DFW CONNECTOR & I3 ORANGE LINE | VIRTUAL DESIGN & CONSTRUCTION, CIFE - STEVE SI TRAN DEC 2015
DFW Connector and I3 Orange Line 3D Modeling
Modeling development record for better management
Virtual Design and Construction
Dallas, Texas
Abstract
The following provides an annotated bibliography of record studies on Virtual Design and Construction with Modeling,
from DFW Connector and the I3 Orange line. The 3D Modeling compares international research and how the work
relates to and informs changes in policy and practice.
1.0 Introduction:
Urban transportation design and development can be a complex and bewildering process when first encountered. This
record is intended to explain how the process of 3D design works, the planning and design, and the steps that are used
in urban 3D transportation design. This is done in order to help better understand the 3D Modeling process and its
implications to help the management, stakeholders and marketing team to interpret and comment on its results. Since
the basic purpose of 3D design and modeling is to answer questions about future 3D design and modeling benefits
versus standards 2D design and plan set. This record will use a question and answer format to explain how the 3D design
modeling process.
2.0 The General Process:
What is 3D Design Modeling?
The 3D Design Modeling is a process that develops model information to help make decisions on the future
construction management in the construction field, especially in urban areas. It details the need for the type of
equipment and the added benefit of providing accuracy during the process of construction to better manage the
equipment demand. Typically construction involves a forecast of travel patterns of one to three years in the future with
an aim to develop a future of the construction system that will work effectively at that time.
Why is 3D Design Modeling necessary?
The 3D Design Modeling can have significant effects on mobility, economic construction environmental quality,
construction finance, and the quality of life. Wise planning is needed to help create high-quality construction facilities
and services at a reasonable cost. Significant transportation projects require a long lead-time for their design and
construction. Furthermore, they can have a major effect on future construction time’s patterns, which need to be
assessed.
What are the steps for 3D Design Modeling?
3D Design Modeling goes through a basic sequence of steps. Several can take place at once, and it is not unusual
to repeat some of the steps several times. The basic steps in the 3D Design Modeling are the following:
Early planning benefits the outcome:
 What are the keys of 3D Design Modeling?
 Economic, issues and problems facing the software and hardware?
 Lack of training?
pg. 2
DFW CONNECTOR & I3 ORANGE LINE | VIRTUAL DESIGN & CONSTRUCTION, CIFE - STEVE SI TRAN DEC 2015
3.0 Methodology
Planning and developing a 3D Model database and standards for VDC implementation practice are often a pre-
requisite for the revolutionary approach that is Virtual Design and Construction modeling. This cutting-edge
methodology has expanded to become the standard within numerous sectors including Architectural, Engineering,
Construction and even the Manufacturing sector, as Architects and Engineer’s demands for VDC ready content from the
Manufacturer for construction supply chain continues to grow. The use of this intelligent, model-based process provides
an insight for creating and managing projects faster, more economical, and with less environmental impact.
As an experienced Lead Design/Modeler Manager, s/he not only defines a better fit application and software for VDC
needed to get started in the world of VDC, but also offers the VDC team the assistance and guidance they may require to
be able to implement VDC with a road map, and get the most of the software investment.
For any business, organization, or project that is working on employing VDC, the actual implementation can be difficult.
Trying to get your team or colleagues to adopt methods and new procedures will certainly need forward thinking at the
initial stage to ensure that you are building a solid foundation that will meet your ongoing requirements.
The Modeler Manager will be able to help form a modeling team at this preliminary stage by gaining an understanding
of objectives the client wish to achieve from implementing VDC to support and plan procedure of deployment.
During the preparation and planning, the Modeler Manager will look to identify the following methods:
 Existing office setup
 Existing standards implemented
 Any existing CAD standards protocols
 Practice VDC aspiration and potential timeline for deployment
 General projects undertaken
 Current Hardware, Software direction and Training expectancy.
It is advised to visit this planning with any project size especially from medium up to complex.
3.1 Template creation
Template creation is an integral part of VDC modeling that enables our business, organization, or project to
have the initial core components for the implementation of the approach in our projects.
The Modeler Manager will guide the VDC team and help develop the database and all of the elements to be
able to get underway with VDC Modeling including:
 Set up a Basic template and database
 Set up Title blocks
 Adapt templates to contain any required Views
 Create and Manage project folder structure
 Create and Manage Schedules required with P6
 Load in any basic families required
 The template with regards to annotation items
 Set up CAD layers standards for exchange with Machine guidance and GIS
 Set up on the ProjectWise server
 Aid the setup of all libraries to VDC modeling structure
 Defines communication and collaboration method
 Process recording.
pg. 3
DFW CONNECTOR & I3 ORANGE LINE | VIRTUAL DESIGN & CONSTRUCTION, CIFE - STEVE SI TRAN DEC 2015
If the right standards are not in place during the development phase, the 3D Model will not be able to update correctly
as future improvements are made. It’s important to enforce 3D Modeling Standards that change not just some static 3D
PDF files or screen captures. Any shortcuts during development phase can forever reduce or eliminate the ability to
locate, retrieve, repurpose and update the database system data.
4.0 Conclusions
The results of DFW Connector and the I3 Orange line prove that the aforementioned methods are working
successfully:
GRAPEVINE (DFWCOM.COM) – Drivers can now cruise through the DFW Connector without having to
maneuver around construction cones or worry about detour signs. After more than three years of construction
and nine months ahead of schedule, the nearly eight-and-a-half mile project is done.
www.dbia.org/awards/2013-Design-Build-Project-Awards
Orange Line extension to DFW Airport to open early
Posted on January 24, 2014 by Travis Hudson
Commuters and travelers to Dallas/Fort Worth International Airport can expect an early Christmas present this
year. The 4.7-mile Orange Line extension to DFW Airport is trending ahead of schedule and we’ll be able to
open the line earlier than the planned December date.
The current goal is to open the new DFW Airport Station at Terminal A by the start of the State Fair of Texas®
in late September.
pg. 4
DFW CONNECTOR & I3 ORANGE LINE | VIRTUAL DESIGN & CONSTRUCTION, CIFE - STEVE SI TRAN DEC 2015
There’s a lot of work to do, so we’re not ready to set an official opening date, but we’re committed to beating
the December target.
You may start seeing test trains this spring around the Terminal A area, but we still have systems testing,
operator training and construction to complete. Stay tuned.
References:
Building Information Modeling (BIM) Task Group
http://www.bimtaskgroup.org/cobie-uk-2012/
McGraw Hill Construction BIM Special Section
http://www.bim.construction.com/research/
NBS National BIM Report 2014
http://www.thenbs.com/pdfs/NBS-National-BIM-Report-2014.pdf
BIM Management for value, cost & carbon improvement
http://www.bimtaskgroup.org/wp-content/uploads/2012/03/BIS-BIM-strategy-Report.pdf
PAS 1192-2 Specification for information management for the capital delivery phase of construction project
using building information modeling.
http://shop.bsigroup.com/en/forms/PASs/PAS-1192-2/
Industrial strategy: government and industry in partnership
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/34710/12-1327-
building-information-modelling.pdf

