This energy audit report summarizes the baseline energy use at M Industries' D Facility. It finds that:
1) D's total annual energy expenditure is $1.84 million, with electricity representing 65.2% of total energy usage but 94.2% of energy costs. Natural gas represents 35.4% of total energy usage but only 5.8% of costs.
2) Over the past 2.5 years, D averaged using 22.5 million kWh of electricity and 420,696 therms of natural gas annually.
3) Analysis of interval meter data shows D's peak electric demands have increased 4.7% from 2012 to 2014, indicating rising energy needs at the facility.
This thesis proposes an innovation called Environmentally Opportunistic Computing (EOC) to address the large amounts of waste heat generated by data centers. EOC nodes would utilize an algorithm to supply waste heat from servers to locations where it is needed, such as for building heating. This would significantly reduce data center cooling costs. The thesis outlines the science and engineering behind EOC, reviews potential applications, discusses intellectual property considerations, identifies barriers to commercialization, and describes additional work needed to develop EOC into a business.
This document discusses various methods and examples for evaluating investment and profitability of projects. It covers topics such as annual costs and profits, traditional measures like return on investment, modern measures like net present value, sensitivity analysis, risk and uncertainty analysis using probabilities, learning curves, and effects of inflation. It also discusses accounting principles, cost of capital, cost control methods, manufacturing cost estimation for single and multiple products, fixed capital cost estimation, and construction costs. Examples provided include calculations related to equipment costs, depreciation, variances, probabilities, breakeven analysis, and total installed plant costs.
Renewable Energy Global Status Report 2015-REN21Ashish Verma
This document is the 2015 Global Status Report published by REN21, an international renewable energy policy network. It provides an overview of global trends in renewable energy development in 2014. Some key findings include:
- Renewable energy capacity and production continued to increase around the world in 2014, with solar photovoltaics and wind power leading growth.
- Total investment in renewable energy declined slightly in 2014 compared to 2013 levels but remained well above 2004 levels.
- Policy support for renewable energy remained strong in 2014, with many countries adopting new targets and policies or strengthening existing ones to drive further deployment of renewables.
Paul Ebbs (2011) - Can lean construction improve the irish construction industryPaul Ebbs
Dissertation completed in 2011 in Dublin Institute of Technology. Survey of the Irish construction industry (n=42). Concluded that lean principles would significantly improve the Irish construction industry
Shale Gas & Hydraulic Fracturing Risks & OpportunitiesTheodor COJOIANU
This document is a project report for an MEng thesis on shale gas and hydraulic fracturing. It includes an introduction outlining the background and aims of the project. The report will analyze risks and opportunities of shale gas development for oil and gas companies and investors based on lessons from development in the US. It will include a literature review on shale gas research trends, a case study of development in Pennsylvania, an analysis of risks to companies operating in Pennsylvania shale gas, an overview of hydraulic fracturing data from the FracFocus national registry, and a worldwide outlook on shale gas resources and development challenges. The student is conducting the project during a placement at MSCI ESG Research in London from June to December 2013 under the supervision of university
The document discusses the potential for offshore wind power in Europe. It notes that Europe's offshore wind potential could power the continent seven times over. Currently over 100 GW of offshore wind projects are planned, which could produce 10% of the EU's electricity while avoiding 200 million tons of CO2 emissions per year. The document advocates for building an offshore grid to connect offshore wind farms and transmit wind power across borders, noting that the EU's offshore grid plans could give Europe a pan-European electricity superhighway. It argues that strong policy support is needed to realize offshore wind power's potential and build a new multi-billion euro industry that delivers green jobs and establishes Europe as a leader in offshore wind technology.
Cobre - Gestión de Activos – Guía para la aplicación de la norma 55001Horacio Felauto
La gestión de activos representa un cambio cultural en el planeamiento estratégico de las empresas que agrega a la visión tradicional sobre productos y clientes la visión de los activos y del valor que estos son capaces de generar al negocio. Autor: International Copper Association Latin America
FICCI strongly believes that the creation of a strong and secure supply chain in India for the solar sector will enable creation of jobs, reduce foreign exchange outflow and lead to increase in investments and sustainable growth of the sector in the long run. There is a strong need to incentivize investments in creating the domestic supply chain with help from both domestic and global players, and to facilitate collaborative arrangements towards enhancing research and development efforts. There is also a strong case for international companies with extensive technology and experience globally to participate in building a strong supply chain in India and be part of India's solar growth story.
This Report on Securing the Solar Supply Chain highlights demand opportunities and key issues for the solar manufacturing supply chain and provides policy recommendations to enable creation of a strong supply chain for solar energy in India.
This thesis proposes an innovation called Environmentally Opportunistic Computing (EOC) to address the large amounts of waste heat generated by data centers. EOC nodes would utilize an algorithm to supply waste heat from servers to locations where it is needed, such as for building heating. This would significantly reduce data center cooling costs. The thesis outlines the science and engineering behind EOC, reviews potential applications, discusses intellectual property considerations, identifies barriers to commercialization, and describes additional work needed to develop EOC into a business.
This document discusses various methods and examples for evaluating investment and profitability of projects. It covers topics such as annual costs and profits, traditional measures like return on investment, modern measures like net present value, sensitivity analysis, risk and uncertainty analysis using probabilities, learning curves, and effects of inflation. It also discusses accounting principles, cost of capital, cost control methods, manufacturing cost estimation for single and multiple products, fixed capital cost estimation, and construction costs. Examples provided include calculations related to equipment costs, depreciation, variances, probabilities, breakeven analysis, and total installed plant costs.
Renewable Energy Global Status Report 2015-REN21Ashish Verma
This document is the 2015 Global Status Report published by REN21, an international renewable energy policy network. It provides an overview of global trends in renewable energy development in 2014. Some key findings include:
- Renewable energy capacity and production continued to increase around the world in 2014, with solar photovoltaics and wind power leading growth.
- Total investment in renewable energy declined slightly in 2014 compared to 2013 levels but remained well above 2004 levels.
- Policy support for renewable energy remained strong in 2014, with many countries adopting new targets and policies or strengthening existing ones to drive further deployment of renewables.
Paul Ebbs (2011) - Can lean construction improve the irish construction industryPaul Ebbs
Dissertation completed in 2011 in Dublin Institute of Technology. Survey of the Irish construction industry (n=42). Concluded that lean principles would significantly improve the Irish construction industry
Shale Gas & Hydraulic Fracturing Risks & OpportunitiesTheodor COJOIANU
This document is a project report for an MEng thesis on shale gas and hydraulic fracturing. It includes an introduction outlining the background and aims of the project. The report will analyze risks and opportunities of shale gas development for oil and gas companies and investors based on lessons from development in the US. It will include a literature review on shale gas research trends, a case study of development in Pennsylvania, an analysis of risks to companies operating in Pennsylvania shale gas, an overview of hydraulic fracturing data from the FracFocus national registry, and a worldwide outlook on shale gas resources and development challenges. The student is conducting the project during a placement at MSCI ESG Research in London from June to December 2013 under the supervision of university
The document discusses the potential for offshore wind power in Europe. It notes that Europe's offshore wind potential could power the continent seven times over. Currently over 100 GW of offshore wind projects are planned, which could produce 10% of the EU's electricity while avoiding 200 million tons of CO2 emissions per year. The document advocates for building an offshore grid to connect offshore wind farms and transmit wind power across borders, noting that the EU's offshore grid plans could give Europe a pan-European electricity superhighway. It argues that strong policy support is needed to realize offshore wind power's potential and build a new multi-billion euro industry that delivers green jobs and establishes Europe as a leader in offshore wind technology.
Cobre - Gestión de Activos – Guía para la aplicación de la norma 55001Horacio Felauto
La gestión de activos representa un cambio cultural en el planeamiento estratégico de las empresas que agrega a la visión tradicional sobre productos y clientes la visión de los activos y del valor que estos son capaces de generar al negocio. Autor: International Copper Association Latin America
FICCI strongly believes that the creation of a strong and secure supply chain in India for the solar sector will enable creation of jobs, reduce foreign exchange outflow and lead to increase in investments and sustainable growth of the sector in the long run. There is a strong need to incentivize investments in creating the domestic supply chain with help from both domestic and global players, and to facilitate collaborative arrangements towards enhancing research and development efforts. There is also a strong case for international companies with extensive technology and experience globally to participate in building a strong supply chain in India and be part of India's solar growth story.
This Report on Securing the Solar Supply Chain highlights demand opportunities and key issues for the solar manufacturing supply chain and provides policy recommendations to enable creation of a strong supply chain for solar energy in India.
Taylor IARU report on building certification schemes pdf (1)Finnoula Taylor
This document provides information on various sustainable building certification schemes, including BREEAM, DGNB, LEED, and STARS. It summarizes the key aspects of each scheme, such as the background, certification process, criteria, costs, and case studies of buildings that have achieved certification. It also profiles the certification schemes used by several universities in the IARU (International Alliance of Research Universities). The document concludes by discussing potential sustainable building projects at the University of Copenhagen that could help raise its green rating under these certification schemes.
This document provides a final report for a proposed wind farm project on the Isle of Cumbrae in Scotland. It summarizes the key aspects of planning and designing the wind farm, including site selection based on environmental and wind analyses, choosing the Vestas-90 2MW turbine model, construction plans, quality management procedures, estimated energy production costs and profitability over 20 years, and permissions required. The project aims to provide renewable energy for the island in an environmentally friendly and financially viable manner.
Project Implementation Review of the NEPAD Infrastructure Short Term Action P...Dr Lendy Spires
Third Project Implementation Review of the NEPAD Infrastructure STAP - 2009 Key Concerns in the Implementation of STAP projects The main intention of the third review of the STAP is to assess where the programme stands today in relation to its status at the time of the last review that was held in 2004. The third review reveals that the implementation progress of the STAP programme has been below expectations. In all, 103 STAP projects were reviewed; of these 16 projects reached completion. Approximately 70% of the STAP projects have progressed in some form or another. Among the STAP projects, 89% of study projects progressed followed by 80% of investment projects, 65% of facilitation projects and 36% of capacity-building projects. A similar ranking is also observed among the STAP completed projects - 33% of studies were completed followed by 20% of investment projects, 6% of facilitation projects and 0% of capacity-building projects. The same has been presented in Figure 1 below. Figure 1: Total number of NEPAD STAP projects The numbers from left to right in Figure 1 under each section in the graph indicate the number of projects in the 2009 review, number of progressed projects followed by the number of completed projects The progress has been particularly slow in the case of capacity-building and facilitation projects due to various reasons such as financing constraints, inadequate mechanisms of project monitoring, unclear definitions of projects, etc.
