This document provides information on HVAC system designs and operating costs for several facilities, including:
1) A drug manufacturing plant with a total air requirement of 22,000 CMH and outdoor conditions of 35°C and 27 g/kg.
2) A chocolate processing facility requiring 24°C±2°C and 45% RH with an equipment load of 12kW.
3) A chewing gum packaging plant requiring 20°C±1°C and 38%±3% RH with an equipment load of 20kW and double doors.
It details the product sizing, air volumes, outdoor conditions, equipment types, and operating costs for the cooling coils and dehumidification systems