Page 1 of 7
AABBIIDD RRAASSOOOOLL
Cellular +92 335 7941281, +966 501628847
E-mail rabid795@gmail.com
abid.rasool@nomac.com
OOBBJJEECCTTIIVVEESS
To enhance my capabilities knowledge and professional skills in the field of OHSE under the
supervision of your esteemed organization
AACCAADDEEMMIICC // TTEECCHHNNIICCAALL QQUUAALLIIFFIICCAATTIIOONN
 DAE Mechanical (Diploma of Associate Engineer in Mechanical) 1999
 Diploma in HSWM (Health, Safety & Welfare Management) 2008
 OHSAS-18001-2007 and ISO 14001-2004 Awareness course 2010
 Certified Lead Auditor OHSAS-18001-2007 2011
 Certified Lead Auditor ISO-14001-2004 2011
 NEBOSH IGC-1 2012
 Advanced Exterior Industrial Fire Brigade Member 2014
EEXXPPEERRIIEENNCCEE
1. From Sep,11-2013 to now
ORGANIZATION: NOMAC (First National Operation &Maintenance Co. Ltd)
 Project: Qurreyah Independent Power Plant 4000 MW
Owner: Hajr
Position: HSE Engineer
Page 2 of 7
Roles and Responsibilities:
 Leading plant HSE Team (HSE Engineer, Officer, Fire Fighter and Male nurse)
 Implementation of Organization IMS (Integrated Management System)
 Prepared Plant specific HSE Procedures like Plant Emergency response plan, Plant
chemicals handling, use and storage procedure, Environmental compliance and
monitoring procedure and Fire Fighting system Impairment procedure etc.
 Prepare the Budget of HSE Material for next 5years and raised the PRs in SAP for
procurement purpose.
 Arranging HSE Training and awareness session within team to prepare the plant
handling like PTW, HIRE, EAI etc.
 Prepared the operation stage detailed design regarding HSE as per requirement HCIS
(Ministry of Interior)
 Preparation of HSE weekly, Monthly, Quarterly reports for project company and
Corporate.
 Preparation of HSE Statistics, Man-hours, incidents/Accident reports, Conduct and
prepare Incident/accident investigation reports, HSE Walk downs, follow up of NM
Reports for corrective action,
 Arranging HSE Monthly meetings, HSE Committee Meetings,
 Identifying the requirement of trainings for employees, preparing the training plan and
arranging internal/external trainings.
 Conducting review of HSE Policies, plans and procedures, Legal and other requirements
(local laws and regulations), Risk assessments, Aspects/impacts, Evaluation of
compliance, HSE Objectives and targets, audits review and managements review report.
 Conducting safety induction of visitors, suppliers and contractors, safety tool box talks
with outage contractors,
2. From 01Jan-2013 to 24Jul-2013:
ORGANIZATION: Abeinsa Teyma Barka (EPC Company)
 Project: 10MIGD RO Water plant Barka-1
Owner: ACWA Power International
Position: HSE Engineer
Page 3 of 7
Roles and Responsibilities:
 Monitoring contractor’s daily activities, like Fabrications, erection, heavy lifting, Fire
fighting arrangements, emergency arrangement and response, housekeeping situation of
project and conducting emergency moke drills to check the response.
 Safety induction of all contractors, visitors and suppliers.
 Reviewing lifting equipments inspections, test certificates, risk assessments of critical
activities,
 Arranging weekly and monthly meetings with all contractors management and
participating in tool box talks with all contractors workers
 Conducting jointly plant visits with all contractors’ management on weekly basis.
 Preparation of HSE Statistics, NM, s, incident/investigation reports, and reporting to Site
Manager.
 Reporting HSE Statistics to Abeinsa Online reporting system.
3. From 07Nov, 2009 to 31Dec-2012:
ORGANIZATION: NOMAC Oman (First National Company for Operation & Maintenance Services)
At ACWA Power and Desalination plant Barka-I Oman.
 Project: 456MW Power and 20MIGD Water Desalination plant.
