Given the following information on a project develop early and late start budgets. Currently it is
week 10 of the project and the amount completed is shown in the table below. What is the status
of the project (over under budget, ahead on behind schedule)?
Solution
The project yet is over budgeted, over budgeed by 1650.
And it is on schedule.

Given the following information on a project develop early and la.pdf

  • 1.
    Given the followinginformation on a project develop early and late start budgets. Currently it is week 10 of the project and the amount completed is shown in the table below. What is the status of the project (over under budget, ahead on behind schedule)? Solution The project yet is over budgeted, over budgeed by 1650. And it is on schedule.