CURRICULAM VITAE
Muhammad Arif Shahzad
Address :Mohala faizabad near Govt elementary school tehseel
And District Lodhran (city).
Cell No.: 03132072872 & 03012072872
E-mail :engr.arif_shahzad@yahoo.com
Objective:
To obtain a challenging technical or management position as deemed suitable to
my skills, experience and background to help a successful organization or company expand
further and to help my self grow further professionally and technically to become and effective
team player in a progressive organization or company. I am highly trained mulch-culture, hard
working,confident,mature,self-motivated,responsible,reliable,skilled individual with practical
engineering skills and consulting methods gained through many years of practical work
experience in engineering. I am a healthy, friendly, outgoing, open-minded and flexible person.
Academic Qualification:
Bachelor in technology B-Tech.(pass) from Indus
University Karachi (January 2010 to march 2011).
Three years Diploma of Associate Engineering in Electrical Technology from Govt Institute of
Technology Hyderabad.(2005 to 2008)
Metric in Science in “B” Grade.(2000) from Multan.
Now I am working in Amna Industries (al-Karam Group) Landhi
Karachi 8.6MW Plant as a Power House Incharge
With exhaust waste Heat recovery Boiler as a Power House Incharge from 21 April 2014 to till
Date.
I am responsible of Operation and Maintenance Plain; Update all record of engines, parts,
maintenance and all plant responsibility with health and safety rule.
Check and maintain daily fuel, energy and oil consumption of power House.
Maintaining day Repair, preventive maintenance of Genset and overhauling of all plant as per
planned.
Check and maintain daily log book and all parameter record.
Maintaining daily, weekly, monthly and shutdown report of plant.
Work on trouble shooting of power plant.
03 Jenbacher JGS-320
02 Caterpillar G-3516B
02 Caterpillar G-3516A
01Jenbacher JGS-420.
02 years Working Experience & Detail of work in Novatex Bopet unit
(Getron Group) 13.84MW Plant in Karachi as a Engineer operation &
maintenance
I work in Novatex Bopet unit Karachi in power House as a Engineer operation & maintenance
from 08 march 2012 to 20 April 2014 .
A project of 13.84 MW power plant erection and all commissioning of mechanical side
caterpillar and jenbacher Genset installing, piping structure fabrication of close and open
circuit of cooling tower ,hot water and W.H.R circuit .H.T and L.V panels installing and all
auxiliaries equipments commissioning under by observation.
07 Jenbacher JGS 320 with Hot water Heat Recovery system to Hot water chiller and Exhaust
waste Heat Recovery system to multi-energy chiller and transfer HTM oil Heater
system.
04 Cat D-3516B Diesel engine with Radiator cooling system.(1600kw each engine)
Check and maintain daily fuel, energy and oil consumption of power House.
Maintaining day Repair, preventive maintenance of Gen set and overhauling of all plant as per
planned.
Work on Mogen system for work permit and MMS store system for SR & DPR in main store.
Check and maintain daily log book and all parameter record.
Maintaining daily, weekly, monthly and shutdown report of plant.
Work on trouble shooting of power plant.
04 years working experience in Artistic fabric mills Karachi spinning unit
as a shift in-charge power House from April 2008 to march 2012.
Artistic fabric mills spinning unit 8.72MW plant.
A project of 8.72 MW power plant erection and all commissioning of mechanical side caterpillar
and jenbacher Genset installing, piping structure fabrication of close and open circuit of
cooling tower ,hot water and W.H.R circuit .H.T and L.V panels installing and all auxiliaries
equipments commissioning under by observation.
02 Jenbacher JGS 420 with Hot water Heat Recovery system to Hot water chiller.(1416kw each
engine) and Exhaust waste Heat Recovery system to steam Boiler(fire tube) 03 no.
Boiler 1*800 kg/h
Boiler 1*1200 kg/h
Boiler 1*1500 kg/h
03Jenbacher JGS 320 with Hot water Heat Recovery system to Hot water chiller. (1063kw each
engine) and Exhaust waste Heat Recovery system to steam Boiler(fire tube) 03 no.
01 Cat G-3516B Gas engine.(1100KW)
01 Cat G-3516C Gas engine.(1600KW)
Worked on 01 R.O Plant of 70200 US Gallon per day.
