The document provides SCE's business update for July 2018. It summarizes SCE's capital expenditure forecast of $13.7 billion from 2018 to 2020, which incorporates spending from SCE's GRC and other CPUC and FERC proceedings. The forecast also includes grid modernization spending and projects like electric vehicle infrastructure and energy storage. The update forecasts SCE's rate base to grow at a compound annual rate of 9.7% from 2017 to 2020 based on requests in SCE's 2018 GRC proceeding.
The document provides a business update for May 2018 that includes the following information:
- It discusses SCE's significant infrastructure investment and above average rate base growth driven by safety, reliability, grid modernization, and California's low-carbon objectives. Rate base is forecasted to grow by 9.7% annually through 2020.
- Key regulatory proceedings and drivers of long-term growth for SCE are outlined, including grid modernization, energy storage, transmission needs, and transportation electrification.
- SCE has a decoupled regulatory framework with major balancing accounts that promote energy conservation and stabilize revenues.
- An overview of SCE's efforts around California's wildfire risk mitigation is provided,
SCE provided a business update and capital expenditure forecast for 2018-2020:
- SCE is forecasting $13.7 billion in capital expenditures over the period driven by infrastructure investment, grid modernization, and transportation electrification.
- Rate base is forecasted to grow at an average annual rate of 9.8% through 2020 to $33.3 billion, supporting continued core earnings growth.
- Key drivers of investment include safety, reliability, achieving California's climate goals, and supporting the expansion of electric vehicles and other clean technologies.
SCE provides electricity to 15 million customers across 50,000 square miles in central and southern California. SCE is forecasting average annual rate base growth of 9.7% through 2020, driven by safety, reliability, and California's clean energy goals. Key drivers of growth include grid modernization, energy storage, and expanding electric vehicle charging infrastructure. SCE operates under a decoupled regulatory framework with balancing accounts that promote energy conservation and revenue stability.
The document provides a business update for SCE in March 2019. It discusses SCE's long-term growth drivers such as infrastructure investment, grid modernization, transmission needs, energy storage investments, transportation electrification, and wildfire prevention and mitigation efforts. SCE expects to spend approximately $350 million on wildfire prevention and mitigation capital in 2019 to help address the increasing wildfire risk in its service territory. The regulatory framework for SCE includes decoupling of revenues from electricity sales and major balancing accounts which help stabilize revenues.
The document provides an update on business activities as of July 26, 2019. It discusses SCE's regulated business model including rate base growth drivers such as infrastructure replacement, grid modernization, and wildfire prevention. SCE's earnings are expected to track its increasing rate base over the long term. The regulatory framework includes decoupling revenues from sales and balancing accounts to provide stability. Forward-looking statements are subject to risks and uncertainties from factors such as regulatory proceedings and natural disasters.
- SCE forecasts $19.3 billion in capital expenditures from 2017-2020, driven by grid modernization, reliability, and supporting California's clean energy goals. This forecast does not include potential future investments in transportation electrification.
- SCE's historical capital expenditures have grown its rate base at a compound annual growth rate of 7% from 2011-2016. However, the CPUC has approved less than full requests in past rate cases.
- SCE's regulatory model includes decoupling, balancing accounts, and forward-looking ratemaking to stabilize revenues and promote cost recovery for prudent investments. However, grid modernization spending faces uncertainty due to lack of past approval experience.
SCE forecasts $18.9 billion in capital expenditures from 2017-2020, driven by grid modernization investments and reliability upgrades. This forecast is based on SCE's 2018 GRC request and includes $2 billion for grid modernization. SCE's historical capital expenditures have grown its rate base by an average of 7% annually from 2011-2016. However, future authorized spending may differ from forecasts as the CPUC has not approved all requested capital in past GRCs.
SCE filed applications at the CPUC and FERC regarding its cost of capital. At the CPUC, SCE requested a three-year cost of capital mechanism starting in 2020. It proposed a weighted average cost of capital of 10.96%, including a conventional ROE of 10.6% and a wildfire risk ROE of 6%. At FERC, SCE filed a new rate case requesting a formula recovery mechanism starting in November 2019, as settlement discussions for its previous filing from 2017 are ongoing.
The document provides a business update for May 2018 that includes the following information:
- It discusses SCE's significant infrastructure investment and above average rate base growth driven by safety, reliability, grid modernization, and California's low-carbon objectives. Rate base is forecasted to grow by 9.7% annually through 2020.
- Key regulatory proceedings and drivers of long-term growth for SCE are outlined, including grid modernization, energy storage, transmission needs, and transportation electrification.
- SCE has a decoupled regulatory framework with major balancing accounts that promote energy conservation and stabilize revenues.
- An overview of SCE's efforts around California's wildfire risk mitigation is provided,
SCE provided a business update and capital expenditure forecast for 2018-2020:
- SCE is forecasting $13.7 billion in capital expenditures over the period driven by infrastructure investment, grid modernization, and transportation electrification.
- Rate base is forecasted to grow at an average annual rate of 9.8% through 2020 to $33.3 billion, supporting continued core earnings growth.
- Key drivers of investment include safety, reliability, achieving California's climate goals, and supporting the expansion of electric vehicles and other clean technologies.
SCE provides electricity to 15 million customers across 50,000 square miles in central and southern California. SCE is forecasting average annual rate base growth of 9.7% through 2020, driven by safety, reliability, and California's clean energy goals. Key drivers of growth include grid modernization, energy storage, and expanding electric vehicle charging infrastructure. SCE operates under a decoupled regulatory framework with balancing accounts that promote energy conservation and revenue stability.
The document provides a business update for SCE in March 2019. It discusses SCE's long-term growth drivers such as infrastructure investment, grid modernization, transmission needs, energy storage investments, transportation electrification, and wildfire prevention and mitigation efforts. SCE expects to spend approximately $350 million on wildfire prevention and mitigation capital in 2019 to help address the increasing wildfire risk in its service territory. The regulatory framework for SCE includes decoupling of revenues from electricity sales and major balancing accounts which help stabilize revenues.
The document provides an update on business activities as of July 26, 2019. It discusses SCE's regulated business model including rate base growth drivers such as infrastructure replacement, grid modernization, and wildfire prevention. SCE's earnings are expected to track its increasing rate base over the long term. The regulatory framework includes decoupling revenues from sales and balancing accounts to provide stability. Forward-looking statements are subject to risks and uncertainties from factors such as regulatory proceedings and natural disasters.
- SCE forecasts $19.3 billion in capital expenditures from 2017-2020, driven by grid modernization, reliability, and supporting California's clean energy goals. This forecast does not include potential future investments in transportation electrification.
- SCE's historical capital expenditures have grown its rate base at a compound annual growth rate of 7% from 2011-2016. However, the CPUC has approved less than full requests in past rate cases.
- SCE's regulatory model includes decoupling, balancing accounts, and forward-looking ratemaking to stabilize revenues and promote cost recovery for prudent investments. However, grid modernization spending faces uncertainty due to lack of past approval experience.
SCE forecasts $18.9 billion in capital expenditures from 2017-2020, driven by grid modernization investments and reliability upgrades. This forecast is based on SCE's 2018 GRC request and includes $2 billion for grid modernization. SCE's historical capital expenditures have grown its rate base by an average of 7% annually from 2011-2016. However, future authorized spending may differ from forecasts as the CPUC has not approved all requested capital in past GRCs.
SCE filed applications at the CPUC and FERC regarding its cost of capital. At the CPUC, SCE requested a three-year cost of capital mechanism starting in 2020. It proposed a weighted average cost of capital of 10.96%, including a conventional ROE of 10.6% and a wildfire risk ROE of 6%. At FERC, SCE filed a new rate case requesting a formula recovery mechanism starting in November 2019, as settlement discussions for its previous filing from 2017 are ongoing.
SCE forecasts $19.4-$21.2 billion in capital expenditures from 2020-2023 to strengthen its infrastructure and meet California's clean energy mandates. Key drivers include replacing aging infrastructure, mitigating wildfire risk through programs like covered conductor installation, enabling transportation electrification, and building transmission to support 60% renewables by 2030. Approximately $1.6 billion of wildfire mitigation spending will be securitized per recent legislation. This investment is expected to drive SCE's rate base to grow at a 6.6% CAGR through 2023.
- The document provides an update on business performance and outlook for Edison International and its subsidiary Southern California Edison.
- It discusses SCE's historical and projected rate base growth of 7-8% annually through 2023, which is expected to drive long-term earnings growth.
- Key drivers of rate base growth include infrastructure replacement, grid modernization, transportation electrification, energy storage, transmission investments, and wildfire prevention and mitigation activities.
The document provides a business update from Southern California Edison (SCE). It discusses SCE's regulatory framework, capital expenditure plans, commitment to sustainability and clean energy initiatives, impacts from COVID-19 and recent wildfires, key regulatory proceedings, and 2020 earnings guidance. SCE expects to invest heavily in safety, reliability, and clean energy through at least 2023, driving average annual rate base growth of 7-8% and allowing stable, long-term earnings growth.
- Ameren reported higher third quarter 2016 earnings compared to third quarter 2015, driven by higher electric sales from warmer summer temperatures and increased investment in electric infrastructure.
- For 2016, Ameren raised its diluted EPS guidance range to $2.65 to $2.75, up from $2.45 to $2.65.
- Ameren is executing its strategic plan of investing in its utility assets consistent with regulatory frameworks, including investments in electric transmission, Illinois electric and gas distribution, and pursuing an enhanced regulatory framework in Missouri to support additional investment.
This document provides an overview of regulatory investment incentives for electricity and gas networks. It discusses major sector trends driving investment needs, such as increasing renewable energy and demand growth. Investments are classified as either market-based or reliability-focused. Regulatory approaches to incentivizing efficient investments are examined, including revenue caps, cost-benefit analysis of projects, and allowing a return on a regulated asset base. Practical examples from countries like the UK, Germany and Norway are also reviewed. The presentation aims to help regulators design frameworks that ensure adequate and efficient network investment.
The document provides an overview of Edison International's business update for July 29, 2020. It discusses forward-looking statements and risk factors that could impact financial performance. Key points of focus are Edison International's role in transforming the electric power industry through investments in grid modernization and clean energy in California, as well as revenue certainty provided by regulatory mechanisms as customer load and payment patterns change.
Presentation and Complete Earnings ExhibitsInvestorPGE
This document provides an earnings call summary and presentation for PG&E Corporation for the third quarter of 2013. Key points include:
- EPS from operations was $0.88 but EPS on a GAAP basis was lower at $0.36 due to $233 million in costs related to natural gas matters.
- Guidance for 2013 EPS from operations is $2.55-$2.75 but estimated EPS on a GAAP basis is lower at $1.60-$1.96 due to estimated natural gas costs of $686-$586 million.
- The company continues work on its Pipeline Safety Enhancement Program and has filed an update removing some pipeline replacement and adding other segments.
- Regulatory proceedings
Choosing Green: Status and Challenges of RE based Open AccessWRI India
This document discusses renewable energy-based open access in India, including its current status, challenges, and proposed solutions. Some key points:
- Renewable energy generation varies seasonally and daily, posing integration challenges for grids.
- Many states have seen increasing renewable energy-based open access transactions in recent years, especially solar and wind.
- Challenges to further scaling include gradually reducing waivers on open access charges and transitioning to medium- and long-term open access. Improved forecasting, scheduling, and deviation settlement is also needed.
- Proposed solutions discussed include a new framework for energy banking that appropriately values banked and unbanked energy to address renewable energy's variability.
This presentation discusses SolarCity's energy storage product opportunities. It notes that SolarCity's solar products have resulted in $7.7 billion in contracted customer payments with 120% annual growth since 2012. SolarCity offers energy storage products for commercial, residential, and utility customers to reduce energy bills and provide backup power. These products pair solar energy with battery storage to firm up power during peak periods and offer savings opportunities like reducing demand charges for commercial customers. The presentation also describes SolarCity's microgrid products for remote communities that can provide power at lower costs than diesel generators.
http://www.leonardo-energy.org/webinar/energy-efficiency-programs-and-policies
This session is part of the Clean Energy Regulators Initiative Webinar Programme.