More Related Content

What's hot

Shawn jr Resume
Shawn jr Resume Shawn jr Resume
Shawn jr Resume
Shawn Caradine
 
BIM for Contractors by Matthew Edwards
BIM for Contractors by Matthew EdwardsBIM for Contractors by Matthew Edwards
BIM for Contractors by Matthew Edwards
inistioge
 
Keeping the Vision Alive: Techniques for Communication Throughout the Project...
Keeping the Vision Alive: Techniques for Communication Throughout the Project...Keeping the Vision Alive: Techniques for Communication Throughout the Project...
Keeping the Vision Alive: Techniques for Communication Throughout the Project...
Design for Context
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
Dr Fereidoun Dejahang
 
VCA Structural Brochure
VCA Structural BrochureVCA Structural Brochure
VCA Structural Brochure
Abraham Blunda, PE, LEED AP
 
Applications 3D Articles
Applications 3D ArticlesApplications 3D Articles
Applications 3D Articles
Applications 3D
 
Medikonda_CRM_PM
Medikonda_CRM_PMMedikonda_CRM_PM
Medikonda_CRM_PM
Srinivas Medikonda
 
update cv
update cvupdate cv
update cv
Marwa Helmy
 
Capella Days 2021 | The long way from Bid to project... supported by Capella
Capella Days 2021 | The long way from Bid to project... supported by CapellaCapella Days 2021 | The long way from Bid to project... supported by Capella
Capella Days 2021 | The long way from Bid to project... supported by Capella
Obeo
 

What's hot (9)

Shawn jr Resume
Shawn jr Resume Shawn jr Resume
Shawn jr Resume
 
BIM for Contractors by Matthew Edwards
BIM for Contractors by Matthew EdwardsBIM for Contractors by Matthew Edwards
BIM for Contractors by Matthew Edwards
 
Keeping the Vision Alive: Techniques for Communication Throughout the Project...
Keeping the Vision Alive: Techniques for Communication Throughout the Project...Keeping the Vision Alive: Techniques for Communication Throughout the Project...
Keeping the Vision Alive: Techniques for Communication Throughout the Project...
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
 