Worked on 02 softer plants
1*1000 Liters/h
1*3000 Liters/h
Check and maintain daily fuel, energy and oil consumption of power House.
Maintaining day Repair, preventive maintenance of Genset and overhauling of all plant as per
planned. Check and maintain daily log book and all parameter record.
Maintaining daily, weekly, monthly and shutdown report of plant.
Work on trouble shooting of power plant.
02 years working experience in Sapphire textile mills kotri spinning unit as
a asst.operator & Operator of power House from January 2006 to march 2008.
Sapphire textile mills kotri 5.61MW Plant.
03 Cat 4EK G-3516A Gas engine.(965KW each engine)
01 Cat 3RC G-3516A Gas engine.(615KW)
01 Cat CSZ G-3516A Gas engine.(1005KW)
01 Cat CSC G-3516B Gas engine.(1100KW)
Check and maintain daily log book and all parameter record.
Maintain house keeping of power House.
KEY SKILLS :
Maintenance Engineering & Management, Oil & Gas Maintenance, Financial&
Project
Management, Utilities, Quality Control(ISO 9001:2000), Auditing,
Supervising, Leadership, Team Building, Boiler
Maintenance & Operation, Heating System, Electromechanical Devices, Outsourcing,
Reporting Expert, Communication & Interpersonal skills, Strong Analytical and
Problem Solving Skills, Ability to perform under pressure, Developing Systems &
Processes (Using SOP),Customer Service, Public Relations.
Understanding about & effect of power factor in power system & correction of
P.F calculation.
Understanding in Dc & Ac control system.
Some experience in electrical control system.
Computer skill:
Ms Office application
Internet
Windows XP
Strange:
Good ability at team working, problem solving, decision making skills and
communicating clearly at all levels.
Time management.
Goal oriented fast leaner.
Flexible and responsive personality.
Self-starter and achievement oriented and highly mobile.
Personal Information:
Father's Name : Allah Bachaya
Date of Birth : 11.09.1983
Religion : Islam
Nationality : Pakistani
Marital Status : Married
Reference:
Will be furnished upon request.

cv comp. (2)

  • 1.
    CURRICULAM VITAE Muhammad ArifShahzad Address :Mohala faizabad near Govt elementary school tehseel And District Lodhran (city). Cell No.: 03132072872 & 03012072872 E-mail :engr.arif_shahzad@yahoo.com Objective: To obtain a challenging technical or management position as deemed suitable to my skills, experience and background to help a successful organization or company expand further and to help my self grow further professionally and technically to become and effective team player in a progressive organization or company. I am highly trained mulch-culture, hard working,confident,mature,self-motivated,responsible,reliable,skilled individual with practical engineering skills and consulting methods gained through many years of practical work experience in engineering. I am a healthy, friendly, outgoing, open-minded and flexible person. Academic Qualification: Bachelor in technology B-Tech.(pass) from Indus University Karachi (January 2010 to march 2011). Three years Diploma of Associate Engineering in Electrical Technology from Govt Institute of Technology Hyderabad.(2005 to 2008) Metric in Science in “B” Grade.(2000) from Multan. Now I am working in Amna Industries (al-Karam Group) Landhi Karachi 8.6MW Plant as a Power House Incharge With exhaust waste Heat recovery Boiler as a Power House Incharge from 21 April 2014 to till Date. I am responsible of Operation and Maintenance Plain; Update all record of engines, parts, maintenance and all plant responsibility with health and safety rule. Check and maintain daily fuel, energy and oil consumption of power House. Maintaining day Repair, preventive maintenance of Genset and overhauling of all plant as per planned. Check and maintain daily log book and all parameter record. Maintaining daily, weekly, monthly and shutdown report of plant. Work on trouble shooting of power plant. 03 Jenbacher JGS-320 02 Caterpillar G-3516B 02 Caterpillar G-3516A 01Jenbacher JGS-420. 02 years Working Experience & Detail of work in Novatex Bopet unit (Getron Group) 13.84MW Plant in Karachi as a Engineer operation & maintenance I work in Novatex Bopet unit Karachi in power House as a Engineer operation & maintenance
  • 2.