Theme 8 - Promotion of Energy Efficiency
Module 3 - Energy Efficiency Programs and Policies
This webinar covers the three main delivery mechanisms that can be incorporated into a national policy to deliver energy savings and reduce greenhouse gas emissions.
First, it is presented the importance of having high-level policies and strategies clearly stated by the government, sometimes expressed more formally through enabling legislation on energy efficiency. Then, it is discussed the regulatory path to establish minimum requirements that each targeted stakeholder in the market has to comply with, which would include building codes, minimum energy performance standards (MEPS), energy manager regulations, mandatory disclosure of energy usage and an annual action plan. The discussion follows on how the government can launch support programs for energy efficiency or establish a regulatory framework that would obligate energy utilities to put programs in place, and to deliver energy savings to their customers. Finally, it is presented the market mechanism based on Energy Service Companies that can act as an integrator and catalyst of private investment in the market, and ultimately demonstrate that a market has been completely transformed towards a greener energy sector.
This presentation discusses SolarCity's business strategies and metrics. It focuses on growing its leadership in distributed solar, monetizing the value of its long-term energy contracts, and achieving best-in-class technology and operating costs. Metrics show SolarCity increasing its share of the growing US solar market while reducing costs per watt and increasing value per watt deployed through low-cost financing and contract monetization.
Training Module on Electricity Market Regulation - SESSION 6 - Efficiency Ass...Leonardo ENERGY
Regulators use efficiency assessment to set the efficiency targets of the regulated service providers. This session explains the role of the efficiency assessment, the methods to measure efficiency and the incorporation of efficiency results in the price control.
Why measure efficiency?
Methods for efficiency assessments : Uni-dimensional ratio analysis / Statistical and econometric methods / Linear programming methods / Virtual network models
Application of efficiency results o TOTEX versus OPEX benchmarking : Building block approach / Cost controllability (short- and long-term) / Efficiency convergence speed / Capping efficiency scores / Using efficiency bands
The document summarizes a presentation given by Larry Weyers, President and CEO of Integrys Energy Group, at the AGA Financial Forum on May 4-6, 2008. The presentation provides an overview of Integrys Energy Group, including its goals, regulated utility businesses serving over 2 million customers across several Midwestern states, investment in capital projects such as the Weston 4 power plant and American Transmission Company, and initiatives for 2008 such as regulatory rate cases.
DTE Energy reported its business and financial results for 2007. Key points include:
- Operating earnings for 2007 were $2.82 per share, driven by strong results across utility and non-utility segments.
- Detroit Edison and MichCon earned near their authorized returns on equity despite challenges from new computer systems.
- Non-utility segments like coal/gas midstream and energy trading significantly contributed to earnings.
- The company is making investments to grow its utilities and pipelines, with plans to file an updated rate case for Detroit Edison.
The document provides an overview of the photovoltaic (PV) market in New Jersey. It discusses the evolution of PV capacity and costs in the US market and New Jersey's solar resources. Key aspects of New Jersey's PV market covered include installed capacity, incentives like rebates and renewable energy credits, utility programs, and business models. It also reviews the state's solar tax exemption and net metering policies which support the market.
The document provides an overview and summary of key elements of Assembly Bill 649 and Senate Bill 450, which address clean energy and climate change issues in Wisconsin. The summary includes goals to reduce greenhouse gas emissions and increase renewable energy and energy efficiency. It also describes programs for energy efficiency, renewable portfolio standards, renewable tariffs, and considerations for new nuclear power plants. Additional sections cover transportation initiatives, energy efficient buildings and equipment, roles for state and local government, bioenergy, industrial efficiency incentives, and coordinating climate change programs.
Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...Fernando Penarroyo
The document discusses legal and regulatory issues affecting the Philippine geothermal industry under the Renewable Energy Act of 2008. It identifies several key challenges, including the government's ambivalence towards foreign ownership, complex rules for obtaining consent from indigenous peoples, lack of transmission infrastructure, and delays in establishing clear feed-in tariff rates. It recommends that regulators address these issues to provide greater policy certainty and incentives to attract more private investment needed to meet the country's renewable energy targets.
- SCE forecasts $18.6 billion in capital expenditures from 2017-2020, including $1.8 billion for grid modernization during the 2018 GRC period.
- SCE's historical rate base grew at a compounded annual rate of 7% from 2011-2016 and core earnings grew at 5% annually over the same period.
- Key drivers of future growth include ongoing infrastructure investment, grid modernization to integrate renewables, and expanding electric transportation.
SCE filed its 2018 General Rate Case application in September 2016 requesting a revenue requirement increase of $196 million or 2.5% for 2018. Intervenors ORA and TURN filed testimony proposing lower spending levels that would result in smaller revenue requirement increases or decreases. SCE rebuttal testimony defended its requested spending levels and forecasted rate base growth of 8.3% annually from 2017-2020. Key upcoming regulatory proceedings for SCE include the 2018 GRC, cost of capital, and programs related to grid modernization, transportation electrification, and distributed energy resources.
SCE filed its 2018 General Rate Case application in September 2016 requesting a revenue requirement increase of 2.7% in 2018 over presently authorized rates to fund ongoing infrastructure investment and initial grid modernization projects. Key items in the 2018 GRC include $2.1 billion for grid modernization capital and increased depreciation expense to reflect updated cost removal estimates. The rate case schedule includes intervenor testimony in early 2017, evidentiary hearings in mid-2017, and a proposed decision by late 2017.
SCE provided a business update for November 2016. The document discusses SCE's strategy to produce shareholder value through sustained earnings and dividend growth led by increasing SCE's rate base. SCE plans to invest $23 billion in capital projects from 2016-2020, including $2.3 billion for grid modernization. This capital investment is expected to drive SCE's average annual rate base growth of 8.5% over the period. Regulatory filings like the 2018 GRC seek approval for these planned expenditures and revenue requirements.
SCE forecasts $19.4-$21.2 billion in capital expenditures from 2020-2023 to strengthen its infrastructure and meet California's clean energy mandates. Key drivers include replacing aging infrastructure, mitigating wildfire risk through programs like covered conductor installation, enabling transportation electrification, and building transmission to support 60% renewables by 2030. Approximately $1.6 billion of wildfire mitigation spending will be securitized per recent legislation. This investment is expected to drive SCE's rate base to grow at a 6.6% CAGR through 2023.
- The document provides an update on business performance and outlook for Edison International and its subsidiary Southern California Edison.
- It discusses SCE's historical and projected rate base growth of 7-8% annually through 2023, which is expected to drive long-term earnings growth.
- Key drivers of rate base growth include infrastructure replacement, grid modernization, transportation electrification, energy storage, transmission investments, and wildfire prevention and mitigation activities.
The document provides a business update from Southern California Edison (SCE). It discusses SCE's regulatory framework, capital expenditure plans, commitment to sustainability and clean energy initiatives, impacts from COVID-19 and recent wildfires, key regulatory proceedings, and 2020 earnings guidance. SCE expects to invest heavily in safety, reliability, and clean energy through at least 2023, driving average annual rate base growth of 7-8% and allowing stable, long-term earnings growth.
- Ameren reported higher third quarter 2016 earnings compared to third quarter 2015, driven by higher electric sales from warmer summer temperatures and increased investment in electric infrastructure.
- For 2016, Ameren raised its diluted EPS guidance range to $2.65 to $2.75, up from $2.45 to $2.65.
- Ameren is executing its strategic plan of investing in its utility assets consistent with regulatory frameworks, including investments in electric transmission, Illinois electric and gas distribution, and pursuing an enhanced regulatory framework in Missouri to support additional investment.
This document provides an overview of regulatory investment incentives for electricity and gas networks. It discusses major sector trends driving investment needs, such as increasing renewable energy and demand growth. Investments are classified as either market-based or reliability-focused. Regulatory approaches to incentivizing efficient investments are examined, including revenue caps, cost-benefit analysis of projects, and allowing a return on a regulated asset base. Practical examples from countries like the UK, Germany and Norway are also reviewed. The presentation aims to help regulators design frameworks that ensure adequate and efficient network investment.
The document provides an overview of Edison International's business update for July 29, 2020. It discusses forward-looking statements and risk factors that could impact financial performance. Key points of focus are Edison International's role in transforming the electric power industry through investments in grid modernization and clean energy in California, as well as revenue certainty provided by regulatory mechanisms as customer load and payment patterns change.
Presentation and Complete Earnings ExhibitsInvestorPGE
This document provides an earnings call summary and presentation for PG&E Corporation for the third quarter of 2013. Key points include:
- EPS from operations was $0.88 but EPS on a GAAP basis was lower at $0.36 due to $233 million in costs related to natural gas matters.
- Guidance for 2013 EPS from operations is $2.55-$2.75 but estimated EPS on a GAAP basis is lower at $1.60-$1.96 due to estimated natural gas costs of $686-$586 million.
- The company continues work on its Pipeline Safety Enhancement Program and has filed an update removing some pipeline replacement and adding other segments.
- Regulatory proceedings
Choosing Green: Status and Challenges of RE based Open AccessWRI India
This document discusses renewable energy-based open access in India, including its current status, challenges, and proposed solutions. Some key points:
- Renewable energy generation varies seasonally and daily, posing integration challenges for grids.
- Many states have seen increasing renewable energy-based open access transactions in recent years, especially solar and wind.
- Challenges to further scaling include gradually reducing waivers on open access charges and transitioning to medium- and long-term open access. Improved forecasting, scheduling, and deviation settlement is also needed.
- Proposed solutions discussed include a new framework for energy banking that appropriately values banked and unbanked energy to address renewable energy's variability.
This presentation discusses SolarCity's energy storage product opportunities. It notes that SolarCity's solar products have resulted in $7.7 billion in contracted customer payments with 120% annual growth since 2012. SolarCity offers energy storage products for commercial, residential, and utility customers to reduce energy bills and provide backup power. These products pair solar energy with battery storage to firm up power during peak periods and offer savings opportunities like reducing demand charges for commercial customers. The presentation also describes SolarCity's microgrid products for remote communities that can provide power at lower costs than diesel generators.
http://www.leonardo-energy.org/webinar/energy-efficiency-programs-and-policies
This session is part of the Clean Energy Regulators Initiative Webinar Programme.
Theme 8 - Promotion of Energy Efficiency
Module 3 - Energy Efficiency Programs and Policies
This webinar covers the three main delivery mechanisms that can be incorporated into a national policy to deliver energy savings and reduce greenhouse gas emissions.
First, it is presented the importance of having high-level policies and strategies clearly stated by the government, sometimes expressed more formally through enabling legislation on energy efficiency. Then, it is discussed the regulatory path to establish minimum requirements that each targeted stakeholder in the market has to comply with, which would include building codes, minimum energy performance standards (MEPS), energy manager regulations, mandatory disclosure of energy usage and an annual action plan. The discussion follows on how the government can launch support programs for energy efficiency or establish a regulatory framework that would obligate energy utilities to put programs in place, and to deliver energy savings to their customers. Finally, it is presented the market mechanism based on Energy Service Companies that can act as an integrator and catalyst of private investment in the market, and ultimately demonstrate that a market has been completely transformed towards a greener energy sector.
This presentation discusses SolarCity's business strategies and metrics. It focuses on growing its leadership in distributed solar, monetizing the value of its long-term energy contracts, and achieving best-in-class technology and operating costs. Metrics show SolarCity increasing its share of the growing US solar market while reducing costs per watt and increasing value per watt deployed through low-cost financing and contract monetization.