VCA Structural Brochure
VCA Structural BrochureVCA Structural Brochure
VCA Structural Brochure
 
Applications 3D Articles
Applications 3D ArticlesApplications 3D Articles
Applications 3D Articles
 
Medikonda_CRM_PM
Medikonda_CRM_PMMedikonda_CRM_PM
Medikonda_CRM_PM
 
update cv
update cvupdate cv
update cv
 
Capella Days 2021 | The long way from Bid to project... supported by Capella
Capella Days 2021 | The long way from Bid to project... supported by CapellaCapella Days 2021 | The long way from Bid to project... supported by Capella
Capella Days 2021 | The long way from Bid to project... supported by Capella
 

Similar to DFW Connector 3D Modeling CIFE

qadeer intern report.pdf
qadeer intern report.pdfqadeer intern report.pdf
qadeer intern report.pdf
QadeerAhmadShaikh
 
The Benefits of 5D BIM Cost Estimation
The Benefits of 5D BIM Cost Estimation The Benefits of 5D BIM Cost Estimation
The Benefits of 5D BIM Cost Estimation
nibtedu
 
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
Application Of Building Information Modeling (BIM) To Civil Engineering ProjectsApplication Of Building Information Modeling (BIM) To Civil Engineering Projects
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
Michele Thomas
 
AW201502hr Article_For Sharing
AW201502hr Article_For SharingAW201502hr Article_For Sharing
AW201502hr Article_For Sharing
Jennifer Suerth, LEED AP
 
BIM workflow for construction
BIM workflow for constructionBIM workflow for construction
BIM workflow for construction
Cesare Caoduro
 
Apps for Construction (CMAA 2014)
Apps for Construction (CMAA 2014) Apps for Construction (CMAA 2014)
Apps for Construction (CMAA 2014)
Rob McKinney, LEED AP BD + C
 
Cscm group assignment
Cscm group assignmentCscm group assignment
Cscm group assignment
jk tan
 
The Benefits Of Software Creation
The Benefits Of Software CreationThe Benefits Of Software Creation
The Benefits Of Software Creation
Jennifer Wood
 
IngSchritte Training Module
IngSchritte Training ModuleIngSchritte Training Module
IngSchritte Training Module
IngSchritte Services
 
PDMS Courses
PDMS Courses PDMS Courses
PDMS Courses
jaymicrosoftva
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...
IRJET Journal
 
How to create an efficient project roadmap in 2022.pdf
How to create an efficient project roadmap in 2022.pdfHow to create an efficient project roadmap in 2022.pdf
How to create an efficient project roadmap in 2022.pdf
PMO Global Institute
 
From 3D to 6D Managing the Information Labyrinth of BIM.pdf
From 3D to 6D Managing the Information Labyrinth of BIM.pdfFrom 3D to 6D Managing the Information Labyrinth of BIM.pdf
From 3D to 6D Managing the Information Labyrinth of BIM.pdf
VincentPoon15
 
Comprehensive Guide to SD, DD, CD in Construction Projects
Comprehensive Guide to SD, DD, CD in Construction ProjectsComprehensive Guide to SD, DD, CD in Construction Projects
Comprehensive Guide to SD, DD, CD in Construction Projects
Chudasama Outsourcing | AutoCAD Drawing and Drafting Services
 
Report
ReportReport
Report
Meet Patel
 
Supply Chain
Supply Chain Supply Chain
Supply Chain
Wan Nee
 
BIM: The Promise of an Integrated Approach to Project Delivery
BIM: The Promise of an Integrated Approach to Project DeliveryBIM: The Promise of an Integrated Approach to Project Delivery
BIM: The Promise of an Integrated Approach to Project Delivery
AWC|WEST
 
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docxPROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
wkyra78
 
Autocad plant-3d
Autocad plant-3dAutocad plant-3d
Autocad plant-3d
Vinnie Rocx
 
Software application (QS)
Software application (QS)Software application (QS)
Software application (QS)
Hasif Alias
 

Similar to DFW Connector 3D Modeling CIFE (20)

qadeer intern report.pdf
qadeer intern report.pdfqadeer intern report.pdf
qadeer intern report.pdf
 
The Benefits of 5D BIM Cost Estimation
The Benefits of 5D BIM Cost Estimation The Benefits of 5D BIM Cost Estimation
The Benefits of 5D BIM Cost Estimation
 
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
Application Of Building Information Modeling (BIM) To Civil Engineering ProjectsApplication Of Building Information Modeling (BIM) To Civil Engineering Projects
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
 
