SlideShare a Scribd company logo
1 of 22
Evaluating the Impact of Community Based DRR
Projects
December 4, 2019
Jody Springer
Data AnalyticsTeam Lead
Hazard MitigationAssistance, Mitigation Division
US Federal Emergency Management Agency
Federal Emergency Management Agency
FEMA Hazard Mitigation Assistance (HMA)
FEMA manages four mitigation programs with one in development
 Pre-Disaster Programs
• Flood Mitigation Assistance – Mitigate National Flood Insurance Program insured structures
• Pre-Disaster Mitigation– Assists communities in implementing sustained pre-disaster mitigation
projects
• Building Resilient Infrastructure and Communities – Provides mitigation for large infrastructure and
critical lifelines
 Post Disaster Programs
• Hazard Mitigation Grant Program– Implements hazard mitigation measures after Presidential
declared disasters
• HMGP-Post Fire – Provides mitigation funding in burned areas
2
Federal Emergency Management Agency
Hazard Mitigation Assistance - Historic Funding
Mitigation funding fluctuates year to year based on event occurrences and Congressional
appropriations.
3
$-
$1,000
$2,000
$3,000
$4,000
$5,000
$6,000
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
In Millions
Federal Emergency Management Agency
Funding by Project Types
The US states, territories and tribal nations
submit grant proposals for mitigation
projects.
 Projects must be pre-identified in the
hazard mitigation plan.
 The states, territories and tribes submit
proposals that are prioritized at the
grantee level for review and approval.
4
Federal Emergency Management Agency
History of Mitigation Projects
5
Federal Emergency Management Agency
Benefit Cost Analysis Requirements
Projects funded by FEMA must demonstrate that the anticipated benefits of a project meet
or exceed the costs.
 Legislative authorizations for the programs require projects are cost-effective.
 The Office of Management and Budget publishes guidance for US agencies to follow when
conducting the benefit cost analysis in Circular A-94, Guidelines and Discount Rates for
Benefit-Cost Analysis of Federal Programs revised October 29, 1992.
 Analysis is performed by the local communities, some with limited technical capabilities or
economic background.
 FEMA provides training and technical assistance.
6
Federal Emergency Management Agency
Benefit Cost Analysis Requirements
OMB A-94 provides general guidance and basic requirements for Federal agencies.
 A fixed discount rate of 7% must be utilized to discount future benefits to today’s dollars.
 Tangible and intangible benefits and costs should be identified.
 Future inflation is highly uncertain and analysts should avoid making assumptions about the
general rate of inflation.
 Direct project benefits should be considered, secondary and tertiary benefits should not be
included as a benefit.
7
Federal Emergency Management Agency
Conducting the Benefit Cost Analysis
To facilitate preparation of a BCA, FEMA has developed the BCA toolkit which calculates a BCR
for the project.
 New Version, v. 6.0 is Excel based and features an improved user experienced and an 80%
reduction in data inputs.
8
Federal Emergency Management Agency
Monetization of Benefits
Benefits are any future costs/damages that can be reduced or avoided as a result of the
mitigation project such as:
 Physical damages
 Loss of service or function of a utility or public facility
 Causalities
 Emergency management costs
 Some projects also qualify for additional benefits: ecosystem services and social benefits.
9
Benefits = Costs Before Mitigation – Costs After Mitigation
Federal Emergency Management Agency
Two Basic BCA Methodologies
 These are built into the BCA toolkit so that all the user has to enter is some data about the
project and facility – the user does not have to do the math themselves!
 Let’s take a closer look at each method.
10
Modeled
Damages
Historic or
Expected
Damages
Federal Emergency Management Agency
Modeled Damages
 The BCA Toolkit uses established models (equations) to estimate damages that would occur
to a specified building type during a specific frequency of event – also known as the
recurrence interval (RI). (The RI is often referred to as the X-year or Y% annual chance event).
 These modeled damages are analyzed over the project useful life (PUL) to get the total
benefits of the project.
11
Federal Emergency Management Agency
Modeled Damages
 Property-specific flood mitigation activities like acquisitions, elevations, floodproofing
 Wind retrofits
 Seismic building retrofits
 Wildfire mitigation
 Tornado and hurricane safe rooms
12
Federal Emergency Management Agency