Training Module on Electricity Market Regulation - SESSION 6 - Efficiency Ass...Leonardo ENERGY
Regulators use efficiency assessment to set the efficiency targets of the regulated service providers. This session explains the role of the efficiency assessment, the methods to measure efficiency and the incorporation of efficiency results in the price control.
Why measure efficiency?
Methods for efficiency assessments : Uni-dimensional ratio analysis / Statistical and econometric methods / Linear programming methods / Virtual network models
Application of efficiency results o TOTEX versus OPEX benchmarking : Building block approach / Cost controllability (short- and long-term) / Efficiency convergence speed / Capping efficiency scores / Using efficiency bands
The document summarizes a presentation given by Larry Weyers, President and CEO of Integrys Energy Group, at the AGA Financial Forum on May 4-6, 2008. The presentation provides an overview of Integrys Energy Group, including its goals, regulated utility businesses serving over 2 million customers across several Midwestern states, investment in capital projects such as the Weston 4 power plant and American Transmission Company, and initiatives for 2008 such as regulatory rate cases.
DTE Energy reported its business and financial results for 2007. Key points include:
- Operating earnings for 2007 were $2.82 per share, driven by strong results across utility and non-utility segments.
- Detroit Edison and MichCon earned near their authorized returns on equity despite challenges from new computer systems.
- Non-utility segments like coal/gas midstream and energy trading significantly contributed to earnings.
- The company is making investments to grow its utilities and pipelines, with plans to file an updated rate case for Detroit Edison.
The document provides an overview of the photovoltaic (PV) market in New Jersey. It discusses the evolution of PV capacity and costs in the US market and New Jersey's solar resources. Key aspects of New Jersey's PV market covered include installed capacity, incentives like rebates and renewable energy credits, utility programs, and business models. It also reviews the state's solar tax exemption and net metering policies which support the market.
The document provides an overview and summary of key elements of Assembly Bill 649 and Senate Bill 450, which address clean energy and climate change issues in Wisconsin. The summary includes goals to reduce greenhouse gas emissions and increase renewable energy and energy efficiency. It also describes programs for energy efficiency, renewable portfolio standards, renewable tariffs, and considerations for new nuclear power plants. Additional sections cover transportation initiatives, energy efficient buildings and equipment, roles for state and local government, bioenergy, industrial efficiency incentives, and coordinating climate change programs.
Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...Fernando Penarroyo
The document discusses legal and regulatory issues affecting the Philippine geothermal industry under the Renewable Energy Act of 2008. It identifies several key challenges, including the government's ambivalence towards foreign ownership, complex rules for obtaining consent from indigenous peoples, lack of transmission infrastructure, and delays in establishing clear feed-in tariff rates. It recommends that regulators address these issues to provide greater policy certainty and incentives to attract more private investment needed to meet the country's renewable energy targets.
- SCE forecasts $18.6 billion in capital expenditures from 2017-2020, including $1.8 billion for grid modernization during the 2018 GRC period.
- SCE's historical rate base grew at a compounded annual rate of 7% from 2011-2016 and core earnings grew at 5% annually over the same period.
- Key drivers of future growth include ongoing infrastructure investment, grid modernization to integrate renewables, and expanding electric transportation.
SCE filed its 2018 General Rate Case application in September 2016 requesting a revenue requirement increase of $196 million or 2.5% for 2018. Intervenors ORA and TURN filed testimony proposing lower spending levels that would result in smaller revenue requirement increases or decreases. SCE rebuttal testimony defended its requested spending levels and forecasted rate base growth of 8.3% annually from 2017-2020. Key upcoming regulatory proceedings for SCE include the 2018 GRC, cost of capital, and programs related to grid modernization, transportation electrification, and distributed energy resources.
SCE filed its 2018 General Rate Case application in September 2016 requesting a revenue requirement increase of 2.7% in 2018 over presently authorized rates to fund ongoing infrastructure investment and initial grid modernization projects. Key items in the 2018 GRC include $2.1 billion for grid modernization capital and increased depreciation expense to reflect updated cost removal estimates. The rate case schedule includes intervenor testimony in early 2017, evidentiary hearings in mid-2017, and a proposed decision by late 2017.
SCE provided a business update for November 2016. The document discusses SCE's strategy to produce shareholder value through sustained earnings and dividend growth led by increasing SCE's rate base. SCE plans to invest $23 billion in capital projects from 2016-2020, including $2.3 billion for grid modernization. This capital investment is expected to drive SCE's average annual rate base growth of 8.5% over the period. Regulatory filings like the 2018 GRC seek approval for these planned expenditures and revenue requirements.
Edison International provides a business update and discusses its strategy and opportunities for growth. Key points include:
- Edison International is leading the transformation to clean energy through its subsidiary SCE and aims to deliver 100% carbon-free power by 2045.
- SCE has over $5 billion in annual infrastructure investment opportunities to modernize the grid and support California's climate goals.
- Edison International is well-positioned for strong growth due to California's aggressive clean energy policies and regulatory mechanisms that support grid investments and provide revenue stability and certainty.
The document is AEP's 3rd Quarter 2022 Earnings Release Presentation. Some key details from the summary:
- AEP reported operating earnings of $1.62 per share or $831 million for 3Q 2022.
- For the year-to-date period ending September 2022, AEP reported operating earnings of $4.04 per share or $2.07 billion.
- AEP narrowed its 2022 operating earnings guidance range to $4.97-$5.07 per share and introduced 2023 operating earnings guidance of $5.19-$5.39 per share.
- AEP is executing a $40 billion capital investment plan between 2023-20
The document discusses delivering superior shareholder value through operational excellence, leveraging Arizona's economic recovery, proactively addressing rate design, and executing a long-term investment plan. It provides an overview of Pinnacle West's financial metrics and Arizona Public Service, discusses Arizona's economic indicators and growth outlook, and outlines capital expenditure plans and expected rate base growth through 2018. Key environmental regulations and their projected costs are also summarized.
QTS reported financial results for the third quarter of 2019. Total revenue increased 17% year-over-year to $125.3 million. Operating FFO grew 16% year-over-year to $63 million. Adjusted EBITDA margin was 50.3%, down from the prior year primarily due to higher-than-expected power and property tax costs. Excluding these costs, adjusted EBITDA margin would have been approximately 53%, up 200 basis points year-over-year. QTS signed $17.4 million in new and modified leases during the quarter and had a record $80 million backlog as of the end of the third quarter.
Overview of Utility Challenges and Responses to Distributed Solar EnergyScottMadden, Inc.
Utility planning is changing with the rapid growth of distributed solar in certain markets. Over the long term, market fundamentals favor the continued growth of distributed solar energy. This will access business and operational challenges for utilities. This insight outlines strategies utilities can deploy to successfully incorporate distributed solar energy into their business model or generation portfolio.
The document discusses the key principles of multi-year tariff (MYT) framework for electricity regulation in India. Some key points:
- MYT aims to incentivize efficiency, reduce regulatory uncertainty, assist utilities in planning, and introduce efficient tariff design.
- It determines the regulatory framework for a period of time including principles for regulating returns, costs, and ongoing regulation.
- The framework separates controllable and uncontrollable costs and treats them differently. Uncontrollable costs like fuel costs are passed through while utilities share gains/losses from controllable costs.
- Utilities file multi-year applications covering ARR, revenue, capital plans and performance targets for a control period of typically 5
Edison International provides a business update, noting that it is leading the transformation of the electric power industry through investing $5 billion annually to modernize the grid and advance California's clean energy goals. The company has strong alignment with California's aggressive climate targets through supporting electrification, infrastructure upgrades, and clean energy. Edison International expects 6.7-7.6% average annual rate base growth through 2023, supporting its target dividend payout of 45-55% of earnings. California's regulatory framework provides revenue certainty through decoupling and other mechanisms that break the link between electricity sales and profits.
QTS Realty Trust held an earnings presentation on July 30, 2019 to review its second quarter 2019 results. The presentation included information on QTS' strong leasing activity in Q2 2019, its focus on the federal vertical market, its differentiated approach to the hyperscale business including a joint venture, its financial results and guidance, and its international expansion through acquisitions in the Netherlands. The presentation also provided an appendix with reconciliations of non-GAAP financial measures to GAAP measures.
Connecticut Self Storage Association PresentationRRinc
The document summarizes an energy summit for self storage owners and managers. It discusses investing in energy efficiency measures and low interest financing options. It also reviews a case study of a solar installation proposal and financial analysis for a Connecticut storage facility. The 46.08 kW solar array is estimated to generate over 50,000 kWh annually and offset 98% of the facility's electricity needs. Financial projections show the project has a 77% return on investment without renewable energy credits and a 121% return on investment including credits over the 25-year system life.
World Bank Group’s Support to Renewable Energy DevelopmentMirzo Ibragimov
On 5-6 December, Tashkent hosted a workshop on renewable energy (RE) policy development jointly organized by the Government of Uzbekistan and the World Bank Group (WBG) in partnership with the International Renewable Energy Agency (IRENA). The presentation was delivered during the above-mentioned event.
The document discusses electric ratemaking in Texas, including how rates are determined through revenue requirements and rate structures, the regulatory process for rate cases, and recent mechanisms introduced in utility ratemaking like distribution cost recovery factors. It also covers concepts like allowed versus earned rates of return and how utilities are regulated differently within and outside the ERCOT grid.
The document discusses Powering Growth, Delivering Value for Pinnacle West Capital Corporation and Arizona Public Service Company. It provides an overview of the company's operations, including its large service territory in Arizona and generation capacity. It also outlines the company's financial metrics and discusses its value proposition in terms of operational excellence, leveraging Arizona's economic recovery, proactively addressing rate design, and executing its long-term investment plan to deliver competitive returns.
The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...Aggregage
Join us for a practical webinar, hosted by Kevin Kai Wong of Emergent Energy, where we'll explore how leveraging data-rich energy management solutions can drive operational excellence in the evolving landscape of energy intelligence and sustainability in manufacturing!
Case study for enabling net metering as a means of broadening a nations energy mix and facilitating increased investment in the renewable energy sector
The document is an investor presentation by SolarCity that provides forward-looking statements regarding the company's growth opportunities in the customer and market, operations, financing strategies, and future financial and operating results. It notes key risks and uncertainties that could impact actual performance, including demand for solar energy systems, supply and pricing of solar components, integration of acquisitions, cost reduction goals, access to capital, regulatory policies, and general market conditions.
OECD presentation - Financing the energy transition in emerging and developin...OECD Environment
1) Meeting net zero emissions by 2030 will require $4 trillion annual investment in clean energy, mostly from private sectors using various financial instruments.
2) Public finance can play a catalytic role by de-risking investments and supporting reforms, but current levels are small and need to scale rapidly using additional concessional finance.
3) Blended finance combining public and private funds is growing but challenges include developing secondary markets and attracting more institutional investors through financial products that pool and aggregate projects across countries.
Similar to Edison International Business Update - July 2018 (20)
The E-Way Bill revolutionizes logistics by digitizing the documentation of goods transport, ensuring transparency, tax compliance, and streamlined processes. This mandatory, electronic system reduces delays, enhances accountability, and combats tax evasion, benefiting businesses and authorities alike. Embrace the E-Way Bill for efficient, reliable transportation operations.
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdfSOFTTECHHUB
The world of blockchain and decentralized technologies is about to witness a groundbreaking event. ZKsync, the pioneering Ethereum Layer 2 network, has announced the highly anticipated airdrop of its native token, ZK. This move marks a significant milestone in the protocol's journey, empowering the community to take the reins and shape the future of this revolutionary ecosystem.
Cleades Robinson, a respected leader in Philadelphia's police force, is known for his diplomatic and tactful approach, fostering a strong community rapport.
