Organizational problem in the company and performance management appraisal
IRAWANPERWANDA
 
9Management 2014Vol.18, No. 1MAŁGORZATA GABLETAA.docx
9Management 2014Vol.18, No. 1MAŁGORZATA GABLETAA.docx9Management 2014Vol.18, No. 1MAŁGORZATA GABLETAA.docx
9Management 2014Vol.18, No. 1MAŁGORZATA GABLETAA.docx
sleeperharwell
 
Models of-pmo-functioning-in-a-multi-project-environment 2014-procedia-social...
Models of-pmo-functioning-in-a-multi-project-environment 2014-procedia-social...Models of-pmo-functioning-in-a-multi-project-environment 2014-procedia-social...
Models of-pmo-functioning-in-a-multi-project-environment 2014-procedia-social...
Bernardo Baiz
 
httpdx.doi.org10.4314gjss.v15i1.5GLOBAL JOURNAL OF SO
httpdx.doi.org10.4314gjss.v15i1.5GLOBAL JOURNAL OF SOhttpdx.doi.org10.4314gjss.v15i1.5GLOBAL JOURNAL OF SO
httpdx.doi.org10.4314gjss.v15i1.5GLOBAL JOURNAL OF SO
LizbethQuinonez813
 

Similar to HR Function in Project-Oriented Organizations and the Problem .docx (20)

IRJET- The Strength of Human Resources in Organization
IRJET-  	  The Strength of Human Resources in OrganizationIRJET-  	  The Strength of Human Resources in Organization
IRJET- The Strength of Human Resources in Organization
 
Running Head THE RESEARCH PROPOSAL BUS8115 – BUS8120 THE RE.docx
Running Head THE RESEARCH PROPOSAL BUS8115 – BUS8120   THE RE.docxRunning Head THE RESEARCH PROPOSAL BUS8115 – BUS8120   THE RE.docx
Running Head THE RESEARCH PROPOSAL BUS8115 – BUS8120 THE RE.docx
 
Deliverables towards hr sustainability
Deliverables towards hr sustainabilityDeliverables towards hr sustainability
Deliverables towards hr sustainability
 
11.the impact of leadership on project performance
11.the impact of leadership on project performance11.the impact of leadership on project performance
11.the impact of leadership on project performance
 
The Factors Influencing to Job Satisfaction with Work Motivation as Moderator
The Factors Influencing to Job Satisfaction with Work Motivation as ModeratorThe Factors Influencing to Job Satisfaction with Work Motivation as Moderator
The Factors Influencing to Job Satisfaction with Work Motivation as Moderator
 
Organizational citizenship Behavior as Attitude Integrity in Measurement of I...
Organizational citizenship Behavior as Attitude Integrity in Measurement of I...Organizational citizenship Behavior as Attitude Integrity in Measurement of I...
Organizational citizenship Behavior as Attitude Integrity in Measurement of I...
 
distinguishing various management levels
distinguishing various management levelsdistinguishing various management levels
distinguishing various management levels
 
Reflection Paper 1Reflection Paper 2Reflection Paper.docx
Reflection Paper 1Reflection Paper 2Reflection Paper.docxReflection Paper 1Reflection Paper 2Reflection Paper.docx
Reflection Paper 1Reflection Paper 2Reflection Paper.docx
 
Hr human resource competencies an empirical study on the hr
Hr human resource competencies an empirical study on the hrHr human resource competencies an empirical study on the hr
Hr human resource competencies an empirical study on the hr
 
2 6-66-722
2 6-66-7222 6-66-722
2 6-66-722
 
12
1212
12
 
SWA_HR_AFTA issues
SWA_HR_AFTA issuesSWA_HR_AFTA issues
SWA_HR_AFTA issues
 
Business Function Human Resources.pptx
Business Function Human Resources.pptxBusiness Function Human Resources.pptx
Business Function Human Resources.pptx
 
Hrm
HrmHrm
Hrm
 
Eng class 12 project Article.docx
Eng class 12 project Article.docxEng class 12 project Article.docx
Eng class 12 project Article.docx
 
Implementing and Monitoring the HR Operating Plan: A Conceptual Framework for...
Implementing and Monitoring the HR Operating Plan: A Conceptual Framework for...Implementing and Monitoring the HR Operating Plan: A Conceptual Framework for...
Implementing and Monitoring the HR Operating Plan: A Conceptual Framework for...
 
Organizational problem in the company and performance management appraisal
Organizational problem in the company and performance management appraisalOrganizational problem in the company and performance management appraisal
Organizational problem in the company and performance management appraisal
 
9Management 2014Vol.18, No. 1MAŁGORZATA GABLETAA.docx
9Management 2014Vol.18, No. 1MAŁGORZATA GABLETAA.docx9Management 2014Vol.18, No. 1MAŁGORZATA GABLETAA.docx
9Management 2014Vol.18, No. 1MAŁGORZATA GABLETAA.docx
 
Models of-pmo-functioning-in-a-multi-project-environment 2014-procedia-social...
Models of-pmo-functioning-in-a-multi-project-environment 2014-procedia-social...Models of-pmo-functioning-in-a-multi-project-environment 2014-procedia-social...
Models of-pmo-functioning-in-a-multi-project-environment 2014-procedia-social...
 
httpdx.doi.org10.4314gjss.v15i1.5GLOBAL JOURNAL OF SO
httpdx.doi.org10.4314gjss.v15i1.5GLOBAL JOURNAL OF SOhttpdx.doi.org10.4314gjss.v15i1.5GLOBAL JOURNAL OF SO
httpdx.doi.org10.4314gjss.v15i1.5GLOBAL JOURNAL OF SO
 

