ORGANIZATION YEAR ATTENDED
Saudi Council of Engineers – SCE 2014 – 2017
Architectural Engineer Associate Degree
(Previous Working Visa Category)
United Architects of the Philippines - IAPOA 2012 – Present
The Integrated and Accredited Professional Organization of Architects
United Architects of the Philippines – Pasig Chapter 2012 – Present
The Integrated and Accredited Professional Organization of Architects
SCHOOL YEAR ATTENDED
TERTIARY/COLLEGE:
Polytechnic University of the Philippines (Mabini Campus) 2002 - 2009
Anonas St., Sta. Mesa Manila, Philippines
Bachelor of Science in Architecture and Fine Arts
SECONDARY/HIGH SCHOOL:
Rizal High School (Main Campus) 1998 - 2002
Dr. Sixto Antonio Avenue St., Brgy. Caniogan, Pasig City, Philippines
PRIMARY/ELEMENTARY:
Bagong Diwa Elementary School 1992 – 1998
#2244 Linceo St. Pandacan Manila, Philippines
*ARCHITECT/DESIGN ASSISTANT
Creative + Productive + Hard Working + Multi-Tasking + Observant
PRC Reg. No. : 29661
Date Issue : July-06, 2012
Date Expired : October-12, 2019
UAP No. : 25914
PTR No. : 1687924
Place Issue : Pasig City Hall, Pasig City, Metro Manila Philippines
Home Address : #0435 Baltazar St., Brgy. Sto. Tomas,
Pasig City, Metro Manila, Philippines
Contact No. : +63 995 4835988 (Globe)
+63 921 4149574 (Smart)
Skype Account : mauipogi_101285
E-mail : mauriciojr.cabanillas@yahoo.com
Career Objective:
“To pursue a professional challenging Architectural & Engineering
working experience in any Architectural/Engineering Firm to help broaden my
experience in the related field & enhances my knowledge & professional growth
in the world of Architecture, Construction, & Oil & Gas Industry.”
Architect MAURICIO P. CABANILLAS JR.
i. AFFILIATION/MEMBERSHIP ORGANIZATION:
ii. EDUCATIONAL BACKGROUND:
Birthday : October – 12, 1985
Birth Place : Giporlos, Eastern Samar, Philippines
Age : 31
Sex : Male
Civil Status : Single
Height : 5’4” (162 cm)
Weight : 145 lbs. (65 kilos)
Religion : Roman Catholic
Nationality : Filipino
Language Spoken : English, Tagalog & Waray
Father’s Name : Mr. Mauricio O. Cabanillas
Occupation : Master Teacher II (Bagong Diwa Elementay School, Pandacan Manila, Philippines)
Mother’s Name : Mrs. Winefreda P. Cabanillas
Occupation : Housewife
Siblings : Patty P. Cabanillas
Occupation : Sales Representative (Duty Free Mall - Dubai, United Arab Emirates)
Person to Contact
In Case of Emergency : Mr. Mauricio O. Cabanillas
Relationship : Father
Address : #0435 Baltazar St., Brgy. Sto. Tomas Pasig City, Philippines
Contact No’s. : +63 949 7648465 / 7470367
* United Architects of the Philippines – Pasig Chapter
The Integrated and Accredited Professional Organization of Architects
PROJECT BLAD: “Blood Letting and Data Banking cum Motorcycle Event”
August-26, 2012, Sunday @ Rizal High School (Main Campus) Pasig City
* United Architects of the Philippines – Pasig Chapter
The Integrated and Accredited Professional Organization of Architects
INDUCTION OF OFFICERS FY: 2012-2013 & New Member Architects Thanks Giving Night
September-20, 2012, Thursday @ CW HOME DEPOT Makati Events Hall
* AUTODESK 3DSMAX 2011 (For Architectural Design)
MICROCADD TECHNOLOGIES Co., Inc.
Main Branch: Cubao
July, 2011 (9 hr. /15 hr.) @ 5th Flr., Doña Consolacion Bldg. 602 General Santos Ave., Cubao, Q. C.
* United Architects of the Philippines – Graduate Auxiliary 101
The Duly Recognized Graduate Auxiliary of the United Architects of the Philippines
BOARDing PASS: “Destination June 2011 ALE”
May-08, 2011, Sunday @ Teatro Arkitekto, UAP Headquarters, Scout Rallos, Tomas Morato, Q. C.
* Exploring the Empowering Spirit of Art and Architecture”
February-03 & 04, 2009 @ P.U.P. Mabini Campus, Sta. Mesa, Manila
* “Church Architecture in Filipino Settings”
Arsobispado, Intramuros, Manila
* “Creative Green Architecture and Design: The Cutting Edge”
College of Engineering Theater, University of the Philippines, Diliman, Q.C.
* “The Science of Feng Shui and Architectural Design”
January-28, 2004 @ College of Engineering Theater, University of the Philippines, Diliman, Q.C.
* Nestle Nido: “Munting Daliri Father & Child Art Workshop”
Batch 1997, @ Museong Pambata, Roxas Boulevard, Taft Manila
* Nestle Nido: “Munting Daliri Mother & Child Art Workshop”
Batch 1995, @ Fort Santiago, Intramuros, Manila
iii. PERSONAL BACKGROUND:
iv. TRAININGS & SEMINARS ATTENDED:
1. Software’s : Auto CAD 2014-2016 Version
Sketch-Up 3D Rendering with V-Ray & i-Render
Photoshop CS5
MS Office 2010 Proficient
2. Knowledge : Aviation Facility & Berthing Facility
Oil Depot Layout Plan, Bulk Plant Layout Plan, & Bunkering Terminal Layout Plan
LPG Filling Plant Layout Plan with Piping & Instrumentation Diagram (P. & I. D.)
Gasoline Service Station (S/S) Layout Plan
Bulilit-Station/Micro-Filling Station (MFS) & Dealer-Owned Filling Station (DOFS)
Prepared Construction/Shop Drawings by the following Drafting Disciplines:
* Architectural
* Structural
* Electrical
* Mechanical
* Sanitary/Plumbing
* Driveway Concreting
* Piping & Instrumentation Diagram (P. & I. D.)
Residential Houses Designing and Rendering
Prepared Estimate Bill of Materials (BOM) & Bill of Quantity (BOQ)
Site Visiting & preparing as-Built Plans
Designing of Roads and Bridges with Typical Sections of Foundation and Footing Details
Northing & Easting of Coordinates & reflect it in Google Earth as KMZ Files
Daily, Weekly & Monthly Cumulative Roads Progress Monitoring
3. Other Skills : Manual Drafting & Rendering, Scale Modeling, Painting, & Mosaic Rendering
4. Self Attributes : Good Oral & Written Communication & Interpersonal Skills
Self-starter and self-motivated
Initiative and organized
Ensure that project deadlines are met and able to Multi Task
Capable of working under pressure to meet tight submission schedules
Willing to work overtime to meet the schedule completion dates
Capable of scheduling and managing own work load plus others
A Team player
Contractor :
2nd
Floor Obeikan Bookstore Building
Prince Sultan Road, Jeddah, Kingdom of Saudi Arabia
Department : Architecture & Building Construction Division – Road Projects Department
Position : QA/QC Department Draftsman
Duration : January-29, 2014 to January-31, 2016 (2 years)
Job Description : Designing of Roads and Bridges with Typical Sections of Foundation and Footing Details for
Makkah Second Ring Road Project by the following Drafting Disciplines: Architectural &
Structural. Prepares Construction/Shop Drawings of QA/QC Department Mobile Laboratory for
the South Border Infrastructure Project (SBIP). Provide Weekly Quantities of Road Progress
Monitoring Report based on daily Request for Inspection (RFI), Request for Testing (RFT), &
Test Report Submittal (TRS), etc. Provide Superpave Hot Mixed Asphalt (HMA) Actual
Daily Accomplishment from the Daily QA/QC Report (DQR) of the Site Area &
completed some as-builts & other miscellaneous projects.