World economy charts case study presented by a Big 4
World economy charts case study presented by a Big 4
World economy charts case
World economy charts case study presented by a Big 4
World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4
World economy charts case study presented by a Big 4
World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4World economy charts case study presented by a Big 4study presented by a Big 4
UnityNet World Environment Day Abraham Project 2024 Press ReleaseLHelferty
June 12, 2024 UnityNet International (#UNI) World Environment Day Abraham Project 2024 Press Release from Markham / Mississauga, Ontario in the, Greater Tkaronto Bioregion, Canada in the North American Great Lakes Watersheds of North America (Turtle Island).
Methanex is the world's largest producer and supplier of methanol. We create value through our leadership in the global production, marketing and delivery of methanol to customers. View our latest Investor Presentation for more details.
2. Statements contained in this presentation about future performance, including, without limitation, operating results, capital
expenditures, rate base growth, dividend policy, financial outlook, and other statements that are not purely historical, are forward-
looking statements. These forward-looking statements reflect our current expectations; however, such statements involve risks and
uncertainties. Actual results could differ materially from current expectations. These forward-looking statements represent our
expectations only as of the date of this presentation, and Edison International assumes no duty to update them to reflect new
information, events or circumstances. Important factors that could cause different results include, but are not limited to the:
• ability of SCE to recover its costs through regulated rates, including costs related to uninsured wildfire-related and mudslide-
related liabilities, spending on grid modernization and other capital spending incurred prior to explicit regulatory approval;
• ability to obtain sufficient insurance at a reasonable cost, including insurance relating to SCE's nuclear facilities and wildfire-
related and mudslide-related exposure, and to recover the costs of such insurance or, in the absence of insurance, the ability to
recover uninsured losses;
• decisions and other actions by the CPUC, the FERC, the NRC and other regulatory authorities, including determinations of
authorized rates of return or return on equity, the 2018 GRC, the recoverability of wildfire-related and mudslide-related costs,
and delays in regulatory actions;
• ability of Edison International or SCE to borrow funds and access the bank and capital markets on reasonable terms;
• actions by credit rating agencies to downgrade our credit ratings or those of our subsidiaries or to place those ratings on
negative watch or outlook;
• risks associated with the decommissioning of San Onofre, including those related to public opposition, permitting,
governmental approvals, on-site storage of spent nuclear fuel, and cost overruns;
• extreme weather-related incidents and other natural disasters (including earthquakes and events caused, or exacerbated, by
climate change, such as wildfires), which could cause, among other things, public safety and operational issues;
• risks associated with cost allocation resulting in higher rates for utility bundled service customers because of possible customer
bypass or departure due to CCAs; and
• risks inherent in SCE's transmission and distribution infrastructure investment program, including those related to project site
identification, public opposition, environmental mitigation, construction, permitting, power curtailment costs (payments due
under power contracts in the event there is insufficient transmission to enable acceptance of power delivery), changes in the
CAISO's transmission plans, and governmental approvals.
Other important factors are discussed under the headings “Forward-Looking Statements”, “Risk Factors” and “Management’s
Discussion and Analysis” in Edison International’s Form 10-K and other reports filed with the Securities and Exchange Commission,
which are available on our website: www.edisoninvestor.com. These filings also provide additional information on historical and
other factual data contained in this presentation.
Forward-Looking Statements
1July 27, 2018
3. Page
Updated (U) or New (N)
from May 2018 Business
Update
EIX Shareholder Value 3
SCE Highlights, SCE Long-Term Growth Drivers, Regulatory Model 4-6 U
SCE’s Approach to Addressing Wildfire Risk 7 U
California’s GHG Emissions Overview, SCE’s Clean Power and Electrification Pathway 8-9 U
Capital Expenditures and Rate Base History and Forecast 10-12 U
2018 General Rate Case 13
Key Regulatory Proceedings 14 U
CPUC Cost of Capital 15 U
2018 Financial Assumptions 16 U
Distribution and Transmission Capital Expenditure Detail 17-20 U
Operational Excellence 21
EIX Responding to Industry Change, Edison Energy Group Summary 22-23 U
Annual Dividends Per Share 24
Appendix
2018 General Rate Case Overview 26
Historical Capital Expenditures 27
Capital Expenditure and Rate Base Detailed Forecast 28
ESG Strategy 29 N
Power Grid of the Future, Grid Modernization 30-33
SCE Customer Demand Trends 34
SCE Bundled Revenue Requirement, System Average Rate Historical Growth 35-36 U
CCA Overview, Residential Rate Reform and Other 37-40 U
SCE Rates and Bills Comparison 41 U
Second Quarter 2018 Earnings Summary, Results of Operations, Non-GAAP Reconciliations 42-47 N,U
Table of Contents
2July 27, 2018
4. EIX Strategy Should Produce Superior Value
Sustained Earnings and Dividend
Growth Led by SCE
Electric-Led Clean Energy Future
SCE Rate Base Growth Drives Earnings
• 9.7% average annual rate base
growth through 2020 at request level
• SCE earnings should track rate base
growth
Constructive Regulatory Structure
• Decoupling of electricity sales
• Balancing accounts
• Forward-looking ratemaking
Sustainable Dividend Growth
• Target dividend growth at higher
than industry average within target
payout ratio of 45-55% of SCE
earnings
EIX Vision
• Lead transformation of the electric
power industry
• Focus on clean energy, efficient
electrification, grid of the future and
customers’ technology choice
Wires-Focused SCE Strategy
• Infrastructure replacement – safety
and reliability
• Grid modernization – California’s low-
carbon goals
• Operational excellence
Edison Energy Strategy
• Services for large commercial and
industrial customers
3July 27, 2018
5. One of the nation’s largest electric utilities
• 15 million residents in service territory
• 5 million customer accounts
• 50,000 square-mile service area
Significant infrastructure investment
• 1.4 million power poles
• 725,000 transformers
• 118,000 miles of distribution and transmission lines
• 3,200 MW owned generation
Above average rate base growth driven by
• Safety and reliability
• California’s low-carbon objectives
Grid modernization
Electric vehicle charging
Energy storage
Transportation electrification
Limited Generation Exposure
• Own less than 20% of its power generation
• Future needs via competitive solicitations
SCE Highlights
4July 27, 2018
6. SCE Long-Term Growth Drivers
Description Timeframe/Regulatory Process
Sustained level of infrastructure investment
required until equilibrium replacement
rates achieved and then maintained
• Ongoing - current and future GRCs
Accelerate circuit upgrades, automation,
communication, and analytics capabilities
at optimal locations to integrate distributed
energy resources
• Today – Grid modernization capital expenditures included
in traditional spend
• 2019-2020 – $1.3 billion capital request in 2018 GRC
application
• 2025 – CPUC target to complete grid modernization but
may take longer
Future transmission needs to meet 50%
renewables mandate in 2030 and to
support reliability
• 2017-2022 – Multiple projects approved by CAISO in
permitting and/or construction
• 2021-2030 – Future needs largely driven by CAISO
planning process
SCE-owned investment opportunities under
existing CPUC proceedings
• Today – Most commitments via contracts
• $49 million of capital spending forecasted for 2018-2020
• SCE’s storage portfolio – procurement target of 580 MW
by 2020
• Energy Storage and Distribution Deferral Application (A.)
17-12-002 - seeks contract approval of 10 MW of
distribution connected storage
Utility investment in programs to build and
support the expansion of transportation
electrification in passenger and light-,
medium- and heavy-duty vehicles and
potentially to support electrification of
other sectors of the economy
• 2016 – Charge Ready Phase I approved
• 2017 – MD/HD Transportation Electrification (TE) plan filed
January 20; Five TE priority projects approved, totaling $16
million
• 2018-2030 – Charge Ready Phase II filed, totaling $760
million; MD/HD TE standard review project approved,
totaling $356 million; potential investments to support
electrification of other sectors of the economy
Infrastructure
Reliability
Grid Modernization
Electrification of
Transportation and
Other Sectors
Energy Storage
Transmission
5July 27, 2018
7. SCE Decoupled Regulatory Framework
6
Regulatory Mechanism Key Benefits
Decoupling of Revenues from
Sales
• Earnings not affected by variability of retail electricity sales
• Differences between amounts collected and authorized levels
either billed or refunded
• Promotes energy conservation
• Stabilizes revenues during economic cycles
Major Balancing Accounts
• Sales
• Fuel and Purchased power
• Energy efficiency
• Pension expense
• Cost-recovery related balancing accounts represented more
than 53% of costs
• Trigger mechanism for fuel and purchased power adjustments
at 5% variance level
Advanced Long-Term
Procurement Planning
• Upfront contract approvals and prudency standards provide
greater certainty of cost recovery (subject to compliance-
related reasonableness review)
Forward-looking Ratemaking • Forward and test year GRC with three-year rate cycle
• Separate cost of capital mechanism
July 27, 2018
8. SCE’s Approach to Addressing Wildfire Risk
7
Prevention and
mitigation
Hardening the
infrastructure
Allocation of risk and
liability
• Effective fire suppression
resources
• Effective vegetation
management policies
• Hazardous fuels reduction
• Zoning regulations for
residential and commercial
development in high fire risk
areas
• Different operating protocol
under Red Flag warnings
• Preemptively de-energizing
lines in high fire risk areas
during severe wind events
• Weather stations and high
definition cameras to improve
situational awareness
• Stronger building codes in
high fire risk areas
• Partnering with state agencies
on improved standards for
climate resilient infrastructure
• Assessing the design and
operation of the system in
high fire risk areas including:
inspecting and
upgrading poles
replacing bare overhead
conductor with covered
conductor
Installing current-
limiting, non-expulsion
fuses
• Policies around allocation of
financial risks, including fire
suppression costs and
damages
• Reforming the application of
inverse condemnation with
strict liability to utilities
• Addressing the high cost of
fire suppression which exceed
state budgets annually
• Addressing increasingly high
premiums for wildfire
insurance coverage
July 27, 2018
We continue to work towards policies and procedures that support SCE’s approach in each of
the legislative, regulatory and legal pathways
9. 8
California’s GHG Emissions Overview
Commercial and
Residential
11%
Electrical
Power
19%
Agriculture
8%
Industrial
23%
Transportation
39%
SCE is taking a leading role to ensure that transportation electrification plays a major part in
reducing GHG and criteria pollutant emissions in California
2015 California GHG Emissions
by Sector
Note: Data for both charts from California Air Resources Board.
July 27, 2018
• On October 7, 2015, Governor Brown signed SB 350, which requires that 50 percent of energy sales to customers come
from renewable power and a doubling of energy efficiency in existing buildings for California by 2030
Also requires Transportation Electrification investments and Integrated Resources Planning
• On September 8, 2016, Governor Brown signed SB 32, which requires statewide GHG emissions to be reduced to 40%
below the 1990 level by 2030
Governor Order set a 2050 target of 80% below 1990 levels
• On July 24, 2017, Governor Brown signed AB 398, which extends cap-and-trade to 2030
• On January 26, 2018, Governor Brown released an Executive Order calling for 5 million zero emission vehicles by 2030
10. % Portfolio Breakdown
Solar 40%
Wind 32%
Geothermal 24%
Small Hydro 3%
Biomass 1%
SCE’s Clean Power and Electrification Pathway
• Emissions targets met through
optimization of renewables
• Implementation of upcoming
IRP filing
• 80% carbon-free electricity
supported by energy storage
• 2017 SCE renewable resources
portfolio = 31.6%
• Accelerate electrification of the
transportation sector
More than 7 million electric
vehicles on California roads
15% of medium-duty
vehicles electrified
6% of heavy-duty vehicles
electrified
• Doubling of energy efficiency in
existing buildings
• Electrify nearly one-third of
residential and commercial
space and water heaters
• Continuation of company
programs and earnings
incentive mechanism
SCE 2018 program budget:
$289 million
$0.03 per share of
estimated earnings in 2018
Electric Power Company Roles
9July 27, 2018
11. SCE Historical Rate Base and Core Earnings
Rate Base
Core Earnings
6%
2%
2012– 2017 CAGR
($ billions, except per share data)
Note: Recorded rate base, year-end basis. See SCE Core EPS Non-GAAP Reconciliations and Use of Non-GAAP Financial Measures. Since 2013, rate base excludes SONGS.