More from wellesleyterresa

Hw059f6dbf-250a-4d74-8f5e-f28f14227edc.jpg__MACOSXHw._059.docx
Hw059f6dbf-250a-4d74-8f5e-f28f14227edc.jpg__MACOSXHw._059.docxHw059f6dbf-250a-4d74-8f5e-f28f14227edc.jpg__MACOSXHw._059.docx
Hw059f6dbf-250a-4d74-8f5e-f28f14227edc.jpg__MACOSXHw._059.docx
wellesleyterresa
 
HW in teams of 3 studentsAn oil remanufacturing company uses c.docx
HW in teams of 3 studentsAn oil remanufacturing company uses c.docxHW in teams of 3 studentsAn oil remanufacturing company uses c.docx
HW in teams of 3 studentsAn oil remanufacturing company uses c.docx
wellesleyterresa
 
HW 5.docxAssignment 5 – Currency riskYou may do this assig.docx
HW 5.docxAssignment 5 – Currency riskYou may do this assig.docxHW 5.docxAssignment 5 – Currency riskYou may do this assig.docx
HW 5.docxAssignment 5 – Currency riskYou may do this assig.docx
wellesleyterresa
 
HW#3 – Spring 20181. Giulia is traveling from Italy to China. .docx
HW#3 – Spring 20181. Giulia is traveling from Italy to China. .docxHW#3 – Spring 20181. Giulia is traveling from Italy to China. .docx
HW#3 – Spring 20181. Giulia is traveling from Italy to China. .docx
wellesleyterresa
 
HW 2Due July 1 by 500 PM.docx
HW 2Due July 1 by 500 PM.docxHW 2Due July 1 by 500 PM.docx
HW 2Due July 1 by 500 PM.docx
wellesleyterresa
 
HW 4 Gung Ho Commentary DUE Thursday, April 20 at 505 PM on.docx
HW 4 Gung Ho Commentary DUE Thursday, April 20 at 505 PM on.docxHW 4 Gung Ho Commentary DUE Thursday, April 20 at 505 PM on.docx
HW 4 Gung Ho Commentary DUE Thursday, April 20 at 505 PM on.docx
wellesleyterresa
 
HW 5 Math 405. Due beginning of class – Monday, 10 Oct 2016.docx
HW 5 Math 405. Due beginning of class – Monday, 10 Oct 2016.docxHW 5 Math 405. Due beginning of class – Monday, 10 Oct 2016.docx
HW 5 Math 405. Due beginning of class – Monday, 10 Oct 2016.docx
wellesleyterresa
 
HW 5-RSAascii2str.mfunction str = ascii2str(ascii) .docx
HW 5-RSAascii2str.mfunction str = ascii2str(ascii)        .docxHW 5-RSAascii2str.mfunction str = ascii2str(ascii)        .docx
HW 5-RSAascii2str.mfunction str = ascii2str(ascii) .docx
wellesleyterresa
 
HW 3 Project Control• Status meeting agenda – shows time, date .docx
HW 3 Project Control• Status meeting agenda – shows time, date .docxHW 3 Project Control• Status meeting agenda – shows time, date .docx
HW 3 Project Control• Status meeting agenda – shows time, date .docx
wellesleyterresa
 
HW 1January 19 2017Due back Jan 26, in class.1. (T.docx
HW 1January 19 2017Due back Jan 26, in class.1. (T.docxHW 1January 19 2017Due back Jan 26, in class.1. (T.docx
HW 1January 19 2017Due back Jan 26, in class.1. (T.docx
wellesleyterresa
 
Hussam Malibari Heckman MAT 242 Spring 2017Assignment Chapte.docx
Hussam Malibari Heckman MAT 242 Spring 2017Assignment Chapte.docxHussam Malibari Heckman MAT 242 Spring 2017Assignment Chapte.docx
Hussam Malibari Heckman MAT 242 Spring 2017Assignment Chapte.docx
wellesleyterresa
 
hw1.docxCS 211 Homework #1Please complete the homework problem.docx
hw1.docxCS 211 Homework #1Please complete the homework problem.docxhw1.docxCS 211 Homework #1Please complete the homework problem.docx
hw1.docxCS 211 Homework #1Please complete the homework problem.docx
wellesleyterresa
 
HUS 335 Interpersonal Helping SkillsCase Assessment FormatT.docx
HUS 335 Interpersonal Helping SkillsCase Assessment FormatT.docxHUS 335 Interpersonal Helping SkillsCase Assessment FormatT.docx
HUS 335 Interpersonal Helping SkillsCase Assessment FormatT.docx
wellesleyterresa
 
HW #1Tech Alert on IT & Strategy (Ch 3-5Ch 3 -5 IT Strategy opt.docx
HW #1Tech Alert on IT & Strategy (Ch 3-5Ch 3 -5 IT Strategy opt.docxHW #1Tech Alert on IT & Strategy (Ch 3-5Ch 3 -5 IT Strategy opt.docx
HW #1Tech Alert on IT & Strategy (Ch 3-5Ch 3 -5 IT Strategy opt.docx
wellesleyterresa
 
HW 2 (1) Visit Monsanto (httpwww.monsanto.com) again and Goog.docx
HW 2 (1) Visit Monsanto (httpwww.monsanto.com) again and Goog.docxHW 2 (1) Visit Monsanto (httpwww.monsanto.com) again and Goog.docx
HW 2 (1) Visit Monsanto (httpwww.monsanto.com) again and Goog.docx
wellesleyterresa
 
Hunters Son Dialogue Activity1. Please write 1-2 sentences for e.docx
Hunters Son Dialogue Activity1. Please write 1-2 sentences for e.docxHunters Son Dialogue Activity1. Please write 1-2 sentences for e.docx
Hunters Son Dialogue Activity1. Please write 1-2 sentences for e.docx
wellesleyterresa
 
