SlideShare a Scribd company logo
HOUSE BUILDING CHECK LIST 1
LOT # ________________________ PERMIT # _______________________
DATE
Activity WHO COMPLETED
LAND
Transferred and Recorded _________
PREPARATION
Building Permit Appomattox County _________
Stakeout the House _________
Well/Septic Permit Health Dept. _________
Temporary Power Pole _________
Apply for Temporary Power CVEC _________
DRIVEWAY
Culvert _________
Gravel _________
LOT WORK
Clearing _________
Dig Basement _________
Get Portable Restroom Taylor's Septic _________
BASEMENT
Footings Knights Dirt Diggers __________
► ► *INSPECTION __________
Pour Footings __________
Dig out between footings __________
Drain pipe along outside __________
Put in gravel __________
Mark for Bricks __________
Basement Walls R & R Concrete __________
Seal Walls __________
► ► *PRE TREAT FOR TERMITES (NAB) __________
IF NEEDED
ROUGH IN FOR PLUMBING Dudley __________
Mark floor level (4”);
Plastic cover gravel and footings __________
Gravel (8” to 10”) and
cloth outside walls __________
► ► *INSPECTION __________
Pour floor
(Formula-Sq. feet/3/27=yds. Cement) Henry Pierce finishes __________
HOUSE BUILDING CHECK LIST 2
LOT # ________________________ PERMIT # _______________________
DATE
Activity WHO COMPLETED
Back fill __________
HOUSE
Order floor trusses, roof trusses Jones Trusses __________
Order Lumber 84 Lumber __________
Order Windows, Outside doors J. E. Jamerson, Bill __________
Get Front Door Home Depot or Lowes __________
Put on Floor Trusses Dad __________
Frame House Dad __________
CHECK POWER
SCHEDULE—Rough in
plumber _____, electrician______, heat pump______, sheet rock______,cabinets______.
GARAGE
Dig footings __________
Mark for Bricks __________
► ► *INSPECTION __________
Pour footings __________
BRICKS
Order bricks, sand, lentels J. E. Jamerson __________
Order Vinyl Sleeves (for lentels) Brick supply—Forest/Boxley __________
Brick house and garage __________
Pour Garage floor __________
Frame Garage Irby Jones __________
HOUSE
Order inside doors J. E. Jamerson __________
Rough in Heat pump Eastbrook Heating and Air __________
Electrical (meter base) Webber __________
Plumber Dudley __________
► ► *INSPECTION __________
(for rough ins)
Roof (color_____________) __________
Siding(color____________Shutters________)Jim Hunter __________
Insulate walls Toler __________
HOUSE BUILDING CHECK LIST 3
LOT # ________________________ PERMIT # _______________________
DATE
Activity WHO COMPLETED
► ► *INSPECTION __________
Sheet rock ordered/ Delivery Date __________
Sheet rock hung Stephen Jackson __________
Sheet rock finished Rick Boyer __________
OUTSIDE
Deck/Patio/ Porch Irby Jones __________
Retaining walls Irby Jones __________
CLEAN UP Me __________
Electric Line put in __________
INSIDE
Order Cabinets Reico __________
Order Appliances (color___________) Sears/Reico __________
Delivery Date_____________
Order Hardwood floors Dillingham Floors __________
(one grade down, sealed)
Install doors Irby Jones __________
Trim on windows, doors, base Irby Jones __________
Painting (color_____________) Tess Morey (Prime) __________
(Done) __________
Basement stairway & garage step Irby Jones __________
Garage door trim, vinyl wrapped Jim Hunter __________
Garage door Amelia __________
Insulate ceilings Toler __________
Install door knobs, door stops Me __________
Tile (Tile name ____________ O'Brien __________
Grout color ____________/Price______
Hardwood floors installed Dillingham Floors __________
Heat pump finished Eastbrook Heating and Air __________
Install Cabinets Reico __________
Delivery Date_____________
Install Date ______________
Company______________Wood______________Color_____________Knob____________
Kitchen Counters_____________Bathroom Counters ____________
OUTSIDE
Well drilled and hooked up to house Fred Jones ___________
Septic System in and hooked up Knights Dirt Diggers ___________
INSIDE
Basement insulation Toler ___________
Order Shelves Toler Shelving ___________
HOUSE BUILDING CHECK LIST 4
LOT # ________________________ PERMIT # _______________________
DATE
Activity WHO COMPLETED
Order Mirrors Toler Shelving ___________
Order Carpet (color_____________) Carpetland ___________
Get Lights ___________
Order Towel Racks Toler Shelving ___________
Final Electrical Webber ___________
Plumbing Dudley ___________
Heat pump(registers basement)Eastbrook ___________
Finish Hardwood Floors Webbs Floors ___________
Carpet installed Carpetland ___________
Shelves installed Toler ___________
Mirrors/Towel racks installed Toler Shelving ___________
Cleaning ___________
Pressure Washing ___________
Paint Touch up Tess Morey ___________
► ► *OCCUPANCY PERMIT ___________
► ► Well test Pro Chem ___________
OUTSIDE
Gutters Irby Jones ___________
Downspout lines Knights Dirt Diggers ___________
Sidewalks/Patio/Basement/Garage ___________
Grass Seeding ___________
► ► Final Termite NAB ___________
PUT ON MARKET _________________________
SOLD DATE ________________________________
After Cleaning—Finish List
____________________________________________________________
____________________________________________________________
____________________________________________________________