$4.20$4.68$4.10 $3.88
Core
EPS $4.22
$21.0 $21.1
$23.3
$24.6
$25.9
$27.8
2012 2013 2014 2015 2016 2017
$4.58
10July 27, 2018
12. SCE Capital Expenditure Forecast
1. Includes 2018 – 2020 capital expenditures of $105 million for Mobile Home Park, $49 million for Energy Storage, $10 million for MD/HD Transportation Electrification Priority
Review, and $4 million for Charge Ready
2. 2017 and 2018 capital expenditures related to grid modernization are included in distribution capital expenditures
3. 2018 spending at budget levels
Note: Forecasted capital spending includes CPUC, FERC and other spending. 2019-2020 based on 2018 CPUC GRC Tax Reform February Update testimony. See Capital
Expenditure/Rate Base Detailed Forecast for further information, including potential investment excluded in forecasts. Delta represents change from May 2018 Business Update.
($ billions)
$13.7 Billion 2018-2020 Capital Program
• Capital expenditure forecast incorporates GRC, FERC and non-
GRC CPUC spending
GRC decision pending; 2018 capital plan will allow SCE to
ramp up its spending program over the three-year GRC
period to meet ultimately authorized capital
2018 Grid Modernization spending focused on safety and
reliability2
Includes $119 million of non-GRC CPUC capital for mobile
home pilot program, charge ready pilot, and priority review
medium- and heavy-duty (MD/HD) Transportation
Electrification projects in 2018-2019
Does not reflect final decision on MD/HD Transportation
Electrification resulting in capital spend increases of $38
million in 2019 and $78 million in 2020
Does not reflect proposed decisions for Alberhill construction
license which would result in a reduction to FERC capital
spend of $35 million in 2019 and $51 million in 2020
• Authorized/Actual may differ from forecast
Since the 2009 GRC, CPUC has approved 81%, 89%, and 92%
of capital requested, respectively
SCE has no prior approval experience on grid modernization
capital spending and, therefore, prior results may not be
predictive
Forecasted FERC capital spending subject to timely receipt of
permitting, licensing, and regulatory approvals
$3.8
$4.2
$4.8 $4.7
2017 (Actual) 2018 2019 2020
Distribution Transmission Generation
Traditional Capital Spending:
Grid Modernization Capital Spending:
Grid Modernization
Prior
Forecast
$3.8 $4.2 $4.8 $4.7
Delta ‒ ‒ ‒ ‒
1
3
2
11July 27, 2018
13. SCE Rate Base Forecast – Request Level
CPUC
• Rate base based on request levels from
2018 GRC Tax Reform February Update
FERC
• FERC rate base, including Construction
Work in Progress (CWIP), is approximately
19% of SCE’s rate base by 2020
• Reflects latest capital forecast; including
the Alberhill System project
Other
• Includes Tax Reform impact
• Includes mobile home pilot program,
Charge Ready pilot, and MD/HD
Transportation Electrification priority
review projects
• Excludes MD/HD Transportation
Electrification standard review project and
Charge Ready Phase 2 application
• Excludes SONGS regulatory asset
($ billions)
3-year CAGR of 9.7%
Note: Weighted-average year basis. 2017 based on 2015 GRC decision. 2018-2020 CPUC based on 2018 GRC Tax Reform February Update testimony, FERC based on latest forecast
and current tax law, “rate-base offset” for the 2015 GRC decision excluded because of write off of regulatory asset related to 2012-2014 incremental tax repairs. Delta represents
change from May 2018 Business Update.
12
$26.2
$29.1
$31.8
$34.6
2017
(Authorized)
2018 2019 2020
Traditional Grid Modernization
Prior
Forecast
$26.2 $29.1 $31.8 $34.6
Delta ‒ ‒ ‒ ‒
July 27, 2018
14. • 2018 GRC Application (A. 16-09-001) filed September 1, 2016
• Addresses CPUC jurisdictional revenue requirement for 2018-2020
Includes operating costs and capital investment
Excludes CPUC jurisdictional costs such as fuel and purchased power, cost of capital and other potential
SCE capital projects (transportation electrification, Charge Ready, and storage outside of the GRC)
Excludes FERC jurisdictional transmission
• SCE’s Updated Testimony for tax reform was filed February 16, 2018, and requests 2018 revenue requirement of
$5.534 billion
$106 million decrease over 2017 GRC revenue requirement
Requests post test year GRC revenue requirement increases: $431 million in 2019 and $503 million in 2020
The requested increase represents an estimated 3% compound annual growth rate in total rates between
2017-2020
• GRC filing advances SCE strategy focusing on safety and reliability by continuing infrastructure investment and
beginning grid modernization investments, mitigating customer rate impacts through lower operating costs
GRC
Application
Filed
Rebuttal Final
Decision
2016
Q1 Q2 Q3 Q4
2017
Q1 Q2 Q3 Q4
Estimated
Intervenor
Testimony
Proposed
Decision
2018 SCE General Rate Case (GRC)
Evidentiary
Hearings
Note: Schedule was set by CPUC, but excludes timing of final decision. The schedule is subject to change over the course of the proceeding.
2018
13July 27, 2018
15. SCE Key Regulatory Proceedings
Proceeding Description Next Steps
Key CPUC Proceedings
2018 General Rate Case
(A. 16-09-001)
Set CPUC base revenue requirement, capital
expenditures and rate base for 2018-2020
Updated Testimony filed on February 16, 2018; hearing held
March 19, 2018; oral arguments held June 20, 2018
Z-Factor Advice Letter (Advice
Letter 3768-E)
Advice letter requesting Z-Factor recovery of
$108 million incurred to obtain a 12-month,
$300 million wildfire insurance policy for 2018
Protest and reply to protests have been filed; no set timeline for
Commission review
Charge Ready Program
(A.14-10-014)
Implementation program for charger
installations and market education
Phase 1 pilot program approved January 2016; Phase 1 report
filed in May 2018; Phase 2 filed in June 2018
2017 Transportation
Electrification (A.17-01-021)
TE proposals to address SB 350 transportation
electrification objectives
Five priority review projects approved in January 2018; Standard
review projects approved in May 2018
Distribution Resources Plan OIR
(R.14-08-013)
Power grid investments to integrate
distributed energy resources
Demo projects underway; Decision on the deferral framework
and distribution forecasting issued in February; Decision on
investment guidance issued in March 2018
Integrated Distributed Energy
Resources OIR (R. 14-10-003)
Creating consistent framework for guidance,
planning and evaluation of Distributed Energy
Resources (DERs)
SCE launched its IDER Incentive Pilot Solicitation on January 12,
2018 with Final Selection notification on May 11, 2018; Amended
scoping memo issued to consider alternate DER sourcing
mechanisms
SONGS OII
(I.12-10-013)
OII resolved (December 2015); Proceeding
record reopened in May 2016
Revised Settlement Agreement reached January 2018; Decision
issued in July 2018
Power Charge Indifference
Adjustment OIR (R.17-06-026)
Review, revise, and consider alternatives to the
PCIA
Scoping memo issued – Track 1 proposed decision in April 2018
and Track 2 proposed decision in third quarter 2018
Integrated Resource Plan (IRP)
OIR (R.16-02-007)
“Umbrella” proceeding to consider all electric
procurement policies/programs and
implement SB 350 requirements
SCE’s IRP expected to be filed August 1, 2018
Key FERC Proceedings
FERC Formula Rates Transmission rate setting with annual updates Replacement rate filed on October 27, 2017 and in effect subject
to refund; proceeding ongoing and settlement discussions are
continuing
14July 27, 2018
16. 3
4
5
6
7
10/1/12 10/1/13 10/1/14 10/1/15 10/1/16 10/1/17 10/1/18 10/1/19
Rate(%)
CPUC Cost of Capital
CPUC Adjustment Mechanism
Moody’s Baa Utility Index Spot Rate
Moving Average (10/1/17 – 04/30/18) = 4.32%
100 basis point +/- Deadband
Starting Value – 5.00%
Two year settlement approved for 2018-2019
• ROE adjustment based on 12-month average of
Moody’s Baa utility bond rates, measured from
October 1 to September 30
• If index exceeds 100 bps deadband from starting
index value, authorized ROE changes by half the
difference
• Starting index value based on trailing 12 months of
Moody’s Baa index as of September 30 of each
year – 5.00%
CPUC Authorized
Settlement
Terms (2018-
2019)
Capital
Structure 2017 2018-2019
Common Equity 48% 10.45% 10.30%
Preferred 9% 5.79% 5.82%
Long-term Debt 43% 5.49% 4.98%
Weighted Average Cost of Capital 7.90% 7.61%
ROE fixed at
10.30% for 2018,
independent of
trigger mechanism
ROE fixed at
10.45% for 2017,
independent of
trigger mechanism
15July 27, 2018
17. 2018 Financial Assumptions
($ billions)
SCE Capital Expenditures
SCE Authorized Cost of Capital Other Items
CPUC Return on Equity 10.3%
CPUC Capital Structure 48% equity
43% debt
9% preferred
FERC Return on Equity 11.5% with incentives
(subject to refund pending
FERC decision)
EIX will provide 2018 earnings guidance after a final decision in the SCE 2018
General Rate Case
Distribution $3.4
Transmission 0.6
Generation 0.2
2018 Plan $4.2
SCE Weighted Average Rate Base
• FERC comprises about 20% of total rate base in 2018
• Based on GRC update submitted February 2018;
incorporates impact of tax reform
Traditional $28.8
Grid Mod 0.3
2018 Request $29.1
• Based on 2018 budgeted expenditures at SCE
• Incremental wildfire insurance costs expected to be $0.38 per
share relative to our current GRC request; continuing to assess
probability of recovery; expect to defer $0.30 per share as a
regulatory asset if the premiums are deemed probable of
recovery
• Energy efficiency of $0.03 per share
• Revenues recorded at 2017 levels until 2018 GRC decision is
received (decision retroactive to January 1, 2018)
• 2018 EIX Parent and Other core EPS guidance range: ($0.25) to
($0.30) per share
Holding company drag of 2 cents per share per month
Includes EPS estimate for Edison Energy; continue to target
breakeven run rate by year-end 2019
16
Note: All tax-affected information on this slide is based on our current combined statutory tax rate of approximately 28%.
