The document provides instructions for completing a two-way lighting circuit installation project. It involves several tasks:
1) Bending conduit, threading conduit pieces, and attaching the conduit to a consumer unit and wall using fittings.
2) Marking and cutting conduit lengths, threading the pieces, and attaching them together using couplings to create the circuit layout.
3) Wiring the circuit by threading wires through the conduit, connecting them to switches and lights in the correct configuration.
4) Testing the circuit for continuity and insulation using a multi-meter to ensure it was correctly installed before energizing.
Egatube uPVC Conduit offers a cost effective solution for wiring installations in new buildings and renovations. It has a wide range of conduit sizes, sections, and fittings that allow for versatile installations. The conduit is durable, impact resistant, and manufactured according to relevant standards.
The knitting section has 20 circular knitting machines of different diameters and gauges from different brands like Pailung and Liskey. The machines can produce different knit fabrics like single jersey, 1x1 rib etc with a total daily capacity of around 6,000 kg.
The document summarizes a student's project to construct a voltage distribution circuit to allow a photomultiplier tube to detect cosmic rays. It describes how cosmic rays interact with the atmosphere, how scintillators convert particle interactions to photons, and how photomultiplier tubes work. It outlines the design and construction process for the circuit, including selecting components, soldering wires, testing, and troubleshooting issues. The student was ultimately able to see pulses from a scintillator indicating detection of cosmic rays and radioactive decays.
The document provides instructions for installing an electric shower. It discusses selecting a location for the shower that allows access to the water supply pipe. It describes running the water supply pipe and making the plumbing connections. It also covers running the electrical cable to the shower, installing an isolating switch, and making the wiring connections at the shower, switch, and circuit breaker. Proper earthing of metallic components is emphasized for safety. A professional electrician should connect the wiring at the main circuit panel.
Under Cabinet Lighting - UC2A Series from iLuXx - Installation Guideiluxx
The document discusses the installation of under cabinet lighting using the UC2A Series from iLuXx Lighting. The series is designed to install inside cabinet cavities between 3/8" and 1" deep. The summary includes selecting luminaires in the desired lengths and outputs, choosing a power supply based on total wattage, and optionally adding a wireless controller for dimming functions. Wiring and accessories are also outlined to connect and install the system within kitchen cabinets.
WIRING SYSTEM(CONDUIT AND CASING CAPPING) Working of Fan with Of DimmerEMEY GUJJAR
This document describes different wiring systems including casing and capping wiring and conduit wiring. Casing and capping wiring uses rectangular PVC casing that has grooves for wires. The capping covers and secures the wires. Conduit wiring uses steel or PVC pipes to encase wires for protection. Both systems provide protection from shocks and fire but conduit wiring has higher installation costs while casing and capping has humidity and repair issues. The document also explains how to connect a dimmer switch to a fan to vary its speed.
This document provides information on various electrical tasks and safety procedures related to plumbing work. It describes the purpose and proper installation of equipotential bonding, supplementary bonding, and temporary continuity bonding. It also outlines safety procedures like testing for polarity and earth continuity when working on electrical systems and cutting into pipework. The document emphasizes the importance of electrical safety precautions to avoid electric shock when plumbing work involves electrical components.
Egatube uPVC Conduit offers a cost effective solution for wiring installations in new buildings and renovations. It has a wide range of conduit sizes, sections, and fittings that allow for versatile installations. The conduit is durable, impact resistant, and manufactured according to relevant standards.
The knitting section has 20 circular knitting machines of different diameters and gauges from different brands like Pailung and Liskey. The machines can produce different knit fabrics like single jersey, 1x1 rib etc with a total daily capacity of around 6,000 kg.
The document summarizes a student's project to construct a voltage distribution circuit to allow a photomultiplier tube to detect cosmic rays. It describes how cosmic rays interact with the atmosphere, how scintillators convert particle interactions to photons, and how photomultiplier tubes work. It outlines the design and construction process for the circuit, including selecting components, soldering wires, testing, and troubleshooting issues. The student was ultimately able to see pulses from a scintillator indicating detection of cosmic rays and radioactive decays.
The document provides instructions for installing an electric shower. It discusses selecting a location for the shower that allows access to the water supply pipe. It describes running the water supply pipe and making the plumbing connections. It also covers running the electrical cable to the shower, installing an isolating switch, and making the wiring connections at the shower, switch, and circuit breaker. Proper earthing of metallic components is emphasized for safety. A professional electrician should connect the wiring at the main circuit panel.