HW 2 - SQL The database you will use for this assignme.docx
HW 2 - SQL   The database you will use for this assignme.docxHW 2 - SQL   The database you will use for this assignme.docx
HW 2 - SQL The database you will use for this assignme.docx
wellesleyterresa
 
Humanities Commons Learning Goals1. Write about primary and seco.docx
Humanities Commons Learning Goals1. Write about primary and seco.docxHumanities Commons Learning Goals1. Write about primary and seco.docx
Humanities Commons Learning Goals1. Write about primary and seco.docx
wellesleyterresa
 
HURRICANE KATRINA A NATION STILL UNPREPARED .docx
HURRICANE KATRINA  A NATION STILL UNPREPARED   .docxHURRICANE KATRINA  A NATION STILL UNPREPARED   .docx
HURRICANE KATRINA A NATION STILL UNPREPARED .docx
wellesleyterresa
 
Humanities 115Short Essay Grading CriteriaExcellentPassing.docx
Humanities 115Short Essay Grading CriteriaExcellentPassing.docxHumanities 115Short Essay Grading CriteriaExcellentPassing.docx
Humanities 115Short Essay Grading CriteriaExcellentPassing.docx
wellesleyterresa
 

More from wellesleyterresa (20)

Hw059f6dbf-250a-4d74-8f5e-f28f14227edc.jpg__MACOSXHw._059.docx
Hw059f6dbf-250a-4d74-8f5e-f28f14227edc.jpg__MACOSXHw._059.docxHw059f6dbf-250a-4d74-8f5e-f28f14227edc.jpg__MACOSXHw._059.docx
Hw059f6dbf-250a-4d74-8f5e-f28f14227edc.jpg__MACOSXHw._059.docx
 
HW in teams of 3 studentsAn oil remanufacturing company uses c.docx
HW in teams of 3 studentsAn oil remanufacturing company uses c.docxHW in teams of 3 studentsAn oil remanufacturing company uses c.docx
HW in teams of 3 studentsAn oil remanufacturing company uses c.docx
 
HW 5.docxAssignment 5 – Currency riskYou may do this assig.docx
HW 5.docxAssignment 5 – Currency riskYou may do this assig.docxHW 5.docxAssignment 5 – Currency riskYou may do this assig.docx
HW 5.docxAssignment 5 – Currency riskYou may do this assig.docx
 
HW#3 – Spring 20181. Giulia is traveling from Italy to China. .docx
HW#3 – Spring 20181. Giulia is traveling from Italy to China. .docxHW#3 – Spring 20181. Giulia is traveling from Italy to China. .docx
HW#3 – Spring 20181. Giulia is traveling from Italy to China. .docx
 
HW 2Due July 1 by 500 PM.docx
HW 2Due July 1 by 500 PM.docxHW 2Due July 1 by 500 PM.docx
HW 2Due July 1 by 500 PM.docx
 
HW 4 Gung Ho Commentary DUE Thursday, April 20 at 505 PM on.docx
HW 4 Gung Ho Commentary DUE Thursday, April 20 at 505 PM on.docxHW 4 Gung Ho Commentary DUE Thursday, April 20 at 505 PM on.docx
HW 4 Gung Ho Commentary DUE Thursday, April 20 at 505 PM on.docx
 
HW 5 Math 405. Due beginning of class – Monday, 10 Oct 2016.docx
HW 5 Math 405. Due beginning of class – Monday, 10 Oct 2016.docxHW 5 Math 405. Due beginning of class – Monday, 10 Oct 2016.docx
HW 5 Math 405. Due beginning of class – Monday, 10 Oct 2016.docx
 
HW 5-RSAascii2str.mfunction str = ascii2str(ascii) .docx
HW 5-RSAascii2str.mfunction str = ascii2str(ascii)        .docxHW 5-RSAascii2str.mfunction str = ascii2str(ascii)        .docx
HW 5-RSAascii2str.mfunction str = ascii2str(ascii) .docx
 
HW 3 Project Control• Status meeting agenda – shows time, date .docx
HW 3 Project Control• Status meeting agenda – shows time, date .docxHW 3 Project Control• Status meeting agenda – shows time, date .docx
HW 3 Project Control• Status meeting agenda – shows time, date .docx
 
HW 1January 19 2017Due back Jan 26, in class.1. (T.docx
HW 1January 19 2017Due back Jan 26, in class.1. (T.docxHW 1January 19 2017Due back Jan 26, in class.1. (T.docx
HW 1January 19 2017Due back Jan 26, in class.1. (T.docx
 
Hussam Malibari Heckman MAT 242 Spring 2017Assignment Chapte.docx
Hussam Malibari Heckman MAT 242 Spring 2017Assignment Chapte.docxHussam Malibari Heckman MAT 242 Spring 2017Assignment Chapte.docx
Hussam Malibari Heckman MAT 242 Spring 2017Assignment Chapte.docx
 
hw1.docxCS 211 Homework #1Please complete the homework problem.docx
hw1.docxCS 211 Homework #1Please complete the homework problem.docxhw1.docxCS 211 Homework #1Please complete the homework problem.docx
hw1.docxCS 211 Homework #1Please complete the homework problem.docx
 
HUS 335 Interpersonal Helping SkillsCase Assessment FormatT.docx
HUS 335 Interpersonal Helping SkillsCase Assessment FormatT.docxHUS 335 Interpersonal Helping SkillsCase Assessment FormatT.docx
HUS 335 Interpersonal Helping SkillsCase Assessment FormatT.docx
 