Modeled Damages Data Requirements
Hazard data for project location
• Flood elevations & discharge (from Flood Insurance Study or H&H)
• Tornado counts
• Wildfire burn recurrence interval
• Windspeeds
• Seismic risk
Structure data
• Type of building (one or two story, basement, etc.)
• Square footage
• Number of occupants
Project data
• Before- and after-mitigation conditions (what is being done?)
13
Built into BCAToolkit
Federal Emergency Management Agency
Modeled Damage Example – Wildfire
FEMA funds three activities to lessen the risk from wildfires
 Vegetation management – Removes fuel loads
 Defensible Space – Creates buffer around structures
 Structural Retrofits – Use of fire resident building materials or installation of water sprinkler
system on the outside of the structure
Each individual activity is estimated to be only 10% effective at reducing the risk of
wildfires and protecting structures.
The local community may only perform structural retrofits if performed in conjunction with
vegetation management and defensible space activities.
14
Federal Emergency Management Agency
Modeled Damage Example – Wildfire
Even though wildfire mitigation projects are only
at best 30% effective and the useful life is short,
they can be very cost effective due to the value of
structures and infrastructure in the protected area.
 Wildfire recurrence intervals is provided by
Landfire (https://www.landfire.gov)
 Project useful life is generally short, 3 to 5 years
 Benefits calculate is based on a maximum project
effectiveness of 30%
 Challenges with meeting environmental and
historic preservation requirements which can
exceed the actual project costs!
15
Upper Lochsa River Idaho Sub-Basin Mean Fire Interval
Federal Emergency Management Agency
Historic or Expected Damages
 The BCA Toolkit uses user-entered damage information associated with specific
calendar years and/or recurrence intervals to estimate damages to the facility.
 Instead of using an established model, the software uses the data points entered by the
user to create a curve.
16
Year or RI
Damage
Federal Emergency Management Agency
Historic or Expected Damages
Can be used to analyze any hazard/project type.
 Best approach for:
 Any project that is mitigating a non-building, such as a utility or road/bridge
 Any project where the primary damages being mitigated are loss of service/function,
rather than physical damages
 More complex projects like flood control and infrastructure protection
 Generator projects
 Projects mitigating hazards other than flood, wind, tornado, seismic, and wildfire
17
Federal Emergency Management Agency
Common BCA issues
Insufficient documentation
 Example: BCA has a Lowest Floor Elevation (LFE) but application does not include
elevation certificate.
Lack of damage history/documentation
 You can still do a BCA! However, you will need a qualified professional to estimate
damages.
Insufficient data/justification on project effectiveness
 All projects – except acquisitions – have a point at which they are no longer effective.
18
Federal Emergency Management Agency
Simplifying Analysis
 To simplify the BCA process, FEMA has several “pre-calculated benefits” for projects that
meet certain conditions.
 Using pre-calculated benefits eliminates the requirement for applicants to conduct a separate
BCA for eligible projects. For more information visit www.fema.gov/benefit-cost-analysis.
19
Federal Emergency Management Agency
Where Analysis Can be Improved Upon
How weather and climate are changing
• Anecdotal evidence that severe weather events are occurring more frequent, are more extreme in
size and longer duration.
• How do we incorporate extreme weather events into analysis and design mitigation projects to
minimize impacts.
Identify more standard values to use in analysis.
• Update existing values or service to account for a change in lifestyle.
• Identify value of services for telecommunications, 911/112/999 services, other lifeline functions.
20
Federal Emergency Management Agency
What is an Appropriate Discount Rate?
The US Government currently requires a 7% discount rate for FEMA’s mitigation projects.
 The 7% discount rate is arguably high and has not been revised since 1992.
 For smaller projects, it is somewhat easy to demonstrate most projects as cost effective.
 For large infrastructure projects in which benefits are accrued for more than 30 years and
provides multigenerational benefits, the 7% discount rate makes it difficult to demonstrate
projects are cost effective.
 The 7% discount rate may drive investment of funds toward smaller projects versus large
community wide infrastructure projects.
21
Questions?