Under Cabinet Lighting - UC2A Series from iLuXx - Installation Guideiluxx
The document discusses the installation of under cabinet lighting using the UC2A Series from iLuXx Lighting. The series is designed to install inside cabinet cavities between 3/8" and 1" deep. The summary includes selecting luminaires in the desired lengths and outputs, choosing a power supply based on total wattage, and optionally adding a wireless controller for dimming functions. Wiring and accessories are also outlined to connect and install the system within kitchen cabinets.
WIRING SYSTEM(CONDUIT AND CASING CAPPING) Working of Fan with Of DimmerEMEY GUJJAR
This document describes different wiring systems including casing and capping wiring and conduit wiring. Casing and capping wiring uses rectangular PVC casing that has grooves for wires. The capping covers and secures the wires. Conduit wiring uses steel or PVC pipes to encase wires for protection. Both systems provide protection from shocks and fire but conduit wiring has higher installation costs while casing and capping has humidity and repair issues. The document also explains how to connect a dimmer switch to a fan to vary its speed.
This document provides information on various electrical tasks and safety procedures related to plumbing work. It describes the purpose and proper installation of equipotential bonding, supplementary bonding, and temporary continuity bonding. It also outlines safety procedures like testing for polarity and earth continuity when working on electrical systems and cutting into pipework. The document emphasizes the importance of electrical safety precautions to avoid electric shock when plumbing work involves electrical components.
This document is a laboratory manual for an Engineering Practices course covering topics like plumbing, carpentry, welding, machining, and machine assembly. It includes an index, contents section, and chapters on safety precautions, plumbing tools and components, and descriptions of common pipe fittings. The manual provides information to students on exercises and demonstrations for various mechanical engineering skills and trades.
The document details a 3MW solar power plant project in Dindigul, India. It includes construction of 1158 piles for the 2MW section and 570 piles for the 1MW section. A total of 7720 solar panels were installed for the 2MW section and 3800 panels for the 1MW section. The project was completed over 7 months with 51 employees and an investment of 50 lakh rupees. Electrical work included laying DC and AC cables in trenches to connect panels to string monitoring boxes, inverters, and transformers to distribute the power generated.
1) This document provides instructions for adding additional wall lights to a room that can be switched independently of the main light.
2) Safety precautions are outlined, including turning off power before working, and having any electrical work tested by a qualified electrician.
3) Step-by-step instructions are given for running new cable from an existing light circuit to add a switch and two wall lights, including necessary materials and diagrams of the circuit.
This document provides information and safety guidelines for electrical work. It discusses checking for wires before cutting walls, obtaining certificates for work, turning off power when working on circuits. It also summarizes types of electrical equipment, how household electrical systems work with main units and consumer boxes distributing power, basic equations for calculating circuits, types of cables and flex, and guidelines for ring main and radial wiring circuits. Safety is emphasized throughout, including ensuring no accidental power restoration.
The document is a lab manual that provides instructions and procedures for various electrical engineering experiments. It includes:
1. An experiment on studying the construction and working of a ceiling fan, including connecting the fan to a speed regulator. The ceiling fan uses a single phase induction motor with start and run windings.
2. Instructions for house wiring that connects various devices like lights, fans and sockets. It describes wiring configurations and safety protocols.
3. An experiment on staircase wiring that allows controlling a light from two different positions using a two-way switch configuration.
The document provides theory, diagrams, component lists and step-by-step procedures for students to conduct hands-on experiments in an electrical engineering lab
E. Flaws in the Resonant Cylinder and the Associated Design IterationsKurt Zeller
This document summarizes design iterations made to address arcing issues in a resonant cylindrical cavity used in an experiment. Small gaps between components led to arcing when high power was applied. Design changes focused on grounding the movable metal end plate and connecting the waveguide adapter to the cylinder. Nylon screws caused arcing and were replaced with a press-fit plate attaching dielectric material. Copper mesh and conductive putty were used to improve grounding between components, but could not fully eliminate arcing without a custom-designed electromagnetic choke or precision waveguide matching. Further testing was postponed due to budget and manufacturing limitations for precision microwave components.
This document presents the design of a wireless power charging system. It discusses the background and objectives of developing a system to wirelessly charge mobile phones using magnetic induction between transmitter and receiver coils. The key components are described, including the transmitter and receiver coil specifications adhering to Qi standards. Initial circuit designs faced constraints in producing sufficient power output. The overall goal is to demonstrate wireless power transfer for charging applications while meeting specifications for efficiency and safety.
