1. EXPLORATORY SURVEY OF WIND AND
SOLAR ENERGY POTENTIAL OF MUSTANG
DISTRICT FOR POWER GENERATION
PRESENTED BY: KUSHAL GURUNG
2.
3.
4. OBJECTIVES OF THE STUDY
• To conduct Wind & Solar Resource Assessment of Mustang with
specific locations
• To identify the policy as well as technical bottlenecks to generate
the energy from wind and solar in Mustang
• To suggest practical ways to produce the energy within short span
of time.
• Limitation: time and resource constraint
5. METHODOLOGY
Identifying Project zones in Mustang
Proposed Zone ID Area (Sq. km)
Lete 1 1.16
Lete 2 0.67
Lete 3 0.40
Larjung 1 1.45
Tukuche 1 0.16
Tukuche 2 0.48
Chhairo 1 0.20
Chhairo 2 0.10
Marpha 1 0.22
Marpha 2 0.26
Marpha 3 0.46
Syang 1 0.76
Jomsom/Thini 1 4.86
Eklebhatti 1 7.00
Eklebhatti 2 3.82
Kagbeni 1 0.49
Kagbeni 2 2.98
Proposed Zone ID Area (Sq. km)
Jhong 1 0.99
Jhong 2 0.43
Jharkot 1 0.96
Tangbe 1 2.31
Tangbe 2 1.01
Tangbe 3 0.93
Tangbe 4 0.73
Chhusang 1 0.10
Chhailey 1 3.66
Ghami 1 1.18
Dhamkar 1 1.74
Syangboche 1 4.28
Syangboche 2 3.41
Tsarang 1 6.89
Tsarang 2 1.95
Tsarang 3 2.25
Proposed Zone ID Area (Sq. km)
Lo Manthang 1 0.73
Lo Manthang 2 0.48
Lo Manthang 3 2.58
Lo Manthang 4 9.68
Lo Manthang 5 3.94
Lo Manthang 6 0.78
Total Zones:
Wind: 39; Solar: 27
Total Area: 77 Sq.km.
Land Covered: 2% of
Mustang District’s
Total Area
8. • Land Procurement: 99% Non-registered Government land; Acquisition
Procedure, Conservation Area
• Planning Approval: EIA requirement >2 years, DoED/IBN license period
only 2 years
• Grid Connection: nearest substation: 220kV Dana, 40km from Jomsom;
NEA restriction 10% of grid capacity
• Infrastructure and Accessibility: Beni-Jomsom 10m wide black topped
road still under construction; existing bridges width very narrow ~4m
CHALLENGES
9. • GoN owned Company: Land acquisition, Planning approval and Global bidding
• Scientific Land Zonation and Land Use Policy: Need for Land Zonation Maps and
specific Land Use Policies for conflict areas (discovery of radioactive elements
in Upper Mustang leading to decision of Govt. to halt one solar project; ACAP)
• Grid Expansion: Expand 220kv line from Dana to Jomsom/Chhusang; Connect
it to Cross border- 400kV New Butwal- New Gorakhpur
• Accessibility: 10m width strong bridges; Blacktop road from Jomsom-Korala
Highway (procurement of turbines from China)
• In-depth research: Legal, Conservation, Power Evacuation, DPR level analysis
RECOMMENDATIONS
11. CALCULATION OF TOTAL WIND/SOLAR ENERGY POTENTIAL IN MUSTANG
Siting suitable project areas/zones based on Elevation, Slope, Land Use and Transportation
METHODOLOGY ADOPTED FOR THE STUDY
Elevation Zone Slope Land Use
<4000m <30° Agriculture, Grassland, Barren Land, Bush
12. CALCULATION OF TOTAL WIND/SOLAR ENERGY POTENTIAL IN MUSTANG
Siting suitable project areas/zones based on Elevation, Slope, Land Use and Transportation
METHODOLOGY ADOPTED FOR THE STUDY
Elevation Slope Land Use Overlapping Common
13. CALCULATION OF TOTAL WIND/SOLAR ENERGY POTENTIAL IN MUSTANG
Siting suitable project areas/zones based on Elevation, Slope, Land Use and Transportation
METHODOLOGY ADOPTED FOR THE STUDY
Transportation Final Overlay Final Overlay
<4km away