HW #1Tech Alert on IT & Strategy (Ch 3-5Ch 3 -5 IT Strategy opt.docx
HW #1Tech Alert on IT & Strategy (Ch 3-5Ch 3 -5 IT Strategy opt.docxHW #1Tech Alert on IT & Strategy (Ch 3-5Ch 3 -5 IT Strategy opt.docx
HW #1Tech Alert on IT & Strategy (Ch 3-5Ch 3 -5 IT Strategy opt.docx
 
HW 2 (1) Visit Monsanto (httpwww.monsanto.com) again and Goog.docx
HW 2 (1) Visit Monsanto (httpwww.monsanto.com) again and Goog.docxHW 2 (1) Visit Monsanto (httpwww.monsanto.com) again and Goog.docx
HW 2 (1) Visit Monsanto (httpwww.monsanto.com) again and Goog.docx
 
Hunters Son Dialogue Activity1. Please write 1-2 sentences for e.docx
Hunters Son Dialogue Activity1. Please write 1-2 sentences for e.docxHunters Son Dialogue Activity1. Please write 1-2 sentences for e.docx
Hunters Son Dialogue Activity1. Please write 1-2 sentences for e.docx
 
HW 2 - SQL The database you will use for this assignme.docx
HW 2 - SQL   The database you will use for this assignme.docxHW 2 - SQL   The database you will use for this assignme.docx
HW 2 - SQL The database you will use for this assignme.docx
 
Humanities Commons Learning Goals1. Write about primary and seco.docx
Humanities Commons Learning Goals1. Write about primary and seco.docxHumanities Commons Learning Goals1. Write about primary and seco.docx
Humanities Commons Learning Goals1. Write about primary and seco.docx
 
HURRICANE KATRINA A NATION STILL UNPREPARED .docx
HURRICANE KATRINA  A NATION STILL UNPREPARED   .docxHURRICANE KATRINA  A NATION STILL UNPREPARED   .docx
HURRICANE KATRINA A NATION STILL UNPREPARED .docx
 
Humanities 115Short Essay Grading CriteriaExcellentPassing.docx
Humanities 115Short Essay Grading CriteriaExcellentPassing.docxHumanities 115Short Essay Grading CriteriaExcellentPassing.docx
Humanities 115Short Essay Grading CriteriaExcellentPassing.docx
 

Recently uploaded

NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
iammrhaywood
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Denish Jangid
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
AyyanKhan40
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
Colégio Santa Teresinha
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
amberjdewit93
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
Israel Genealogy Research Association
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
imrankhan141184
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
siemaillard
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
GeorgeMilliken2
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
Celine George
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Fajar Baskoro
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
heathfieldcps1
 
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching AptitudeUGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
S. Raj Kumar
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
TechSoup
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
EduSkills OECD
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 

Recently uploaded (20)

NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
 
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching AptitudeUGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 