This document provides a critical design review for an unmanned aerial system (UAS) challenge project. It includes sections on project management, quad-rotor design, mass and cost breakdowns, structural analysis, stress analysis, performance and propulsion specifications, component selection rationale, subsystem descriptions, a payload box mechanism, manufacturing details, testing plans, safety considerations, and technical specifications. Structural analysis was performed using load cases, free body diagrams, and finite element analysis. Stress analysis included calculations for various components under different loading conditions.
This document provides an overview of an unmanned aerial system (UAS) project conducted by a team of engineering students. It includes acknowledgements, a table of contents, list of figures, glossary, and 12 sections that detail the project management, quad-rotor design, mass and cost breakdowns, structural analysis, propulsion and systems engineering, and UAS subsystems. The team designed, built, and tested a quad-rotor UAS to compete in an engineering challenge. Their work involved defining requirements, developing the design, conducting analyses, managing the project, and integrating various subsystems.
Les ministres français et allemand de l'Economie, Bruno Le Maire et Peter Altmaier, ont présenté jeudi un document de 40 pages sur le futur cloud européen.
This document describes three computational fluid dynamics (CFD) case studies conducted using Star-CCM+ software. The first case examines air flow within an annulus and compares analytical and numerical solutions. The second case models supersonic air flow over two airfoil profiles, a diamond wedge and RAE2822, analyzing pressure and velocity fields. The third case models convective heat transfer from a heat source within an enclosed room, visualizing temperature, velocity, pressure, density, vorticity and enthalpy fields.
This document discusses the health and economic impacts of air pollution. It finds that air pollution poses significant threats to both human health and economic prosperity worldwide. Exposure to ambient (outdoor) air pollution and household air pollution from cooking with solid fuels causes millions of premature deaths annually. The economic costs of air pollution are also substantial, resulting in the loss of trillions of dollars worldwide each year in reduced economic output and welfare. While some regions have made progress in reducing indoor air pollution, ambient air pollution exposure continues to increase in many areas as economies develop. Stronger action is needed to address both indoor and outdoor air pollution to improve health outcomes and drive sustainable economic growth.
Global Energy Savings from High Efficiency Distribution TransformersLeonardo ENERGY
The International Copper Association is pleased to announce the launch of “PROPHET II: The potential for global energy savings from high-efficiency distribution transformers.” This significant and strategically important report, prepared by Waide Strategic Efficiency Limited and N14 Energy Limited, is an update of the 2006 report of the same title, continuing the story and supplying much new information while retaining the original core material.
The report covers various aspects of distribution transformers: technical, economic, environmental, social and business. It describes key electric utility regulatory measures and discusses ongoing initiatives in countries around the world, including Australia, Brazil, China, India and USA, and throughout Europe. Also covered are policy issues including market barriers and failures, labelling, voluntary schemes and minimum energy performance standards. It rounds off with some detailed and wide-ranging recommendations.
Consistent policy
One of the report’s key findings is that the global energy savings from distribution transformers, through implementing a progressive and integrated policy based around the Super-efficient Equipment and Appliance Deployment (SEAD) Initiatives, could amount to between 100 and 500 TWh/year.
“The fact that all electricity is passed through several transformers, prior to its final use, means that opportunities to reduce losses in distribution transformers are highly significant in improving the efficiency of electricity networks as a whole,” says Lead Consultant Paul Waide. “Failure to access the savings potential of distribution transformers through a coherent policy framework will lead to significant economic costs, lower competitiveness and substantial environmental damage.”
The report suggests that the objective of public policy should be to create a framework which ensures that the procurement and operation of transformers produces outcomes that minimise the economic and environmental impacts of transformers over their long service lives.
Key recommendations
To help attain this goal, the report makes a number of recommendations in respect to the product, the utility sector and the broader market.
At the product level, recommendations include ensuring that a minimum level of energy performance is achieved, that declared transformer energy performance is reliable, and that transformer energy performance is visible in the market. There is also a call to establish a R&D fund to support further investment in energy efficient transformer technology.
At the utility level, the report recommends that network utilities have the full incentive to provide the lowest lifecycle cost network losses from the final customer perspective. “Network utilities account for 80% of global transformer purchases yet are often not adequately incentivised to reduce network losses,” adds Waide. “Appropriate utility regulation is an essential measure to help ad
This document discusses several case studies of market transformation projects related to energy efficiency and renewable energy. It describes projects in China, India, and other countries that aimed to transition markets toward more sustainable technologies. The China case involved establishing minimum energy performance standards for refrigerators which led manufacturers to improve efficiency and consumers to purchase more efficient models. India's renewable energy program provided support to entrepreneurs and helped develop the market for technologies like wind, biogas, and solar water heaters. Other cases discuss energy efficiency standards, labeling programs, and promoting renewable energy adoption in various national contexts. Overall the cases illustrate how market interventions can help mainstream energy efficient and renewable energy options.
The document provides information about the Ontario-Montclair School District, including its governing board, organizational structure, strategic plan, budgets, site information, and test score data. It discusses the district's 112 years of service, belief statements, objectives, goals, and action teams as part of its strategic plan. It also outlines the district's budgets, revenue sources, negotiations process, and enrollment trends. Site-specific information including test scores, Academic Performance Index, Annual Yearly Progress, and budgets are provided for each school.
This document outlines the systems engineering management plan for the Wire Routing System project. It describes the need for automating wire harness fabrication to reduce costs and errors. Requirements are developed through customer interviews and technical analysis. Multiple system architectures are explored and evaluated against requirements before selecting a hybrid design. Verification and validation testing is planned in four phases. The project work is organized using a work breakdown structure and managed through the defined lifecycle.
Strategic Technology Roadmap Houston Community College 2005schetikos
Developed this for very large community college with 90,000 student enrollment for Houston Community College. Ten Year strategic technology roadmap that was used to guide new CIO. For details contact Lafayette Howell 281-728-5842
This document provides policies and procedures for configuration, change, and release management. It contains four main sections: an introduction that defines key terms and processes, policies that establish the overall policy statement and process owners, processes that describe the steps for identifying, approving, implementing, testing, and tracking changes, and procedures that provide detailed instructions for each process. The overall goal is to formally manage all changes to information systems through documentation, approval, testing, and auditing in order to maintain system integrity and stability.
Improving software testing efficiency using automation methods by thuravupala...Ravindranath Tagore
This document presents a project report on developing a test automation framework for software testing of network elements. The project aims to create test automation scripts for Tellabs' 8800 series router to evaluate advantages like cost savings, increased productivity and testability. The report describes developing test automation using TCL scripts, executing tests on the 8800 router, and analyzing results to validate that automation improves efficiency over manual testing. It also covers an economic justification analysis to market the automation framework.
This document is the Comprehensive Annual Financial Report for the City of Raleigh, North Carolina for the fiscal year ended June 30, 2008. It was prepared by the City's Finance Department and includes introductory information, financial statements, notes to the financial statements, required supplementary information, and combining statements for individual funds. The report provides a comprehensive overview of the City's financial position and activities for the 2008 fiscal year.
This document is the City of Raleigh, North Carolina's Comprehensive Annual Financial Report for the fiscal year ended June 30, 2009. It was prepared by the City's Finance Department and includes various sections such as introductory information, financial statements, notes to the financial statements, and required supplementary information. The financial statements provide information on the City's financial position and activities for the fiscal year.
Cloud Computing Security (Final Year Project) by Pavlos StefanisPavlos Stefanis
Pavlos Stefanis' final year project discusses cloud computing security. It begins with definitions of cloud computing and an overview of cloud types (private, public, hybrid) and service models (IaaS, PaaS, SaaS). The document then reviews the history and literature around cloud security threats and solutions. It analyzes system requirements and management use cases for cloud environments. Pavlos goes on to design and implement security features for the Tonido and ownCloud cloud platforms, testing the Tonido security implementation. The project concludes with reflections on cloud computing security.
Cognitive Market Research provides detailed analysis of Automotive Piston Market in our recently published report titled, "Automotive Piston Market 2020" The market study focuses on industry dynamics including driving factors to provide the key elements fueling the current market growth. The report also identifies restraints and opportunities to identify high growth segments involved in the Automotive Piston market. Key industrial factors such as macroeconomic and microeconomic factors are studied in detail with help of PESTEL analysis in order to have a holistic view of factors impacting Automotive Piston market growth across the globe. Market growth is forecasted with the help of complex algorithms such as regression analysis, sentiment analysis of end-users, etc.
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuidePrivate Consultants
This document provides guidance for developing utility-scale solar photovoltaic power plant projects. It covers the entire project development process from initial site selection and resource assessment through construction and long-term operation. Key topics discussed include solar PV technology, assessing the solar resource, predicting energy yield, site selection factors, plant design considerations, permitting requirements, engineering procurement and construction contracts, and financial analysis methods. The intended audience is project developers of large-scale solar power projects.
This document provides guidance for developing utility-scale solar photovoltaic power plant projects. It covers the entire project development process from initial site selection and design through construction, operation and maintenance. Key topics discussed include solar PV technology, predicting energy yield, environmental permitting, power purchase agreements, and financial analysis. The intended audience is project developers.
Taylor IARU report on building certification schemes pdf (1)Finnoula Taylor
This document provides information on various sustainable building certification schemes, including BREEAM, DGNB, LEED, and STARS. It summarizes the key aspects of each scheme, such as the background, certification process, criteria, costs, and case studies of buildings that have achieved certification. It also profiles the certification schemes used by several universities in the IARU (International Alliance of Research Universities). The document concludes by discussing potential sustainable building projects at the University of Copenhagen that could help raise its green rating under these certification schemes.
This document provides a final report for a proposed wind farm project on the Isle of Cumbrae in Scotland. It summarizes the key aspects of planning and designing the wind farm, including site selection based on environmental and wind analyses, choosing the Vestas-90 2MW turbine model, construction plans, quality management procedures, estimated energy production costs and profitability over 20 years, and permissions required. The project aims to provide renewable energy for the island in an environmentally friendly and financially viable manner.