Project-in-Charge : Engr. Nabeel H. Abu Sadah
v. SKILLS:
vi. HISTORY OF EMPLOYMENT & WORKING EXPERIENCE:
QA/QC Manager for Road Projects Department
Year : 2014 Projects
* QA/QC Department Mobile Laboratory for South Border Infrastructure Project
Asphalt/Aggregates Sections & Concrete/Soil Sections (Construction Drawings)
- March-11, 2014
* QA/QC Department Mobile Laboratory for South Border Infrastructure Project with Metal
Curing Tank Room (Proposed Layout Plan) - August-05, 2014
* Makkah Second Ring Road Project (Zoning, Foundation Plan, Footings, & Typical Road
Section Details) - June-28, 2014
* South Border Infrastructure Project (Kingdom of Saudi Arabia) Road Progress Monitoring
Report – Weekly & Monthly Cumulative & Combined Summary of Roads & Fence Activity
(Microsoft Excel Files) - August-31, 2014 to the January-31, 2016.
i. Area-1 (JIZAN) Region
ii. Area-2 (ASEER) Region
iii. Area-3A (NAJRAN) Region
iv. Area-3B (SHARURAH) Region
v. Area-4A (D. POINT) Region
vi. Area-4B (ARADAH) Region
* Abu Sadah Property Proposed Commercial Complex: Restaurant, Rentable Warehouses,
Medical Doctor Clinic/Offices, Proposed Showroom, & Proposed Hotel
2224 Ann Arbor, Oklahoma City, USA
(Proposed Conceptual Land Use Plan & Proposed Conceptual Site Development Plan)
- May-11, 2014
Project-in-Charge : Engr. Eric M. Guillermo, MSE
Planning Manager for Road Projects Department
Year : 2014 Projects
* ±721.04 SQ. M. South Border Infrastructure Project Office As-Built Layout Plan &
Organizational Chart - April-23, 2014
Project-in-Charge : Dr. Alyass Hosin
Technical Manager for Road Projects Department
Year : 2014 Projects
* Kingdom of Saudi Arabia Ministry of Communications Standard Reinforced Concrete Box
Culvert (R.C.B.C.) - April-05, 2014
i. Standard Single Cell Reinforced Concrete Box Culvert (R.C.B.C.)
ii. Standard Double Cell Reinforced Concrete Box Culvert (R.C.B.C.)
iii. Standard Reinforced Concrete Box Culvert (R.C.B.C.) Inlet/Outlet
Project-in-Charge : Engr. Bader Maskoun, M. Sc. CSLA, USA
Tendering Division for Road Projects Department
Year : 2014 Projects
* Makkah Mass Rail Transit Project Line-B & Line–C (UG Structural Layout) (Zoning of Tunnel
Type using AutoCAD & Google Earth software) - June-04, 2014
* Makkah Public Transport Program (MPTP) (Quantitative Analysis for Volume of Excavation
using Excel software) - June-24, 2014
* Makkah Metro Rail Transit Line-B & Line-C Architectural Finishes - November-03, 2014
i. MMRTC-SYS-00302-SY-417_Material Specifications for Underground Stations &
ii. MMRTC-SYS-00302-SY-416_Material Specifications for Elevated & At Grade Stations
iii. MMRT-PRB-DOC-CAR-ESTA-SY-90065-B Elevated Stations Architectural Drawings
iv. MMRT-PRB-DOC-CAR-USTA-SY-90062-A Underground Stations Arch’l. Drawings - A3
v. STATION TYPE-1 C03-N UNDERGROUND
* MPTP PHASE 1 – STATIONS Makkah Metro Line B & Line C Section - 1 (Architectural Design,
Fit-Out & Signage Material Specifications) - November-03, 2014
i. Makkah Metro Line B
* B02-E (Underground)
* B01b-E(Underground)
* B01-E (Elevated + Viaduct)
* B01-W (At Grade)
* B04-W (Underground)
ii. Makkah Metro Line C
* C05-N (TBM)
* C04-N (Underground)
* C03-N (Underground)
* C02-N (Interchange)
* C01-N (Underground)
* C01-S (Ramp + Viaduct)
* MPTP PHASE 1 – STATIONS Makkah Metro Line C Section - 2 (Architectural Design, Fit-Out
& Signage Material Specifications) - November-03, 2014
i. Makkah Metro Line B
* C02-S (Elevated)
* C03-S (Elevated)
* C03b-S (Elevated)
* C04-S (Elevated)
* C05-S (Elevated)
* C06-S (Elevated)
* C07-S (Elevated)
* C07b-S (Elevated)
* C08-S (Elevated)
Project-in-Charge : Engr. Talal Touqan
Project Director for Road Projects Department
Year : 2014 Projects
* ±19.78 SQ. M. South Border Infrastructure Project Conference Room As-Built Layout Plan
- April-23, 2014
Year : 2015 Projects
* ±193.82 SQ. M. Saudi Bin Ladin Group – Architecture & Building Construction Division:
Roads & Bridges Department As-Built Office Floor Layout Plan - February-02, 2014
* ±193.82 SQ. M. Saudi Bin Ladin Group – Architecture & Building Construction Division:
Roads & Bridges Department Proposed Office Floor Layout Plan (Scheme-1 & Scheme-2)
- February-02, 2014
Project-in-Charge : Engr. Ashraf Abed
Contract Manager for Road Projects Department
Year : 2014 Projects
* ±276 SQ. M. 4-Storey Family Apartment Proposed layout Plan (Scheme-1) - March-05, 2014
* ±312.5 SQ. M. TYPE-A: 2-Storey Residential with Roof Deck Proposed layout Plan
(Option-1 & Option-2) - March-05, 2014
***** E N D *****
Sub-Contractor : E. T. QUIAMBAO ENGINEERING SERVICES
#1 Wallnut Road, SPH Telephone No. (02) 948-6214
Makiling Street, Hacienda Heights Cellphone No. 09173195087
Brgy. Concepcion 2, Marikina City, Philippines
Department : Petron CTESG Design & Construction Group – Plant Engineering
Position : Design Assistant/AutoCAD Operator
Duration : July-25, 2011 to January-31, 2013
Job Description : Prepares Construction/Working Drawings of Oil Depot, Bulk Plant, & Bunkering Terminal by
the following Drafting Disciplines: Architectural, Structural, Electrical, Mechanical, Sanitary,
Driveway Concreting Plan, & Piping & Instrumentation Diagram (P. & I.D.) with necessary Bill
of Quantity (BoQ) & Bill of Materials (BoM). Conduct site visit & provide as-Built Plans.
Company/Client :
#151 Archen Technologies Building,
Brgy. Wack-Wack,
Mandaluyong City
Philippines (T 886-3888)
Project-in-Charge : Engr. Conrado C. Adorable
Project Engineer
Year : 2013 Projects
* Rosario Terminal as-Built Plans Project Consolidation 1998-2012 (PowerPoint Files)
– February-01, 2013
* Rosario Terminal Project Directory 1998-2012 (Excel Files) – January-17, 2013
Year : 2012 Projects
* Limay Depot Proposed New Bay-KL Tank Truck Loading Rack Expansion
– October-05, 2012
* Limay Depot Updated Layout Plan of ADO Product Tank 625, 623, 619, & 611
- October-03, 2012
* Limay Depot Proposed New Bay-KL & Bay-A1 Tank Truck Loading Rack Expansion
- November-20, 2013
* Navotas Depot Proposed New Tank Truck Loading Rack (TTLR) – August-25, 2012
* Abra de Ilog Depot Proposed Layout Plan – August-24, 2012
* Limay Depot Proposed New Tank Truck Loading Rack Canopy Extension – July-30, 2012
* Limay Depot Proposed New 20MB Tank-408 Receiving Nozzle & Pad Construction
– July-24, 2012
* Limay Depot Proposed New Ethanol Pump & Pump Slab Extension – July-19, 2012
* LimayDepot Proposed Jet A-1 Bottom Loading Layout Plan – July-16, 2012
* Limay Depot Proposed Driveway Concreting Layout Plan – July-16, 2012
* Iloilo Depot Proposed Upgrading of Fire-Fighting Facility – April-30, 2012
* Tagum Davao EEI Power Plant Proposed New Generic Depot – April-25, 2012
* Amlan Depot Proposed Layout Plan – February-08, 2012
* Bawing Depot Proposed Supervisor’s Residence – March-02, 2012
* Limay Depot Proposed New 5-Bay Tank Truck Loading Rack – February-02, 2012
* Bawing Depot Proposed Oil Depot Expansion – January-18, 2012
* Limay Depot Proposed New 5-Bay Tank Truck Loading Rack – January-10, 2012
* Limay Bulk Plant Proposed New 6-Bay Tank Truck Loading Rack – January-05, 2012
Year : 2011 Projects
* Davao Depot Proposed General Plant Layout for 2012 Construction – November-16, 2011
* Bawing Depot Oil Depot Expansion for 2013 Construction – October-05, 2011
* Romblon Depot Proposed Piping & Instrumentation Diagram – September-23, 2011
Project-in-Charge : Engr. Paul A. Cabrera
Project Engineer
Year : 2012 Projects
* Laguindigan Airport Proposed Aviation Facility - December-27, 2012
* Proposed New Generator Room & MCC Shed Generic Standard - November-05, 2012
* Manila North Harbor Proposed Interim Bunkering Terminal Revision (Scheme-5)
- October-08, 2012
* Manila North Harbor Proposed Interim Bunkering Terminal - June-27, 2012
* Palawan Depot Proposed New Generator Room & MCC Shed Relocation - August-23, 2012
* Palawan Depot New Generator Room & MCC Shed - April-25, 2012
* Palawan Depot Proposed Single Line Diagram - April-17, 2012
* Iligan Depot Proposed Office Building & Tank Track Inspection Platform - March-07, 2012
Year : 2011 Projects
* Palawan Depot Proposed LPG Receiving Line - November-09, 2011
* Navotas Depot Proposed Fire Hydrant Layout Plan - October-05, 2011
* Navotas Depot Proposed New MCC Shed - September-15, 2011
* Navotas Depot Existing & Proposed Layout Plan - September-15, 2011
* Tagoloan Depot Proposed MCC Shed Expansion - July-18, 2011
Project-in-Charge : Engr. Catherine D. Jose
Project Engineer
Year : 2012 Projects
* San Fernando Depot Installation of New CCTV System - July-20, 2012
* Batangas Terminal Proposed New Oil Spill Equipment Shed Renovation - May-02, 2012
* Batangas Terminal Proposed Sprinkler Layout Plan - March-01, 2012
* Batangas Terminal Proposed Filling Plant Power & Lighting Layout Plan - March-01, 2012
* Batangas Terminal Proposed P. & I. D. for Fire Protection System - February-16, 2012
* Poro Depot Proposed P. & I. D. for Fire Protection System - February-15, 2012
* Poro Depot Proposed Sprinkler Layout Plan - February-15, 2012
* Poro Depot Proposed tank Truck Loading Rack Power & Lighting Layout Plan
- February-15, 2012
* Subic Techno Park Petron Refinery Proposed QC laboratory Room Renovation
- January-25, 2012
* Subic Techno Park Petron Refinery Proposed Driver's Lounge - January-25, 2012
* Subic Techno Park Petron Refinery Proposed ISO Tank Loading Canopy Extension
- January-21, 2012
* Subic Techno Park Petron Refinery Proposed Drum Filling Area Canopy Extension
- January-21, 2012
* Gasul Pasig Terminal Installation of New CCTV System - January-02, 2012
Year : 2011 Projects
* Jocasp Depot Installation of New CCTV System - September-22, 2011
Project-in-Charge : Engr. Ricardo R. Daclan Jr.