HR Function in Project-Oriented Organizations and the Problem .docx

  • 1. HR Function in Project-Oriented Organizations and the Problem of its Internal Consistency Katarzyna Piwowar-Sulej Wroclaw University of Economics, Wroclaw, Poland [email protected] Abstract: Nowadays, repetitive or routine activities are slowly giving way to unique and complicated activities – i.e. projects. Many enterprises implement the so-called management by projects (MBP). The enterprises following such an approach are referred to as project-oriented organizations (PORORs). A project and an organization cannot exist without appropriate human capital. This capital is developed in the process of HR function fulfillment (R&S, training, HR appraisal, remuneration and HR flow). In every enterprise, which implements MBP, HR function takes a two-way course: in an organization-wide perspective (general HR function) and within the framework of a particular project (HR function in projects). The objective of the article is to answer the following research questions: Q1: Should the same operational schemes in both “courses” of HR function be used from the perspective of an effective functioning of project-oriented organizations? Q2: What kind of gaps occur in the area of HR function internal consistency within the analyzed organizations? The article presents the results of empirical studies carried out in 2014 and 2015 in 100 project-oriented organizations. The methodology for measuring HR function’s internal consistency was proposed. Data triangulation was applied in the research process. The conducted studies indicate
  • 2. that the multidimensional consistency of the personnel function results in an increased efficiency of not only projects, but also the entire organization. The surveyed organizations present higher general HR function consistency than the HR function in projects. Moreover, some gaps in consistency between both personnel function courses were indicated. The presented results of empirical studies provide knowledge about the specificity of project-oriented organizations. The presented discussion can also become the foundation for developing further research. Keywords: HRM, HR function, project-oriented organization, management challenges, management by projects 1. Introduction A thesis can be put forward that since the 90s of the 20 th century the interest in the way people function within organizational structures has been increasing continuously. Therefore, managing people (human resources management, HRM) can be considered as the key management area. Such management is identified with personnel function (HR function), which covers tasks related to attracting workers, adequate development of their capital and taking advantage of it in the course of any organization functioning. Currently this function is focused on achieving organizational goals along with meeting its employees’ needs. Its development remains within the responsibility of human resources department as a strategic partner. The interest in project management issues is also continuously growing. The analyses cover the application of specific knowledge, skills and tools in terms of operations
  • 3. performed in the course of carried out projects. Nowadays, not only launching new products or services is implemented in the form of projects. Project- oriented approach, based on appointing interdisciplinary teams and using tools typical for project management, is extensively applied within the framework of managing changes (Young, 2006). These enterprises which take advantage of such approach are referred to as project-oriented organizations. Among them there are project-based organizations – in which project implementation remains their core business – and also organizations focused on repetitive actions (e.g. banks or manufacturing companies) which, however, implement projects. Task-oriented organizational structure represents the factor which differentiates the analyzed organizations from the so-called traditional enterprises. In practice, pure project-based structures – i.e. the ones within which no other permanent units have been established – occur very rarely. Therefore, the usual alternative to this type of structure is the matrix structure, in which project teams are formed and dissolved (Young, 2003). In this case the complexity of personnel function is increasing. HRM has a two-way course: on the one hand, in the general organizational field, and on the other, within a given project. The two ways of the HR function have been respectively called the general personnel function and the personnel function in project. In the course of this function development in project-oriented organizations, “new” subjects, absent in traditional organizations, such as project managers gain more importance. 238
  • 4. Katarzyna Piwowar-Sulej As Huselid (2005) points out, a HRM system, based on complementary practices, is the source of lasting competitive advantage in an enterprise. The subject literature presents various types of fit within the framework of HRM. The problem of HRM consistency is broadly discussed in the literature on traditional organizations (e.g. Boon et al, 2007; Kepes and Delery, 2007; Banks, 2014). Due to the two-way course of personnel function in project-oriented organizations, internal fit has been recognized as particularly important. Even though the subject literature discussing project management calls for the standardization of operations in the subsequent projects in order to develop project management maturity (Crawford, 2014), it seems, however, that the consistency (fit) of activities taken up in projects only, along with the existing discrepancies between the practices applied in the general personnel function and a personnel function in project , shall result in some organizational disorder. The latter, on the other hand, has negative impact on the effectiveness of the entire enterprise. Lundy and Crowling (2000) are of the opinion that internal effectiveness in an enterprise results from implementing and establishing managerial mechanisms along with maintaining consistency, harmony and feasibility . Consistency can be understood as harmony or compatibility, the condition of cohering or holding together and retaining form, solidity or firmness (Dictionary.com). Nadler and Tushman (1980) define consistency or fit as the level at which needs, requirements, goals, the construction of one element remain in compliance with the
  • 5. needs, requirements, goals, structure of another component. It was observed that the discussion presented in subject literature on human resources management in a project-oriented organization persists, to some extent, “in isolation” from the problem of organizational structure. Furthermore, so far the issue of personnel function consistency, in the specific functioning conditions of project-oriented organizations, has not been discussed. The purpose of the article was defined, i.e. answering the following research questions: Q1: Should the same operational schemes in both “courses” of HR function be used from the perspective of effective functioning of project-oriented organizations? Q2: What kind of gaps occur in the area of personnel function internal consistency in the analyzed organizations? In order to carry out the purpose defined in this way the relationships between the two courses of personnel function were discussed. The theory referring to HRM consistency was also explained. Finally, the results of the empirical research were discussed. The above-mentioned research constitutes the component of a broader research project covering methods for personnel function implementation in project-oriented organizations. The research project was financed by The National Science Centre Poland (DEC-2013/09/D/HS4/00566). 2. Literature Background