Project Implementation Review of the NEPAD Infrastructure Short Term Action P...Dr Lendy Spires
Third Project Implementation Review of the NEPAD Infrastructure STAP - 2009 Key Concerns in the Implementation of STAP projects The main intention of the third review of the STAP is to assess where the programme stands today in relation to its status at the time of the last review that was held in 2004. The third review reveals that the implementation progress of the STAP programme has been below expectations. In all, 103 STAP projects were reviewed; of these 16 projects reached completion. Approximately 70% of the STAP projects have progressed in some form or another. Among the STAP projects, 89% of study projects progressed followed by 80% of investment projects, 65% of facilitation projects and 36% of capacity-building projects. A similar ranking is also observed among the STAP completed projects - 33% of studies were completed followed by 20% of investment projects, 6% of facilitation projects and 0% of capacity-building projects. The same has been presented in Figure 1 below. Figure 1: Total number of NEPAD STAP projects The numbers from left to right in Figure 1 under each section in the graph indicate the number of projects in the 2009 review, number of progressed projects followed by the number of completed projects The progress has been particularly slow in the case of capacity-building and facilitation projects due to various reasons such as financing constraints, inadequate mechanisms of project monitoring, unclear definitions of projects, etc.
This document provides a critical design review for an unmanned aerial system (UAS) challenge project. It includes sections on project management, quad-rotor design, mass and cost breakdowns, structural analysis, stress analysis, performance and propulsion specifications, component selection rationale, subsystem descriptions, a payload box mechanism, manufacturing details, testing plans, safety considerations, and technical specifications. Structural analysis was performed using load cases, free body diagrams, and finite element analysis. Stress analysis included calculations for various components under different loading conditions.
This document provides an overview of an unmanned aerial system (UAS) project conducted by a team of engineering students. It includes acknowledgements, a table of contents, list of figures, glossary, and 12 sections that detail the project management, quad-rotor design, mass and cost breakdowns, structural analysis, propulsion and systems engineering, and UAS subsystems. The team designed, built, and tested a quad-rotor UAS to compete in an engineering challenge. Their work involved defining requirements, developing the design, conducting analyses, managing the project, and integrating various subsystems.
Les ministres français et allemand de l'Economie, Bruno Le Maire et Peter Altmaier, ont présenté jeudi un document de 40 pages sur le futur cloud européen.
This document describes three computational fluid dynamics (CFD) case studies conducted using Star-CCM+ software. The first case examines air flow within an annulus and compares analytical and numerical solutions. The second case models supersonic air flow over two airfoil profiles, a diamond wedge and RAE2822, analyzing pressure and velocity fields. The third case models convective heat transfer from a heat source within an enclosed room, visualizing temperature, velocity, pressure, density, vorticity and enthalpy fields.
This document discusses the health and economic impacts of air pollution. It finds that air pollution poses significant threats to both human health and economic prosperity worldwide. Exposure to ambient (outdoor) air pollution and household air pollution from cooking with solid fuels causes millions of premature deaths annually. The economic costs of air pollution are also substantial, resulting in the loss of trillions of dollars worldwide each year in reduced economic output and welfare. While some regions have made progress in reducing indoor air pollution, ambient air pollution exposure continues to increase in many areas as economies develop. Stronger action is needed to address both indoor and outdoor air pollution to improve health outcomes and drive sustainable economic growth.
Global Energy Savings from High Efficiency Distribution TransformersLeonardo ENERGY
The International Copper Association is pleased to announce the launch of “PROPHET II: The potential for global energy savings from high-efficiency distribution transformers.” This significant and strategically important report, prepared by Waide Strategic Efficiency Limited and N14 Energy Limited, is an update of the 2006 report of the same title, continuing the story and supplying much new information while retaining the original core material.
The report covers various aspects of distribution transformers: technical, economic, environmental, social and business. It describes key electric utility regulatory measures and discusses ongoing initiatives in countries around the world, including Australia, Brazil, China, India and USA, and throughout Europe. Also covered are policy issues including market barriers and failures, labelling, voluntary schemes and minimum energy performance standards. It rounds off with some detailed and wide-ranging recommendations.
Consistent policy
One of the report’s key findings is that the global energy savings from distribution transformers, through implementing a progressive and integrated policy based around the Super-efficient Equipment and Appliance Deployment (SEAD) Initiatives, could amount to between 100 and 500 TWh/year.
“The fact that all electricity is passed through several transformers, prior to its final use, means that opportunities to reduce losses in distribution transformers are highly significant in improving the efficiency of electricity networks as a whole,” says Lead Consultant Paul Waide. “Failure to access the savings potential of distribution transformers through a coherent policy framework will lead to significant economic costs, lower competitiveness and substantial environmental damage.”
The report suggests that the objective of public policy should be to create a framework which ensures that the procurement and operation of transformers produces outcomes that minimise the economic and environmental impacts of transformers over their long service lives.
Key recommendations
To help attain this goal, the report makes a number of recommendations in respect to the product, the utility sector and the broader market.
At the product level, recommendations include ensuring that a minimum level of energy performance is achieved, that declared transformer energy performance is reliable, and that transformer energy performance is visible in the market. There is also a call to establish a R&D fund to support further investment in energy efficient transformer technology.
At the utility level, the report recommends that network utilities have the full incentive to provide the lowest lifecycle cost network losses from the final customer perspective. “Network utilities account for 80% of global transformer purchases yet are often not adequately incentivised to reduce network losses,” adds Waide. “Appropriate utility regulation is an essential measure to help ad
This document discusses several case studies of market transformation projects related to energy efficiency and renewable energy. It describes projects in China, India, and other countries that aimed to transition markets toward more sustainable technologies. The China case involved establishing minimum energy performance standards for refrigerators which led manufacturers to improve efficiency and consumers to purchase more efficient models. India's renewable energy program provided support to entrepreneurs and helped develop the market for technologies like wind, biogas, and solar water heaters. Other cases discuss energy efficiency standards, labeling programs, and promoting renewable energy adoption in various national contexts. Overall the cases illustrate how market interventions can help mainstream energy efficient and renewable energy options.
The document provides information about the Ontario-Montclair School District, including its governing board, organizational structure, strategic plan, budgets, site information, and test score data. It discusses the district's 112 years of service, belief statements, objectives, goals, and action teams as part of its strategic plan. It also outlines the district's budgets, revenue sources, negotiations process, and enrollment trends. Site-specific information including test scores, Academic Performance Index, Annual Yearly Progress, and budgets are provided for each school.
This document outlines the systems engineering management plan for the Wire Routing System project. It describes the need for automating wire harness fabrication to reduce costs and errors. Requirements are developed through customer interviews and technical analysis. Multiple system architectures are explored and evaluated against requirements before selecting a hybrid design. Verification and validation testing is planned in four phases. The project work is organized using a work breakdown structure and managed through the defined lifecycle.
Strategic Technology Roadmap Houston Community College 2005schetikos
Developed this for very large community college with 90,000 student enrollment for Houston Community College. Ten Year strategic technology roadmap that was used to guide new CIO. For details contact Lafayette Howell 281-728-5842
This document provides policies and procedures for configuration, change, and release management. It contains four main sections: an introduction that defines key terms and processes, policies that establish the overall policy statement and process owners, processes that describe the steps for identifying, approving, implementing, testing, and tracking changes, and procedures that provide detailed instructions for each process. The overall goal is to formally manage all changes to information systems through documentation, approval, testing, and auditing in order to maintain system integrity and stability.
Improving software testing efficiency using automation methods by thuravupala...Ravindranath Tagore
This document presents a project report on developing a test automation framework for software testing of network elements. The project aims to create test automation scripts for Tellabs' 8800 series router to evaluate advantages like cost savings, increased productivity and testability. The report describes developing test automation using TCL scripts, executing tests on the 8800 router, and analyzing results to validate that automation improves efficiency over manual testing. It also covers an economic justification analysis to market the automation framework.
This document is the Comprehensive Annual Financial Report for the City of Raleigh, North Carolina for the fiscal year ended June 30, 2008. It was prepared by the City's Finance Department and includes introductory information, financial statements, notes to the financial statements, required supplementary information, and combining statements for individual funds. The report provides a comprehensive overview of the City's financial position and activities for the 2008 fiscal year.
This document is the City of Raleigh, North Carolina's Comprehensive Annual Financial Report for the fiscal year ended June 30, 2009. It was prepared by the City's Finance Department and includes various sections such as introductory information, financial statements, notes to the financial statements, and required supplementary information. The financial statements provide information on the City's financial position and activities for the fiscal year.
Cloud Computing Security (Final Year Project) by Pavlos StefanisPavlos Stefanis
Pavlos Stefanis' final year project discusses cloud computing security. It begins with definitions of cloud computing and an overview of cloud types (private, public, hybrid) and service models (IaaS, PaaS, SaaS). The document then reviews the history and literature around cloud security threats and solutions. It analyzes system requirements and management use cases for cloud environments. Pavlos goes on to design and implement security features for the Tonido and ownCloud cloud platforms, testing the Tonido security implementation. The project concludes with reflections on cloud computing security.
Cognitive Market Research provides detailed analysis of Automotive Piston Market in our recently published report titled, "Automotive Piston Market 2020" The market study focuses on industry dynamics including driving factors to provide the key elements fueling the current market growth. The report also identifies restraints and opportunities to identify high growth segments involved in the Automotive Piston market. Key industrial factors such as macroeconomic and microeconomic factors are studied in detail with help of PESTEL analysis in order to have a holistic view of factors impacting Automotive Piston market growth across the globe. Market growth is forecasted with the help of complex algorithms such as regression analysis, sentiment analysis of end-users, etc.
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuidePrivate Consultants
This document provides guidance for developing utility-scale solar photovoltaic power plant projects. It covers the entire project development process from initial site selection and resource assessment through construction and long-term operation. Key topics discussed include solar PV technology, assessing the solar resource, predicting energy yield, site selection factors, plant design considerations, permitting requirements, engineering procurement and construction contracts, and financial analysis methods. The intended audience is project developers of large-scale solar power projects.
This document provides guidance for developing utility-scale solar photovoltaic power plant projects. It covers the entire project development process from initial site selection and design through construction, operation and maintenance. Key topics discussed include solar PV technology, predicting energy yield, environmental permitting, power purchase agreements, and financial analysis. The intended audience is project developers.