Project Engineer
Year : 2012 Projects
* Aparri Depot Proposed P. & I. D. for Mini-LPG Filling Plant - February-17, 2012
Year : 2011 Projects
* Calbeg, Malasiqui Pangasinan Proposed Mini-LPG Refilling Plant - October-19, 2011
* San Vicente, San Pedro Laguna Proposed Mini- LPG Refilling Plant - October-18, 2011
* Solano, Nueva Vizcaya Proposed Mini-LPG Refilling Plant - September-29, 2011
Project-in-Charge : Jason D. Soberano
Project Engineer
Year : 2012 Projects
* Bawing Depot Proposed Fire Hydrant R/S Pipeline Layout Plan - February-16, 2012
Year : 2011 Projects
* Davao Depot Proposed General Plant Layout - November-16, 2011
Project-in-Charge : Jhomar G. Azarcon
Project Engineer
Year : 2012 Projects
* Navotas Depot Proposed New 3-Bay Concrete Tank Truck Loading Rack - March-29, 2012
Project-in-Charge : Engr. Edelino T. Quiambao
Proprietor
Year : 2013 Projects
* Site Inspection at Various Service Stations 2013 (P-Shop Pharma Plus) - March-11, 2013
i. Alma Aquino Service Station: Commonwealth Ave., North Fairview, Q. C.
ii. Corral Service Station: East Ave., Cor. BIR Road, Piñaha, Q. C.
iii. Dizon Service Station: #53 Kamuning Cor., Scout Ybardolaza, Kamuning, Q. C.
iv. Favila Service Station: Cong. Ave., Cor. Virginia St., Proj. 6, Brgy. Bahay Toro, Q. C.
v. Casares Service Station: West Avenue, Cor. Del Monte, Q. C.
vi. Calalay Service Station: Timog Morato Cor. Tomas Morato, Q.C.
Company/Client :
PETROTECH MPJ, Incorporated
"Bridging Gaps Between You and Your Markets"
No. 22 VRCC Rd. Veterans Center, Western Bicutan, Taguig City
Tel. No. 839-2117 Fax No. 839-2094
Project-in-Charge : Engr. Edelino T. Quiambao
Proprietor
Year : 2012 Projects
* Consolacion Cebu Proposed Oil Depot - July-27, 2012
* Linao, Ormoc Leyte Proposed Mini Oil Depot Layout Plan - July-13, 2012
* Taytay Palawan EON Petroleum Inc. Proposed Mini Oil Depot - January-09, 2012
Company/Client : Rubite Trading & General Services
9 10-A Provincial Road Matungao, Bulakan, Bulacan
Telefax (044) 7922521 Tel (044) 7922889
Project-in-Charge : Engr. Edelino T. Quiambao
Proprietor
Year : 2012 Projects
* Navotas Depot Proposed New Service Pipeline Layout Plan - August-22, 2012
Company/Client : SAVIOR CONSTRUCTION
OFFICES: 251 TUMANA, STA. MARIA, BULACAN
CELL NO.: (0916) 939-6660
TELEFAX: (044) 641-1729
E-MAIL: saviorcons@yahoo.com
Project-in-Charge : Engr. Edelino T. Quiambao
Proprietor
Year : 2013 Projects
* As-Built Plans of Car Tricycle Awning Pump Island - June-03, 2013
* Iligan Depot Conversion of Tank-6 (ADO) as-Built Plans - May-28, 2013
* Bawing Depot as-Built Plans of Tank-1 (X-93), Tank-2 (Kero), & Tank-3 (X-93)
- February-18, 2013
Year : 2012 Projects
* Ormoc Bulk Plant as-Built Plans of 10,000 USG Ethanol Tank - December-17, 2012
***** E N D *****
Sub-Contractor : BJ & G Consultancy Inc.
San Isidro, Baao, Camarines Sur, Philippines
Contact No.: 09274736531
E-mail Address: Gabriel_adan@yahoo.com
Department : Petron CTESG Design & Construction Group – Plant Engineering
Position : Design Assistant/AutoCAD Operator
Duration : July-25, 2012 to January-31, 2013
Job Description : Prepares Construction/Working Drawings of Mini-LPG Refilling Plant by the following
Drafting Disciplines: Architectural, Structural, Electrical, Mechanical, Sanitary, Driveway
Concreting Plan, & Piping & Instrumentation Diagram (P. & I.D.) with necessary Bill of
Quantity (BoQ) & Bill of Materials (BoM). Conduct site visit & provide as-Built Plans.
Company/Client :
#151 Archen Technologies Building,
Brgy. Wack-Wack,
Mandaluyong City
Philippines (T 886-3888)
Project-in-Charge : Mr. Gabriel M. Adan
Proprietor
Year : 2012 Projects
* Manila Harbor Centre Proposed New Administration Building - March-31, 2012
Year : 2011 Projects
* El Nido Palawan Proposed Mini-LPG Refilling Plant - October-24, 2011
Company/Client : PTT Philippines Corporation
32nd Floor LKG Bldg., Ayala Avenue, Makati City
Tel. Nos. 884-81-55 Fax No. 884-81-50
Department : Engineering Department
Position : Design Assistant/AutoCAD Operator
Duration : August-01, 2012 to February-28, 2013
Job Description : Prepares Construction/Working Drawings of PTT Gasoline Station by the following Drafting
Disciplines: Architectural, Structural, Electrical, Mechanical, Sanitary, & Driveway Concreting
Plan.
