2. S.No. Activity
Statutory
Time
(in months)
Non statutory Time
(in months)
1
Proposal for declaration of Regional Planning Area – Director –
Government u/s 10(5)
- 1
2
Proposal for constitution of Rp.Au – Director-Government u/s
11(1) & 11(2)
- 2
3
Appointment of Consultant (Preparation of ToR, inviting RFP,
bidding & selection of consultant)
- 4
4 Preparation of existing land use map u/s 16 & u/r 3 12 -
5
Preparation of draft Regional plan u/s 15(1), u/r 4 and
submission to Government u/r 5
12 -
6 Consent of Govt. or advise for corrections u/r 6(1) 2 -
7
Rp.Au to carry out corrections and resubmit to Government u.r
6(2)
3 -
8 Government to give consent u/r 6(3) - 1
9
Publication of notice on preparation of draft regional plan in
TNGG u/s 26(1) by the Rp.Au
- 1
10
Republication of notice in District Gazette, Newspaper, Notice
boards u/r 10 by the Rp.Au.
1
3. S.No. Activity
Statutory
Time
(in months)
Non
statutory
Time
(in months)
11
Inviting objections & suggestions from public, DTCP, District
Collector, HOD’s u/r 7 & 8
2 -
12 Approval of Draft Regional Plan by the Rp.Au. u/r 8 2 -
13 Submission of Draft Regional Plan to the Government u/r 8 3 -
14 Approval of plan by Government or advice for corrections u/r 9( 1) 3 -
15 Rp.Au to carry out corrections and resubmit to Govt u/r 9(2) 6 -
16 Approval of plan by Government u/r 9(4) - 1
17
Publication of approval of the regional plan in the TNGG by the
Government u/s 30(1)
- 1
Total 46 11
Total time for statutory and Non statutory
57 months
(4 yrs 9 months)