This document provides guidance for developers of utility-scale solar photovoltaic power plants. It covers the entire project development process from early stage development through to construction, operation and financing. The document discusses key topics such as solar PV technology, site selection, plant design, permitting, contracts, construction, operations and maintenance, policies to support solar development, and financial analysis. It is intended to help project developers successfully develop, build and operate large-scale solar power plants.
This document provides guidance for developers of utility-scale solar photovoltaic power plants. It covers the entire project development process from early stage development through to construction, operation and financing. Key topics covered include solar PV technology, site selection, plant design, permitting, contracts, construction, operation and maintenance. The intended audience is project developers seeking to build large-scale solar farms.
Democratic Republic of the Congo - Energy OutlookRachit Kansal
The Democratic Republic of the Congo is a very resource-rich country, with the second largest rainforest basin in the world and an abundance of hydro resources.
The country is now at crossroads. Going down one path can guarantee its citizens robust energy security and make it a strong energy exporter. The other path could lead to over-exploitation of its resources, environmental destruction and higher economic disparity.
This report examines various scenarios in the country's future, each of which prioritize different goals and policies.
SSTRM - StrategicReviewGroup.ca - Workshop 2: Power/Energy and Sustainability...Phil Carr
This document describes the Power/Energy/Sustainability workshop which was part of the Soldier Systems Technology Roadmap initiative to identify technologies that could contribute to a superior soldier system. The workshop focused on power/energy as it is a key enabler of soldier capabilities. Participants identified six potential collaborative projects in areas like power standards, storage, and fuel cells.
This business plan is for a proposed recycling and upcycling plant called NewGate India located in Hyderabad, Andhra Pradesh. The plan outlines setting up a facility that will collect post-consumer and industrial waste to recycle into new materials and upcycle into saleable products. It will focus on plastic, paper, and e-waste recycling initially. The plan discusses conducting market research to identify opportunities, setting up the production process with necessary equipment and partnerships, and implementing strategies for pricing, distribution, promotion and organizational structure. The goal is to divert waste from landfills while generating profit and creating jobs.
380 Vdc Architectures for the Modern Data CenterEltek
The public mandate to develop and operate more efficient, lower cost, more
reliable, more sustainable infrastructure clearly includes data center design and
operation. Ideally, these concepts are addressed at the concept and design stage
and implemented from the foundation to daily operations. Practically, new and
different approaches (evolving thinking and technologies) are implemented in all
facilities. This paper presents an overview of the case for the application of 380
Vdc as a vehicle for optimization and simplification of the critical electrical system
in the modern data center.
The Mobile Marketing Association (MMA) is the premier global non-profit trade association established to lead the growth of mobile marketing and its associated technologies. The MMA is an action-oriented organization designed to clear obstacles to market development, establish mobile media guidelines and best practices for sustainable growth, and evangelize the use of the mobile channel. The more than 750 member companies, representing over forty countries around the globe, include all members of the mobile media ecosystem. The Mobile Marketing Association’s global headquarters are located in the United States and it has regional chapters including North America (NA), Europe, Latin American (LATAM) and Asia Pacific (APAC) branches.
As the primary source for mobile marketing information and expertise, the MMA is dedicated to:
Provide an industry forum to work cooperatively to resolve key issues
Unify industry-wide, global and regional work groups that focus on industry initiatives
Provide representation for the mobile marketing industry for major legislative bodies worldwide
Globally share perspectives on mobile marketing for Europe, Asia, Americas, and Africa
Fuel B2B interaction through seminars, conferences and events
Develop metrics to measure ad delivery and consumer response
Develop open and compatible mobile marketing technical and creative standards
Define and publish mobile marketing practices on privacy, ad delivery, ad measurement, etc.
Provide effective guidelines for mobile marketing to advertisers, agencies and consumers
Serve as the key advocate on behalf of the mobile marketing industry
Mobile Marketing Association - Best Practices Guide 2011Mosio
This document provides the version 6.0 of the U.S. Consumer Best Practices published by the Mobile Marketing Association on March 1, 2011. It establishes guidelines for standard rate, premium rate, and free-to-end-user mobile marketing programs. The guidelines cover topics like opt-in/opt-out procedures, messaging frequency, content restrictions, dispute resolution, and certification requirements. The document aims to standardize practices and simplify mobile advertising while protecting consumers.
This document presents the results of a study analyzing the global photovoltaic power potential by country. The study uses high resolution solar resource and other geospatial data to estimate the theoretical, practical, and economic potential for solar PV development in each country. The theoretical potential represents the total solar energy available without constraints, while the practical potential accounts for physical and environmental exclusions. The economic potential limits the analysis to locations where PV is cost competitive based on levelized cost of energy calculations. Key findings show significant PV potential globally, with the practical potential able to supply multiple times current global electricity demand.
This document is a cheat sheet for the C programming language. It provides an introduction to C and covers basic data types, control flow, expressions, operators, program structure, advanced data types like arrays and pointers, advanced concepts like file I/O and dynamic memory allocation, and multi-file programs. The cheat sheet was written by Andrew Sterian and contains a table of contents and 8 sections covering various aspects of the C language.
This document describes an internship report on cost modeling of offshore wind farm installations. The report examines the installation process of offshore wind farms, including foundations, turbines, and electrical infrastructure. It details the ECN Install modeling tool and its cost module. A case study application to the Gemini offshore wind farm is presented, with results on resource utilization, delays, and costs. The report aims to contribute to improved cost estimations for offshore wind farm installations.
This document outlines the regulations for the 2012/13 UAE F1 in Schools Secondary Schools Challenge competition. It defines key terms and sets expectations for competing teams. Teams must design, manufacture, and race model formula one cars. They will be judged on their specifications, engineering solutions, portfolio displaying their design process, and ability to discuss their project. National champions will be selected based on points earned across the various judging categories.
The document is a project report for an Integrated Building Management System (IBMS) created by Hamza Khan. It details the goals of creating a programmable logic controller card to integrate diverse building systems and automate control for improved energy efficiency. The report outlines tasks completed during an internship including learning microcontrollers, understanding the IBMS schematics, writing firmware codes, and debugging the controller card.
This document provides a technical proposal for a 2000MW photovoltaic power plant project in Syria. It outlines the project implementation, engineering design, construction organization ability, cost control measures, schedule and progress control measures, quality standards and control measures, and on-site health, safety and environment management measures. The key points addressed include a standard 100MW PV module design with 230kV grid-connected substations, engineering tasks and scope, construction organization and sequence, cost control during construction and completion, ensuring the construction schedule is met, following quality standards and specifications, and managing health, safety and environment on-site.
The Economics of Sustainability in the Comemrcial Real Estate Sectorscottbrooker
The goal of this white peper is to help real estate managers better understand the motivations behind management decisions, through qualitative and quantitative research and models, an provide recommendations to make the case for energy effeciency improvements. Questions answered with the paper include;
-How does energy effeciency improvement get implemented?
-Who is the driver behind the decision?
-What financial metrics are used to determine if an investment makes economic sense?
How does a real estate amanger choose one investment vehicle over another?
This document presents the design of a new concentrated solar power plant in Morocco. Six potential locations were considered and Ouarzazate was selected as the most suitable. A central tower configuration was chosen over a parabolic trough design. A MATLAB model was developed to size the solar field, power cycle components, and optimize the storage size and turbine capacity. The final optimized plant produces 150 MW, has 7 hours of molten salt storage, and annually produces 731 GWh at 19.3% overall efficiency. The payback period is 10 years with a levelized cost of electricity of 16.7 cents/kWh and annual CO2 emissions reductions of 403,500 tons.
The document reports on renewable power generation costs in 2022. It finds that despite supply chain issues and rising costs, the average global cost of electricity from solar PV fell by 2% and wind by 5% in 2022. At least 86% of new utility-scale solar and 87% of onshore wind projects had lower costs than fossil fuel options. However, fossil fuel price rises improved the competitiveness of renewables even more in some countries. The document provides details on latest cost trends for solar PV and onshore wind technologies.
Con Edison completed its 2008 stray voltage testing and facility inspection programs in accordance with New York PSC requirements. Key aspects include:
- Stray voltage testing of underground and overhead distribution structures, substations, transmission lines and streetlights. Quality assurance measures were instituted.
- Facility inspections of underground and overhead distribution structures, substations, transmission lines were also completed. Deficiencies identified and repairs made.
- Additional stray voltage detection methods were used including mobile detectors and routine work testing.
- Analysis shows stray voltage detection programs have reduced electric shocks associated with company equipment by 94% since 2004.
- Future recommendations include improving transmission and substation testing.
Similar to Generic Industrial Audit Report-2-24-15 (20)
1. North America l Europe l Africa l Australia l Asia
Energy Audit Report
Prepared for:
M Industries, Inc.