Project-in-Charge : Engr. Joel M. Tolosa
Project Engineer
Mr. Gabriel M. Adan
Proprietor
Year : 2013 Projects
* PTT Mabalacat Proposed Gasoline Station - February-11, 2013
* PTT Clark Proposed Trellis Details - January-21, 2011
* PTT Regalado Proposed Gasoline Station - January-07, 2013
* PTT Molino-2 Proposed Extension - January-04, 2013
Year : 2012 Projects
* PTT Cabanatuan Revision-1 - December-05, 2012
* PTT Bulacan Proposed Gasoline Station - October-27, 2012
* PTT Villasis Proposed Gasoline Station - October-15, 2012
* PTT San Marcelino Proposed Gasoline Station - September-25, 2012
* PTT Taytay Proposed BSLO Layout Plan - September-25, 2012
* PTT KM 18 East Service Road Proposed Gasoline Station - September-13, 2013
* PTT Clark Proposed Gasoline Station - August-27, 2013
* PTT San Jose Proposed Road Shoulder - August-25, 2012
* PTT Magalang Proposed BSLO Layout Plan (Sch.-2) - August-16, 2012
* PTT Concepcion Proposed BSLO Layout Plan (Sch.-2) - August-15, 2012
* PTT Congressional Avenue Proposed BSLO Layout Plan (Sch.-2) - August-14, 2012
* PTT Bantayan-2 Proposed Gasoline Station - August-08, 2012
***** E N D *****
Company/Client : EON PETROLEUM INCORPORATED
2207 TYCOON CENTER BUIILDING,
PEARL DRIVE ORTIGAS, PASIG CITY
Project-in-Charge : Mr. Gabriel M. Adan
Proprietor
Year : 2013 Projects
* EON Lite Prototype Bulilit Station (PowerPoint Files) - January-07, 2013
Year : 2012 Projects
* EON Muñoz Nueva Ecija Proposed New Service Station - September-15, 2012
Client : Mr. Gigi Santos
Project-in-Charge : Mr. Gabriel M. Adan
Proprietor
Year : 2012 Projects
* 2-Storey Residential as-Built Layout Plan - September-13, 2012
***** E N D *****
Sub-Contractor : C. JANSEN
TECHNICAL SERVICES
Marina Ave., St. Joseph Subdivision,
Bayan, Orani, Bataan – 2112 Philippines
CP: 09999904720
Department : Petron CTESG Design & Construction Group – Design Group
Position : Junior Architect/AutoCAD Operator
Duration : March-05, 2010 to May-31, 2011
Job Description : Prepares Construction/Working Drawings of Petron Service Station, Micro-Filling Station
(MFS), & Dealer-Owned Filling Station (DOFS) by the following Drafting Disciplines:
Architectural, Structural, Electrical, Mechanical, Sanitary, & Driveway Concreting Plan with
Site Visiting & provide as-Built Plans.
Company/Client :
#151 Archen Technologies Building,
Brgy. Wack-Wack,
Mandaluyong City
Philippines (T 886-3888)
Project-in-Charge : Arch. Enrico M. Santos
Head Architect
Year : 2011 Projects
* Proposed Axcess Sports Bar & KTV - July-08, 2011
* PEC-1 Proposed Expansion (Phase-2) Lakbay Alalay - March-31, 2011
* RLT's Residences Proposed Guest Room & Bedroom-1 Renovation - February-02, 2011
Project-in-Charge : Arch. Dreyden B. Villoso
Architect
Year : 2011 Projects
* Proposed Service Station Building Layout (Generic) - April-14, 2011
* PEC-1 NLEX Northbound Proposed Expansion - March-25, 2011
Project-in-Charge : Arch. Jane Q. Ramirez
Architect
Year : 2011 Projects
* Micro-Filling Station (Petron Bulilit) report 2011(Excel Files) – April-30, 2011
* Proposed COSS Mendoza Office & Sales Room Layout, Cebu City - April-20, 2010
* Proposed New Dealer-Owned Filling Station: M. Highway, Quezon - April-14, 2011
* Proposed New Dealer-Owned Filling Station: San Roque, Pasay City - April-14, 2011
* Proposed New Dealer-Owned Filling Station: San Antonio, Quezon - April-14, 2011
* Proposed New Dealer-Owned Filling Station: Meycauyan, Bulacan - April-05, 2011
* Proposed Dealer-Owned Filling Station: Urdaneta Pangasinan - April-04, 2011
* Proposed New Dealer-Owned Filling Station: R & E Taxi - March-14, 2011
* Proposed Dealer-Owned Filling Station: Regalado, Quezon City - February-24, 2011
* Proposed CODO BSLO Request: Evangelista, Teodoro - February-23, 2011
Year : 2010 Projects
* Proposed New Dealer-Owned Filling Station: Baguio City - November-30, 2010
* Proposed New Single Pump Island Station: Calaca, Batangas - November-19, 2010
* Proposed New Service Station PMC Wachovia Angeles, Pampanga - November-03, 2010
* Proposed New Work Bench Details - November-02, 2010
* Proposed New Dealer-Owned Filling Station: Binalonan, Pangasinan - October-20, 2010
* Proposed New Dealer-Owned Filling Station: San Juan, La Union - September-13, 2010
* Proposed Petron Clinic San Miguel Corporation, Mandaluyong City - September-09, 2010
* Proposed New Two Pump Island Filling Station: Nabua, Camarines Sur - August-25, 2010
* Proposed Micro-Filling Station (Petron Bulilit) Gasbar Generic - July-24, 2010
* Proposed Service Station Major Rehab, Intramuros, Manila - July-23, 2010
* Proposed New Dealer-Owned Filling Station: San Carlos, Pangasinan - June-28, 2010
* Proposed New Service Station EDSA-NIA, Quezon City - May-24, 2010
* Micro Filling Station (Petron Bulilit) Enhancement - April-21, 2010
i. MFS Type - 1: MFS-1a & MFS-1b
ii. MFS Type - 2: MFS-2a & MFS-2b
iii. MFS Type - 3: MFS-3a & MFS-3b
iv. MFS Type - 4z
v. MFS Type - 5
vi. MFS Type - 6
vii. MFS Type - Gasbar
***** E N D *****
Consultant : ALEJANDRO SO MANOTA
& ASSOCIATES
ARCHITECTS CONSULTANTS
BLK. 8 LOT 31, SAN PEDRO SUBDIVISION 7 TEL. 4261379
SAN BARTOLOME, NOVALICHES, Q.C. PHILS. CELL. 0920-5965347
Department : In-House Design Office Address:
Blk. 8 Lot-31, San Pedro Subdivision 7, San Bartolome, Novaliches, Q.C. Philippines
Position : AutoCAD Operator
Duration : August, 2009 to January, 2010
Job Description : Prepares Construction/Working Drawings of Standard Bank Layout Plan of Banco de Oro
(BDO), Bank of the Philippine Island (BPI), & EastWest Bank by the following Drafting
Disciplines: Architectural, Structural, Electrical, Mechanical, & Sanitary. Conduct site visit &
provide as-Built Plans.
Company/Client : BDO Corporate Center
7899 Makati Avenue,
Makati City, Philippines
Project-in-Charge : Arch. Alejandro So Manota
Architect/Proprietor
Year : 2010 Projects
* BDO - San Pablo Branch Interior Renovation - January, 2010
Year : 2009 Projects
* BDO - Marikina Branch (Transfer Site), Conception Marikina - November-22, 2009
* BDO - Ayala Alabang Madrigal Branch, Zapote Rd., Muntinlupa, City - November, 2009
* BDO - Libis Branch, Acropolis, Libis, Quezon City - July-13, 2009
Company/Client : 6768Ayala Avenue Cor. Paseo de Roxas Ave.,
Makati Central Business District, Makati City,
Metro Manila, Philippines
Project-in-Charge : Arch. Alejandro So Manota
Architect/Proprietor
Year : 2009 Projects
* BPI - Cainta Saint Anthony, Ortigas Ave. Ext., Cainta, Rizal - November, 2009
Company/Client : 20/F PBCom Tower,
6795 Ayala Avenue Cor. V.A. Rufino St.,
Salcedo Village, Makati City,
Metro Manila, Philippines
Project-in-Charge : Arch. Alejandro So Manota
Architect/Proprietor
Year : 2009 Projects
* EastWest Bank West Avenue Branch Iterior Renovation - August-10, 2009
* EastWest Bank T. Alonzo Branch Interior Construction - June, 2009
Company/Client : Mr. & Mrs. Fortaleza
Year : 2009 Projects
* Two Storey Residence Renovation & Expansion - August, 2009
***** E N D *****
vii. CHARACTER REFERENCES:
Reference No.1 :
2nd
Floor Obeikan Bookstore Building
Prince Sultan Road, Jeddah, Kingdom of Saudi Arabia
Contact Person : Engr. Nabeel H. Abu Sadah
QA/QC Manager for Road Projects Department
P.O. Boxn11789 Jeddah 21463 Saudi Arabia
Tel.: 6927105 Ext.
Fax: 6922198
Mobile: +966 540925900
E-mail: nabeels@sbgabc.com & abusada61@hotmail.com
Contact Person : Engr. Eric M. Guillermo, MSE
Planning Manager for Road Projects Department
P.O. Box 11789 Jeddah 21463 Saudi Arabia
Tel.: 012-6927105 Ext. 256
Fax: 012-6163979 Ext. 8135
Mobile: +966 569056350
E-mail: eguillermo@SBGABC.COM
Reference No.2 : E. T. QUIAMBAO ENGINEERING SERVICES
#1 Wallnut Road, SPH Telephone No. (02) 948-6214
Makiling Street, Hacienda Heights Cellphone No. 09173195087
Brgy. Concepcion 2, Marikina City, Philippines
Contact Person : Engr. Edelino T. Quiambao
Proprietor/Owner
Reference No.3 : BJ & G Consultancy Inc.
San Isidro, Baao, Camarines Sur, Phillipines
Contact No.: 09274736531
E-mail Address: Gabriel_adan@yahoo.com
Contact Person : Mr. Gabriel M. Adan
Proprietor/Owner
Reference No.4 : C. JANSEN
TECHNICAL SERVICES
Marina Ave., St. Joseph Subdivision,
Bayan, Orani, Bataan – 2112 Philippines
CP: 09999904720
Contact Person : Mr. Rex A. Peña
Proprietor/Owner
"I hereby certify that the above information is true and correct.