More Related Content

Similar to Evaluating the Impact of Community Based DRR Projects

Evaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR ProjectsEvaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR ProjectsOECD Governance
 
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...Robert Muir
 
ASFPM 2016: Phase and Forget?
ASFPM 2016: Phase and Forget?ASFPM 2016: Phase and Forget?
ASFPM 2016: Phase and Forget?CDM Smith
 
Seismic mitigation final
Seismic mitigation finalSeismic mitigation final
Seismic mitigation finalSiDdu GowTham
 
Federal Dollars for Improving Energy Infrastructure Resilience (NASEO 2019)
Federal Dollars for Improving Energy Infrastructure Resilience (NASEO 2019)Federal Dollars for Improving Energy Infrastructure Resilience (NASEO 2019)
Federal Dollars for Improving Energy Infrastructure Resilience (NASEO 2019)ICF
 
Appraising Adaptation Actions
Appraising Adaptation ActionsAppraising Adaptation Actions
Appraising Adaptation ActionsNAP Events
 
Disaster Resilience Scorecard for Cities
Disaster Resilience Scorecard for CitiesDisaster Resilience Scorecard for Cities
Disaster Resilience Scorecard for CitiesIBM Government
 
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013david zhang
 
'The role of insurance and reinsurance in disaster risk management'
'The role of insurance and reinsurance in disaster risk management''The role of insurance and reinsurance in disaster risk management'
'The role of insurance and reinsurance in disaster risk management'UNDP Climate
 
Energy Event Index: Weather risk forecasts for power utilities
Energy Event Index: Weather risk forecasts for power utilitiesEnergy Event Index: Weather risk forecasts for power utilities
Energy Event Index: Weather risk forecasts for power utilitiesSchneider Electric
 
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...Robert Muir
 
Using Data Integration to Deliver Intelligence to Anyone, Anywhere
Using Data Integration to Deliver Intelligence to Anyone, AnywhereUsing Data Integration to Deliver Intelligence to Anyone, Anywhere
Using Data Integration to Deliver Intelligence to Anyone, AnywhereSafe Software
 
Business Continuity Detailed Plan
Business Continuity Detailed PlanBusiness Continuity Detailed Plan
Business Continuity Detailed PlanWissam Abdel Baki
 
Write 2 pages user manual report of this projectRead the proj.docx
Write 2 pages user manual report of this projectRead the proj.docxWrite 2 pages user manual report of this projectRead the proj.docx
Write 2 pages user manual report of this projectRead the proj.docxambersalomon88660
 
Economic Consequence Analysis, Prof. Adam Rose, USC
Economic Consequence Analysis, Prof. Adam Rose, USCEconomic Consequence Analysis, Prof. Adam Rose, USC
Economic Consequence Analysis, Prof. Adam Rose, USCOECD Governance
 
An Economic Analysis of Green v. Grey Infrastructure
An Economic Analysis of Green v. Grey InfrastructureAn Economic Analysis of Green v. Grey Infrastructure
An Economic Analysis of Green v. Grey InfrastructureRobert Muir
 
Doe Oai Audit Report On Sg Program Jan 2012
Doe   Oai   Audit Report On Sg Program   Jan 2012Doe   Oai   Audit Report On Sg Program   Jan 2012
Doe Oai Audit Report On Sg Program Jan 2012John Chowdhury
 
Whitepaper : Building a disaster ready infrastructure
Whitepaper : Building a disaster ready infrastructureWhitepaper : Building a disaster ready infrastructure
Whitepaper : Building a disaster ready infrastructureJake Weaver
 

Similar to Evaluating the Impact of Community Based DRR Projects (20)

Evaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR ProjectsEvaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR Projects
 
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
 
ASFPM 2016: Phase and Forget?
ASFPM 2016: Phase and Forget?ASFPM 2016: Phase and Forget?
ASFPM 2016: Phase and Forget?
 