This document provides instructions for adding extra electrical sockets in a home. It describes how to convert single sockets to doubles by replacing the mounting box with a double box and connecting it to the existing circuit. It also explains how to add new sockets by installing "spurs" which connect a new cable and socket to an existing socket on the ring circuit. Proper safety precautions like turning off the power and checking for live wires are emphasized.
1) The author carried out a risk assessment and gathered tools before beginning work on an Octopus circuit. Components were marked out on the board according to diagrams and dimensions were kept workable.
2) Cables were run between components and clipped in place. Components like switches and lamp holders were attached to the board with screws. Cables were stripped and wires were terminated in each component.
3) A dead test was performed using a multi-functional tester to check continuity and insulation resistance between wire pairs. Readings showed the circuit was wired correctly. A live test under tutor supervision proved functionality of all switches and lamps.
This document provides information on cables and cable termination for electricians. It defines key terms and lists common electrical conducting and insulating materials. It describes the construction and applications of PVC, PVC/PVC, and flexible cords. It also covers tools, marking, fixing, clipping, terminating cables, and the roles of electrical bodies and rules. The purpose is to familiarize electrician apprentices with cables, tools, and installation standards.
Ebbin Daniel performed maintenance and troubleshooting tasks from October 11-16. This included rewiring hydraulic connectors on the cuber arm, troubleshooting a power outage on the dry side by reconnecting loose wires, troubleshooting issues with the BSA panel by rewiring various inputs and outputs, adjusting the safe position photo eye on the wrapper machine, and fixing a cuber up/down mechanism by replacing a loose wire and blown fuse. Current projects include adjusting heights for pavers on the wet side by contacting manufacturers for measurement systems and replacing limit switches on conveyors for the block plant.
This document provides details on the fabrication of a regulated DC power supply project. It includes a block diagram showing the main components - step down transformer, rectifier, smoothing capacitor and voltage regulators. The circuit diagram and list of components used are also included. The project aims to construct 12V and 5V regulated DC power supplies using a transformer, bridge rectifier, filtering capacitor and IC voltage regulators 7812 and 7805 respectively.
Report on PCB designing and fabrication by Prince RohanRohan Das
This is a report on our printed circuit board training on Central Mechanical Engineering Research Institute, Durgapur.
I hope this will help some student. Thank you
D2 (A4) Björn Täljsten - Wireless monitoring for assessment of concrete railw...Svenska Betongföreningen
The document summarizes wireless monitoring of a concrete railway bridge in Sweden to investigate the cause of cracks and the bridge's ability to handle increased axle loads. A monitoring system was installed using sensors to measure temperature, strain, deflection, and acceleration. Non-destructive testing mapped rebar location, tendon placement, and crack depths. Preliminary results found the concrete cover varies significantly and temperature does not cause the cracks, which are likely from bursting forces during construction. Modelling of the bridge is ongoing.
It's electric accessory that protects and conceals electrical wires. It is normally a hollow pipe which can be made from various materials. Normally, electrical conduits are really simple to setup. The way you install electrical conduits depends on the material they are made from plus the set up layout. Your expertise and experience in the subject will additionally play a decisive role in how efficiently you can do the installation.
An example of a storyboard that employs Merrill's First Principles of Instruction model to structure the learning. This is for a lesson on Basic Hand Tools for Electricians.
How to Make an LED Microcope Light from a FlashlightSam Droege
German Perilla has created a lovely demonstration on how to modify a LED flashlight and make it into a high powered microscope light that can be plugged into an electrical outlet. Comparable to, but much cheaper than, fiber optic lights.
Do it!
The document describes the design and working of an AC generator. It includes:
- The main components of an AC generator are the stator, which has copper coil windings, and the rotor, which has magnets and spins inside the stator.
- Electromagnetic induction causes an alternating current to be generated in the stator coils as the rotor's magnetic field cuts across them during rotation.
- The document provides step-by-step instructions to construct a simple AC generator using readily available materials like copper wire, magnets, pipes, and wood. It also includes diagrams of the circuit and internal components.