To the best of my personality and to the extent of my knowledge and belief"
Arch. Mauricio P. Cabanillas Jr.
Signature

CURRICULUM VITAE with SIGNATURE - UPDATED 11.29.16

  • 1.
    ORGANIZATION YEAR ATTENDED SaudiCouncil of Engineers – SCE 2014 – 2017 Architectural Engineer Associate Degree (Previous Working Visa Category) United Architects of the Philippines - IAPOA 2012 – Present The Integrated and Accredited Professional Organization of Architects United Architects of the Philippines – Pasig Chapter 2012 – Present The Integrated and Accredited Professional Organization of Architects SCHOOL YEAR ATTENDED TERTIARY/COLLEGE: Polytechnic University of the Philippines (Mabini Campus) 2002 - 2009 Anonas St., Sta. Mesa Manila, Philippines Bachelor of Science in Architecture and Fine Arts SECONDARY/HIGH SCHOOL: Rizal High School (Main Campus) 1998 - 2002 Dr. Sixto Antonio Avenue St., Brgy. Caniogan, Pasig City, Philippines PRIMARY/ELEMENTARY: Bagong Diwa Elementary School 1992 – 1998 #2244 Linceo St. Pandacan Manila, Philippines *ARCHITECT/DESIGN ASSISTANT Creative + Productive + Hard Working + Multi-Tasking + Observant PRC Reg. No. : 29661 Date Issue : July-06, 2012 Date Expired : October-12, 2019 UAP No. : 25914 PTR No. : 1687924 Place Issue : Pasig City Hall, Pasig City, Metro Manila Philippines Home Address : #0435 Baltazar St., Brgy. Sto. Tomas, Pasig City, Metro Manila, Philippines Contact No. : +63 995 4835988 (Globe) +63 921 4149574 (Smart) Skype Account : mauipogi_101285 E-mail : mauriciojr.cabanillas@yahoo.com Career Objective: “To pursue a professional challenging Architectural & Engineering working experience in any Architectural/Engineering Firm to help broaden my experience in the related field & enhances my knowledge & professional growth in the world of Architecture, Construction, & Oil & Gas Industry.” Architect MAURICIO P. CABANILLAS JR. i. AFFILIATION/MEMBERSHIP ORGANIZATION: ii. EDUCATIONAL BACKGROUND:
  • 2.
    Birthday : October– 12, 1985 Birth Place : Giporlos, Eastern Samar, Philippines Age : 31 Sex : Male Civil Status : Single Height : 5’4” (162 cm) Weight : 145 lbs. (65 kilos) Religion : Roman Catholic Nationality : Filipino Language Spoken : English, Tagalog & Waray Father’s Name : Mr. Mauricio O. Cabanillas Occupation : Master Teacher II (Bagong Diwa Elementay School, Pandacan Manila, Philippines) Mother’s Name : Mrs. Winefreda P. Cabanillas Occupation : Housewife Siblings : Patty P. Cabanillas Occupation : Sales Representative (Duty Free Mall - Dubai, United Arab Emirates) Person to Contact In Case of Emergency : Mr. Mauricio O. Cabanillas Relationship : Father Address : #0435 Baltazar St., Brgy. Sto. Tomas Pasig City, Philippines Contact No’s. : +63 949 7648465 / 7470367 * United Architects of the Philippines – Pasig Chapter The Integrated and Accredited Professional Organization of Architects PROJECT BLAD: “Blood Letting and Data Banking cum Motorcycle Event” August-26, 2012, Sunday @ Rizal High School (Main Campus) Pasig City * United Architects of the Philippines – Pasig Chapter The Integrated and Accredited Professional Organization of Architects INDUCTION OF OFFICERS FY: 2012-2013 & New Member Architects Thanks Giving Night September-20, 2012, Thursday @ CW HOME DEPOT Makati Events Hall * AUTODESK 3DSMAX 2011 (For Architectural Design) MICROCADD TECHNOLOGIES Co., Inc. Main Branch: Cubao July, 2011 (9 hr. /15 hr.) @ 5th Flr., Doña Consolacion Bldg. 602 General Santos Ave., Cubao, Q. C. * United Architects of the Philippines – Graduate Auxiliary 101 The Duly Recognized Graduate Auxiliary of the United Architects of the Philippines BOARDing PASS: “Destination June 2011 ALE” May-08, 2011, Sunday @ Teatro Arkitekto, UAP Headquarters, Scout Rallos, Tomas Morato, Q. C. * Exploring the Empowering Spirit of Art and Architecture” February-03 & 04, 2009 @ P.U.P. Mabini Campus, Sta. Mesa, Manila * “Church Architecture in Filipino Settings” Arsobispado, Intramuros, Manila * “Creative Green Architecture and Design: The Cutting Edge” College of Engineering Theater, University of the Philippines, Diliman, Q.C. * “The Science of Feng Shui and Architectural Design” January-28, 2004 @ College of Engineering Theater, University of the Philippines, Diliman, Q.C. * Nestle Nido: “Munting Daliri Father & Child Art Workshop” Batch 1997, @ Museong Pambata, Roxas Boulevard, Taft Manila * Nestle Nido: “Munting Daliri Mother & Child Art Workshop” Batch 1995, @ Fort Santiago, Intramuros, Manila iii. PERSONAL BACKGROUND: iv. TRAININGS & SEMINARS ATTENDED:
  • 3.
    1. Software’s :Auto CAD 2014-2016 Version Sketch-Up 3D Rendering with V-Ray & i-Render Photoshop CS5 MS Office 2010 Proficient 2. Knowledge : Aviation Facility & Berthing Facility Oil Depot Layout Plan, Bulk Plant Layout Plan, & Bunkering Terminal Layout Plan LPG Filling Plant Layout Plan with Piping & Instrumentation Diagram (P. & I. D.) Gasoline Service Station (S/S) Layout Plan Bulilit-Station/Micro-Filling Station (MFS) & Dealer-Owned Filling Station (DOFS) Prepared Construction/Shop Drawings by the following Drafting Disciplines: * Architectural * Structural * Electrical * Mechanical * Sanitary/Plumbing * Driveway Concreting * Piping & Instrumentation Diagram (P. & I. D.) Residential Houses Designing and Rendering Prepared Estimate Bill of Materials (BOM) & Bill of Quantity (BOQ) Site Visiting & preparing as-Built Plans Designing of Roads and Bridges with Typical Sections of Foundation and Footing Details Northing & Easting of Coordinates & reflect it in Google Earth as KMZ Files Daily, Weekly & Monthly Cumulative Roads Progress Monitoring 3. Other Skills : Manual Drafting & Rendering, Scale Modeling, Painting, & Mosaic Rendering 4. Self Attributes : Good Oral & Written Communication & Interpersonal Skills Self-starter and self-motivated Initiative and organized Ensure that project deadlines are met and able to Multi Task Capable of working under pressure to meet tight submission schedules Willing to work overtime to meet the schedule completion dates Capable of scheduling and managing own work load plus others A Team player Contractor : 2nd Floor Obeikan Bookstore Building Prince Sultan Road, Jeddah, Kingdom of Saudi Arabia Department : Architecture & Building Construction Division – Road Projects Department Position : QA/QC Department Draftsman Duration : January-29, 2014 to January-31, 2016 (2 years) Job Description : Designing of Roads and Bridges with Typical Sections of Foundation and Footing Details for Makkah Second Ring Road Project by the following Drafting Disciplines: Architectural & Structural. Prepares Construction/Shop Drawings of QA/QC Department Mobile Laboratory for the South Border Infrastructure Project (SBIP). Provide Weekly Quantities of Road Progress Monitoring Report based on daily Request for Inspection (RFI), Request for Testing (RFT), & Test Report Submittal (TRS), etc. Provide Superpave Hot Mixed Asphalt (HMA) Actual Daily Accomplishment from the Daily QA/QC Report (DQR) of the Site Area & completed some as-builts & other miscellaneous projects. Project-in-Charge : Engr. Nabeel H. Abu Sadah v. SKILLS: vi. HISTORY OF EMPLOYMENT & WORKING EXPERIENCE:
  • 4.
