SlideShare a Scribd company logo
1 of 4
Duration is the total time taken to complete an activity from
start to finish.
ProcessTime represents the actual work time.




             ProcessTime of aninclude
             The ProcessTime ‘clock’includeactual work amiddle ofsits in activity.
             Consider the activitywhen starts whentimestarts. Duration an ‘Inbox’.
             This Durationbeginsactivitythe when thean item is complete. represents
                  Duration may also stops waiting inRequest”.
                                   “Managerdelays review arrives thethe
                                              Review the request at review due
             to external demand order arrives at an like phone the Time
             For total elapsed time for the Manager operator’s desk, or an spent
             the example: a workfor Manager time…to completecalls.review.
             The Duration ‘clock’ machinist’s workstation.
             addressing interruptions would the item leaves the activity.
             assembly arrives at astops whennot be included in the ProcessTime.
                           includes the ProcessTime.
             Duration includes all the time an item is waiting, delayed, and being
             In this example, activity.
             worked on at an the ‘clock’ starts when the request is submitted to the
             Manager for review.
ProcessTime represents the work time.




    Consider the activity “Manager Review Request”.
    The ‘clock’ stops if the review is interrupted the toto
        ProcessTime whennot include the time due
                starts does the time actually invested
                records onlythe Manager actually begins
    ProcessTime represents the actual work time
    the review.
    complete the the ‘Inbox’.
    externalsits inreview. phone calls.
    request demands… like
    required to complete the review.
When there are no delays, the
Duration and ProcessTime are equal.
Duration vs ProcessTime

More Related Content

Similar to Duration vs ProcessTime (10)

Operations Scheduling
Operations SchedulingOperations Scheduling
Operations Scheduling
 
cycle time, normal time and standard allowance
cycle time, normal time and standard allowancecycle time, normal time and standard allowance
cycle time, normal time and standard allowance
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work measurement
Work measurementWork measurement
Work measurement
 
Process analysis
Process analysisProcess analysis
Process analysis
 
Work study Training Manual
Work study Training ManualWork study Training Manual
Work study Training Manual
 
What is cycle time in the manufacturing process
What is cycle time in the manufacturing processWhat is cycle time in the manufacturing process
What is cycle time in the manufacturing process
 
7. work study and method measurement
7. work study and method measurement7. work study and method measurement
7. work study and method measurement
 
Good work measurement
Good work measurementGood work measurement
Good work measurement
 
Work Measurement
Work MeasurementWork Measurement
Work Measurement
 

Duration vs ProcessTime

  • 1. Duration is the total time taken to complete an activity from start to finish. ProcessTime represents the actual work time. ProcessTime of aninclude The ProcessTime ‘clock’includeactual work amiddle ofsits in activity. Consider the activitywhen starts whentimestarts. Duration an ‘Inbox’. This Durationbeginsactivitythe when thean item is complete. represents Duration may also stops waiting inRequest”. “Managerdelays review arrives thethe Review the request at review due to external demand order arrives at an like phone the Time For total elapsed time for the Manager operator’s desk, or an spent the example: a workfor Manager time…to completecalls.review. The Duration ‘clock’ machinist’s workstation. addressing interruptions would the item leaves the activity. assembly arrives at astops whennot be included in the ProcessTime. includes the ProcessTime. Duration includes all the time an item is waiting, delayed, and being In this example, activity. worked on at an the ‘clock’ starts when the request is submitted to the Manager for review.
  • 2. ProcessTime represents the work time. Consider the activity “Manager Review Request”. The ‘clock’ stops if the review is interrupted the toto ProcessTime whennot include the time due starts does the time actually invested records onlythe Manager actually begins ProcessTime represents the actual work time the review. complete the the ‘Inbox’. externalsits inreview. phone calls. request demands… like required to complete the review.
  • 3. When there are no delays, the Duration and ProcessTime are equal.