  • 6. 2.1 HR function in a traditional organization vs. HR function in a project-oriented organization The discussion on HRM has been going on in the subject literature for many years. It is characterized by the diversity of definitions referring to the problem of human resources management, as well as a the broad spectrum of activities which could be assigned to this concept. It was adopted that every organization is characterized by a certain set of basic physical functions, indispensable in achieving its goals. One of them is a personnel function which refers to all employees and covers the tasks usually carried out by HR department. As it has already been pointed out, its primary goal is to ensure proper staffing in order to achieve the results identified by an enterprise. In the 50s of the 20 th century this function was still not perceived globally and no need was observed to consider the relationships occurring between its many components. The author – having considered the relations occurring between the particular HR function components – suggests its presentation in the form illustrated in figure 1. It was adopted that the recruitment and selection of candidates (R&S) is not finalized while signing an employment agreement or a civil contract. In practice the so-called trial period agreements are frequently signed. During such time an employee goes through a break-in period and his/her practical competences are verified, therefore he/she is still subject to the selection process. The term of HR flow is understood as promotions (horizontal, vertical), transfers (organizational unit changing while remaining at the same or similar position), demotions and layoffs. The feedbacks occurring between
  • 7. personnel function components are marked by a dotted line. For example, staff leaving implies the need for 239 Katarzyna Piwowar-Sulej personnel recruitment. A dotted line on the figure below illustrates that within the framework of R&S – and specifically while breaking into work – adequate training are provided. It refers to mandatory training associated with signing employment agreements. (e.g. trainings in occupational health and safety), but also additional onboarding training. Figure 1: Model presentation of a HR function in a traditional organization Source: Piwowar-Sulej (2016) At this point it is worth emphasizing that the presented perspective is a model oriented one. The result of HR appraisal, either formal or informal, should imply offering adequate training in terms of remuneration and transfer. On the basis of literature studies combining the problems of project management and HRM two approaches to personnel function presentation were identified. The dominating practice is manifested in focusing on personnel function only as representing the set of activities addressed to project team members (see Clark and Colling, 2005; Melnic and Puiu, 2011). The second and also
  • 8. quite uncommon approach – which precursors are Huemann and Keegan and Turner (2007) – consists in noticing two courses of this function. The above- mentioned authors prepared a graphic presentation of differences occurring between personnel function in a traditional organization (managed in a “classical” way, where project-oriented approach is not applied) and a project-oriented one (see figure 2). Figure 2 shows that a project involves people already employed in an organization. However, in business practice both recruitment process and the selection of candidates from an external labor market can be arranged specifically for the needs of a particular project. Figure 2: HRM in the project-oriented company vs. HRM in the classically managed (traditional) enterprise Source: Huemann and Keegan and Turner (2007) 240 Katarzyna Piwowar-Sulej As it has been indicated in the introduction to the study an organizational structure determines the form of personnel function. Personnel function in a project-oriented organization takes a two-way course. Personnel function in a project is made up of the same components as the personnel function at the general organizational level. There are mutual relations between the particular components of a personnel function in a project and a general personnel function, as shown in figure 3.
  • 9. They are strictly connected with the problem of internal HRM fit. Figure 3: Two-way course of the personnel function in a project-oriented organization Source: Piwowar-Sulej (2014) 2.2 The problem of HRM internal consistency Scientific literature distinguishes between four different types of fit in terms of HRM, i.e. (Wood, 1999): a) Strategic fit: the relationship between HRM system and business strategy. It occurs when HRM practices concentrate on stimulating people to meet organizational goals. b) Internal fit: the relationship between various HRM practices in the entire HRM system. Following this approach HR system should remain internally consistent. c) Organizational fit: the relationship between HRM system and other systems in an organization (e.g. technological, manufacturing, control systems). d) Environmental fit: related to HRM system and external environment. Following this logic, HRM system should be fit to changes in the environment, as well as principles and expectations of this environment against an organization. Within the framework of human resources strategic management concept the need of so-called vertical
  • 10. (strategic) integration is primarily emphasized. The author is of the opinion that all of the above -mentioned types of HRM fit are equally important. Due to the specific nature of personnel function in a project-oriented organization it was decided that the problem of horizontal (internal) fit regarding HR practices is worth discussing in more detail, i.e. having considered the relationships marked with a dotted line in figure 3. Recruitment and selection were recognized as major activities carried out within the framework of personnel function. It is justified by the fact that the decisions referring to employment of a candidate presenting a particular human capital remain fundamental for taking up actions in the course of the subsequent HRM stages. A project team member can be recruited from either internal or external labor market. In the first case a temporary transfer of an employee from a permanent organizational unit to a project takes place. The general 241 Katarzyna Piwowar-Sulej personnel function stage, referred to as HR flow, provides “resources” at the stage of staff recruitment for project purposes. Attracting project staff from external labor market can take the same forms as in the case of recruiting candidates for positions in an enterprise permanent structure. It consists in applying appropriate R&S methods or techniques. Moreover, when an employment agreement is
  • 11. concluded – in the light of Polish labor law – employee’s position in an organizational permanent unit has to be defined. In this way the relationship between recruiting people for organizations and attracting project team members becomes visible. After project completion the stage of team members’ transfer takes place. They can be recruited to the next project or return to their functional department. Once the project is finalized an employee can be offered a position in an organizational permanent structure. The above presented examples illustrate objective relations occurring between the stage of staff transfer in a project and also R&S and HR flow stages in the general organizational structure. Therefore, how should internal consistency of the personnel function be approached in the analyzed organizations? The problem of interest for the author refers primarily to: a. internal consistency within each course of the discussed function, b. consistency between both courses of the personnel function. Internal consistency within a particular course takes the form of making staff oriented decisions based on the results of an employee appraisal. Training should result from the needs defined in the course of periodical staff appraisal. The consistency between personnel function courses means, on the other hand, that the practices applied within the framework of a general personnel function and a personnel function in project remain mutually fit. Not only are they linked by the relationships presented in figure 3, but also use similar methods in
  • 12. both courses within the particular stages of personnel functions implementation. It is not about applying exactly the same techniques e.g. candidates’ selection for work on positions in an organizational permanent structure and techniques for project members selection. It is about the same rules applying in both identified cases. For example, if the selection of candidates for the positions in an enterprise permanent structure takes advantage of recruitment addressed to a wide range of people, the same rule should apply in case of projects. It ensures order and the sense of justice. Furthermore – since the organizational strategy is implemented based on a project-oriented approach – the general personnel function should support projects. Such adjustment can take the form of e.g. checking at the stage of selecting candidates’ suitability for project- oriented work in an enterprise. These and other relationships between the particular personnel function components were subject to empirical verification. 3. Research methodology As it has already been mentioned in the introduction to the study, so far no scientific debate has been going on regarding personnel function consistency in project-oriented organizations. On the other hand, the research on HRM consistency in traditional organizations has, so far, been mainly applying quantitative methods such as: reliability analysis, factor and cluster analysis, multiple regression analysis, sequence analysis (Boon, 2008). An alternative approach to research methods in this area of knowledge was recognized as desirable. Within the framework of empirical research an idiographic approach, based on purposive sample, was used (for more see: Piwowar-Sulej, 2016). It covered 100 enterprises