Owner: ACWA Power International
Position: Plant HSE Engineer
Roles and Responsibilities:
 Implementation of Organization Occupational Health, Safety and Environment
management system procedures, on day by day activities as per OHSAS-18001-2007 and
ISO-14001-2004 requirements,
 Preparation of HSE weekly, Monthly, Quarterly reports for (MECA) Ministry of
Environment and Climate Affairs, Ministry of Manpower, ACWA Power Barka and NOMAC
Oman, Preparation of HSE Statistics, Man-hours, incidents/Accident reports, Conduct
and prepare Incident/accident investigation reports, HSE Walk downs, follow up of NM
Reports for corrective action,
 Arranging HSE Monthly meetings, HSE Committee Meetings, preparing outage plans,
arranging annual Safety and Environment day celebration,
 Conducting routine inspection of lifting equipments, Fire fighting equipments, Emergency
equipments (ELSA, SCBA, AED, AMBULANCE, Communication system, First aid and
chlorine leakage kit etc)
Page 4 of 7
 Identifying the requirement of trainings for employees, preparing the training plan and
arranging internal/external trainings.
 Preparing the HSE Audit plan for the year, conducting audit, preparing audit report for
management and also arranging annual audit from SGS for surveillance/reissuance of
OHSAS/ISO Certification,
 Conducting review of HSE Policies, plans and procedures, Legal and other requirements
(local laws and regulations), Risk assessments, Aspects/impacts, Evaluation of
compliance, HSE Objectives and targets, audits review and managements review report.
 Conducting safety induction of visitors, suppliers and contractors, safety tool box talks
with outage contractors,
 As an auditee completed successfully two detail Recertification and two surveillance
audits of OHSAS-18001-2007 and ISO-14001-2004 by SGS.
 Participated in International IOSH Middle east conference On 25 April-2012 in Oman.
 In 02 May, 2012 we completed 10years without LTA.
Training completed:
 Awareness training of OHSAS-18001-2007 and ISO-14001-2004.
 Occupation Health safety and loss prevention training.
 Fire Fighting and First aid training completed.
 Risk assessment training completed.
 Scaffolding inspection training completed.
 Safe use of Fork lift, Bob cat and cranes.
 Confined space and rescue procedure in case of emergency.
 Behavior based safety training completed.
 Hazardous Material First responder awareness training.
4. From 21 Sep, 2008 to 03 Oct, 2009:
ORGANIZATION: AES Corporation.
Amman East Power Plant Jordan
 Project: 370 MW Combined Cycle Power Project Jordan.
Owner: AES
Position: EHS Engineer
Roles and responsibilities:
 Joined the AES at Amman East Power Plant (AEPP) Jordan during construction phase
and my role was as a EHS Engineer implementation of HSE Manual/procedures agreed
Page 5 of 7
between AES (owner), Doosan (EPC), Astraco (Mechanical and Electrical contractor
company) and Atcco (civil contracting company)
 Monitoring contractor’s daily activities, like Fabrications, erection, heavy lifting, Fire
fighting arrangements, emergency arrangement and response, housekeeping situation of
project and conducting emergency moke drills to check the response.
 Reviewing lifting equipments inspections, test certificates, risk assessments of critical
activities,
 Arranging weekly and monthly meetings with all contractors management and
participating in tool box talks with all contractors workers
 Conducting jointly plant visits with all contractors’ management on weekly basis.
 Preparation of HSE Statistics, NM, s, incident/investigation reports, and reporting to Site
Manager.
 Reporting HSE Statistics to AES Online reporting system.
 AES Completed that critical project more than 4 Million man-hours without any LTA and
won the Golden helmat award from AES Corp.
5. From “29 Jun, 2006” to 15, Sep, 2008:
ORGANIZATION: Albario Engineering (Pvt.) Limited.
Rasool Building Shahra-e-Quaid-e-Azam, Lahore Pakistan 54000
 Project: 225 MW Combined Cycle Power Project, Balloki, PAKISTAN.
Client: Orient Power
Technical Advisers: GE Energy Europe (Product Supplier)
Duration: 26 April 2007 to 15 September 16, 2008.
Position: HSE Engineer
 Project: 150 MW GE Rental Power Project Sheikhupura, PAKISTAN.
Client: WAPDA
Consultant: General Electrics Energy Europe.
Technical Advisers: GE Energy Europe (Product Supplier)
Duration: 29 October 2006 to 10 April 2007.
Position: HSE Engineer
 Project: Uch Power Plant 586MW Major Outage Balochistan, PAKISTAN.
Client: ESBI (Electric Supply Board International)
Consultant: General Electrics Energy Europe.