D Facility
Dec 17, 2014
2. M Industries – Dynacor Facility
Energy Audit Report Executive Summary
1
Table of Contents
Executive Summary......................................................................................................................4
Project Overview ....................................................................................................................... 4
Summary of Findings and Recommendations ........................................................................... 4
Baseline Energy Use.....................................................................................................................7
Electricity Use............................................................................................................................ 7
Natural Gas Use ......................................................................................................................... 8
D’s Energy End-use Breakdown................................................................................................. 9
Energy Efficiency Measures and Recommendations............................................................... 11
Energy Efficiency Measure (EEM) Details.....................................................................................12
EEMs for Current Implementation .......................................................................................... 12
EEM-1 Synthetic Hydraulic Fluid...................................................................................... 12
Existing Conditions............................................................................................... 12
Measure Description............................................................................................ 13
Savings ................................................................................................................. 13
Installed Cost Estimate......................................................................................... 13
Measurement and Verification (M&V) ................................................................ 13
EEM-2 Energy Star/Miser on Vending Machines ............................................................. 13
ExistingConditions............................................................................................... 13
Measure Description............................................................................................ 14
Savings ................................................................................................................. 14
Installed Cost Estimate......................................................................................... 14
Measurement and Verification (M&V)................................................................. 14
Background Information...................................................................................... 14
EEM-3 Extend LED Lighting to the Rest of D Parking Lot.................................................. 14
ExistingConditions............................................................................................... 14
Measure Description............................................................................................ 15
Savings ................................................................................................................. 15
Installed Cost Estimate......................................................................................... 16
Measurement and Verification (M&V)................................................................. 16
EEM-4 Convert Diesel Generators to bi-fuel Adding Natural Gas ................................... 16
ExistingConditions............................................................................................... 16
Measure Description............................................................................................ 16
Savings ................................................................................................................. 16
Installed Cost Estimate......................................................................................... 17
Measurement and Verification (M&V)................................................................. 17
Background Information...................................................................................... 17
EEM for Future Implementation When Replacing or Adding Molds........................................ 18
EEM-5 All-Electric Auburg Versus Husky Hydraulic Mold ................................................. 18
ExistingConditions............................................................................................... 18
Measure Description............................................................................................ 18
Savings ................................................................................................................. 21
Installed Cost Estimate......................................................................................... 21
Measurement and Verification (M&V) ................................................................ 21
Background Information...................................................................................... 21
Energy Cost Savings EEM (No reduction in energy or carbon emissions)................................ 22
EEM-6 Forklift Battery Off-peak Charging........................................................................ 22
3. M Industries – Dynacor Facility
Energy Audit Report Executive Summary
2
ExistingConditions............................................................................................... 22
Measure Description............................................................................................ 22
Savings ................................................................................................................. 23
Installed Cost Estimate......................................................................................... 23
Measurement and Verification (M&V)................................................................. 23
BackgroundInformation....................................................................................... 24
D Interval Meter DataAppendix A:
AdditionalElectronicDocumentationAppendix B:
List of Tables
Table 1: Summary of Energy Efficiency Measures.................................................................................. 6
Table 2: D Historical Electricity and Natural Gas Use ............................................................................. 7
Table 3: Twelve Electric Billing Meters ................................................................................................... 8
Table 4: D Exterior Lighting Baseline and Proposed Energy Use and EEM Cost Estimate.................... 15
Table 5: Auburg Calculated Annual Energy Use.................................................................................... 20
Table 6: Husky Calculated Annual Energy Use...................................................................................... 20
Table 7: Electric Versus Hydraulic Molds.............................................................................................. 22
Table 8: Comparative Forklift Charger Test Results .............................................................................. 25
List of Figures
Figure 1: Total Energy by End-Use for D ................................................................................................. 9
Figure 2: D’s Electricity Consumption by End-use ................................................................................ 10
Figure 3: D Gas Energy End-use............................................................................................................ 10
Figure 4: Metal Halide and LED Exterior Lamp..................................................................................... 15
Figure 5: Power Draw of Auburg 165 ton Electric Mold....................................................................... 19
Figure 6: Power Draw of Husky 120 ton Hydraulic Mold...................................................................... 20
Figure 7: Sample Electric Bill for One M Place Campus........................................................................ 24
Figure 8: D Meter# ####908 Typical Daily Energy Profiles 2012.......................................................... 26
Figure 9: D Meter# #####908 Typical Daily Energy Profiles 2014........................................................ 26
Figure 10: D Meter# #####683 Typical Daily Energy Profiles 2012...................................................... 26
Figure 11: D Meter# #####683 Typical Daily Energy Profiles 2014...................................................... 26
Figure 12: D Meter# ####3085 Typical Daily Energy Profiles 2012...................................................... 26
Figure 13: D Meter# 141643085 Typical Daily Energy Profiles 2014.................................................... 26
4. M Industries – Dynacor Facility
Energy Audit Report Executive Summary
3
5. M Industries – Dynacor Facility
Energy Audit Report Executive Summary
4
EXECUTIVE SUMMARY
Project Overview
The objective of this building evaluation and report is to provide M Industries, Inc. with a technical
and economic strategy to understand energy use by D and its operating systems and practices, to
achieve greater energy efficiency, and reduce energy use while maintaining productivity.
This audit was conducted in accordance with ASHRAE’s Energy Audit Guidelines for Commercial
Buildings and included a thorough review of the mechanical and electrical systems, maintenance
practices and operating procedures. After review of the audit report by building management and
staff, First Carbon Solutions staff will meet with M to develop a strategy for implementation of the
recommended measures.
Summary of Findings and Recommendations
Table 1 shows the energy cost savings for six (6) energy efficiency measures (EEMs) identified for D.
It outlines three groups of recommended energy efficiency measures (EEMs): immediate; upon
upgrade; and reduction of energy cost.
The first group of four EEMs can be implemented immediately. They will reduce the electricity use by
5,274,529 kWh/year, a 23.4% reduction in electricity purchased from the grid. However, because of
the on-site electrical generation, the amount of natural gas actually will increase by 403,758 therms
per year an increase of 96%, almost doubling the current gas use. Fortunately, the cost of natural gas
is so much lower than the cost of electricity there is a reduction in D’s energy cost of 15.7% or
$289,656 per year.
The contractor calculated net non-energy dollars savings to be a negative $-29,752 per year. The
savings due to reductions in labor, lamp and hydraulic oil for the molds were more than offset by the
added O&M cost of the electric generators as they will run 3,250 hours per year instead of less than
200 hours a year. Emissions from producing electricity on-site by burning natural gas are less per
kWh produced that the emissions emitted when the area grid produces electric power. The four
EEMs reduce carbon dioxide (CO2) by (3.22 million pounds) 1,462 metric tonnes.
The second group of EEMs has only one EEM that saves 1,543,362 kWh/year. It can be implemented
when D needs to add new injections molding machines. This EEM would save an additional 6.46% of
energy cost or $118,812 per year. There are no “non-energy” benefits. The energy savings will
reduce CO2 by (2.32 million pounds) 1,055 metric tonnes.
The EEM of group three does not save energy or reduce carbon emissions, but it does reduce energy
cost by taking advantage of the off-peak electricity rates which are 35% lower than on-peak rates. It
will reduce overall energy costs by about 1.1%.
If all six EEMs are implemented, electricity use will be reduced by 30.3% or 6,817,892 kWh/year.
Natural gas use goes up by 403,758 therms/year a 96% increase. However, the total annual energy
cost is reduced by $415,111. Unfortunately the additional use of the on-site electrical generators
6. M Industries – Dynacor Facility
Energy Audit Report Executive Summary
5
increases annual O&M cost so non-energy benefits are negative by $-29,752 per year. With the six
EEMs, D’s total net cost reduction is $385,359. The total net CO2 reduction for the six EEMs is (5.54
million pounds) 2,517 metric tonnes.
To implement all six EEMs, the estimated investment cost is $417,707 which will be recovered in
1.1 years. This does not include any state, federal or utility incentives or tax advantages.
7. M Industries – Dynacor Facility
Energy Audit Report Executive Summary
6
Table 1: Summary of Energy Efficiency Measures
EEM # Measure Name
KWh/yr
Savings
Therm
savings
Net Energy
Dollar
Savings
Total Dollar
Savings w/Non-
energy Benefits
Estimated
Dollar cost
Simple
Payback
(years)
1
Shell Tellus S4 ME46 Synthetic
hydraulic fluid
104,396 0 $8,037 $15,571 $23,826 1.5
2
Energy Star/Miser on vending
machines
9,000 0 $693 $693 $1,790 2.6
3
Extend LED Lights to Rest of
Parking Lot
91,133 0 $7,016 $25,500 $93,325 3.7
4
Convert diesel generators to
bi-fuel adding natural gas
5,070,000 -403,758 $273,911 $218,141 $178,846 0.8
Totals 5,274,529 -403,758 $289,656 $259,905 $297,787 1.1
5
All-electric Auburg Vs Husky
Hydraulic (Assumes adding
10% more molds, 1,246 tons
1,543,362 0 $118,812 $118,812 $109,620 0.9
6
Forklift Battery Off-peak
charging
0 0 $6,643 $6,643 $10,300 1.6
Future EEMs that could be implemented when equipment needs to be replaced or business expands
These four EEMs can be implemented at Dynacor immediately to achieve energy cost savings
This EEM reduces energy cost but does not save energy or reduce carbon emissions
8. Facility
Energy Audit Report D’s Baseline Energy Use
7
BASELINE ENERGY USE
D is located at the M headquarters campus. D’s total annual energy expenditure is $1,840,000.
As shown in Table 2 below, historical electricity use at D has averaged 22,512,696 kWh/year over the
last two and a half years. The natural gas use averaged 420,696 therms per year over the same
period. Converting the electricity and natural gas energy to British thermal unit (Btus), the total
energy use is 119 million Btus per year.
The natural gas is 35.4% of the total Btus of energy and electricity is 64.6%; however, in energy
dollars, natural gas is only 5.8% ($106,785) and electricity is 94.2% ($1,733,696) of D’s total energy
cost.
Table 2: D Historical Electricity and Natural Gas Use
Electric Use (kWh) Natural Gas Use (Therm)
2012 2013 2014 Average 2012 2013 2014 Average
Jan 1,930,852 2,136,039 1,732,635 1,933,175 76,672 81,460 50,025 69,386
Feb 1,728,829 1,838,589 2,174,727 1,914,049 63,606 79,576 47,974 63,719
Mar 1,870,195 1,506,637 1,790,601 1,722,477 39,533 66,867 31,617 46,005
Apr 1,792,484 1,899,179 1,501,372 1,731,012 17,835 34,883 10,420 21,046
May 1,878,650 2,124,515 2,068,740 2,023,968 6,371 11,515 0 8,943
Jun 2,029,609 1,941,340 1,671,457 1,880,802 2,757 5,328 0 4,042
Jul 1,951,131 1,600,428 1,808,497 1,786,685 3,097 5,458 0 4,278
Aug 1,695,660 2,016,028 0 1,855,844 5,861 5,334 0 5,598
Sep 2,144,000 1,750,996 0 1,947,498 16,156 23,750 0 19,953
Oct 1,812,511 1,593,100 0 1,702,805 47,313 48,937 0 48,125
Nov 2,269,764 2,119,493 0 2,194,629 62,786 54,285 0 58,535
Dec 1,906,868 1,732,635 0 1,819,751 84,411 57,723 0 71,067
TOTAL 23,010,553 22,258,979 12,748,028 22,512,696 426,396 475,116 140,036 420,696
TOTAL ENERGY USE IN KBTU 118,905,448
ENERGY USE INDEX(KBTU/SF/YR) 253.7
Electricity Use
Electricity use at D is provided by ComEd and Constellation Energy. The overall campus bill is
consolidated with readings from 12 electric meters as shown in Table 3. The three meters
highlighted in green (meter numbers 1, 2, and 3) all serve the D facility.