    QA/QC Manager forRoad Projects Department Year : 2014 Projects * QA/QC Department Mobile Laboratory for South Border Infrastructure Project Asphalt/Aggregates Sections & Concrete/Soil Sections (Construction Drawings) - March-11, 2014 * QA/QC Department Mobile Laboratory for South Border Infrastructure Project with Metal Curing Tank Room (Proposed Layout Plan) - August-05, 2014 * Makkah Second Ring Road Project (Zoning, Foundation Plan, Footings, & Typical Road Section Details) - June-28, 2014 * South Border Infrastructure Project (Kingdom of Saudi Arabia) Road Progress Monitoring Report – Weekly & Monthly Cumulative & Combined Summary of Roads & Fence Activity (Microsoft Excel Files) - August-31, 2014 to the January-31, 2016. i. Area-1 (JIZAN) Region ii. Area-2 (ASEER) Region iii. Area-3A (NAJRAN) Region iv. Area-3B (SHARURAH) Region v. Area-4A (D. POINT) Region vi. Area-4B (ARADAH) Region * Abu Sadah Property Proposed Commercial Complex: Restaurant, Rentable Warehouses, Medical Doctor Clinic/Offices, Proposed Showroom, & Proposed Hotel 2224 Ann Arbor, Oklahoma City, USA (Proposed Conceptual Land Use Plan & Proposed Conceptual Site Development Plan) - May-11, 2014 Project-in-Charge : Engr. Eric M. Guillermo, MSE Planning Manager for Road Projects Department Year : 2014 Projects * ±721.04 SQ. M. South Border Infrastructure Project Office As-Built Layout Plan & Organizational Chart - April-23, 2014 Project-in-Charge : Dr. Alyass Hosin Technical Manager for Road Projects Department Year : 2014 Projects * Kingdom of Saudi Arabia Ministry of Communications Standard Reinforced Concrete Box Culvert (R.C.B.C.) - April-05, 2014 i. Standard Single Cell Reinforced Concrete Box Culvert (R.C.B.C.) ii. Standard Double Cell Reinforced Concrete Box Culvert (R.C.B.C.) iii. Standard Reinforced Concrete Box Culvert (R.C.B.C.) Inlet/Outlet Project-in-Charge : Engr. Bader Maskoun, M. Sc. CSLA, USA Tendering Division for Road Projects Department Year : 2014 Projects * Makkah Mass Rail Transit Project Line-B & Line–C (UG Structural Layout) (Zoning of Tunnel Type using AutoCAD & Google Earth software) - June-04, 2014 * Makkah Public Transport Program (MPTP) (Quantitative Analysis for Volume of Excavation using Excel software) - June-24, 2014 * Makkah Metro Rail Transit Line-B & Line-C Architectural Finishes - November-03, 2014 i. MMRTC-SYS-00302-SY-417_Material Specifications for Underground Stations & ii. MMRTC-SYS-00302-SY-416_Material Specifications for Elevated & At Grade Stations iii. MMRT-PRB-DOC-CAR-ESTA-SY-90065-B Elevated Stations Architectural Drawings iv. MMRT-PRB-DOC-CAR-USTA-SY-90062-A Underground Stations Arch’l. Drawings - A3 v. STATION TYPE-1 C03-N UNDERGROUND * MPTP PHASE 1 – STATIONS Makkah Metro Line B & Line C Section - 1 (Architectural Design, Fit-Out & Signage Material Specifications) - November-03, 2014
  • 5.
    i. Makkah MetroLine B * B02-E (Underground) * B01b-E(Underground) * B01-E (Elevated + Viaduct) * B01-W (At Grade) * B04-W (Underground) ii. Makkah Metro Line C * C05-N (TBM) * C04-N (Underground) * C03-N (Underground) * C02-N (Interchange) * C01-N (Underground) * C01-S (Ramp + Viaduct) * MPTP PHASE 1 – STATIONS Makkah Metro Line C Section - 2 (Architectural Design, Fit-Out & Signage Material Specifications) - November-03, 2014 i. Makkah Metro Line B * C02-S (Elevated) * C03-S (Elevated) * C03b-S (Elevated) * C04-S (Elevated) * C05-S (Elevated) * C06-S (Elevated) * C07-S (Elevated) * C07b-S (Elevated) * C08-S (Elevated) Project-in-Charge : Engr. Talal Touqan Project Director for Road Projects Department Year : 2014 Projects * ±19.78 SQ. M. South Border Infrastructure Project Conference Room As-Built Layout Plan - April-23, 2014 Year : 2015 Projects * ±193.82 SQ. M. Saudi Bin Ladin Group – Architecture & Building Construction Division: Roads & Bridges Department As-Built Office Floor Layout Plan - February-02, 2014 * ±193.82 SQ. M. Saudi Bin Ladin Group – Architecture & Building Construction Division: Roads & Bridges Department Proposed Office Floor Layout Plan (Scheme-1 & Scheme-2) - February-02, 2014 Project-in-Charge : Engr. Ashraf Abed Contract Manager for Road Projects Department Year : 2014 Projects * ±276 SQ. M. 4-Storey Family Apartment Proposed layout Plan (Scheme-1) - March-05, 2014 * ±312.5 SQ. M. TYPE-A: 2-Storey Residential with Roof Deck Proposed layout Plan (Option-1 & Option-2) - March-05, 2014 ***** E N D ***** Sub-Contractor : E. T. QUIAMBAO ENGINEERING SERVICES
  • 6.
    #1 Wallnut Road,SPH Telephone No. (02) 948-6214 Makiling Street, Hacienda Heights Cellphone No. 09173195087 Brgy. Concepcion 2, Marikina City, Philippines Department : Petron CTESG Design & Construction Group – Plant Engineering Position : Design Assistant/AutoCAD Operator Duration : July-25, 2011 to January-31, 2013 Job Description : Prepares Construction/Working Drawings of Oil Depot, Bulk Plant, & Bunkering Terminal by the following Drafting Disciplines: Architectural, Structural, Electrical, Mechanical, Sanitary, Driveway Concreting Plan, & Piping & Instrumentation Diagram (P. & I.D.) with necessary Bill of Quantity (BoQ) & Bill of Materials (BoM). Conduct site visit & provide as-Built Plans. Company/Client : #151 Archen Technologies Building, Brgy. Wack-Wack, Mandaluyong City Philippines (T 886-3888) Project-in-Charge : Engr. Conrado C. Adorable Project Engineer Year : 2013 Projects * Rosario Terminal as-Built Plans Project Consolidation 1998-2012 (PowerPoint Files) – February-01, 2013 * Rosario Terminal Project Directory 1998-2012 (Excel Files) – January-17, 2013 Year : 2012 Projects * Limay Depot Proposed New Bay-KL Tank Truck Loading Rack Expansion – October-05, 2012 * Limay Depot Updated Layout Plan of ADO Product Tank 625, 623, 619, & 611 - October-03, 2012 * Limay Depot Proposed New Bay-KL & Bay-A1 Tank Truck Loading Rack Expansion - November-20, 2013 * Navotas Depot Proposed New Tank Truck Loading Rack (TTLR) – August-25, 2012 * Abra de Ilog Depot Proposed Layout Plan – August-24, 2012 * Limay Depot Proposed New Tank Truck Loading Rack Canopy Extension – July-30, 2012 * Limay Depot Proposed New 20MB Tank-408 Receiving Nozzle & Pad Construction – July-24, 2012 * Limay Depot Proposed New Ethanol Pump & Pump Slab Extension – July-19, 2012 * LimayDepot Proposed Jet A-1 Bottom Loading Layout Plan – July-16, 2012 * Limay Depot Proposed Driveway Concreting Layout Plan – July-16, 2012 * Iloilo Depot Proposed Upgrading of Fire-Fighting Facility – April-30, 2012 * Tagum Davao EEI Power Plant Proposed New Generic Depot – April-25, 2012 * Amlan Depot Proposed Layout Plan – February-08, 2012 * Bawing Depot Proposed Supervisor’s Residence – March-02, 2012 * Limay Depot Proposed New 5-Bay Tank Truck Loading Rack – February-02, 2012 * Bawing Depot Proposed Oil Depot Expansion – January-18, 2012 * Limay Depot Proposed New 5-Bay Tank Truck Loading Rack – January-10, 2012 * Limay Bulk Plant Proposed New 6-Bay Tank Truck Loading Rack – January-05, 2012 Year : 2011 Projects * Davao Depot Proposed General Plant Layout for 2012 Construction – November-16, 2011 * Bawing Depot Oil Depot Expansion for 2013 Construction – October-05, 2011 * Romblon Depot Proposed Piping & Instrumentation Diagram – September-23, 2011 Project-in-Charge : Engr. Paul A. Cabrera Project Engineer
  • 7.