Scotsem-Economic Resilience_F.PDF
Scotsem-Economic Resilience_F.PDFScotsem-Economic Resilience_F.PDF
Scotsem-Economic Resilience_F.PDF
 
Seismic mitigation final
Seismic mitigation finalSeismic mitigation final
Seismic mitigation final
 
Federal Dollars for Improving Energy Infrastructure Resilience (NASEO 2019)
Federal Dollars for Improving Energy Infrastructure Resilience (NASEO 2019)Federal Dollars for Improving Energy Infrastructure Resilience (NASEO 2019)
Federal Dollars for Improving Energy Infrastructure Resilience (NASEO 2019)
 
Appraising Adaptation Actions
Appraising Adaptation ActionsAppraising Adaptation Actions
Appraising Adaptation Actions
 
Disaster Resilience Scorecard for Cities
Disaster Resilience Scorecard for CitiesDisaster Resilience Scorecard for Cities
Disaster Resilience Scorecard for Cities
 
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
 
'The role of insurance and reinsurance in disaster risk management'
'The role of insurance and reinsurance in disaster risk management''The role of insurance and reinsurance in disaster risk management'
'The role of insurance and reinsurance in disaster risk management'
 
Energy Event Index: Weather risk forecasts for power utilities
Energy Event Index: Weather risk forecasts for power utilitiesEnergy Event Index: Weather risk forecasts for power utilities
Energy Event Index: Weather risk forecasts for power utilities
 
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
 
Using Data Integration to Deliver Intelligence to Anyone, Anywhere
Using Data Integration to Deliver Intelligence to Anyone, AnywhereUsing Data Integration to Deliver Intelligence to Anyone, Anywhere
Using Data Integration to Deliver Intelligence to Anyone, Anywhere
 
Business Continuity Detailed Plan
Business Continuity Detailed PlanBusiness Continuity Detailed Plan
Business Continuity Detailed Plan
 
Write 2 pages user manual report of this projectRead the proj.docx
Write 2 pages user manual report of this projectRead the proj.docxWrite 2 pages user manual report of this projectRead the proj.docx
Write 2 pages user manual report of this projectRead the proj.docx
 
BCI Counting The Cost
BCI Counting The CostBCI Counting The Cost
BCI Counting The Cost
 
Economic Consequence Analysis, Prof. Adam Rose, USC
Economic Consequence Analysis, Prof. Adam Rose, USCEconomic Consequence Analysis, Prof. Adam Rose, USC
Economic Consequence Analysis, Prof. Adam Rose, USC
 
An Economic Analysis of Green v. Grey Infrastructure
An Economic Analysis of Green v. Grey InfrastructureAn Economic Analysis of Green v. Grey Infrastructure
An Economic Analysis of Green v. Grey Infrastructure
 
Doe Oai Audit Report On Sg Program Jan 2012
Doe   Oai   Audit Report On Sg Program   Jan 2012Doe   Oai   Audit Report On Sg Program   Jan 2012
Doe Oai Audit Report On Sg Program Jan 2012
 
Whitepaper : Building a disaster ready infrastructure
Whitepaper : Building a disaster ready infrastructureWhitepaper : Building a disaster ready infrastructure
Whitepaper : Building a disaster ready infrastructure
 

More from OECD Governance

Public Integrity Indicators Slides
Public Integrity Indicators SlidesPublic Integrity Indicators Slides
Public Integrity Indicators SlidesOECD Governance
 
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...OECD Governance
 
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...OECD Governance
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)OECD Governance
 
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...OECD Governance
 
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...OECD Governance
 
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...OECD Governance
 
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...OECD Governance
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmOECD Governance
 
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...OECD Governance
 
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...OECD Governance
 
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...OECD Governance
 
Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023OECD Governance
 
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...OECD Governance
 
Digital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsDigital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsOECD Governance
 
Buliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfBuliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfOECD Governance
 
Session-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxSession-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxOECD Governance
 
Session-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxSession-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxOECD Governance
 
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxSession-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxOECD Governance
 
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxSession-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxOECD Governance
 

More from OECD Governance (20)

Public Integrity Indicators Slides
Public Integrity Indicators SlidesPublic Integrity Indicators Slides
Public Integrity Indicators Slides
 
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
 
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
 
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
 
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
 
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
 
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
 
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
 
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
 
Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023
 
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
 
Digital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsDigital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and Recommendations
 
Buliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfBuliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdf
 
Session-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxSession-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptx
 
Session-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxSession-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptx
 
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxSession-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
 
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxSession-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
 

Recently uploaded

2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...Suhani Kapoor
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...Suhani Kapoor
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...CedZabala
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos WebinarLinda Reinstein
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...Suhani Kapoor
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxaaryamanorathofficia
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCongressional Budget Office
 