Electricity at D represents approximately 65.2% of the total electric energy but it has a combined
peak demand of 2,755 kW or 91.1% of the total billing demand.
9. Facility
Energy Audit Report D’s Baseline Energy Use
8
Table 3: Twelve Electric Billing Meters
Figure 8 through Figure 13 in Appendix A shows how each of the three D meters uses electric energy
every 30 minutes for several typical days of the week for two different years. For August 2012, the
data is plotted for a Monday, a Tuesday, a Saturday and a Sunday; whereas, for July 2014 the data is
plotted for a Monday, a Tuesday, July 4th holiday on a Friday, a Saturday, and a Sunday.
The most striking difference between 2012 and 2014 is the wider range of energy values.
D’s Boiler Meter has a tight range with kW varying from a low of 400 kW at noon Monday 8/6/2012
to a high of 600 kW at 5:00 AM Sunday 8/12/2012. The range for 2014 is from a low of 400 kW at
4:30 AM Monday 6/30/2014 to a high of 815 kW at 8:30 AM Tuesday 7/1/2014. The range in 2012
was only 200 kW, but in 2014 the range was 415 kW.
D’s Chiller Meter shows a significant change from 2012 to 2014. In 2012, the energy use was
essentially flat for weekdays and weekends. Usage varied from a low of 650 kW to a high of 740 kW,
a range of less than 90 kW. However, in 2014, the range widened significantly with the low going
lower to 470 kW on Sunday 7/6/2014 and the high going higher to 800 kW on Monday 6/30/2014.
The range in 2014 widened to 330 kW more than 3.5 times wider than in 2012.
D’s Injection Molding Machine meter has the highest energy use of the three meters. The range of
energy demand has also widened for this meter with 2012 going from a low of 850 kW at 14:30
Sunday 8/12/2014 to a high of 1410 at 14:30 Monday 8/6/2012. In 2014, the range was from a low
of 660 kW at 3:00 AM Saturday to a high of 1500 kW at 13:00 Monday 6/30/2014. The 2012 range
was 560 kW compared to the range in 2014 of 840 kW.
For the three meters, combined peak demand has grown from 2,970 kW in 2012 to 3,110 kW in
2014. This translates to a 4.7 % increase over two years or about 2.5% per year.
Natural Gas Use
North Shore Gas provided natural gas data for two meters,1 (57.2%) and 2 (42.6%). Unlike electricity
data which is available in 30-minute intervals, natural gas metering is limited to monthly data.
10. Facility
Energy Audit Report D’s Baseline Energy Use
9
D’s Energy End-use Breakdown
Energy use at D’s warehouse and manufacturing facility has been broken down into multiple end-
uses based on engineering judgment, field metering and data logging. This breakdown assures that
when estimating energy savings, the calculations are applied to a specific portion of the total energy,
thus preventing overly optimistic energy savings estimates. Total energy use is provided as BTUs, so
that gas and electricity can be compared on an equitable basis.
As mentioned above, electricity accounts for 64.6% of total energy use, while natural gas use
accounts for 35.4% of energy. Due to the very low cost for natural gas on an energy cost basis,
natural gas is only about 5% of D’s energy bill in dollars. Therefore, the focus of the energy audit is
on electricity savings.
As shown in Figure 1 below, the majority of D’s total energy in Btus (48.0%) is used by the injection
molding machines and the process cooling system for the molds. The next largest energy user is
natural gas for Space Heating (31%). The Compressed Air System is expected to use about 8% of the
energy, and the HVAC fans and cooling are estimated to use 5%. The gas-fired service water heating
is also about 5% of the total energy use. Lighting energy is estimated to be very small at 2% and the
warehouse forklift battery charging system uses 0.72% of the total energy.
Figure 1: Total Energy by End-Use for D
11. Facility
Energy Audit Report D’s Baseline Energy Use
10
Figure 2 shows electricity use at D broken down by end-using equipment. The molds and process
cooling use 74.8% of the total electricity. The compressed air system uses about 12% of the
energy and HVAC Fans and cooling use 8.1%. Lighting is 3% and the forklift battery charging is
about 1.1% of electricity use.
Figure 2: D’s Electricity Consumption by End-use
Figure 3 shows that a small portion, 13.2% of the natural gas is estimate to be used for service
water heating based on summer gas use when the boilers are not operating. 86.8% is used by the
three space heating boilers.
Figure 3: D Gas Energy End-use
12. Facility
Energy Audit Report D’s Baseline Energy Use
11
Energy Efficiency Measures and Recommendations
Energy Efficiency Measures (EEM) are listed in Table 1 on page 2. The EEMs are in three groups
according to timeframe for implementation (immediate, future equipment upgrade and cost savings
only). Within each group the EEMs are arranged with the shortest simple payback first. Below, each
EEM is described in greater detail, including some of the baseline data that was gathered by THE
CONTRACTOR during the audit process with a definition of how the energy savings were determined,
how the costs were estimated, and how the final recommendations were derived.
A brief recommendation on how to measure and verify the energy savings after implementation is
also included. These Measurement and Verification (M&V) methods are recommended in
accordance with the International Performance for Measurement and Verification Protocol (IPMVP)
guidelines. The recommended EEMs were determined based on a combination of cost, magnitude of
savings, and reasonableness of implementation.
Potential EEMs were evaluated after the site survey and collection of data necessary to perform the
technical and economic analyses. This evaluation was completed to ASHRAE Level II standards
through spreadsheet analysis. It is recommended that complex measures be further evaluated to
Level III standards prior to implementation. Of particular concern is the actual cost data from
vendors which is needed before the electric or gas utility can prepare an estimate of their incentive
for each EEM. As a result, the costs provided here do not reflect bids or incentives.
13. Facility
Energy Audit Report Energy Efficiency Measure (EEM) Details
12
ENERGY EFFICIENCY MEASURE (EEM) DETAILS
To assess energy savings associated with each measure, the baseline for consumption was compared
individually to consumption totals calculated for each measure. The baseline for equipment was
obtained from monthly utility bills for natural gas and electricity. For electricity 30-minute interval
was also reviewed to see how energy use has varied by hour and day type over that last 2.5 years. In
some cases additional energy data was gathered by the contractor using data loggers. In particular
data was gathered on the warehouse lights, the compressed air system, and the injection molds.
Energy consumption associated with each measure was then assessed individually based on the
technical performance of new equipment and then compared to the corresponding baseline in order
to determine energy savings. Energy cost savings were determined using the projected energy
savings and the average energy rate from natural gas and electricity bills.
Many potential EEMs were analyzed but only those meeting the requirement for a 4 year or shorter
simple payback are presented. Prior to implementation, it is essential to get approved vendor bids
for the energy efficiency improvements. Bids are required before the utility can provide incentive
estimates.
The following assumptions were used in calculating the savings:
1. Building energy usage patterns remain relatively unchanged in the near future. (No significant
occupancy change and/or space conversion.)
2. Energy costs remain relatively stable.
3. Operation of building systems remains relatively unchanged (unless change is related to a
recommended EEM).
An economic analysis was performed for each measure using historical cost estimates from similar
projects and pricing solicited from vendors. The cost savings from both energy savings and non-
energy benefits were divided by implementation costs in order to get a simple payback for each
measure.
EEMs for Current Implementation
Of the five EEMs, three are considered worthy of immediate consideration and should be submitted
to vendors for bids.
EEM-1 Synthetic Hydraulic Fluid
Existing Conditions
The audit of the molds indicated that only three molds (#24 - 1000 ton, #19 - 400 tons, and #22 - 400
tons) are currently using Shell’s Tellus S4 ME46 synthetic hydraulic fluid. A report in August 2012
documented a test that Shell Oil ran on D’s Mold#24, a Husky 1000 ton unit. A copy of Shell’s report
is included in Appendix B.
14. Facility
Energy Audit Report Energy Efficiency Measure (EEM) Details
13
The Shell report over-estimated the baseline energy use of the 1000 ton mold it tested, reporting it
used 6,220,000 kWh/year or 6,220 kWh/ton. Given that there are 31 injection molding machines
with a total capacity of 12,459 tons, the total energy use for just the molds would be 77.5 million
kWh/year, more than three times D’s entire electricity use of 22.5 million kWh/year.
The auditor obtained a more reasonable baseline energy use of 1,352 kWh/ton-year, derived from
seven days of field metering Mold#17, a 120 ton Husky.
Measure Description
It is recommended that M consider replacing the standard hydraulic oil with Shell’s Tellus S4 ME46
synthetic hydraulic fluid in molds that do not currently have the synthetic oil. Four molds (numbers
17, 20, 3, and 4) are able to accept the synthetic oil. These molds add up to a total of 1,520 tons of
clamping power. Energy savings and cost are calculated per ton of clamping power so the savings can
be scaled up if there are more molds that can begin using the synthetic oil.
Savings
The Shell report used a true rms ammeter to measure the power draw of Mold#24 before with
standard oil and after with synthetic oil. The measured power reduction was 5.08%. Using baseline
energy use of 1,352 kWh/ton and the power reduction of 5.08%, the energy savings is 68.7
kWh/ton-year. The total savings for the four molds will be 104,396 kWh/year. Shell’s report also
suggested that non-energy benefits would include increased lubricant life of three years versus one
year, increased pump life, and decreased cycle time leading to increased productivity. The longer life
of the oil has non-energy dollar benefits since the oil does not have to be replaced every year. The
value of the energy savings at $0.077/kWh would be $8,037. The non-energy benefit of reduced
labor and avoided standard oil purchases is $7,534 per year for total dollar savings of $15,571.
Installed Cost Estimate
The incremental cost to buy the synthetic oil is $15.68/ton. For 1,520 tons of molds, the total oil cost
is $23,826 for a simple pay back of 1.5 years.
Measurement and Verification (M&V)
To properly verify the energy savings, a simple spot check of power reduction would not be
sufficient. It requires power sensors (CTs) to be installed on the electric service and data for 1 to 2
weeks with the old oil pre-test and 1 to 2 weeks with the synthetic oil post-test. This longer test will
account for any reduction in production time as well as lower power draw.
EEM-2 Energy Star/Miser on Vending Machines
Existing Conditions
Most cold beverage and hot snack vending machines in D do not have Energy Star/Miser controls to
turn off the compressors and lights when no one is around, resulting in energy waste.
