The document contains sales forecasts from multiple employees for 10 different styles of products. It calculates the average forecast, standard deviation, and coefficient of variation for each product style. It recommends using the coefficient of variation to determine production quantities for styles with low risk (CV <= 0.2), and ordering the minimum amounts for styles with higher risk (CV > 0.2). The summary provides an example calculation and production plan for one low-risk and one high-risk style.
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Forecast without historical data - How can?
1. FORECASTING : SPORT OBERMEYER
06
Style Laura Carolyn Greg Wendy Tom Wally Average Std. Dev
2X Std
Dev
Assault
Seduced
Entice
Electra
Gail
Daphne
Isis
Anita
Teri
Stephanie
Total
Employee’ names
Productname
X1 + X2 + ⋯ . +Xn
n
Standard Deviation
2 x Standard Deviation
2. FORECASTING : SPORT OBERMEYER
06
Style Laura Carolyn Greg Wendy Tom Wally Average Std. Dev
2X Std
Dev
Assault 2,500 1,900 2,700 2,450 2,800 2,800 2,525 340 680
Seduced
Entice
Electra
Gail
Daphne
Isis
Anita
Teri
Stephanie
Total
4. X1 + X2 + ⋯ . +Xn
n
AVERAGE FORECASTMETHOD
A normal random variable
with the mean equal to
average of member’s
forecast and 2 x standard
deviation
FORECASTING : SPORT OBERMEYER
06
2 X STANDARD DEVIATION
5. METHOD
Coefficient of variation (CV)
is popular index of statistic
to measure risk.
FORECASTING : OUR RECOMMENDATION
Standard deviation
Average (mean)
COEFFIECIENT OF VARIATION
06
0.2RULE OF THUMB:
Benchmark point is
CV <= 0.2: Low risk
0.2 < CV < 1: Higher risk
7. FORECASTING : OUR RECOMMENDATION
• COEFFICIENT OF VARIATION IS RISK
• % TO BE ORDERED = 1 – RISK = 1 –CV
• QUANTITY ORDER = EXPECTED QUANTITY x (1- CV) = AVG x (1- CV)
Example:
For style Gail ~ Avg: 1017, Standard Deviation: 194
• CV = 194/1017 = 0.19 ~ 19 % (Low risk)
• 1- CV = 1- 0.19 = 0.81
• Quantity order = 1017 x 0.81 = 823 Units
FORMULA
8. SOLUTIONS FOR QUESTION 1 &3
• INITIAL PRODUCTION COMMITMENT
: 10.000 UNITS
• 10 STYLES REPRESENTED 10 %
DEMAND
• NOW IS NOVEMBER. TIME FOR LAS
VEGAS SHOW : MARCH
• MINIMUM ORDER:
• HONGKONG: 60 UNITS / MONTH
• CHINA: 120 UNITS / MONTH
ASSUMPTIONS
• MONTHS FOR PRODUCTION: 4
• MINIMUM ORDER:
• HONG KONG: 60 X 4 = 240 UNITS
• CHINA: 120 X 4 = 480 UNITS
9. SOLUTIONS FOR QUESTION 1 &3
• CALCULATE CV
• EVALUATE RISK FOR EACH STYLE
• CHOOSE TACTICS FOR PRODUCTION
STEPS