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 

Recently uploaded (20)

2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
 
How to Save a Place: 12 Tips To Research & Know the Threat
How to Save a Place: 12 Tips To Research & Know the ThreatHow to Save a Place: 12 Tips To Research & Know the Threat
How to Save a Place: 12 Tips To Research & Know the Threat
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptx
 
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 

Evaluating the Impact of Community Based DRR Projects

  • 1. Evaluating the Impact of Community Based DRR Projects December 4, 2019 Jody Springer Data AnalyticsTeam Lead Hazard MitigationAssistance, Mitigation Division US Federal Emergency Management Agency
  • 2. Federal Emergency Management Agency FEMA Hazard Mitigation Assistance (HMA) FEMA manages four mitigation programs with one in development  Pre-Disaster Programs • Flood Mitigation Assistance – Mitigate National Flood Insurance Program insured structures • Pre-Disaster Mitigation– Assists communities in implementing sustained pre-disaster mitigation projects • Building Resilient Infrastructure and Communities – Provides mitigation for large infrastructure and critical lifelines  Post Disaster Programs • Hazard Mitigation Grant Program– Implements hazard mitigation measures after Presidential declared disasters • HMGP-Post Fire – Provides mitigation funding in burned areas 2
  • 3. Federal Emergency Management Agency Hazard Mitigation Assistance - Historic Funding Mitigation funding fluctuates year to year based on event occurrences and Congressional appropriations. 3 $- $1,000 $2,000 $3,000 $4,000 $5,000 $6,000 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 In Millions
  • 4. Federal Emergency Management Agency Funding by Project Types The US states, territories and tribal nations submit grant proposals for mitigation projects.  Projects must be pre-identified in the hazard mitigation plan.  The states, territories and tribes submit proposals that are prioritized at the grantee level for review and approval. 4
  • 5. Federal Emergency Management Agency History of Mitigation Projects 5
  • 6. Federal Emergency Management Agency Benefit Cost Analysis Requirements Projects funded by FEMA must demonstrate that the anticipated benefits of a project meet or exceed the costs.  Legislative authorizations for the programs require projects are cost-effective.  The Office of Management and Budget publishes guidance for US agencies to follow when conducting the benefit cost analysis in Circular A-94, Guidelines and Discount Rates for Benefit-Cost Analysis of Federal Programs revised October 29, 1992.  Analysis is performed by the local communities, some with limited technical capabilities or economic background.  FEMA provides training and technical assistance. 6
  • 7. Federal Emergency Management Agency Benefit Cost Analysis Requirements OMB A-94 provides general guidance and basic requirements for Federal agencies.  A fixed discount rate of 7% must be utilized to discount future benefits to today’s dollars.  Tangible and intangible benefits and costs should be identified.  Future inflation is highly uncertain and analysts should avoid making assumptions about the general rate of inflation.  Direct project benefits should be considered, secondary and tertiary benefits should not be included as a benefit. 7
  • 8. Federal Emergency Management Agency Conducting the Benefit Cost Analysis To facilitate preparation of a BCA, FEMA has developed the BCA toolkit which calculates a BCR for the project.  New Version, v. 6.0 is Excel based and features an improved user experienced and an 80% reduction in data inputs. 8
  • 9. Federal Emergency Management Agency Monetization of Benefits Benefits are any future costs/damages that can be reduced or avoided as a result of the mitigation project such as:  Physical damages  Loss of service or function of a utility or public facility  Causalities  Emergency management costs  Some projects also qualify for additional benefits: ecosystem services and social benefits. 9 Benefits = Costs Before Mitigation – Costs After Mitigation
  • 10. Federal Emergency Management Agency Two Basic BCA Methodologies  These are built into the BCA toolkit so that all the user has to enter is some data about the project and facility – the user does not have to do the math themselves!  Let’s take a closer look at each method. 10 Modeled Damages Historic or Expected Damages
  • 11. Federal Emergency Management Agency Modeled Damages  The BCA Toolkit uses established models (equations) to estimate damages that would occur to a specified building type during a specific frequency of event – also known as the recurrence interval (RI). (The RI is often referred to as the X-year or Y% annual chance event).  These modeled damages are analyzed over the project useful life (PUL) to get the total benefits of the project. 11