15. Facility
Energy Audit Report Energy Efficiency Measure (EEM) Details
14
Measure Description
The the contractor contacted the vending machine supplier Classic Group and Chicago Coffee & Tea.
They are very willing to do a detailed review of the number and type of vending machines at D and
M’s other Chicago area plants. They will determine how many machines are on-site and the related
cost to upgrade them to Energy Star/Miser.
Savings
Savings per machine are estimated to be 900 kWh/year which is 24% of the baseline energy use of
3,743 kWh/year for an average cold beverage vending machine. At the electric rate of $0.077/kWh,
the dollar savings for 10 vending machines at D is 9,000 kWh/year ($693/year).
Installed Cost Estimate
The cost of each upgrade is estimated at $179 based on similar projects in the Pacific Northwest. The
total installed cost for 10 machines would be approximately $1,790 for a simple payback of 2.6 years.
It is likely that ComEd or Constellation Energy has an incentive available for this type of project. The
the contractor has experienced other utilities offering an incentive of about $90, cutting the payback
to 1.3 years.
Measurement and Verification (M&V)
This measure has been validated extensively by multiple utilities and savings are generally
accepted without M&V.
Background Information
M’s vending machines are provided by Classic Group and Chicago Coffee & Tea. Their contact is Jim
Carbone at 773-252-7000 Ext 609, e-mail: Jim@TheClassicGrp.com. They will provide a quote to M
to upgrade all of their vending machines, estimate of 50 to 70 units in the Chicago area.
There will be a charge to M for the upgrade. The equipment comes from USA Technologies, the
supplier of the Energy (Vending) Miser. The contact at USA is Scott Larkin 262-617-0221
SLarkin@USATech.com.
EEM-3 Extend LED Lighting to the Rest of D Parking Lot
Existing Conditions
The parking lot around D and the corporate office has some light that has been converted to LED
fixtures, but there are still 76 pole lights and 15 lights on the exterior walls of the buildings that
could be converted to LED. These metal halide fixtures draw 41.86 kW of power and use 152,789
kWh/year.
16. Facility
Energy Audit Report Energy Efficiency Measure (EEM) Details
15
Table 4: D Exterior Lighting Baseline and Proposed Energy Use and EEM Cost Estimate
Existing Baseline Condition Proposed Measures
Fixture Type Lamp type
Connected
Load
(Watts)
Number
of
Fixtures
Total
Watts
Hours of
Operation
Baseline
kWh/yr
Lamp
type
Connected
load
Total
Watts
Hours of
Operation kWh/yr
Individual
Measure
Cost*
Total
Measure
Equipment
Cost
Pole Lights Metal Halide 460 76 34,960 3,650 127,604 LED 197 14,972 3,650 54,648 $ 1,100 $ 83,600
Bldg Exterior Metal Halide 460 15 6,900 3,650 25,185 LED 128 1,920 3,650 7,008 $ 800 $ 12,000
Totals 91 41,860 152,789 16,892 61,656 $ 95,600
* Measure cost is based on estimates from M the contractor Connextions
Measure Description
Table 4 above shows the existing number of fixtures and lamps and the installed Watts as well as the
current annual energy use. It also shows the proposed Watts and the proposed energy use as well as
the estimated cost of the lighting measures. The baseline energy use is 152,789 kWh/year and the
proposed energy use is 61,656 kWh/year. The savings are 91,133 kWh/year which reduce the annual
energy cost by $7,016. Shown below, Figure 4: Metal Halide and LED Exterior Lamp shows that only
the type of lamp has to be changed from metal halide to LED at a cost of $93,325. The LED has a
much longer life than the metal halide lamp which means fewer lamps need to be purchased and
less labor is needed to replace burned out lamps.
Figure 4: Metal Halide and LED Exterior Lamp
Savings
The total energy savings are estimated at 91,133 kWh/year, which has a value of $7,016 per year at
historic utility rates. The metal halide lamps lose 70% of their light intensity in 5,000 hours of
operation. LED lights maintain brightness of 87% and higher for 100,000 hours. This means the LEDs
will last about 20 years when metal halide needs to be replaced every other year. The halide lamps
cost $25 each, so for 91 lamps, that is $2,275/year. There is also additional labor savings from
avoiding the replacement of the halide lamps every two years. The labor savings is $16,209, based
on a labor rate of $75/hour and replacement of two lamps per hour. The total annual non-energy
benefit is $18,484 (lamp cost + avoided labor).
17. Facility
Energy Audit Report Energy Efficiency Measure (EEM) Details
16
Installed Cost Estimate
The cost of purchasing LED lamps is estimated by Connexions at $95,600. The avoided cost of
purchasing the halide lamps replacements results in a savings of $2,275. The total cost of installing
LED lamps is therefore $93,325 (total LED purchase cost – halide lamp total purchase cost). The
labor cost of installing is neutral, as the LED and a new metal halide would be the same cost to
install. The energy savings ($7016) and non-energy savings ($18,484) is $25,500, which allows cost
recovery in 3.7 years.
Measurement and Verification (M&V)
This measure is very straight-forward and utilities do not generally require any M&V as long as the
number of fixtures and lamps are verified, it is usually assumed the nighttime hours are changing. If
a new time clock or other control such as a new photocell, then the hours of operation may have to
be verified.
EEM-4 Convert Diesel Generators to bi-fuel Adding Natural Gas
Existing Conditions
D has four on-site electrical generators of which three are operational. These three are about 1,500
kW and diesel fired. The generators are for back-up power and they rarely operate. Because of the
diesel emissions they are regulated and can run only a few hours per year for regular maintenance,
in emergencies when grid power is lost, and on-demand as requested by ComEd.
Measure Description
THE CONTRACTOR proposes installing conversion kits on these three generators to allow them to
operate with “bi-fuel,” using 30% diesel fuel and 70% natural gas. Such a conversion kit can be seen
on the diesel2gas web-site: http://www.diesel2gas.com/ This site has short video showing how the
retrofit kit works. Contact information for the manufacturer and the distributor closest to M are
included in the Background section below.
Savings
The the contractor estimates that D’s cost to self-generate electricity will be $0.052 per kWh. This
cost is 29.6% lower than the current electricity price for on-peak energy, which is $0.074/kWh. The
current off-peak electricity rate is $0.048/kWh, so it is not cost effective to self-generate during off-
peak hours. On-peak hours are 9:00 AM to 10:00 Pm on weekdays or 13 hours per day (65 hours per
week). Allowing for holidays, which are off-peak, there are 50 weeks per year or 3,250 hours per
year when the bi-fuel generators can run thus avoiding 5,050,000 million kWh/year of grid
purchased electricity. This is a 22.5% reduction in metered electricity for D. The annual cost savings
in electricity is $376,397.
However, the generators will consume 403,758 therms/year of natural gas beyond what D is
currently using 420,696 therms/year. The cost of the natural gas is subtracted from the electricity
cost savings. The current cost of natural gas is $0.254 per therm for a total added gas cost of
$102,486 per year.
18. Facility
Energy Audit Report Energy Efficiency Measure (EEM) Details
17
The longer hours of operation will also add to the maintenance cost for more oil changes, repairs
and major overhauls. The added O&M cost is $55,770 and it is like a negative non-energy benefit
that has to subtracted from the net energy cost savings. D’s total cost to self-generate 5,050,000
kWh per year is $158,256 or $0.031. Including the added gas and O&M costs, the net annual cost
savings is $273,911 per year.
Installed Cost Estimate
The the contractor found two sources for estimated cost to install the conversion kit, one was $100
per kW generator capacity and the other was $119/kW. Using the larger cost, the installed cost for
1,500 kW is $178,500. The simple payback is 1.6 years.
Measurement and Verification (M&V)
Because the expected electricity savings are very large, it IMPVP standards would allow the savings
to be verified by using several months of electric and gas billing data. After the conversion the
electricity bill will go down considerably as compared to the same months of billing data before the
conversion. The opposite is true for the gas bills as they will go up dramatically since the new gas use
will about three times the old gas use. The added O&M cost is less easy to verify as it may take a
couple years of pre and post O&M records.
Background Information
http://www.diesel2gas.com/ Nice introductory video showing how the retrofit is installed and how it
works
Altronic 712 Trumbull Avenue, Girard, Ohio 44420; 330-545-9768 www.gti-altronic.com
Chicago Area Distributor: Sulzer Turbo Services, 422 Pine Street, Kalkaska, MI 49646
P: 231-258-2500; C: 231-564-1085 Scott Brooks; scott.brooks@sulzer.com
Four case studies of electric generators converted from diesel only to diesel+nat gas:
http://www.diesel2gas.com/projects/?page=4
Cummin KTA-19 350 kW gen-set GTI Bi-fuel kit, series II-A16,
CAT D349 800 kW gen-set , GTI Bi-fuel Kit, series III-C26
CAT C-18 500 kW gen-set, GTI Bi-fuel kit, series II-B26
CAT 3412 TA 380 kVA gen-set, GTI Bi-fuel kit, series I-A16
19. Facility
Energy Audit Report Energy Efficiency Measure (EEM) Details
18
EEM for Future Implementation When Replacing or Adding Molds
EEM-5 All-Electric Auburg Versus Husky Hydraulic Mold
Existing Conditions
D has 31 molds and only one, the Auburg Mold#21 is all-electric. Literature mentions that all-
electric mold use less energy than hydraulic molds. Two molds, the Auburg Mold#21 (165 ton unit)
and the Husky Mold# 17(a 120 ton hydraulic unit), were both producing the same product during the
audit so it was an excellent opportunity to install metering equipment to compare energy use. If D
needs to replace or add more injection molding machines, they should be all-electric. THE
CONTRACTOR conducted field test of the energy use of and electric mold and a hydraulic mold. D’s
current all-electric mold used only 626 kWh/ton-year or 34% of the energy of a similar hydraulic
mold which used 1,851 kWh/ton-year doing the same work.
Measure Description
The contractor had an electrician install power measurement sensors, CTs (current transformers) on
one leg of the electric service to Mold#21 (the Auburg 165 ton) and to Mold#17 (the Husky 120 ton).
The power draw was measured every 2-minutes for 165 hours as shown in Figure 5: Power Draw of
Auburg 165 ton Electric Mold and Figure 6: Power Draw of Husky 120 ton Hydraulic Mold. Using this
data, the contractor was able to estimate the annual energy use of the two molds as shown in Table
5: Auburg Calculated Annual Energy Use and Table 6: Husky Calculated Annual Energy Use.