Technical Advisers: GE Energy Europe (Product Supplier)
Page 6 of 7
Duration: 29 June 2006 to 20 September 2006.
Position: HSE Coordinator
6. From “08 Apr-1999” to “25 Jun-2006”
ORGANIZATION: Engineering Kinetics (Pvt.) Limited.
73/GII Model Town, Lahore. PAKISTAN.
 Project: DG Cement Khairpur Chakwal, PAKISTAN.
Duration: 17 January 2006 to 25 June 2006.
Position: Assistant HSE Engineer.
 Project: Uch Power Plant 586MW Dera Murad Jamali, PAKISTAN.
Duration: 15 July 2005 to 26 December 2005.
Position: Assistant HSE Engineer.
 Project: Rafhan Maize Products Jaranwallah, PAKISTAN.
Duration: 01 December 2004 to 15 July 2005.
Position: Assistant HSES Engineer.
 Project: Fauji & Askari Cement Projects, PAKISTAN.
Duration: 03 March 2004 to 11 October 2004.
Position: HSE Supervisor.
 Project: 1450MW Ghazi Brotha Hydro Power Project
PAKISTAN.
Duration: 05 August 2002 to 02 March 2004.
Position: HSE Supervisor.
 Project: Ibrahim Fiber Phase-II Faisalabad, PAKISTAN.
Duration: 19 May 2001 to 02 July 2002.
Position: HSE Supervisor.
 Project: 184MW Chashma Hydro Power Project PAKISTAN.
Duration: 08 April 1999 to 26 March 2001.
Position: Assistant HSE Supervisor.
Page 7 of 7
AApppprreecciiaattiioonn::
 Received appreciation letter from GE in Uch power major outage 2006
 Received appreciation letter from AES in Amman east power plant Jordan
CCOOMMPPUUTTEERR SSKKIILLLLSS
 Internet (Browsing, Searching, Surfing & E-mailing)
MMSS OOFFFFIICCEE
 MS Word.
 MS Excel.
 MS Outlook
Personal information:
Father Name Ghulam Rasool
Date of Birth January 01, 1979
NIC # 36401-0878512-9
Passport # AD9805122 valid till 2017
Nationality Pakistani
Religion Islam
Marital Status Married
Address Chack No. 22 / EB, Tehsil: Arifwalla, District: Pakpatan.

CV Abid Rasool (HSE Engineer).

  • 1.
    Page 1 of7 AABBIIDD RRAASSOOOOLL Cellular +92 335 7941281, +966 501628847 E-mail rabid795@gmail.com abid.rasool@nomac.com OOBBJJEECCTTIIVVEESS To enhance my capabilities knowledge and professional skills in the field of OHSE under the supervision of your esteemed organization AACCAADDEEMMIICC // TTEECCHHNNIICCAALL QQUUAALLIIFFIICCAATTIIOONN  DAE Mechanical (Diploma of Associate Engineer in Mechanical) 1999  Diploma in HSWM (Health, Safety & Welfare Management) 2008  OHSAS-18001-2007 and ISO 14001-2004 Awareness course 2010  Certified Lead Auditor OHSAS-18001-2007 2011  Certified Lead Auditor ISO-14001-2004 2011  NEBOSH IGC-1 2012  Advanced Exterior Industrial Fire Brigade Member 2014 EEXXPPEERRIIEENNCCEE 1. From Sep,11-2013 to now ORGANIZATION: NOMAC (First National Operation &Maintenance Co. Ltd)  Project: Qurreyah Independent Power Plant 4000 MW Owner: Hajr Position: HSE Engineer
  • 2.