AW201502hr Article_For Sharing
AW201502hr Article_For SharingAW201502hr Article_For Sharing
AW201502hr Article_For Sharing
 
BIM workflow for construction
BIM workflow for constructionBIM workflow for construction
BIM workflow for construction
 
Apps for Construction (CMAA 2014)
Apps for Construction (CMAA 2014) Apps for Construction (CMAA 2014)
Apps for Construction (CMAA 2014)
 
Cscm group assignment
Cscm group assignmentCscm group assignment
Cscm group assignment
 
The Benefits Of Software Creation
The Benefits Of Software CreationThe Benefits Of Software Creation
The Benefits Of Software Creation
 
IngSchritte Training Module
IngSchritte Training ModuleIngSchritte Training Module
IngSchritte Training Module
 
PDMS Courses
PDMS Courses PDMS Courses
PDMS Courses
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...
 
How to create an efficient project roadmap in 2022.pdf
How to create an efficient project roadmap in 2022.pdfHow to create an efficient project roadmap in 2022.pdf
How to create an efficient project roadmap in 2022.pdf
 
From 3D to 6D Managing the Information Labyrinth of BIM.pdf
From 3D to 6D Managing the Information Labyrinth of BIM.pdfFrom 3D to 6D Managing the Information Labyrinth of BIM.pdf
From 3D to 6D Managing the Information Labyrinth of BIM.pdf
 
Comprehensive Guide to SD, DD, CD in Construction Projects
Comprehensive Guide to SD, DD, CD in Construction ProjectsComprehensive Guide to SD, DD, CD in Construction Projects
Comprehensive Guide to SD, DD, CD in Construction Projects
 
Report
ReportReport
Report
 
Supply Chain
Supply Chain Supply Chain
Supply Chain
 
BIM: The Promise of an Integrated Approach to Project Delivery
BIM: The Promise of an Integrated Approach to Project DeliveryBIM: The Promise of an Integrated Approach to Project Delivery
BIM: The Promise of an Integrated Approach to Project Delivery
 
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docxPROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
 
Autocad plant-3d
Autocad plant-3dAutocad plant-3d
Autocad plant-3d
 
Software application (QS)
Software application (QS)Software application (QS)
Software application (QS)
 