More Related Content

Viewers also liked

Economic evaluation and comparison between green building and conventional bu...
Economic evaluation and comparison between green building and conventional bu...Economic evaluation and comparison between green building and conventional bu...
Economic evaluation and comparison between green building and conventional bu...
Manthan Shah
 
Ibe quantity surveyor 2013
Ibe quantity surveyor 2013Ibe quantity surveyor 2013
Ibe quantity surveyor 2013
nurun2010
 
Low Cost Housing Presentation
Low Cost Housing PresentationLow Cost Housing Presentation
Low Cost Housing Presentation
kyleeichler
 
LOW COST HOUSING
LOW COST HOUSING LOW COST HOUSING
LOW COST HOUSING
Amol Pawar
 
Low cost housing India
Low cost housing IndiaLow cost housing India
Project proposal
Project proposalProject proposal
Project proposal
Jayson Patalinghug
 
Belapur Incremental housing - A case study
Belapur Incremental housing - A case studyBelapur Incremental housing - A case study
Belapur Incremental housing - A case study
Rithika Ravishankar
 

Viewers also liked (7)

Economic evaluation and comparison between green building and conventional bu...
Economic evaluation and comparison between green building and conventional bu...Economic evaluation and comparison between green building and conventional bu...
Economic evaluation and comparison between green building and conventional bu...
 
Ibe quantity surveyor 2013
Ibe quantity surveyor 2013Ibe quantity surveyor 2013
Ibe quantity surveyor 2013
 
Low Cost Housing Presentation
Low Cost Housing PresentationLow Cost Housing Presentation
Low Cost Housing Presentation
 
LOW COST HOUSING
LOW COST HOUSING LOW COST HOUSING
LOW COST HOUSING
 
Low cost housing India
Low cost housing IndiaLow cost housing India
Low cost housing India
 
Project proposal
Project proposalProject proposal
Project proposal
 
Belapur Incremental housing - A case study
Belapur Incremental housing - A case studyBelapur Incremental housing - A case study
Belapur Incremental housing - A case study
 