  • 13. based in Poland and applying a project- oriented approach. The research sample was balanced, i.e. covered an equal number of project-based enterprises (with projects as their core business) and the other ones which conduct projects. In the process of the research sample construction it was considered that while a defined number of project-based enterprises is operating on the market, it is difficult to identify the other organizations which apply a project-oriented approach. There are no objective registers to define the entire population of project-oriented organizations and enable representative sampling. The study covered enterprises offering a position or a function (role) of a project manager. An additional condition to include an enterprise in a research sample was HR department presence in an enterprise structure. Thus, medium and large enterprises participated in the research. 242 Katarzyna Piwowar-Sulej Having considered the above-mentioned problems in obtaining a representative sample, along with an intention to ensure higher quality of the conducted research, data triangulation was used in the research process. Structured interview (using PAPI method) with a project manager, project executor and HR specialist was performed in each enterprise. Research tools were developed in the form of structured interview questionnaires. The questionnaires addressed to each group of respondents contained 300
  • 14. questions. Due to size limitations of the article and its purpose, the author decided to focus on the research part which referred directly to the problem of personnel function consistency. 24 questions/statements (see table 1) were addressed to each group of respondents, which referred directly to internal consistency of the personnel function. The respondents had to choose the answer (“yes” or “now”). Kruskal-Wallis test was applied to check the convergence level of the answers provided by representatives of various respondent groups. It turned out that in case of 17 out of 24 questions the level of significance was less than 0,05, which indicates that the respondents were providing significantly different answers to a particular question. It became a reason for the use in the research process additionally in-depth interview method. The answers to research questions will be provided in the next part of the study. Table 1: Hypothesis test summary (Kruskal-Wallis test for independent samples) No. Null hypothesis Significance Decision 1. A project team member is brought into operation in a planned manner (formal information about the project objective, project implementation methodology, methods of work, duties). ,007 Reject null hypothesis 2. During staff employment in an enterprise their suitability for project-oriented work is taken into account.
  • 15. 0,804 Accept null hypothesis 3. The system of periodical appraisal, taking project-oriented work into account, functions in an enterprise. ,174 Accept null hypothesis 4. Decisions about employees’ remuneration result from periodical appraisals in an enterprise. ,000 Reject null hypothesis 5. Decisions about training result from periodical appraisals in an enterprise. ,000 Reject null hypothesis 6. Decisions about employee promotions result from periodical appraisals in an enterprise. ,386 Accept null hypothesis 7. Decisions about moving an employee from an organizational structure to a project result from periodical appraisals in an enterprise. ,000 Reject null
  • 16. hypothesis 8. Training offered in the workplace is necessary for the successful implementation of a particular project. ,013 Reject null hypothesis 9. During a long-term project the decision is made about a team member training based on his/her work appraisal. ,893 Accept null hypothesis 10. Project-oriented training is organized in the workplace. ,000 Reject null hypothesis 11. The analysis of training needs in the company is based on employee appraisal. ,014 Reject null hypothesis 12. After finalizing training its effectiveness is analyzed. ,006 Reject null hypothesis
  • 17. 13. Base salary level (including e.g. pay rise) depends on the variety of roles performed by a particular employee. ,046 Reject null hypothesis 14. Base salary level (including e.g. pay rise) depends on employee’s achievements in projects. ,000 Reject null hypothesis 15. Career paths in the enterprise take into account project-oriented career (offer opportunities not only for climbing the career ladder from an administration clerk position to a department manager, but also for taking the position/function of a project manager or specialist in project management office). ,006 Reject null hypothesis 16. Success in projects is taken into account while making decisions about an internal promotion in a department where an employee works on a daily basis. ,093 Accept null hypothesis 17.
  • 18. Recruitment to the enterprise and project team members’ recruitment follows the same general principles. ,003 Reject null hypothesis 18. The selection of candidates for enterprise employees and the selection of project team members is performed based on the same professional methods. ,000 Reject null hypothesis 19. A new employee and a new project team member breaks into work in a planned manner (there is a formal onboarding process). ,173 Accept null hypothesis 20. New employees representing different departments are informed about the possibility of participation in projects. ,017 Reject null hypothesis 21. Formal appraisal system for projects is applied based on the same methods used in the appraisal system in permanent organizational units (e.g. appraisal based on competencies,
  • 19. management by objectives, 360 degree feedback). ,000 Reject null hypothesis 22. Decisions about salaries, training and promotions result from periodical appraisals in an enterprise. ,001 Reject null hypothesis 243 Katarzyna Piwowar-Sulej 23. Decisions about project team members’ salaries and role changes result from periodical HR appraisals in a particular project. ,280 Accept null hypothesis 24. All employees have access to information about the principles of participation in projects. ,001 Reject null hypothesis The presentation of asymptomatic significance. The level of significance is ,05. Source: author’s research project
  • 20. 4. The results of empirical studies with reference to the research questions Q1: Should the same operational schemes in both “courses” of personnel function be used from the perspective of an effective functioning of project-oriented organizations? Having taken into account the first research question (Q1) the author distinguished two detailed areas of organizational effectiveness, i.e.: A database of common answers provided by all groups of respondents was established for the purposes of the conducted analysis. Respondents from 88% of the studied organizations stated unanimously that multidimensional consistency increases the effectiveness of the entire organization (see table 2). Internal personnel function consistency increases the effectiveness of personnel function fulfillment and project success probability in opinion of respondents from 85% of the organizations. Table 2: The impact areas of personnel function internal consistency Number of enterprises (n=100) Statement