20. Facility
Energy Audit Report Energy Efficiency Measure (EEM) Details
19
Figure 5: Power Draw of Auburg 165 ton Electric Mold
21. M Industries – Facility
Energy Audit Report
Table 5: Auburg Calculated Annual Energy Use
Auburg 165 ton Bin 2-minute periods
0-10 Amp 10 - 30 A 30+ Amps 2-Min int
425 4384 1384947
8.6% 88.6% 2.8%% runtime
7.6 11.8 26.1kW
5,721 91,242 6,384 103,347 kWh per year
5.5% 88.3% 6.2%percent of annual energy
Table 6: Husky Calculated Annual Energy Use
Husky 120 ton Bin 2-minute periods
0 to 24 24+ to 45 45+ 2-Min int
352 4230 365 4947
7.1% 85.5% 7.4%% of period
18.2 24.8 39.0kW
11,373 185,582 25,193 222,148kWh per year
5.1% 83.5% 11.3%percent of annual energy
Figure 6: Power Draw of Husky 120 ton Hydraulic Mold
22. M Industries – Facility
Energy Audit Report
Figure 5: Power Draw of Auburg 165 ton Electric Mold and Table 5: Auburg Calculated Annual Energy
Use show that the Auburg all-electric mold during 7 days of monitoring pulled between 10 and 30
Amps for 88.6% of the time. For 8.6% of the time, power dropped below 10 Amps. The annualized
energy use came to 103,347 kWh/year, for the 165 ton mold.
Figure 6: Power Draw of Husky 120 ton Hydraulic Mold and Table 6: Husky Calculated Annual Energy
Use show that during the monitoring period, the hydraulic mold pulled between 24 and 45 Amps for
85.5% of the time. For 7.1% of the time, power dropped below 24 Amps. The annualized energy use
came to 222,148 kWh/year, for the 120 ton mold.
When the energy use for the Auburg electric mold is normalized per ton, the annual energy use is
626 kWh/ton-year. The Husky hydraulic mold’s normalized annual energy use per ton is 1,851
kWh/ton-year, more than three times as much.
Savings
The estimated savings by using an all-electric mold would be 1,225 kWh/ton-year. At $0.077/kWh,
the cost savings for an electric mold would be $94.30 per ton-year. Assuming D added 10% or 1,246
tons of new molds, the energy savings from all-electric molds would be 1.54 million kWh/year with a
cost savings of $118,812 per year.
Installed Cost Estimate
An all-electric mold costs about $109,620 which is comparable to an equivalent hydraulic mold
costing $114,200. Assuming the typical average size mold is 400 tons, the all-electric mold cost
would be $274/ton and the hydraulic mold would be $285.50/ton. The incremental cost for all-
electric mold would be $87/ton.
If M were to add 1,225 tons of new molds, the total incremental cost would be $109,620 and result
in a savings of $118,812 for a simple payback 0.92 years.
Measurement and Verification (M&V)
Measurement and verification would be done the same way that THE CONTRACTOR did the field
testing, installing electric power sensors and gather data while two matched machines did the same
work.
Background Information
A discussion of the savings from an electric mold is provided by Auberg Tech Talk at web site:
http://www.arburg.com/fileadmin/redaktion/Mediathek/today/ARBURG_today40_2009_680276_e
n_GB/?page=22#. The all-electric Allrounder’s has regenerative braking and it uses energy-efficient
drives which can save up to 30% by slowing the motor when the mold is in the cooling mode.
Additionally, a May 2007 article at web site http://www.ptonline.com/articles/electric-hydraulic-or-
hybrid-what%27s-the-rightinjection-press-for-you says that all-electric molds cost 20% more but can
save 30% to 70% of the energy. One example quoted is: “Apex purchased an electric machine for
$150,000 and received a $35,000 rebate check from the utility. A hydraulic machine of similar size
cost $110,000 to $120,000. So the rebate erased the price premium.”
23. M Industries – Facility
Energy Audit Report
Another article at web site http://www.htiplastic.com/news/hydraulic-vs-electric-injection-mold-
machines has data presented in Table 7: Electric Versus Hydraulic Molds. The article notes, “The
difference in unit cost is readily apparent when a hydraulic machine is replaced by an equivalent
electric machine. With tight, repeatable control of operations, the product is produced with less
material and fewer additives, dramatically reducing waste. Independent functionality in electric
machines means multiple tasks can run simultaneously, resulting in much faster cycles. Additionally,
electric machines have no consumables, such as oil and filters, which must be periodically replaced.
Operating cost also is significantly lower due to the substantially smaller power requirements of an
electric machine.”
Table 7: Electric Versus Hydraulic Molds
ELECTRIC Vs HYDRAULIC COMPARISON
Supplier Clamp Tonnage
Material,
Shot Wt.,
Cycle Time
Energy Consumption
Electric Hydraulic Hybrid Electric Hydraulic Savings
Engel
220 220 220
15% GF PBT
12.2-sec
cycle
0.259
kwh/kg
material
0.353 kwh/kg
material 26.6%
Milacron
935 880 —
29-oz part,
17.9-sec
cycle
99.6kw 167kw
40.4%
Sumitomo 198 198 —
16-sec cycle
(estimated) 6.23kw 23.1kw 73.0%
Energy Cost Savings EEM (No reduction in energy or carbon emissions)
EEM-6 Forklift Battery Off-peak Charging
Existing Conditions
The D warehouse has electric forklifts with a battery charging station. The D charging station is an
EnerSys Enforcer SCR Charge Control. This system has the ability to delay charging until off-peak
hours. The existing charger is an SCR which has low energy efficiency (81% to 88%). If it needs to be
replaced, more energy efficient models such as the High frequency charger (91% to 92%) are
available. http://www.enersys.com/EnForcer_SCR_Chargers.aspx.
Measure Description
Delay charging until off-peak rates apply, thereby using less expensive energy. Another opportunity
is to add a solar photovoltaic system on the warehouse to provide day time battery charging. These
systems are not cost effective without substantial incentives, however these projects are perceived
positively as a demonstration of commitment to sustainable energy. And they can receive significant
state, federal and utility incentives.
D currently receives electricity from Constellation Energy through ComEd’s distribution system.
There are two rates: On-peak is $0.07424/kWh and off-peak is $0.04788/kWh. M’s average electric
rate is $0.077 which includes other charges such as transportation cost and demand charges.
Figure 7: Sample Electric Bill for One M Place Campus shows on-peak energy use of 1,092,809
kWh/month and off-peak use of 1,592,781 kWh/month for a total of 2,685,590. On-peak energy use
24. M Industries – Facility
Energy Audit Report
is 40.6% and off-peak use is 59.4%. On-peak time is 9:00 AM to 10:00 PM and any electrical energy
use shifted from on-peak to off-peak will save 35.5% of the dollar cost. Since batteries store energy,
they can be charged at night after 10:00 PM and be ready for the morning shift.
Savings
Assuming there are 45 forklifts and each uses 5,600 kWh/year to charge batteries, the total energy
use for charging is 252,000 kWh/year. Based on on-peak day time rate ($0.07424/kWh), this costs D
$18,708 per year. If this load can be switched to off-peak rate ($0.04788/kWh) the cost would be
reduced to $12,066 per year. The total annual energy cost savings would be $6,643 per year.
Installed Cost Estimate
It is likely the existing battery charging system, which is newer, can be adjusted to use off-peak rates.
This would result in non-upfront cost in a simply payback that can be instantaneous. If the charging
system cannot be switched and needs to be changed, the estimated cost to change the charging
station is $10,300. At a cost of $10,300, the simple payback would be 1.6 years.
Measurement and Verification (M&V)
There is no need for M&V on this EEM.
25. M Industries – Facility
Energy Audit Report
Figure 7: Sample Electric Bill for One M Place Campus
Background Information
The link below provides information on upgrading forklift battery charging and discusses using solar
to charge the batteries. It suggests that a forklift consumes about 5,600 kWh/year but upgraded
systems could reduce this to 2,400 kWh/year:
http://wmich.edu/mfe/mrc/greenmanufacturing/pdf/Posters/Borroughs%20Poster.pdf
The link below takes you to a Southern California paper on off-peak forklift charging, “SCE hoped to
demonstrate that customer bills can be reduced substantially by moving the charging function off-
peak, with annual savings from $300 -$500 per forklift (5 kW charger used daily).”
http://www.lifepo4.info/Battery_study/Articles_on_V2G/Electric_Forklift_and_Non-
Road_EV_Fleets_-_Demand_Response_and_Load_Management_Strategies.pdf
Table 8 below shows Comparative Forklift Charger Test Results from a Pacific Gas & Electric paper
from the web site below:
http://www.pge.com/includes/docs/pdfs/mybusiness/energysavingsrebates/moneybacksolu
tions/gr ocery/fb_ib/forklift_battery_charger_fs.pdf
26. M Industries – Facility
Energy Audit Report
Table 8: Comparative Forklift Charger Test Results
27. M Industries – Facility
Energy Audit Report
Appendix A:
D Interval Meter Data
28. M Industries – Facility
Energy Audit Report
Figure 8: D Meter# ####908 Typical Daily Energy Profiles 2012
29. M Industries – Facility
Energy Audit Report
Figure 9: D Meter# #####908 Typical Daily Energy Profiles 2014
30. M Industries – Facility
Energy Audit Report
Figure 10: D Meter# #####683 Typical Daily Energy Profiles 2012
31. M Industries – Facility
Energy Audit Report
Figure 11: D Meter# #####683 Typical Daily Energy Profiles 2014
32. M Industries – Facility
Energy Audit Report
Figure 12: D Meter# ####3085 Typical Daily Energy Profiles 2012
33. M Industries – Facility
Energy Audit Report
Figure 13: D Meter# #####085 Typical Daily Energy Profiles 2014
34. M Industries – Facility
Energy Audit Report
Appendix B:
Additional Electronic Documentation
35. M Industries – Facility
Energy Audit Report
The items listed below are data sets too large to be included in the body of this report. They are
provided to M in electronic format.
Energy Calculation Excel Workbooks
Utility Bills and Interval Data
Vendor List
Product Literature
Logger Data
Audit Photographs
Field Notes
Background Energy Studies and Reports