    Year : 2012Projects * Laguindigan Airport Proposed Aviation Facility - December-27, 2012 * Proposed New Generator Room & MCC Shed Generic Standard - November-05, 2012 * Manila North Harbor Proposed Interim Bunkering Terminal Revision (Scheme-5) - October-08, 2012 * Manila North Harbor Proposed Interim Bunkering Terminal - June-27, 2012 * Palawan Depot Proposed New Generator Room & MCC Shed Relocation - August-23, 2012 * Palawan Depot New Generator Room & MCC Shed - April-25, 2012 * Palawan Depot Proposed Single Line Diagram - April-17, 2012 * Iligan Depot Proposed Office Building & Tank Track Inspection Platform - March-07, 2012 Year : 2011 Projects * Palawan Depot Proposed LPG Receiving Line - November-09, 2011 * Navotas Depot Proposed Fire Hydrant Layout Plan - October-05, 2011 * Navotas Depot Proposed New MCC Shed - September-15, 2011 * Navotas Depot Existing & Proposed Layout Plan - September-15, 2011 * Tagoloan Depot Proposed MCC Shed Expansion - July-18, 2011 Project-in-Charge : Engr. Catherine D. Jose Project Engineer Year : 2012 Projects * San Fernando Depot Installation of New CCTV System - July-20, 2012 * Batangas Terminal Proposed New Oil Spill Equipment Shed Renovation - May-02, 2012 * Batangas Terminal Proposed Sprinkler Layout Plan - March-01, 2012 * Batangas Terminal Proposed Filling Plant Power & Lighting Layout Plan - March-01, 2012 * Batangas Terminal Proposed P. & I. D. for Fire Protection System - February-16, 2012 * Poro Depot Proposed P. & I. D. for Fire Protection System - February-15, 2012 * Poro Depot Proposed Sprinkler Layout Plan - February-15, 2012 * Poro Depot Proposed tank Truck Loading Rack Power & Lighting Layout Plan - February-15, 2012 * Subic Techno Park Petron Refinery Proposed QC laboratory Room Renovation - January-25, 2012 * Subic Techno Park Petron Refinery Proposed Driver's Lounge - January-25, 2012 * Subic Techno Park Petron Refinery Proposed ISO Tank Loading Canopy Extension - January-21, 2012 * Subic Techno Park Petron Refinery Proposed Drum Filling Area Canopy Extension - January-21, 2012 * Gasul Pasig Terminal Installation of New CCTV System - January-02, 2012 Year : 2011 Projects * Jocasp Depot Installation of New CCTV System - September-22, 2011 Project-in-Charge : Engr. Ricardo R. Daclan Jr. Project Engineer Year : 2012 Projects * Aparri Depot Proposed P. & I. D. for Mini-LPG Filling Plant - February-17, 2012 Year : 2011 Projects * Calbeg, Malasiqui Pangasinan Proposed Mini-LPG Refilling Plant - October-19, 2011 * San Vicente, San Pedro Laguna Proposed Mini- LPG Refilling Plant - October-18, 2011 * Solano, Nueva Vizcaya Proposed Mini-LPG Refilling Plant - September-29, 2011 Project-in-Charge : Jason D. Soberano Project Engineer Year : 2012 Projects * Bawing Depot Proposed Fire Hydrant R/S Pipeline Layout Plan - February-16, 2012 Year : 2011 Projects * Davao Depot Proposed General Plant Layout - November-16, 2011
  • 8.
    Project-in-Charge : JhomarG. Azarcon Project Engineer Year : 2012 Projects * Navotas Depot Proposed New 3-Bay Concrete Tank Truck Loading Rack - March-29, 2012 Project-in-Charge : Engr. Edelino T. Quiambao Proprietor Year : 2013 Projects * Site Inspection at Various Service Stations 2013 (P-Shop Pharma Plus) - March-11, 2013 i. Alma Aquino Service Station: Commonwealth Ave., North Fairview, Q. C. ii. Corral Service Station: East Ave., Cor. BIR Road, Piñaha, Q. C. iii. Dizon Service Station: #53 Kamuning Cor., Scout Ybardolaza, Kamuning, Q. C. iv. Favila Service Station: Cong. Ave., Cor. Virginia St., Proj. 6, Brgy. Bahay Toro, Q. C. v. Casares Service Station: West Avenue, Cor. Del Monte, Q. C. vi. Calalay Service Station: Timog Morato Cor. Tomas Morato, Q.C. Company/Client : PETROTECH MPJ, Incorporated "Bridging Gaps Between You and Your Markets" No. 22 VRCC Rd. Veterans Center, Western Bicutan, Taguig City Tel. No. 839-2117 Fax No. 839-2094 Project-in-Charge : Engr. Edelino T. Quiambao Proprietor Year : 2012 Projects * Consolacion Cebu Proposed Oil Depot - July-27, 2012 * Linao, Ormoc Leyte Proposed Mini Oil Depot Layout Plan - July-13, 2012 * Taytay Palawan EON Petroleum Inc. Proposed Mini Oil Depot - January-09, 2012 Company/Client : Rubite Trading & General Services 9 10-A Provincial Road Matungao, Bulakan, Bulacan Telefax (044) 7922521 Tel (044) 7922889 Project-in-Charge : Engr. Edelino T. Quiambao Proprietor Year : 2012 Projects * Navotas Depot Proposed New Service Pipeline Layout Plan - August-22, 2012 Company/Client : SAVIOR CONSTRUCTION OFFICES: 251 TUMANA, STA. MARIA, BULACAN CELL NO.: (0916) 939-6660 TELEFAX: (044) 641-1729 E-MAIL: saviorcons@yahoo.com Project-in-Charge : Engr. Edelino T. Quiambao Proprietor Year : 2013 Projects * As-Built Plans of Car Tricycle Awning Pump Island - June-03, 2013 * Iligan Depot Conversion of Tank-6 (ADO) as-Built Plans - May-28, 2013 * Bawing Depot as-Built Plans of Tank-1 (X-93), Tank-2 (Kero), & Tank-3 (X-93) - February-18, 2013 Year : 2012 Projects * Ormoc Bulk Plant as-Built Plans of 10,000 USG Ethanol Tank - December-17, 2012
  • 9.
    ***** E ND ***** Sub-Contractor : BJ & G Consultancy Inc. San Isidro, Baao, Camarines Sur, Philippines Contact No.: 09274736531 E-mail Address: Gabriel_adan@yahoo.com Department : Petron CTESG Design & Construction Group – Plant Engineering Position : Design Assistant/AutoCAD Operator Duration : July-25, 2012 to January-31, 2013 Job Description : Prepares Construction/Working Drawings of Mini-LPG Refilling Plant by the following Drafting Disciplines: Architectural, Structural, Electrical, Mechanical, Sanitary, Driveway Concreting Plan, & Piping & Instrumentation Diagram (P. & I.D.) with necessary Bill of Quantity (BoQ) & Bill of Materials (BoM). Conduct site visit & provide as-Built Plans. Company/Client : #151 Archen Technologies Building, Brgy. Wack-Wack, Mandaluyong City Philippines (T 886-3888) Project-in-Charge : Mr. Gabriel M. Adan Proprietor Year : 2012 Projects * Manila Harbor Centre Proposed New Administration Building - March-31, 2012 Year : 2011 Projects * El Nido Palawan Proposed Mini-LPG Refilling Plant - October-24, 2011 Company/Client : PTT Philippines Corporation 32nd Floor LKG Bldg., Ayala Avenue, Makati City Tel. Nos. 884-81-55 Fax No. 884-81-50 Department : Engineering Department Position : Design Assistant/AutoCAD Operator Duration : August-01, 2012 to February-28, 2013 Job Description : Prepares Construction/Working Drawings of PTT Gasoline Station by the following Drafting Disciplines: Architectural, Structural, Electrical, Mechanical, Sanitary, & Driveway Concreting Plan. Project-in-Charge : Engr. Joel M. Tolosa Project Engineer Mr. Gabriel M. Adan Proprietor Year : 2013 Projects * PTT Mabalacat Proposed Gasoline Station - February-11, 2013 * PTT Clark Proposed Trellis Details - January-21, 2011 * PTT Regalado Proposed Gasoline Station - January-07, 2013 * PTT Molino-2 Proposed Extension - January-04, 2013 Year : 2012 Projects * PTT Cabanatuan Revision-1 - December-05, 2012 * PTT Bulacan Proposed Gasoline Station - October-27, 2012
  • 10.