House Building Check List

  • 1. HOUSE BUILDING CHECK LIST 1 LOT # ________________________ PERMIT # _______________________ DATE Activity WHO COMPLETED LAND Transferred and Recorded _________ PREPARATION Building Permit Appomattox County _________ Stakeout the House _________ Well/Septic Permit Health Dept. _________ Temporary Power Pole _________ Apply for Temporary Power CVEC _________ DRIVEWAY Culvert _________ Gravel _________ LOT WORK Clearing _________ Dig Basement _________ Get Portable Restroom Taylor's Septic _________ BASEMENT Footings Knights Dirt Diggers __________ ► ► *INSPECTION __________ Pour Footings __________ Dig out between footings __________ Drain pipe along outside __________ Put in gravel __________ Mark for Bricks __________ Basement Walls R & R Concrete __________ Seal Walls __________ ► ► *PRE TREAT FOR TERMITES (NAB) __________ IF NEEDED ROUGH IN FOR PLUMBING Dudley __________ Mark floor level (4”); Plastic cover gravel and footings __________ Gravel (8” to 10”) and cloth outside walls __________ ► ► *INSPECTION __________ Pour floor (Formula-Sq. feet/3/27=yds. Cement) Henry Pierce finishes __________
  • 2. HOUSE BUILDING CHECK LIST 2 LOT # ________________________ PERMIT # _______________________ DATE Activity WHO COMPLETED Back fill __________ HOUSE Order floor trusses, roof trusses Jones Trusses __________ Order Lumber 84 Lumber __________ Order Windows, Outside doors J. E. Jamerson, Bill __________ Get Front Door Home Depot or Lowes __________ Put on Floor Trusses Dad __________ Frame House Dad __________ CHECK POWER SCHEDULE—Rough in plumber _____, electrician______, heat pump______, sheet rock______,cabinets______. GARAGE Dig footings __________ Mark for Bricks __________ ► ► *INSPECTION __________ Pour footings __________ BRICKS Order bricks, sand, lentels J. E. Jamerson __________ Order Vinyl Sleeves (for lentels) Brick supply—Forest/Boxley __________ Brick house and garage __________ Pour Garage floor __________ Frame Garage Irby Jones __________ HOUSE Order inside doors J. E. Jamerson __________ Rough in Heat pump Eastbrook Heating and Air __________ Electrical (meter base) Webber __________ Plumber Dudley __________ ► ► *INSPECTION __________ (for rough ins) Roof (color_____________) __________ Siding(color____________Shutters________)Jim Hunter __________ Insulate walls Toler __________
  • 3. HOUSE BUILDING CHECK LIST 3 LOT # ________________________ PERMIT # _______________________ DATE Activity WHO COMPLETED ► ► *INSPECTION __________ Sheet rock ordered/ Delivery Date __________ Sheet rock hung Stephen Jackson __________ Sheet rock finished Rick Boyer __________ OUTSIDE Deck/Patio/ Porch Irby Jones __________ Retaining walls Irby Jones __________ CLEAN UP Me __________ Electric Line put in __________ INSIDE Order Cabinets Reico __________ Order Appliances (color___________) Sears/Reico __________ Delivery Date_____________ Order Hardwood floors Dillingham Floors __________ (one grade down, sealed) Install doors Irby Jones __________ Trim on windows, doors, base Irby Jones __________ Painting (color_____________) Tess Morey (Prime) __________ (Done) __________ Basement stairway & garage step Irby Jones __________ Garage door trim, vinyl wrapped Jim Hunter __________ Garage door Amelia __________ Insulate ceilings Toler __________ Install door knobs, door stops Me __________ Tile (Tile name ____________ O'Brien __________ Grout color ____________/Price______ Hardwood floors installed Dillingham Floors __________ Heat pump finished Eastbrook Heating and Air __________ Install Cabinets Reico __________ Delivery Date_____________ Install Date ______________ Company______________Wood______________Color_____________Knob____________ Kitchen Counters_____________Bathroom Counters ____________ OUTSIDE Well drilled and hooked up to house Fred Jones ___________ Septic System in and hooked up Knights Dirt Diggers ___________ INSIDE Basement insulation Toler ___________ Order Shelves Toler Shelving ___________
  • 4. HOUSE BUILDING CHECK LIST 4 LOT # ________________________ PERMIT # _______________________ DATE Activity WHO COMPLETED Order Mirrors Toler Shelving ___________ Order Carpet (color_____________) Carpetland ___________ Get Lights ___________ Order Towel Racks Toler Shelving ___________ Final Electrical Webber ___________ Plumbing Dudley ___________ Heat pump(registers basement)Eastbrook ___________ Finish Hardwood Floors Webbs Floors ___________ Carpet installed Carpetland ___________ Shelves installed Toler ___________ Mirrors/Towel racks installed Toler Shelving ___________ Cleaning ___________ Pressure Washing ___________ Paint Touch up Tess Morey ___________ ► ► *OCCUPANCY PERMIT ___________ ► ► Well test Pro Chem ___________ OUTSIDE Gutters Irby Jones ___________ Downspout lines Knights Dirt Diggers ___________ Sidewalks/Patio/Basement/Garage ___________ Grass Seeding ___________ ► ► Final Termite NAB ___________ PUT ON MARKET _________________________ SOLD DATE ________________________________ After Cleaning—Finish List ____________________________________________________________ ____________________________________________________________ ____________________________________________________________