    from 08 march2012 to 20 April 2014 . A project of 13.84 MW power plant erection and all commissioning of mechanical side caterpillar and jenbacher Genset installing, piping structure fabrication of close and open circuit of cooling tower ,hot water and W.H.R circuit .H.T and L.V panels installing and all auxiliaries equipments commissioning under by observation. 07 Jenbacher JGS 320 with Hot water Heat Recovery system to Hot water chiller and Exhaust waste Heat Recovery system to multi-energy chiller and transfer HTM oil Heater system. 04 Cat D-3516B Diesel engine with Radiator cooling system.(1600kw each engine) Check and maintain daily fuel, energy and oil consumption of power House. Maintaining day Repair, preventive maintenance of Gen set and overhauling of all plant as per planned. Work on Mogen system for work permit and MMS store system for SR & DPR in main store. Check and maintain daily log book and all parameter record. Maintaining daily, weekly, monthly and shutdown report of plant. Work on trouble shooting of power plant. 04 years working experience in Artistic fabric mills Karachi spinning unit as a shift in-charge power House from April 2008 to march 2012. Artistic fabric mills spinning unit 8.72MW plant. A project of 8.72 MW power plant erection and all commissioning of mechanical side caterpillar and jenbacher Genset installing, piping structure fabrication of close and open circuit of cooling tower ,hot water and W.H.R circuit .H.T and L.V panels installing and all auxiliaries equipments commissioning under by observation. 02 Jenbacher JGS 420 with Hot water Heat Recovery system to Hot water chiller.(1416kw each engine) and Exhaust waste Heat Recovery system to steam Boiler(fire tube) 03 no. Boiler 1*800 kg/h Boiler 1*1200 kg/h Boiler 1*1500 kg/h 03Jenbacher JGS 320 with Hot water Heat Recovery system to Hot water chiller. (1063kw each engine) and Exhaust waste Heat Recovery system to steam Boiler(fire tube) 03 no. 01 Cat G-3516B Gas engine.(1100KW) 01 Cat G-3516C Gas engine.(1600KW) Worked on 01 R.O Plant of 70200 US Gallon per day. Worked on 02 softer plants 1*1000 Liters/h 1*3000 Liters/h Check and maintain daily fuel, energy and oil consumption of power House. Maintaining day Repair, preventive maintenance of Genset and overhauling of all plant as per planned. Check and maintain daily log book and all parameter record. Maintaining daily, weekly, monthly and shutdown report of plant. Work on trouble shooting of power plant.
  • 3.
    02 years workingexperience in Sapphire textile mills kotri spinning unit as a asst.operator & Operator of power House from January 2006 to march 2008. Sapphire textile mills kotri 5.61MW Plant. 03 Cat 4EK G-3516A Gas engine.(965KW each engine) 01 Cat 3RC G-3516A Gas engine.(615KW) 01 Cat CSZ G-3516A Gas engine.(1005KW) 01 Cat CSC G-3516B Gas engine.(1100KW) Check and maintain daily log book and all parameter record. Maintain house keeping of power House. KEY SKILLS : Maintenance Engineering & Management, Oil & Gas Maintenance, Financial& Project Management, Utilities, Quality Control(ISO 9001:2000), Auditing, Supervising, Leadership, Team Building, Boiler Maintenance & Operation, Heating System, Electromechanical Devices, Outsourcing, Reporting Expert, Communication & Interpersonal skills, Strong Analytical and Problem Solving Skills, Ability to perform under pressure, Developing Systems & Processes (Using SOP),Customer Service, Public Relations. Understanding about & effect of power factor in power system & correction of P.F calculation. Understanding in Dc & Ac control system. Some experience in electrical control system. Computer skill: Ms Office application Internet Windows XP Strange: Good ability at team working, problem solving, decision making skills and communicating clearly at all levels. Time management. Goal oriented fast leaner. Flexible and responsive personality. Self-starter and achievement oriented and highly mobile. Personal Information: Father's Name : Allah Bachaya Date of Birth : 11.09.1983 Religion : Islam Nationality : Pakistani
  • 4.
    Marital Status :Married Reference: Will be furnished upon request.