    * PTT VillasisProposed Gasoline Station - October-15, 2012 * PTT San Marcelino Proposed Gasoline Station - September-25, 2012 * PTT Taytay Proposed BSLO Layout Plan - September-25, 2012 * PTT KM 18 East Service Road Proposed Gasoline Station - September-13, 2013 * PTT Clark Proposed Gasoline Station - August-27, 2013 * PTT San Jose Proposed Road Shoulder - August-25, 2012 * PTT Magalang Proposed BSLO Layout Plan (Sch.-2) - August-16, 2012 * PTT Concepcion Proposed BSLO Layout Plan (Sch.-2) - August-15, 2012 * PTT Congressional Avenue Proposed BSLO Layout Plan (Sch.-2) - August-14, 2012 * PTT Bantayan-2 Proposed Gasoline Station - August-08, 2012 ***** E N D ***** Company/Client : EON PETROLEUM INCORPORATED 2207 TYCOON CENTER BUIILDING, PEARL DRIVE ORTIGAS, PASIG CITY Project-in-Charge : Mr. Gabriel M. Adan Proprietor Year : 2013 Projects * EON Lite Prototype Bulilit Station (PowerPoint Files) - January-07, 2013 Year : 2012 Projects * EON Muñoz Nueva Ecija Proposed New Service Station - September-15, 2012 Client : Mr. Gigi Santos Project-in-Charge : Mr. Gabriel M. Adan Proprietor Year : 2012 Projects * 2-Storey Residential as-Built Layout Plan - September-13, 2012 ***** E N D ***** Sub-Contractor : C. JANSEN TECHNICAL SERVICES Marina Ave., St. Joseph Subdivision, Bayan, Orani, Bataan – 2112 Philippines CP: 09999904720 Department : Petron CTESG Design & Construction Group – Design Group Position : Junior Architect/AutoCAD Operator Duration : March-05, 2010 to May-31, 2011 Job Description : Prepares Construction/Working Drawings of Petron Service Station, Micro-Filling Station (MFS), & Dealer-Owned Filling Station (DOFS) by the following Drafting Disciplines: Architectural, Structural, Electrical, Mechanical, Sanitary, & Driveway Concreting Plan with Site Visiting & provide as-Built Plans. Company/Client : #151 Archen Technologies Building, Brgy. Wack-Wack, Mandaluyong City Philippines (T 886-3888) Project-in-Charge : Arch. Enrico M. Santos Head Architect
  • 11.
    Year : 2011Projects * Proposed Axcess Sports Bar & KTV - July-08, 2011 * PEC-1 Proposed Expansion (Phase-2) Lakbay Alalay - March-31, 2011 * RLT's Residences Proposed Guest Room & Bedroom-1 Renovation - February-02, 2011 Project-in-Charge : Arch. Dreyden B. Villoso Architect Year : 2011 Projects * Proposed Service Station Building Layout (Generic) - April-14, 2011 * PEC-1 NLEX Northbound Proposed Expansion - March-25, 2011 Project-in-Charge : Arch. Jane Q. Ramirez Architect Year : 2011 Projects * Micro-Filling Station (Petron Bulilit) report 2011(Excel Files) – April-30, 2011 * Proposed COSS Mendoza Office & Sales Room Layout, Cebu City - April-20, 2010 * Proposed New Dealer-Owned Filling Station: M. Highway, Quezon - April-14, 2011 * Proposed New Dealer-Owned Filling Station: San Roque, Pasay City - April-14, 2011 * Proposed New Dealer-Owned Filling Station: San Antonio, Quezon - April-14, 2011 * Proposed New Dealer-Owned Filling Station: Meycauyan, Bulacan - April-05, 2011 * Proposed Dealer-Owned Filling Station: Urdaneta Pangasinan - April-04, 2011 * Proposed New Dealer-Owned Filling Station: R & E Taxi - March-14, 2011 * Proposed Dealer-Owned Filling Station: Regalado, Quezon City - February-24, 2011 * Proposed CODO BSLO Request: Evangelista, Teodoro - February-23, 2011 Year : 2010 Projects * Proposed New Dealer-Owned Filling Station: Baguio City - November-30, 2010 * Proposed New Single Pump Island Station: Calaca, Batangas - November-19, 2010 * Proposed New Service Station PMC Wachovia Angeles, Pampanga - November-03, 2010 * Proposed New Work Bench Details - November-02, 2010 * Proposed New Dealer-Owned Filling Station: Binalonan, Pangasinan - October-20, 2010 * Proposed New Dealer-Owned Filling Station: San Juan, La Union - September-13, 2010 * Proposed Petron Clinic San Miguel Corporation, Mandaluyong City - September-09, 2010 * Proposed New Two Pump Island Filling Station: Nabua, Camarines Sur - August-25, 2010 * Proposed Micro-Filling Station (Petron Bulilit) Gasbar Generic - July-24, 2010 * Proposed Service Station Major Rehab, Intramuros, Manila - July-23, 2010 * Proposed New Dealer-Owned Filling Station: San Carlos, Pangasinan - June-28, 2010 * Proposed New Service Station EDSA-NIA, Quezon City - May-24, 2010 * Micro Filling Station (Petron Bulilit) Enhancement - April-21, 2010 i. MFS Type - 1: MFS-1a & MFS-1b ii. MFS Type - 2: MFS-2a & MFS-2b iii. MFS Type - 3: MFS-3a & MFS-3b iv. MFS Type - 4z v. MFS Type - 5 vi. MFS Type - 6 vii. MFS Type - Gasbar ***** E N D ***** Consultant : ALEJANDRO SO MANOTA & ASSOCIATES ARCHITECTS CONSULTANTS BLK. 8 LOT 31, SAN PEDRO SUBDIVISION 7 TEL. 4261379 SAN BARTOLOME, NOVALICHES, Q.C. PHILS. CELL. 0920-5965347 Department : In-House Design Office Address: Blk. 8 Lot-31, San Pedro Subdivision 7, San Bartolome, Novaliches, Q.C. Philippines Position : AutoCAD Operator Duration : August, 2009 to January, 2010 Job Description : Prepares Construction/Working Drawings of Standard Bank Layout Plan of Banco de Oro (BDO), Bank of the Philippine Island (BPI), & EastWest Bank by the following Drafting Disciplines: Architectural, Structural, Electrical, Mechanical, & Sanitary. Conduct site visit & provide as-Built Plans.
  • 12.
    Company/Client : BDOCorporate Center 7899 Makati Avenue, Makati City, Philippines Project-in-Charge : Arch. Alejandro So Manota Architect/Proprietor Year : 2010 Projects * BDO - San Pablo Branch Interior Renovation - January, 2010 Year : 2009 Projects * BDO - Marikina Branch (Transfer Site), Conception Marikina - November-22, 2009 * BDO - Ayala Alabang Madrigal Branch, Zapote Rd., Muntinlupa, City - November, 2009 * BDO - Libis Branch, Acropolis, Libis, Quezon City - July-13, 2009 Company/Client : 6768Ayala Avenue Cor. Paseo de Roxas Ave., Makati Central Business District, Makati City, Metro Manila, Philippines Project-in-Charge : Arch. Alejandro So Manota Architect/Proprietor Year : 2009 Projects * BPI - Cainta Saint Anthony, Ortigas Ave. Ext., Cainta, Rizal - November, 2009 Company/Client : 20/F PBCom Tower, 6795 Ayala Avenue Cor. V.A. Rufino St., Salcedo Village, Makati City, Metro Manila, Philippines Project-in-Charge : Arch. Alejandro So Manota Architect/Proprietor Year : 2009 Projects * EastWest Bank West Avenue Branch Iterior Renovation - August-10, 2009 * EastWest Bank T. Alonzo Branch Interior Construction - June, 2009 Company/Client : Mr. & Mrs. Fortaleza Year : 2009 Projects * Two Storey Residence Renovation & Expansion - August, 2009 ***** E N D ***** vii. CHARACTER REFERENCES:
  • 13.
    Reference No.1 : 2nd FloorObeikan Bookstore Building Prince Sultan Road, Jeddah, Kingdom of Saudi Arabia Contact Person : Engr. Nabeel H. Abu Sadah QA/QC Manager for Road Projects Department P.O. Boxn11789 Jeddah 21463 Saudi Arabia Tel.: 6927105 Ext. Fax: 6922198 Mobile: +966 540925900 E-mail: nabeels@sbgabc.com & abusada61@hotmail.com Contact Person : Engr. Eric M. Guillermo, MSE Planning Manager for Road Projects Department P.O. Box 11789 Jeddah 21463 Saudi Arabia Tel.: 012-6927105 Ext. 256 Fax: 012-6163979 Ext. 8135 Mobile: +966 569056350 E-mail: eguillermo@SBGABC.COM Reference No.2 : E. T. QUIAMBAO ENGINEERING SERVICES #1 Wallnut Road, SPH Telephone No. (02) 948-6214 Makiling Street, Hacienda Heights Cellphone No. 09173195087 Brgy. Concepcion 2, Marikina City, Philippines Contact Person : Engr. Edelino T. Quiambao Proprietor/Owner Reference No.3 : BJ & G Consultancy Inc. San Isidro, Baao, Camarines Sur, Phillipines Contact No.: 09274736531 E-mail Address: Gabriel_adan@yahoo.com Contact Person : Mr. Gabriel M. Adan Proprietor/Owner Reference No.4 : C. JANSEN TECHNICAL SERVICES Marina Ave., St. Joseph Subdivision, Bayan, Orani, Bataan – 2112 Philippines CP: 09999904720 Contact Person : Mr. Rex A. Peña Proprietor/Owner "I hereby certify that the above information is true and correct. To the best of my personality and to the extent of my knowledge and belief" Arch. Mauricio P. Cabanillas Jr. Signature