    Page 2 of7 Roles and Responsibilities:  Leading plant HSE Team (HSE Engineer, Officer, Fire Fighter and Male nurse)  Implementation of Organization IMS (Integrated Management System)  Prepared Plant specific HSE Procedures like Plant Emergency response plan, Plant chemicals handling, use and storage procedure, Environmental compliance and monitoring procedure and Fire Fighting system Impairment procedure etc.  Prepare the Budget of HSE Material for next 5years and raised the PRs in SAP for procurement purpose.  Arranging HSE Training and awareness session within team to prepare the plant handling like PTW, HIRE, EAI etc.  Prepared the operation stage detailed design regarding HSE as per requirement HCIS (Ministry of Interior)  Preparation of HSE weekly, Monthly, Quarterly reports for project company and Corporate.  Preparation of HSE Statistics, Man-hours, incidents/Accident reports, Conduct and prepare Incident/accident investigation reports, HSE Walk downs, follow up of NM Reports for corrective action,  Arranging HSE Monthly meetings, HSE Committee Meetings,  Identifying the requirement of trainings for employees, preparing the training plan and arranging internal/external trainings.  Conducting review of HSE Policies, plans and procedures, Legal and other requirements (local laws and regulations), Risk assessments, Aspects/impacts, Evaluation of compliance, HSE Objectives and targets, audits review and managements review report.  Conducting safety induction of visitors, suppliers and contractors, safety tool box talks with outage contractors, 2. From 01Jan-2013 to 24Jul-2013: ORGANIZATION: Abeinsa Teyma Barka (EPC Company)  Project: 10MIGD RO Water plant Barka-1 Owner: ACWA Power International Position: HSE Engineer
  • 3.
    Page 3 of7 Roles and Responsibilities:  Monitoring contractor’s daily activities, like Fabrications, erection, heavy lifting, Fire fighting arrangements, emergency arrangement and response, housekeeping situation of project and conducting emergency moke drills to check the response.  Safety induction of all contractors, visitors and suppliers.  Reviewing lifting equipments inspections, test certificates, risk assessments of critical activities,  Arranging weekly and monthly meetings with all contractors management and participating in tool box talks with all contractors workers  Conducting jointly plant visits with all contractors’ management on weekly basis.  Preparation of HSE Statistics, NM, s, incident/investigation reports, and reporting to Site Manager.  Reporting HSE Statistics to Abeinsa Online reporting system. 3. From 07Nov, 2009 to 31Dec-2012: ORGANIZATION: NOMAC Oman (First National Company for Operation & Maintenance Services) At ACWA Power and Desalination plant Barka-I Oman.  Project: 456MW Power and 20MIGD Water Desalination plant. Owner: ACWA Power International Position: Plant HSE Engineer Roles and Responsibilities:  Implementation of Organization Occupational Health, Safety and Environment management system procedures, on day by day activities as per OHSAS-18001-2007 and ISO-14001-2004 requirements,  Preparation of HSE weekly, Monthly, Quarterly reports for (MECA) Ministry of Environment and Climate Affairs, Ministry of Manpower, ACWA Power Barka and NOMAC Oman, Preparation of HSE Statistics, Man-hours, incidents/Accident reports, Conduct and prepare Incident/accident investigation reports, HSE Walk downs, follow up of NM Reports for corrective action,  Arranging HSE Monthly meetings, HSE Committee Meetings, preparing outage plans, arranging annual Safety and Environment day celebration,  Conducting routine inspection of lifting equipments, Fire fighting equipments, Emergency equipments (ELSA, SCBA, AED, AMBULANCE, Communication system, First aid and chlorine leakage kit etc)
  • 4.
    Page 4 of7  Identifying the requirement of trainings for employees, preparing the training plan and arranging internal/external trainings.  Preparing the HSE Audit plan for the year, conducting audit, preparing audit report for management and also arranging annual audit from SGS for surveillance/reissuance of OHSAS/ISO Certification,  Conducting review of HSE Policies, plans and procedures, Legal and other requirements (local laws and regulations), Risk assessments, Aspects/impacts, Evaluation of compliance, HSE Objectives and targets, audits review and managements review report.  Conducting safety induction of visitors, suppliers and contractors, safety tool box talks with outage contractors,  As an auditee completed successfully two detail Recertification and two surveillance audits of OHSAS-18001-2007 and ISO-14001-2004 by SGS.  Participated in International IOSH Middle east conference On 25 April-2012 in Oman.  In 02 May, 2012 we completed 10years without LTA. Training completed:  Awareness training of OHSAS-18001-2007 and ISO-14001-2004.  Occupation Health safety and loss prevention training.  Fire Fighting and First aid training completed.  Risk assessment training completed.  Scaffolding inspection training completed.  Safe use of Fork lift, Bob cat and cranes.  Confined space and rescue procedure in case of emergency.  Behavior based safety training completed.  Hazardous Material First responder awareness training. 4. From 21 Sep, 2008 to 03 Oct, 2009: ORGANIZATION: AES Corporation. Amman East Power Plant Jordan  Project: 370 MW Combined Cycle Power Project Jordan. Owner: AES Position: EHS Engineer Roles and responsibilities:  Joined the AES at Amman East Power Plant (AEPP) Jordan during construction phase and my role was as a EHS Engineer implementation of HSE Manual/procedures agreed
  • 5.