July 27, 2018
18. SCE Distribution System Investments
1. Other includes GRC energy storage, Charge Ready Pilot and mobile home pilot programs
2. 2018 Grid Modernization spending, included in distribution, is focused on safety and reliability; most spending focused on integration of distributed energy resources has been
deferred
Distribution Trends
• Continued focus on safety and reliability with
infrastructure replacement representing 45% of total
distribution capital spend, but not yet reaching
equilibrium replacement rate
Includes pole loading replacement program and
overhead conductor replacements
• Distribution grid requires upgrades to circuit
capacity, automation, and control systems to
support reliability as use of distributed energy
resources increases
• Includes grid modernization capital which is
expected to become a larger portion of spend
beyond 2018
2018 – 2020 Capital Spending Forecast
for Distribution including Grid Modernization1,2
$10.9 Billion
2018-2020 Capital Spending Drivers
• Automation of over 850 distribution circuits
• Over 2,000 miles of cable replacements
• 4kV cutovers/removals
• Distribution preventive maintenance
• Overhead conductor replacements
• Circuit breaker replacements/upgrades
Load
Growth New Service
Connections
Infrastructure
Replacement
General Plant
Grid
Modernization2
Other
17July 27, 2018
19. SCE Transportation Electrification (TE) Proposals
• By 2030, SCE calls for:
an electric grid supplied by 80 percent carbon-free energy supported by 10 GWs of energy storage,
more than 7 million light-duty electric vehicles on California roads,
15% of medium-duty and 6% of heavy-duty vehicles to be electrified, and
using electricity to power nearly one-third of space and water heaters in increasingly energy-efficient buildings
• To support around 7 million electric vehicles in California by 2030, California needs substantial investment in charging ports
18July 27, 2018
MD/HD Transportation Electrification Programs Charge Ready Phase I and II
• Range anxiety and EV awareness must be addressed
through significant deployment of EV fueling
infrastructure and increased market education and
outreach
Charge Ready Pilot - $22 million Total Cost1; approved
January 2016
• $12 million rate base opportunity included in capital
spend and rate base forecasts
• Supports close to 1,270 chargers
Charge Ready Phase 2 – $760 million Total Cost1 (in
2018 dollars); filed June 2018
• 4-year program, providing up to 48,000 chargers
• $561 million in capital spend; O&M of $199 million
• Not included in capital spend or rate base forecasts
MD/HD TE Priority Review Programs – $16 million Total
Cost1; approved January 2018
• Residential Make-Ready Rebate Pilot
• Urban Direct Current Fast Charge Clusters Pilot
• Electric Transit Bus Make-Ready Pilot
• Port of Long Beach (POLB) Terminal Yard Tractor Pilot
• POLB Rubber Tire Gantry Crane Electrification Pilot
• All included in capital spend and rate base forecasts
MD/HD TE Program - $356 million Total Cost1 (in 2016
dollars); approved May 2018
• 5-year program
• Capital spend of $242 million; O&M of $115 million
• Not included in capital spend and rate base forecasts
1. Total Cost include both O&M and capital spend.
20. 200
120
50
0
50
100
150
200
250
Transmission Distribution Customer
MW
SCE 2018 Storage Portfolio
*85 MW
excess may
offset T&D
targets
CPUC Energy Storage Program Requirements:
• Storage Rulemaking (R.10-12-007) established 1,325 MW target for
IOUs by 2024 (580 MW SCE share; spread as biennial targets
during 2014-20); ownership allowed up to 290 MW for SCE
• Flexibility to transfer across categories, expanded in Storage
Rulemaking (R.15-03-011)*
• Decision (D. 17-04-039) added AB 2868 opportunity for programs
and investments of an additional 500 MW of distribution-level
energy storage systems, distributed equally among the IOUs (166
MW SCE share; spread as biennial targets, 2018 and onward)
SCE Procurement Activities to Meet CPUC Requirements:
• SCE has procured over 500 MW of energy storage, and following
the recent approval of SCE’s Second Preferred Resources Pilot,
~424 MW of which is eligible to count towards CPUC targets. The
recent approval puts SCE ahead of its 370 MW 2018 interim
Storage Targets, and ~156 MW from achieving 2020 Targets
• SCE filed its 2018 Energy Storage and Investment Plan on March 1
The 2018 Plan included AB 2868 proposals for Energy Storage
Programs and Investments, in addition to procurement of
energy storage via other solicitations (e.g., 20 MW min. for SB
801 – 2018 Aliso Canyon ES, + any eligible storage procured
through IDER RFO, 2018 LCR RFP)
SCE expects to expand on its energy storage position to meet
the AB 2514 storage targets through various procurement
activities
19
Eligible storage included in 2018
Storage Plan (pending approval)
*Storage that is permitted to
count in different categories due
to flex counting rules
Currently above
targets
2018 Cumulative
Procurement Target
Energy Storage
July 27, 2018
21. SCE Large Transmission Projects
FERC Cost of Capital
11.5% ROE in 2018 (subject to refund):
• ROE = Requested Base of 10.3% + CAISO Participation
+ weighted average of individual project incentives
Application for 2018 FERC Formula recovery
mechanism filed on October 27, 2017
Requested 50 bp CAISO adder; approved, but
application for rehearing requested by CPUC
ROE and proposed 2018 Transmission Revenue
Requirement are accepted and suspended pending
settlement discussions
Summary of Large Transmission Projects
Project Name Total Cost4 Remaining Investment
(as of June 30, 2018)
Estimated In-Service
Date
West of Devers1,2 $848 million $716 million 2021
Mesa Substation1 $646 million $457 million 2022
Alberhill System3 $486 million $448 million 2021
Riverside Transmission Reliability $405 million $397 million 2023
Eldorado-Lugo-Mohave Upgrade $233 million $188 million 2021
20
1. CPUC approved
2. Morongo Transmission holds an option to invest up to $400 million, or half of the estimated cost of the transmission facilities only, at the in-service date. If the option is
exercised, SCE’s rate base would be offset by that amount
3. Received Proposed Decision and Alternate Proposed Decision from CPUC in April 2018 and June 2018, respectively, denying SCE’s application for a certificate of public
convenience and necessity for the Alberhill System Project.
4. Total Costs are nominal direct expenditures, subject to CPUC and FERC cost recovery approval. SCE regularly evaluates the cost and schedule based on permitting processes,
given that SCE continues to see delays in securing project approvals
July 27, 2018
22. SCE Operational Excellence
Top Quartile
• Safety
• Reliability
• Customer service
• Cost efficiency
Optimize
• Capital productivity
• Purchased power cost
High performing, continuous
improvement culture
Defining Excellence Measuring Excellence
• Employee and public safety
metrics
• System performance and
reliability (SAIDI, SAIFI,
MAIFI)
• J.D. Power customer
satisfaction
• O&M cost per customer
• Reduce system rate growth
with O&M / purchased
power cost reductions
Ongoing
Operational
Excellence
Efforts
21July 27, 2018
23. Responding to Industry Change
Long-Term Industry Trends Strategy
• The technology landscape is evolving at
an unprecedented pace, with innovation
driving advances in cost and capabilities of
distributed energy resources
• Customer expectations are changing with
increasing choices and alternatives, a
growing priority of sustainability
objectives, and flattening demand
• The regulatory environment for utilities is
complex, increasingly supportive of new
forms of competition but unable to keep
pace with new business models
• Policies both in California and globally are
setting aggressive greenhouse gas
reduction targets
SCE Strategy
• Clean the power system by accelerating
the de-carbonization of electricity supply
• Help customers make cleaner energy
choices to support electrification and
leverage flexible energy demand
• Strengthen and modernize the grid by
replacing aging infrastructure and
deploying technology
• Achieve operational and service excellence
with top tier performance in safety,
reliability, affordability, and customer
satisfaction
Beyond SCE
• Position Edison Energy as an independent
energy advisor and integrator for large
commercial and industrial customers
22July 27, 2018
24. • Energy is a significant risk large commercial and
industrial customers face. Edison Energy creates
competitive advantage for market leaders by
quantifying this risk and designing the portfolio
solution to protect shareholder value threatened
by complex energy policies, technological
advancements, and new products.
• Optimized portfolio solutions based on robust
analytics of the customer’s energy portfolio in
alignment with their goals and strategic
objectives
• Implementation of solutions through existing
service lines or brokering with third parties
• Edison International investment $106 million as
of June 30, 2018
Edison Energy
Edison Energy Summary
The Opportunity: Trusted Advisor and Solution Integrator
23
Managed
Portfolio
Solution
Renewables &
Sustainability
Supply
Solutions
Demand
Solutions
Installations
July 27, 2018
25. EIX Annual Dividends Per Share
$0.80
$1.00
$1.08
$1.16
$1.22 $1.24 $1.26 $1.28 $1.30
$1.35
$1.42
$1.67
$1.92
$2.17
$2.42
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
1. 2018 Dividend annualized based on December 7, 2017 declaration increase
Fourteen Years of Dividend Growth
Target dividend growth at a higher than industry average growth rate within its
target payout ratio of 45-55% of SCE earnings
24
1
July 27, 2018
27. 1. Cost of removal is the cost to remove existing equipment that is being replaced
2018 SCE GRC
26
Items Carried Over
from 2015 GRC
New Items from 2018
GRC
Previous Intervenor
Testimony
• Requests continuation of Tax
Accounting Memorandum
Account (TAMA) adjusting
revenues annually for over and
undercollection of specified tax
items
• Forecasting over $85 million in
2018 O&M savings from
Operational Excellence
initiatives
• Requests recovery for short-
term incentive compensation
plans for full-time employees
($41 million disallowance in
2015 GRC decision)
• Requests continuation of pole
loading capital recovery
through balancing account
• Capital expenditures of $1.8
billion for grid modernization
capital to support improved
safety and reliability and
increased levels of distributed
energy resources (DER)
• Increased depreciation
expense to reflect updated
cost of removal estimates1
Limiting cost of removal
request to mitigate
customer rate impact
beginning with $84 million
increase in 2018
Further increases will likely
be required over multiple
GRC cycles
• ORA - Proposed no Grid
Modernization capital
expenditures and ~90% of
traditional capital expenditures
• TURN - Proposed ~22% of
Grid Modernization capital
expenditures and ~85% of
traditional capital expenditures
July 27, 2018
29. Detailed Capital Expenditures – 2017-2020
2017
(Actual)
2018 2019 2020 Total
Distribution1,2 $3.1 $3.4 $3.2 $3.0 $12.7
Transmission1 0.5 0.6 0.8 0.9 2.7
Generation1 0.2 0.2 0.2 0.2 0.8
Total Traditional $3.8 $4.2 $4.1 $4.1 $16.3
Grid Modernization3 - - 0.6 0.6 1.3
Total $3.8 $4.2 $4.8 $4.7 $17.6
Capital Expenditure/Rate Base Detailed Forecast
Detailed Rate Base at Request Levels – 2017-2020
2017
(Actual)
2018 2019 2020
Traditional Rate Base $26.2 $28.8 $31.1 $33.3
Grid Modernization - 0.3 0.7 1.3
Total $26.2 $29.1 $31.8 $34.6
1. Includes allocated capitalized overheads and general plant
2. Includes 2018 – 2020 capital expenditures of $105 million for Mobile Home Park, $49 million for Energy Storage, $10 million for transportation electrification priority
review, and $4 million for Charge Ready Pilot
3. 2017 and 2018 capital expenditures related to grid modernization are included in distribution capital expenditures
Note: Totals may not foot due to rounding.
