2. Challenges encountered the District
Finding Accommodation : There is not so difficulties and challenges
to get accommodation in district , but in field geographical , rainy
season, fooding and lodging Problems occurred and disturbed in
Field only, which are the described below in fact.
1. Unsafe lodging and fooding uses to stay night in field.
2. Expensive fooding and unavailable of Snack in field, I mean
scarcity of Hotel in the Field .
3. We are provided daily allowance for fooding not for lodging when
we Move to field night stay, so there is difficulty and risk to live in
hotel join to chargeable lodge.
3. Challenges …………….
Communication with Government Institution
There is easy to communicate with Government
Institution working in district , we have always
get good response and helpful behavior from all
government officials such as organize Meeting,
take important data , information and any other
helps and tasks.
4. Challenges …………….
• Working With DPC and DAES
• It is stress-free to work with both person we got lots of help
and smooth response from DPC and DAES, for location
identification, social mapping and to prepare for field
planning and returning I think we should stay always in
Close relation and under kind contact of both person in the
district to provide the SMS in district.
• DPC and DAES both may the Guiding person
and Source of the lead information for Field visit to find the
location and link with the people and Concern government
agencies.
5. Establishing office and LRP meeting
• There was problem to establish the office in district for Social
Mobilization team for the House and Location for joint station with DPC
and DAES/AEC for HIMALI.
• DPC office may more effective for office station than others in the
context of Coordination with all government institution.
• Separate Office ,on direct supervision of DPC joint with DAES may Quiet
in districts.
• LRPs meeting with SM team is also viable in district we realize that there
should be a system for one formal Staff meeting with DPC, DAES , DCCI,
LRPs and other Support government institution need to organize by SM
team per month in our Office ,So that Field experience ,meeting with
Communities ,interest of Communities , and level of the progress of
Monitoring system being shared and may instinctive any other solution
and ideas for problems and new entrepreneurs such as except
recognized by HIMALI.
6. First Meeting with Clients:
Meeting with First Clint in Talium VDC ward
Challenges
no 4 in Dalit Basti Local resource person of
• Meeting with First Clints
DADO Jumla.
7. Challenges ………….
• When we organize first meeting in the talium Vdc in Masses
we got good response and interest after our briefing about
HIMALI.
• But at first Communities could not belief us about our grant
System, they asked if your grant like a PAF program we are
Sorry to join with your Project as a Entrepreneur For
funding. They says to us “PAF has already invest the amount
to our group and provide us some IG activities, after one
year they threat our groups to return the amount with
interest too and PAF appear in our Community with police
man to terrify all the people who received the Budget form
PAF program’’. Sanigoun VDC ward no 9 says so.
8. Process we followed in District making
easy to work…
• DLSO ,DADO,DFO,WDO DCCI,DAES, AEC ,District
cooperative division and Small Cottage&
industries office DDC, VDCs, and other
Entrepreneurs of district level who are already
exist and raise in district in agribusiness and
innovative, village level farmer group are
absolutely hence, path and points to work in
district and communities for HIMALI.
9. Strategies to work for Social Mobilization activities
we have followed by
• Prepare Work plan coordinating with DPC ,DAES DCCI and other related
Government and Private institution
• Prepare the inventory of project and agribusiness interest group in District .
• Prepare and Approval of national /intl Team leader .
• Prepare Field work plan in close coordination with DPC/DAES and fill MAL,
verify with DPC informing to DAES.
• Pre approval of NTL , drive to field and organize the meeting with farmer group
,Entrepreneur and other interested ,DAG with Project Promotion
,Communication and operate project orientation to interested Communities and
group.
• Return to district and visit to DPC and shearing the experiences , progress and
feedback.
• Visit other government and private institution
• Prepare the field progress report
10. Progress in two months in District
• Complete Office Establishment with Furniture
• Agreement of Hall for office with DCCI.
• Field visit in nearly 20 vdcs out of 30 VDCs in the period of
two month.
• Visit, meeting and inform about HIMALI in the field and
district with more than 500 people
• Visit and meeting around with 40 groups farmer ,
entrepreneur, Proponent, forest group toll group etcs.
• Prepare the inventory of interest group and DAG around
450 unit/Group.
11. Progress on…….
• Two Business plan received till our returning date 26 September 2013,and other
2 BPs are on touch process forward by DAES.
• List of Received business plan.
• 1- Malika falful tatha Jadibuti udhyog, Malika bota 2 jumla
- By Muga Rawat.
• 2- Mahadev Falful tatha jadibuti udhyog Malika bota 2 jumla
-By Jaye Bdr Rawat
• And 15 business plans are on Contact to receive in District.
• Assist to Subproject Verification to DPC DAES and DCCI/AEC in 4 events
• Verified four approval sub project in in district.
• 1- Cheremalika Bakhra palan
• 2- Himali jadibuti : Jatamashi processing
• 3- Ghase odar Leason forest ( NTF plant production and processing)
• 4- GSM Kesher kheti
21. Best Wishes to all HIMALI TEAM and Participants