    Page 5 of7 between AES (owner), Doosan (EPC), Astraco (Mechanical and Electrical contractor company) and Atcco (civil contracting company)  Monitoring contractor’s daily activities, like Fabrications, erection, heavy lifting, Fire fighting arrangements, emergency arrangement and response, housekeeping situation of project and conducting emergency moke drills to check the response.  Reviewing lifting equipments inspections, test certificates, risk assessments of critical activities,  Arranging weekly and monthly meetings with all contractors management and participating in tool box talks with all contractors workers  Conducting jointly plant visits with all contractors’ management on weekly basis.  Preparation of HSE Statistics, NM, s, incident/investigation reports, and reporting to Site Manager.  Reporting HSE Statistics to AES Online reporting system.  AES Completed that critical project more than 4 Million man-hours without any LTA and won the Golden helmat award from AES Corp. 5. From “29 Jun, 2006” to 15, Sep, 2008: ORGANIZATION: Albario Engineering (Pvt.) Limited. Rasool Building Shahra-e-Quaid-e-Azam, Lahore Pakistan 54000  Project: 225 MW Combined Cycle Power Project, Balloki, PAKISTAN. Client: Orient Power Technical Advisers: GE Energy Europe (Product Supplier) Duration: 26 April 2007 to 15 September 16, 2008. Position: HSE Engineer  Project: 150 MW GE Rental Power Project Sheikhupura, PAKISTAN. Client: WAPDA Consultant: General Electrics Energy Europe. Technical Advisers: GE Energy Europe (Product Supplier) Duration: 29 October 2006 to 10 April 2007. Position: HSE Engineer  Project: Uch Power Plant 586MW Major Outage Balochistan, PAKISTAN. Client: ESBI (Electric Supply Board International) Consultant: General Electrics Energy Europe. Technical Advisers: GE Energy Europe (Product Supplier)
  • 6.
    Page 6 of7 Duration: 29 June 2006 to 20 September 2006. Position: HSE Coordinator 6. From “08 Apr-1999” to “25 Jun-2006” ORGANIZATION: Engineering Kinetics (Pvt.) Limited. 73/GII Model Town, Lahore. PAKISTAN.  Project: DG Cement Khairpur Chakwal, PAKISTAN. Duration: 17 January 2006 to 25 June 2006. Position: Assistant HSE Engineer.  Project: Uch Power Plant 586MW Dera Murad Jamali, PAKISTAN. Duration: 15 July 2005 to 26 December 2005. Position: Assistant HSE Engineer.  Project: Rafhan Maize Products Jaranwallah, PAKISTAN. Duration: 01 December 2004 to 15 July 2005. Position: Assistant HSES Engineer.  Project: Fauji & Askari Cement Projects, PAKISTAN. Duration: 03 March 2004 to 11 October 2004. Position: HSE Supervisor.  Project: 1450MW Ghazi Brotha Hydro Power Project PAKISTAN. Duration: 05 August 2002 to 02 March 2004. Position: HSE Supervisor.  Project: Ibrahim Fiber Phase-II Faisalabad, PAKISTAN. Duration: 19 May 2001 to 02 July 2002. Position: HSE Supervisor.  Project: 184MW Chashma Hydro Power Project PAKISTAN. Duration: 08 April 1999 to 26 March 2001. Position: Assistant HSE Supervisor.
  • 7.
    Page 7 of7 AApppprreecciiaattiioonn::  Received appreciation letter from GE in Uch power major outage 2006  Received appreciation letter from AES in Amman east power plant Jordan CCOOMMPPUUTTEERR SSKKIILLLLSS  Internet (Browsing, Searching, Surfing & E-mailing) MMSS OOFFFFIICCEE  MS Word.  MS Excel.  MS Outlook Personal information: Father Name Ghulam Rasool Date of Birth January 01, 1979 NIC # 36401-0878512-9 Passport # AD9805122 valid till 2017 Nationality Pakistani Religion Islam Marital Status Married Address Chack No. 22 / EB, Tehsil: Arifwalla, District: Pakpatan.