($ in billions)
28July 27, 2018
30. Edison International’s ESG Strategy
Key 2018 ESG Achievements:
• ESG materiality assessment completed in March 2018
identifying 19 ESG issues as priorities1 for EIX, many
related to the electric-led clean energy future
• Enhanced 2017 Sustainability Report issued in June
2018, including sustainability scorecard and 2017
accomplishments
• Enhanced voluntary ESG reporting and disclosure
practices by reporting through a pilot program
developed by the Edison Electric Institute (EEI) in
collaboration with investors and member companies
29July 27, 2018
EIX 2017 Sustainability Report can be accessed at www.edison.com/sustainability
“At Edison International, we are leading the transformation of the electric power industry toward a clean
energy future by focusing on opportunities in clean energy, efficient electrification, the grid of the future,
and customer choice. As we pursue this vision, sustainability remains at the core of who we are and what
we do.” – Pedro Pizarro, Edison International CEO
1. A “material” ESG issue is one that has the potential to impact long-term sustainability, based on the perspectives of internal and external stakeholders. This is different from, but
related to, financial materiality, which is a threshold for influencing the economic decisions of investors
31. Distribution Power Grid of the Future
One-Way Electricity Flow
• System designed to distribute electricity
from large central generating plants
• Increasing penetration of distributed
energy resources
• Voltage centrally maintained
• Limited situational awareness and
visualization tools for power grid
operators
Renewable Generation Mandates
Subsidized Residential Solar
Limited Electric Vehicle Charging
Infrastructure
Variable, Two-Way Electricity Flow
• Distribution system at the center of the
power grid
• System designed to manage fluctuating
resources and customer demand
• Digital monitoring and control devices and
advanced communications systems to
improve safety and reliability, and integrate
DERs
• Improved data management and power
grid operations with cyber mitigation
• Modernize utility distribution planning with
distributed energy resources
Maximize Distributed Resources and
Electric Vehicle Adoption
• Distribution power grid infrastructure
design supports customer choice and
greater resiliency
Current State Future State
30July 27, 2018
32. Computing intelligence inside
electrical substations
Future circuit
designs integrate
Distributed
Energy Resources
and increase
flexibility
The distribution
system will require
transformative
technologies in
planning, design,
construction and
operation
Net benefits to
customers include
increased safety,
reliability, access to
affordable
programs, and
ability to adopt
new clean and
distributed
technologies
State of the art
operating tools
for utility
operators and
engineers
Remote sensors that collect
localized information about the grid
Devices that provide
more flexibility during
outage events
Devices that provide stable voltage and power quality
High speed wireless and
fiber communications
infrastructure
Smart meters that provide
information to facilitate
customer reliability and
affordability
Grid Modernization Highlights
Legend
Remote Fault Indicator
High speed bandwidth field area network
(communication system)
Intelligent Remote Switches
Centrally controlled switched capacitor bank w/ voltage
control
31July 27, 2018
33. Building next generation electric grid requires
accelerating traditional Transmission and Distribution
/ Information Technology programs and investing in
new capabilities
• Upgrade portions of grid (such as 4kV system) to
increase capacity, improve reliability, and address
technology obsolescence
• Automation to monitor and control grid equipment in
real-time and improve flexibility of grid operations
• Expansion of Communication Networks
Capital will be deployed to achieve two primary
objectives
• Improving safety and reliability
Focus on worst performing circuits in conjunction
with traditional infrastructure replacement
activities
• Increase DER integration and enable advanced
operations on circuits with high forecasted
penetration or where DERs can provide grid services
1. 2018 Grid Modernization spending is focused on safety and reliability and 2019-2020 spending is based on 2018 GRC Tax Reform February Update testimony; most 2018 spending
focused on integration of distributed energy resources has been deferred and, if not approved in GRC decision, is expected to be requested in future GRC applications
2. Forecast excludes capitalized overheads
SCE Grid Modernization – Request Level
($ billions)
$1.3 Billion Capital Request for 2019-20201,2
$0.65
$0.61
2019 2020
2017 and 2018 capital expenditures related to grid modernization are included in
traditional capital expenditures
32July 27, 2018
34. Distributed Energy Resources (DER) Proceedings
2018 Activities
• Incentive Pilot Solicitation
• Approval of DER contracts
• Pilot Report on lessons learned
• Societal Cost Test
• Programs, Tariffs, and
Streamlined Procurement
2018 Activities
• DER Hosting Capacity analysis
• Locational Net Benefits
• DER forecasting and
distribution planning
alignment
• DER driven grid
modernization and
integration into GRC
• Distribution Deferral
framework
• Grid Needs Assessment and
Distribution Deferral
Opportunity Report
•Integration of DERs in distribution planning and
operations
•Development of tools and methodologies,
including optimal locations & value of DERs
•Framework for Grid Modernization
•Field demonstrations
Distribution
Resource Plan (DRP)
Proceeding’s Scope
Elements
•Define DER products & grid services
•Sourcing DERs for grid need via competitive
procurement, programs, and tariffs
•DER cost-effectiveness methods
•Utility incentives to pursue DERs for grid need,
instead of traditional infrastructure
•Utility role in DER markets; utility business model
Integrated
Distributed Energy
Resources (IDER)
Proceeding’s Scope
Elements
33July 27, 2018
35. SCE Customer Demand Trends
Note: See 2017 Edison International Financial and Statistical Reports for further information.
34
2013 2014 2015 2016 2017
Kilowatt-Hour Sales (millions of kWh)
Residential 29,889 30,115 29,959 29,141 29,765
Commercial 40,649 42,127 42,207 41,565 41,873
Industrial 8,472 8,417 7,589 7,056 6,559
Public authorities 5,012 4,990 4,774 4,645 4,639
Agricultural and other 1,885 2,025 1,940 1,776 1,475
Subtotal 85,907 87,674 86,469 84,183 84,311
Resale 1,490 1,312 1,075 1,794 1,568
Total Kilowatt-Hour Sales 87,397 88,986 87,544 85,977 85,879
Customers
Residential 4,344,429 4,368,897 4,393,150 4,417,340 4,447,706
Commercial 554,5892 557,957 561,475 565,222 569,222
Industrial 10,584 10,782 10,811 10,445 10,274
Public authorities 46,323 46,234 46,436 46,133 46,410
Agricultural 21,679 21,404 21,306 21,233 21,045
Railroads and railways 99 105 130 133 137
Interdepartmental 23 22 22 22 24
Total Number of Customers 4,977,729 5,005,401 5,033,330 5,060,528 5,094,818
Number of New Connections 27,370 29,879 31,653 38,076 39,621
Area Peak Demand (MW) 22,534 23,055 23,079 23,091 23,508
July 27, 2018
36. SCE 2018 Bundled Revenue Requirement
Note: Rates in effect as of June 1, 2018. Represents bundled service which excludes Direct Access/CCA customers that do not receive generation services.
SCE Systemwide Average Rate History (¢/kWh)
2010 2011 2012 2013 2014 2015 2016 2017 2018
14.3 14.1 14.3 15.9 16.7 16.2 14.8 15.7 16.3
Fuel & Purchased Power
(43%)
Distribution
(38%)
Transmission (9%)
Generation
(9%)
Other (1%)
2017 Bundled
Revenue
Requirement
2018 Bundled
Revenue
Requirement
$millions ¢/kWh $millions ¢/kWh
Fuel & Purchased Power – includes CDWR Bond
Charge
5,130 7.1 4,869 7.0
Distribution – poles, wires, substations, service
centers; Edison SmartConnect®
4,386 6.1 4,362 6.2
Generation – owned generation investment and O&M 1,075 1.5 1,075 1.5
Transmission – greater than 220kV 1,064 1.5 1,032 1.5
Other – CPUC and legislative public purpose
programs, system reliability investments, nuclear
decommissioning, and prior-year over collections
(380) (0.4) 53 0.1
Total Bundled Revenue Requirement ($millions) $11,275 $11,391
Bundled kWh (millions) 71,961 69,856
= Bundled Systemwide Average Rate (¢/kWh) 15.7¢ 16.3¢
35July 27, 2018
37. 36
9.7¢
16.3¢
8.0¢
10.0¢
12.0¢
14.0¢
16.0¢
18.0¢
20.0¢
22.0¢
1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018
¢/kWh
System Average Rate Historical Growth
SCE’s system average rate has grown in line with inflation over the last 25 years
SCE System Average Rate
Los Angeles Area Inflation
Comparative System
Average Rates
% Delta
EIX 16.3¢ --
PG&E 19.5¢1 20%
SDG&E 24.0¢1 40%
CAGR
20-yr
('98-’18)
10-yr
('08-'18)
5-yr
('13-'18)
2.7% 1.8% 0.5%
2.2% 1.6% 1.5%
Energy Crisis and
return to normal
Higher gas price forecast post-Katrina
leads to higher rates with subsequent
refund of over collection
Delay in 2012 GRC leads
to shorter ramp-up of
rate increase
Rates reduced due to the implementation of
1) the SONGS Settlement, including NEIL
insurance benefits, 2) lower fuel &
purchased power costs, and 3) a lower 2015
GRC revenue requirement that includes
flow-through tax benefits
July 27, 2018
1. PG&E Advice 5231-E, SDG&E Advice 3167-E
38. Q1 2018 Q2 2018 Q3 2018
Track 12 Opening/Reply Briefs Proposed Decision Final Decision
Track 22 File Testimony File Opening/Reply Briefs Proposed Decision
• Assembly Bill 1171 permits cities and counties or a Joint Power
Authority (JPA) to act as CCAs to purchase and sell electricity on
behalf of the utility customers within their jurisdiction
• An Order Instituting Rulemaking (OIR R.17-06-026) was opened on
June 29, 2017 to review, revise, and consider alternatives to the
“Power Charge Indifference Adjustment” or PCIA
The PCIA allocates a proportional share of above-market costs of
SCE’s energy procurement portfolio to departing load customers
to ensure remaining bundled service customers are indifferent
While not an impact on earnings, for every 1% of departing load,
~$6 million is shifted to remaining bundled service customers
under the current PCIA
• On February 8, 2018, the Commission approved Resolution E-4907
requiring CCA’s to demonstrate compliance with annual Resource
Adequacy (RA) requirements prior to commencing operations
• Existing Direct Access and CCA load is ~15% of SCE’s total load, and
another ~15% is scheduled to join CCAs in 2019
1. AB 117 was introduced into the Assembly 1/22/2001 by Assembly member Migden, chaptered into law 9/24/2002
2. Track 1 refers to PCIA exemptions for CARE and medical baseline customers; Track 2 refers to evaluation and possible modification of the PCIA methodology
Investor-Owned Utility
(IOU)
Community Choice Aggregation
(CCA)
Community Choice Aggregation (CCA) Overview
PCIA OIR Timeline (R. 17-06-026)
30%-50% of SCE’s bundled service load could be part of a CCA by 2020
37July 27, 2018
39. Residential Rate Design OIR Decision
• CPUC Order Instituting Ratemaking R. 12-06-013 comprehensively reviewed residential rate structure, including a future
transition to Time of Use (TOU) rates
In March 2018, nearly 400,000 residential customers migrated to TOU rate structures
Remaining residential customers to be migrated beginning October 2020
• July 2015 CPUC Decision D. 15-07-001 includes:
Transition to 2 tiered rate structure, coupled with Super-user Electric (SUE) Surcharge, by 2019
“Super User Electric Surcharge” for usage 400% above baseline (~5% of current and forecasted residential load)
Minimum bills of approximately $10/month (applied to delivery revenue only)
January 2014 2019
1.00
(55% of system usage)
2.19
(5%)
Tier 1:
100%
Tier 2:
101-400%
SUE:
>400%
1.25
(40%)
Usage Level (% of Baseline)Usage Level (% of Baseline)
Tier 1:
100%
Tier 2:
101-130%
Tier 4:
>200%
TieredRateLevel
(RelativetoTier1Rate)
Fixed Charge:
(Single-Family) $0.94/month
(Multi-Family) $0.73/month
Minimum Bill:
$10.28/month
38
TieredRateLevel
(RelativetoTier1Rate)
Tier 3:
131-200%
1.00
(51% of system usage)
1.20
(11%)
2.10
(16%)
2.30
(22%)
Non-CARE1, Unbundled Rates
Fixed Charge:
(Single-Family) $0.94/month
(Multi-Family) $0.73/month
Minimum Bill:
$10.28/month
July 27, 2018
1. SCE’s California Alternate Rates for Energy (CARE) program is an income-qualifying program that reduces energy bills for eligible customers by about 30%
40. Impacts of Abundant Solar Energy (Duck Curve)
Season Existing Proposed
On-Peak Summer Weekdays: 12-6pm Weekdays: 4-9pm
Mid-Peak Summer Weekdays: 8am-12pm; 6pm-11pm Weekends: 4-9pm
Winter Weekdays: 8am-9pm Weekdays and Weekends: 4-9pm
Off-Peak Summer Weekdays: 11pm-8am
Weekends: All
Weekdays and Weekends: All except
4-9pm
Winter Weekdays: 9pm-8am
Weekends: All
Weekdays and Weekends: 9pm-8am
Super Off-Peak Winter N/A Weekdays and Weekends: 8am-4pm
39
New Time-of-Use (TOU) Periods (CPUC approved SCE’s proposal on July 12, 2018)
• In 2019, SCE is changing its TOU pricing period definition for the first time in over 30 years
All non-residential and new residential NEM 2.0 customers are served on mandatory TOU
rates
3.3 million residential customers will be defaulted to TOU rates starting in Oct 20201
• Abundant mid-day renewable energy lowers prices from 8am-4pm
• Highest cost period is now 4pm-9pm, all-days
July 27, 2018
1. Default will begin in Oct 2020 through end of 2021 with the option to opt-out to tiered rates; CARE and FERA customers in hot climate zones 10, 13, 14 and 15 are not eligible
for default; Customers who receive Medical Baseline Allocations are not eligible for default
41. 40
Residential Solar Installations in SCE Territory
• 272,177 combined residential and non-residential projects – 2,287
MW installed
• 99.6% solar projects
• 265,781 residential – 1,435 MW
• 6,396 non-residential – 852 MW
• Approximately 4,167,804 MWh/year generated
July 1, 2017
• Official start of NEM successor tariff; customers are subject to:
Mandatory TOU rate
Non-bypassable charges
Application fees
July 31, 2017
• Residential customers who meet this deadline are grandfathered for
current TOU periods for maximum of 5 years (10 for non-residential)
September 9, 2017
• Smart Inverters required on all solar installations
July 25, 2018
• Smart Inverters with Reactive Power Priority required on all solar
installations
Near Term Outlook
• Combination of a flatter tiered rate and the mandatory TOU NEM 2.0
rate structure has helped contain and reduce the cost shift; further
efforts to reduce the shift through new TOU pricing periods
• Commission to revisit NEM Successor Tariff in 2019 where increased
customer/demand charges and market priced export compensation
rates will be explored
Key Dates
Monthly Residential Solar
Installations and MW Installed
SCE Net Metering Statistics (6/18)
July 27, 2018
0
5
10
15
20
25
30
35
40
0
1000
2000
3000
4000
5000
6000
7000
2011 2012 2013 2014 2015 2016 2017 2018
MWInstalled
NumberofResidentialInstallations
Installations MW
Note: NEM solar installations in SCE service territory include projects with solar PV only
less than 1 MW.