  • 21. Total (n=100) Internal personnel function consistency increases project success probability. 85 (85%) Internal personnel function consistency increases the effectiveness of personnel function fulfillment. 85 (85%) Internal personnel function consistency increases the entire organization effectiveness. 88 (88%) Source: author’s research project Q2: What kind of gaps occur in the area of the personnel function internal consistency in the analyzed organizations? The survey consisted of 24 questions focused exclusively on diagnosing internal consistency level of the personnel function. The maximum number of positive responses was thus 24 (24 questions to which the respondents answered unanimously “yes”). The highest possible level of personnel function consistency – in accordance with the provided responses – was not achieved in any of the analyzed organizations. The arithmetic mean was 8,74, at standard deviation of 4,87. The median was set at the level of 9, lower quartile – 5, upper quartile – 12. Based on the statistical measures one can state that the personnel function is not
  • 22. consistent in the majority of organizations. Moreover, in-depth data analysis confirmed: a. higher internal consistency of the general personnel function than the project-oriented personnel function, b. some shortcomings in the consistency of both personnel function courses (see table 3). 244 Katarzyna Piwowar-Sulej Table 3: Main shortcomings in the personnel function internal consistency – summary of the empirical research results Stage of HR function Revealed shortcomings Recruitment and selection (R&S) There are certain discrepancies in the area of recruitment between both personnel function courses. Recruitment to permanent structures – whether internal or external – takes an open form, whereas
  • 23. project-oriented recruitment is usually based on addressing the offer for project participation to the individuals selected from an internal labor market. It often happens that project managers do not decide about the composition of their team, whereas line unit managers recruit staff for their projects themselves. Competence profiles are used in the process of selecting candidates for permanent organizational units, whereas it is not applied in the course of project-oriented selection. The criteria for getting a job in the first case are of substantive nature. In recruiting project team members, however, availability remains the crucial attribute of a candidate. While selecting candidates for permanent structures their project oriented competencies are not verified. Personnel appraisal The appraisals – but rather the organization-wide ones – result in the decisions about salaries, transfers and trainings. Rewarding The project staff doesn’t know the rewarding system which is used in projects. Training and development The so-called “hard training”, related to project-oriented topics, are mainly organized. The effectiveness of trainings is subject to verification. Source: author’s research project In the responding organizations the general personnel function remains internally consistent. It, however, cannot be decided whether it supports personnel function fulfillment in a project. It results, e.g. in the absence of individuals, in an organization, featuring the human capital
  • 24. required for work in interdisciplinary teams. However, the disorder revealed in a project-oriented personnel function – manifested by the absence of clear principles – results in the sense of injustice. It mainly refers to the selection process of project team members. The above presented observations can result from the lack of HR specialists involvement in projects. Moreover, as O. Zwikael and E. Unger-Aviram (2010) indicated, the absence of an appropriate training remains one of the main reasons of the underutilization of project team management tools. 5. Conclusions and directions for further research In the modern economic reality factors such as rapid changes in the environment require, e.g. such organizational structure adjustment which ensures immediate reaction to the occurring opportunities. In these conditions flexible organizational structures, including matrix ones, function very well, whereas organizational changes are implemented in the form of projects. The discussed situation is implied by the two-way course of the personnel function. This particular function, in accordance with the theory of management and empirical studies presented in the article, should remain internally consistent. Such consistency should be analyzed in terms of practices applied in the area of each functional course and with regard to mutual relations between both personnel function courses. Moreover, the conducted empirical research leads to the conclusion that the general personnel function is characterized by higher consistency than a project-oriented one. The analyzed organizations revealed numerous consistency gaps between the two personnel function courses.
  • 25. The practical significance of this research project consists in supplying HR departments and those involved in project management with information in how many dimensions should the personnel function be analyzed and how should its particular components be arranged to facilitate an effective project implementation and increase the effectiveness of the entire organization. HRM is a complex and multi-dimensional object of academic studies. The organizational structures in current enterprises are more and more complicated. There are organizations which also implement so called process- oriented approach and process manager positions. If permanent units (departments) coexist not only with projects (project teams) but also with well-described and formalized cross-functional processes, the complexity of HR function increases even more. This issue seems nowadays to be an interesting research problem. References Banks, G.C. (2015), “The influence of internal HRM activity fit on the dynamics within the “black box”“, Human Resource Management Review, Vo. 25, Issue 4, pp 352-367. 245 Katarzyna Piwowar-Sulej Boon, C. et al (2007), “MEASURING STRATEGIC AND INTERNAL FIT IN HRM: AN ALTERNATIVE APPROACH”, Academy Of Management Proceedings, August 1, pp 1-6.
  • 26. Boon, C. (2008), HRM and fit. Survival of the fittest?, Erasmus University, Rotterdam. Clark, I. and Colling, T. (2005), “The management of human resources in project management-led organizations”, Personnel Review, Vol. 34 No. 2, pp 178-191. Crawford, J.K. (2014), Project Management Maturity Model. Third Edition, CRC Press, Boca Raton. Dictionary.com, Unabridged. [online], Random House, Inc. http://dictionary.reference.com/browse/consistency. Huemann, M. and Keegan, A. and Turner, J.R. (2007), “Human Resources Management in the project-oriented company. A Review”, International Journal of Project Management, No. 25, pp 315-323. Huselid, M.A. (2005), “The impact of human resource management practices on turnover, productivity, and corporate financial performance”, Academy of Management Journal, No. 38(3), pp 635-672. Kepes, S. and Delery, J.E. (2007), HRM Systems and the Problem of Internal Fit, in: The Oxford Handbook of Human Resource Management, Boxall Peter F., Purcell John, Wrigh Patrick M. (eds.), Oxford University Press, New York, pp 385-405. Lundy, O. and Crowling, A. (2000), Strategiczne zarządzanie zasobami ludzkimi [Strategic human resources management], Oficyna Ekonomiczna, Kraków. Melnic, A.-S. and Puiu, T. (2011), “The Management of Human Resources within Projects: the Structures of Project Team, the Responsibility Assignment Matrix”, Economy Transdisciplinarity Cognition, Vol. XIV, Issue 1, pp 476-484.
  • 27. Nadler, D.A. and Tushman, M.L. (1980), “A model for diagnosing organizational behavior”, Organizational Dynamics, No. 9(2), pp 35-51. Piwowar-Sulej, K. (2014), “Personnel function in a project- oriented organization - its form and a matter of consistency”, International Journal of Academic Research, Part B; No. 6(2), pp 249-253. Piwowar-Sulej, K. (2016), Zarządzanie ludźmi w organizacji zorientowanej na projekty [People Management in a Project- Oriented Organization], Difin, Warszawa. Wood, S. (1999), “Getting a measure of the transformed high- performance organization”, British Journal of Industrial Relations, No. 37(3), pp. 391-417. Young, D. (2003), Eit Industrial Review. For the Fundamentals of Engineering Exam, Engineering Press, Austin. Zwikael, O. and Unger-Aviram, E. (2010), “HRM in project groups: The effect on project duration on team development effectiveness”, International Journal of Project Management, No. 28 (5), pp 413-421. 246 Copyright of Proceedings of the European Conference on Intellectual Capital is the property of Academic Conferences & Publishing International Ltd. and
  • 28. its content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written permission. However, users may print, download, or email articles for individual use.