DFW Connector 3D Modeling CIFE

  • 1. pg. 1 DFW CONNECTOR & I3 ORANGE LINE | VIRTUAL DESIGN & CONSTRUCTION, CIFE - STEVE SI TRAN DEC 2015 DFW Connector and I3 Orange Line 3D Modeling Modeling development record for better management Virtual Design and Construction Dallas, Texas Abstract The following provides an annotated bibliography of record studies on Virtual Design and Construction with Modeling, from DFW Connector and the I3 Orange line. The 3D Modeling compares international research and how the work relates to and informs changes in policy and practice. 1.0 Introduction: Urban transportation design and development can be a complex and bewildering process when first encountered. This record is intended to explain how the process of 3D design works, the planning and design, and the steps that are used in urban 3D transportation design. This is done in order to help better understand the 3D Modeling process and its implications to help the management, stakeholders and marketing team to interpret and comment on its results. Since the basic purpose of 3D design and modeling is to answer questions about future 3D design and modeling benefits versus standards 2D design and plan set. This record will use a question and answer format to explain how the 3D design modeling process. 2.0 The General Process: What is 3D Design Modeling? The 3D Design Modeling is a process that develops model information to help make decisions on the future construction management in the construction field, especially in urban areas. It details the need for the type of equipment and the added benefit of providing accuracy during the process of construction to better manage the equipment demand. Typically construction involves a forecast of travel patterns of one to three years in the future with an aim to develop a future of the construction system that will work effectively at that time. Why is 3D Design Modeling necessary? The 3D Design Modeling can have significant effects on mobility, economic construction environmental quality, construction finance, and the quality of life. Wise planning is needed to help create high-quality construction facilities and services at a reasonable cost. Significant transportation projects require a long lead-time for their design and construction. Furthermore, they can have a major effect on future construction time’s patterns, which need to be assessed. What are the steps for 3D Design Modeling? 3D Design Modeling goes through a basic sequence of steps. Several can take place at once, and it is not unusual to repeat some of the steps several times. The basic steps in the 3D Design Modeling are the following: Early planning benefits the outcome:  What are the keys of 3D Design Modeling?  Economic, issues and problems facing the software and hardware?  Lack of training?
  • 2. pg. 2 DFW CONNECTOR & I3 ORANGE LINE | VIRTUAL DESIGN & CONSTRUCTION, CIFE - STEVE SI TRAN DEC 2015 3.0 Methodology Planning and developing a 3D Model database and standards for VDC implementation practice are often a pre- requisite for the revolutionary approach that is Virtual Design and Construction modeling. This cutting-edge methodology has expanded to become the standard within numerous sectors including Architectural, Engineering, Construction and even the Manufacturing sector, as Architects and Engineer’s demands for VDC ready content from the Manufacturer for construction supply chain continues to grow. The use of this intelligent, model-based process provides an insight for creating and managing projects faster, more economical, and with less environmental impact. As an experienced Lead Design/Modeler Manager, s/he not only defines a better fit application and software for VDC needed to get started in the world of VDC, but also offers the VDC team the assistance and guidance they may require to be able to implement VDC with a road map, and get the most of the software investment. For any business, organization, or project that is working on employing VDC, the actual implementation can be difficult. Trying to get your team or colleagues to adopt methods and new procedures will certainly need forward thinking at the initial stage to ensure that you are building a solid foundation that will meet your ongoing requirements. The Modeler Manager will be able to help form a modeling team at this preliminary stage by gaining an understanding of objectives the client wish to achieve from implementing VDC to support and plan procedure of deployment. During the preparation and planning, the Modeler Manager will look to identify the following methods:  Existing office setup  Existing standards implemented  Any existing CAD standards protocols  Practice VDC aspiration and potential timeline for deployment  General projects undertaken  Current Hardware, Software direction and Training expectancy. It is advised to visit this planning with any project size especially from medium up to complex. 3.1 Template creation Template creation is an integral part of VDC modeling that enables our business, organization, or project to have the initial core components for the implementation of the approach in our projects. The Modeler Manager will guide the VDC team and help develop the database and all of the elements to be able to get underway with VDC Modeling including:  Set up a Basic template and database  Set up Title blocks  Adapt templates to contain any required Views  Create and Manage project folder structure  Create and Manage Schedules required with P6  Load in any basic families required  The template with regards to annotation items  Set up CAD layers standards for exchange with Machine guidance and GIS  Set up on the ProjectWise server  Aid the setup of all libraries to VDC modeling structure  Defines communication and collaboration method  Process recording.
  • 3. pg. 3 DFW CONNECTOR & I3 ORANGE LINE | VIRTUAL DESIGN & CONSTRUCTION, CIFE - STEVE SI TRAN DEC 2015 If the right standards are not in place during the development phase, the 3D Model will not be able to update correctly as future improvements are made. It’s important to enforce 3D Modeling Standards that change not just some static 3D PDF files or screen captures. Any shortcuts during development phase can forever reduce or eliminate the ability to locate, retrieve, repurpose and update the database system data. 4.0 Conclusions The results of DFW Connector and the I3 Orange line prove that the aforementioned methods are working successfully: GRAPEVINE (DFWCOM.COM) – Drivers can now cruise through the DFW Connector without having to maneuver around construction cones or worry about detour signs. After more than three years of construction and nine months ahead of schedule, the nearly eight-and-a-half mile project is done. www.dbia.org/awards/2013-Design-Build-Project-Awards Orange Line extension to DFW Airport to open early Posted on January 24, 2014 by Travis Hudson Commuters and travelers to Dallas/Fort Worth International Airport can expect an early Christmas present this year. The 4.7-mile Orange Line extension to DFW Airport is trending ahead of schedule and we’ll be able to open the line earlier than the planned December date. The current goal is to open the new DFW Airport Station at Terminal A by the start of the State Fair of Texas® in late September.
  • 4. pg. 4 DFW CONNECTOR & I3 ORANGE LINE | VIRTUAL DESIGN & CONSTRUCTION, CIFE - STEVE SI TRAN DEC 2015 There’s a lot of work to do, so we’re not ready to set an official opening date, but we’re committed to beating the December target. You may start seeing test trains this spring around the Terminal A area, but we still have systems testing, operator training and construction to complete. Stay tuned. References: Building Information Modeling (BIM) Task Group http://www.bimtaskgroup.org/cobie-uk-2012/ McGraw Hill Construction BIM Special Section http://www.bim.construction.com/research/ NBS National BIM Report 2014 http://www.thenbs.com/pdfs/NBS-National-BIM-Report-2014.pdf BIM Management for value, cost & carbon improvement http://www.bimtaskgroup.org/wp-content/uploads/2012/03/BIS-BIM-strategy-Report.pdf PAS 1192-2 Specification for information management for the capital delivery phase of construction project using building information modeling. http://shop.bsigroup.com/en/forms/PASs/PAS-1192-2/ Industrial strategy: government and industry in partnership https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/34710/12-1327- building-information-modelling.pdf