42. 13.3 ₵
16.3 ₵
US Average SCE
23%
Higher
SCE Rates and Bills Comparison
41
SCE’s average residential rates are above national average,
but residential bills are below national average due to lower usage
• SCE’s residential rates are above national
average due, in part, to a cleaner fuel mix,
high cost of living in the state, and lower
system load factor than the rest of the
country.
• SCE’s residential customer usage is lower
than the national average due to mild
climate and higher energy efficiency
appliance and building standards.
• Average monthly residential bills are lower
than national average as higher rate levels
are more than offset by lower usage.
Key FactorsKey Factors
Source: EIA's Form 826 Data Monthly Electric Utility Sales and Revenue Data for 12 Months Ending Apr 2018. https://www.eia.gov/electricity/data/eia861m/index.html.
2017-18 Average Residential Rates
(¢/kWh)
2017-18 Average Residential Bills
($ per Month)
$127
$91
US Average SCE
29%
Lower
July 27, 2018
43. Second Quarter Earnings Summary
42
1. See Earnings Non-GAAP reconciliations and Use of Non-GAAP Financial Measures in Appendix
2. SCE’s 2018 core EPS drivers other than income taxes are adjusted to reflect consistent tax rates; income tax line item reflects impact of change in tax rate
3. Excludes 2017 San Onofre revenue of $(0.09), depreciation of $0.06, interest expense of $0.01 which was offset by income tax of $0.02
4. Excludes $0.07 of income tax benefits related to Tax Reform refunded to customers
Note: Diluted earnings were $0.84 and $0.85 per share for the three months ended June 30, 2018 and 2017, respectively.
Q2
2018
Q2
2017
Variance
Basic Earnings Per Share (EPS)1
SCE $0.91 $0.94 $(0.03)
EIX Parent & Other (0.06) (0.09) 0.03
Discontinued Operations
Basic EPS $0.85 $0.85 $
Less: Non-Core Items
SCE $ $ $
EIX Parent & Other
Discontinued Operations
Total Non-Core Items $ $ $
Core Earnings Per Share (EPS)1
SCE $0.91 $0.94 $(0.03)
EIX Parent & Other (0.06) (0.09) 0.03
Core EPS1 $0.85 $0.85 $
Key SCE EPS Drivers2
Revenue3,4 $0.07
- CPUC revenue 0.05
- FERC revenue 0.02
Higher O&M (0.08)
Lower depreciation 0.03
Higher net financing costs (0.04)
Income taxes4 0.01
Property and other taxes (0.02)
Total core drivers $(0.03)
Non-core items
Total $(0.03)
Key EIX EPS Drivers
EIX Parent
(0.03)
0.02
$(0.01)
0.04
- IRS tax settlement in 2017 and Tax Reform
- Lower corporate expenses
EEG - SoCore Energy goodwill impairment in
2017 and other
Total core drivers $0.03
Non-core items
Total $0.03
July 27, 2018
44. Year to Date Earnings Summary
43
1. See Earnings Non-GAAP reconciliations and Use of Non-GAAP Financial Measures in Appendix
2. Impact of hypothetical liquidation at book value (HLBV) accounting method and loss on sale of
SoCore Energy
3. SCE’s 2018 core EPS drivers other than income taxes are adjusted to reflect consistent tax rates;
income tax line item reflects impact of change in tax rate
4. Excludes 2017 San Onofre revenue of $(0.05), depreciation of $0.13, interest expense of $0.01
which was offset by income tax of $(0.09)
5. Excludes $0.18 of income tax benefits related to Tax Reform refunded to customers
YTD
2018
YTD
2017
Variance
Basic Earnings Per Share (EPS)1
SCE $1.79 $2.01 $(0.22)
EIX Parent & Other (0.27) (0.05) (0.22)
Discontinued Operations
Basic EPS $1.52 $1.96 $(0.44)
Less: Non-Core Items
SCE $ $ $
EIX Parent & Other2 (0.13) (0.13)
Discontinued Operations
Total Non-Core Items $(0.13) $ $(0.13)
Core Earnings Per Share (EPS)1
SCE $1.79 $2.01 $(0.22)
EIX Parent & Other (0.14) (0.05) (0.09)
Core EPS1 $1.65 $1.96 $(0.31)
Key SCE EPS Drivers3
Revenue4,5 $0.07
- CPUC revenue 0.03
- FERC and other operating revenue 0.04
Higher O&M (0.18)
Lower depreciation 0.03
Higher net financing costs (0.05)
Income taxes5 (0.03)
Other (0.06)
- Property and other taxes (0.04)
- Other income and expenses (0.02)
Total core drivers $(0.22)
Non-core items
Total $(0.22)
Key EIX EPS Drivers
EIX parent
(0.15)
0.03
$(0.12)
0.03
- Tax benefits on stock based compensation,
IRS tax settlement in 2017 and Tax Reform
- Lower corporate expenses
EEG − SoCore Energy goodwill impairment in
2017
Total core drivers $(0.09)
Non-core items2 (0.13)
Total $(0.22)
July 27, 2018
Note: Diluted earnings were $1.51 and $1.95 per share for the six months ended June 30, 2018 and 2017, respectively.
45. SCE Annual Results of Operations
• Earning activities – revenue authorized by CPUC and FERC to provide reasonable cost recovery and return on investment
• Cost-recovery activities – CPUC- and FERC-authorized balancing accounts to recover specific project or program costs, subject
to reasonableness review or compliance with upfront standards
($ millions)
20171 20161
Earnings
Activities
Cost-Recovery
Activities
Total
Consolidated
Earnings
Activities
Cost-Recovery
Activities
Total
Consolidated
Operating revenue $6,611 $5,643 $12,254 $6,504 $5,326 $11,830
Purchased power and fuel — 4,873 4,873 — 4,527 4,527
Operation and maintenance 1,902 769 2,671 1,939 798 2,737
Depreciation and amortization 2,032 — 2,032 1,998 — 1,998
Property and other taxes 372 — 372 351 — 351
Impairment and other charges 716 — 716 — — —
Other operating income (8) — (8) — — —
Total operating expenses 5,014 5,642 10,656 4,288 5,325 9,613
Operating income 1,597 1 1,598 2,216 1 2,217
Interest expense (588) (1) (589) (540) (1) (541)
Other income and expenses 97 — 97 79 — 79
Income before income taxes 1,106 — 1,106 1,755 — 1,755
Income tax (benefit) expense (30) — (30) 256 — 256
Net income 1,136 — 1,136 1,499 — 1,499
Preferred and preference stock dividend
requirements
124 — 124 123 — 123
Net income available for common stock $1,012 — $1,012 $1,376 — $1,376
Less: Non-core earnings (481) —
Core Earnings $1,493 $1,376
44July 27, 2018
1. Results of operations for 2017 and 2016 do not reflect the retrospective adoption of the new accounting standards update on the presentation of the components of net periodic
benefit costs for defined benefit pension and other postretirement plans.
Note: See Use of Non-GAAP Financial Measures
46. Earnings Non-GAAP Reconciliations
45
Note: See Use of Non-GAAP Financial Measures.
1. Non-core income of $3 million ($2 million after-tax) and non-core loss of $57 million ($42 million after-tax) for the three and six months ended June 30, 2018, respectively,
related to the sale of SoCore Energy. The non-core loss for the six months ended June 31, 2018 was partially offset by income related to losses (net of distributions) allocated to
tax equity investors under the HLBV accounting method.
($ millions)
Reconciliation of EIX GAAP Earnings to EIX Core Earnings
Earnings Attributable to Edison International
Q2
2018
Q2
2017
YTD
2018
YTD
2017
SCE $297 $307 $583 $656
EIX Parent & Other (21) (29) (89) (16)
Basic Earnings $276 $278 $494 $640
Non-Core Items
SCE $ – $ – $ – $ –
EIX Parent & Other1 2 – (42) 1
Total Non-Core $ 2 $ – $(42) $ 1
Core Earnings
SCE $297 $307 $583 $656
EIX Parent & Other (23) (29) (47) (17)
Core Earnings $274 $278 $536 $639
July 27, 2018
47. EIX Core EPS Non-GAAP Reconciliations
46
Reconciliation of Edison International Basic Earnings Per Share to Edison International Core Earnings Per Share
Note: See Use of Non-GAAP Financial Measures.
Earnings Per Share Attributable to Edison International 2015 2016 2017 CAGR
Basic EPS 3.13 $4.02 $1.73 (26%)
Non-Core Items
SCE
Write down, impairment and other charges (1.18) — (1.38)
Re-measurement of deferred taxes — — (0.10)
Insurance recoveries 0.04 — —
Edison International Parent and Other
Re-measurement of deferred taxes — — (1.33)
Edison Capital sale of affordable housing portfolio 0.03 — —
Income from allocation of losses to tax equity investor 0.03 0.02 0.04
Discontinued operations 0.11 0.03 —
Less: Total Non-Core Items (0.97) 0.05 (2.77)
Core EPS $4.10 $3.97 $4.50 5%
July 27, 2018
48. Use of Non-GAAP Financial Measures
Edison International's earnings are prepared in accordance with generally accepted
accounting principles used in the United States. Management uses core earnings internally
for financial planning and for analysis of performance. Core earnings are also used when
communicating with investors and analysts regarding Edison International's earnings results
to facilitate comparisons of the Company's performance from period to period. Core
earnings are a non-GAAP financial measure and may not be comparable to those of other
companies. Core earnings (or losses) are defined as earnings or losses attributable to Edison
International shareholders less income or loss from discontinued operations and income or
loss from significant discrete items that management does not consider representative of
ongoing earnings, such as: exit activities, including sale of certain assets, and other activities
that are no longer continuing; asset impairments and certain tax, regulatory or legal
settlements or proceedings.
A reconciliation of Non-GAAP information to GAAP information is included either on the
slide where the information appears or on another slide referenced in this presentation.
EIX Investor Relations Contact
Sam Ramraj, Vice President (626) 302-2540 sam.ramraj@edisonintl.com
Allison Bahen, Senior Manager (626) 302-5493 allison.bahen@edisonintl.com
47July 27, 2018