  • 12. Federal Emergency Management Agency Modeled Damages  Property-specific flood mitigation activities like acquisitions, elevations, floodproofing  Wind retrofits  Seismic building retrofits  Wildfire mitigation  Tornado and hurricane safe rooms 12
  • 13. Federal Emergency Management Agency Modeled Damages Data Requirements Hazard data for project location • Flood elevations & discharge (from Flood Insurance Study or H&H) • Tornado counts • Wildfire burn recurrence interval • Windspeeds • Seismic risk Structure data • Type of building (one or two story, basement, etc.) • Square footage • Number of occupants Project data • Before- and after-mitigation conditions (what is being done?) 13 Built into BCAToolkit
  • 14. Federal Emergency Management Agency Modeled Damage Example – Wildfire FEMA funds three activities to lessen the risk from wildfires  Vegetation management – Removes fuel loads  Defensible Space – Creates buffer around structures  Structural Retrofits – Use of fire resident building materials or installation of water sprinkler system on the outside of the structure Each individual activity is estimated to be only 10% effective at reducing the risk of wildfires and protecting structures. The local community may only perform structural retrofits if performed in conjunction with vegetation management and defensible space activities. 14
  • 15. Federal Emergency Management Agency Modeled Damage Example – Wildfire Even though wildfire mitigation projects are only at best 30% effective and the useful life is short, they can be very cost effective due to the value of structures and infrastructure in the protected area.  Wildfire recurrence intervals is provided by Landfire (https://www.landfire.gov)  Project useful life is generally short, 3 to 5 years  Benefits calculate is based on a maximum project effectiveness of 30%  Challenges with meeting environmental and historic preservation requirements which can exceed the actual project costs! 15 Upper Lochsa River Idaho Sub-Basin Mean Fire Interval
  • 16. Federal Emergency Management Agency Historic or Expected Damages  The BCA Toolkit uses user-entered damage information associated with specific calendar years and/or recurrence intervals to estimate damages to the facility.  Instead of using an established model, the software uses the data points entered by the user to create a curve. 16 Year or RI Damage
  • 17. Federal Emergency Management Agency Historic or Expected Damages Can be used to analyze any hazard/project type.  Best approach for:  Any project that is mitigating a non-building, such as a utility or road/bridge  Any project where the primary damages being mitigated are loss of service/function, rather than physical damages  More complex projects like flood control and infrastructure protection  Generator projects  Projects mitigating hazards other than flood, wind, tornado, seismic, and wildfire 17
  • 18. Federal Emergency Management Agency Common BCA issues Insufficient documentation  Example: BCA has a Lowest Floor Elevation (LFE) but application does not include elevation certificate. Lack of damage history/documentation  You can still do a BCA! However, you will need a qualified professional to estimate damages. Insufficient data/justification on project effectiveness  All projects – except acquisitions – have a point at which they are no longer effective. 18
  • 19. Federal Emergency Management Agency Simplifying Analysis  To simplify the BCA process, FEMA has several “pre-calculated benefits” for projects that meet certain conditions.  Using pre-calculated benefits eliminates the requirement for applicants to conduct a separate BCA for eligible projects. For more information visit www.fema.gov/benefit-cost-analysis. 19
  • 20. Federal Emergency Management Agency Where Analysis Can be Improved Upon How weather and climate are changing • Anecdotal evidence that severe weather events are occurring more frequent, are more extreme in size and longer duration. • How do we incorporate extreme weather events into analysis and design mitigation projects to minimize impacts. Identify more standard values to use in analysis. • Update existing values or service to account for a change in lifestyle. • Identify value of services for telecommunications, 911/112/999 services, other lifeline functions. 20
  • 21. Federal Emergency Management Agency What is an Appropriate Discount Rate? The US Government currently requires a 7% discount rate for FEMA’s mitigation projects.  The 7% discount rate is arguably high and has not been revised since 1992.  For smaller projects, it is somewhat easy to demonstrate most projects as cost effective.  For large infrastructure projects in which benefits are accrued for more than 30 years and provides multigenerational benefits, the 7% discount rate makes it difficult to demonstrate projects are cost effective.  The 7% discount rate may drive investment of funds toward smaller projects versus large community wide infrastructure projects. 21