Rishabh Kumar completed a physics project on assembling an electrical extension board under the guidance of his teacher Mr. Vivek Chauhan. The project involved identifying live, neutral and earth terminals of sockets and wires. It explains how to safely assemble the extension board by connecting wires between sockets and switches according to a circuit diagram. Proper twisting of wires and tightening of screws is important for safety. The extension board allows supplying electricity from one main socket to multiple sockets.
The document describes a project to build a portable FM transmitter and receiver. Key requirements were that the devices be handheld, use a portable power source, transmit and receive wireless signals, and be able to change frequencies. Prototypes were created and tested. The transmitter was able to broadcast between 89.5-93.5 MHz and the receiver could receive signals from 105.5-107.5 MHz. Future improvements discussed include adding casing and external antennae to both devices.
This document is a laboratory manual for an Engineering Practices course covering topics like plumbing, carpentry, welding, machining, and machine assembly. It includes an index, contents section, and chapters on safety precautions, plumbing tools and components, and descriptions of common pipe fittings. The manual provides information to students on exercises and demonstrations for various mechanical engineering skills and trades.
The document details a 3MW solar power plant project in Dindigul, India. It includes construction of 1158 piles for the 2MW section and 570 piles for the 1MW section. A total of 7720 solar panels were installed for the 2MW section and 3800 panels for the 1MW section. The project was completed over 7 months with 51 employees and an investment of 50 lakh rupees. Electrical work included laying DC and AC cables in trenches to connect panels to string monitoring boxes, inverters, and transformers to distribute the power generated.
1) This document provides instructions for adding additional wall lights to a room that can be switched independently of the main light.
2) Safety precautions are outlined, including turning off power before working, and having any electrical work tested by a qualified electrician.
3) Step-by-step instructions are given for running new cable from an existing light circuit to add a switch and two wall lights, including necessary materials and diagrams of the circuit.
This document provides information and safety guidelines for electrical work. It discusses checking for wires before cutting walls, obtaining certificates for work, turning off power when working on circuits. It also summarizes types of electrical equipment, how household electrical systems work with main units and consumer boxes distributing power, basic equations for calculating circuits, types of cables and flex, and guidelines for ring main and radial wiring circuits. Safety is emphasized throughout, including ensuring no accidental power restoration.
The document is a lab manual that provides instructions and procedures for various electrical engineering experiments. It includes:
1. An experiment on studying the construction and working of a ceiling fan, including connecting the fan to a speed regulator. The ceiling fan uses a single phase induction motor with start and run windings.
2. Instructions for house wiring that connects various devices like lights, fans and sockets. It describes wiring configurations and safety protocols.
3. An experiment on staircase wiring that allows controlling a light from two different positions using a two-way switch configuration.
The document provides theory, diagrams, component lists and step-by-step procedures for students to conduct hands-on experiments in an electrical engineering lab
E. Flaws in the Resonant Cylinder and the Associated Design IterationsKurt Zeller
This document summarizes design iterations made to address arcing issues in a resonant cylindrical cavity used in an experiment. Small gaps between components led to arcing when high power was applied. Design changes focused on grounding the movable metal end plate and connecting the waveguide adapter to the cylinder. Nylon screws caused arcing and were replaced with a press-fit plate attaching dielectric material. Copper mesh and conductive putty were used to improve grounding between components, but could not fully eliminate arcing without a custom-designed electromagnetic choke or precision waveguide matching. Further testing was postponed due to budget and manufacturing limitations for precision microwave components.
This document presents the design of a wireless power charging system. It discusses the background and objectives of developing a system to wirelessly charge mobile phones using magnetic induction between transmitter and receiver coils. The key components are described, including the transmitter and receiver coil specifications adhering to Qi standards. Initial circuit designs faced constraints in producing sufficient power output. The overall goal is to demonstrate wireless power transfer for charging applications while meeting specifications for efficiency and safety.
This document provides instructions for adding extra electrical sockets in a home. It describes how to convert single sockets to doubles by replacing the mounting box with a double box and connecting it to the existing circuit. It also explains how to add new sockets by installing "spurs" which connect a new cable and socket to an existing socket on the ring circuit. Proper safety precautions like turning off the power and checking for live wires are emphasized.
1) The author carried out a risk assessment and gathered tools before beginning work on an Octopus circuit. Components were marked out on the board according to diagrams and dimensions were kept workable.
2) Cables were run between components and clipped in place. Components like switches and lamp holders were attached to the board with screws. Cables were stripped and wires were terminated in each component.
3) A dead test was performed using a multi-functional tester to check continuity and insulation resistance between wire pairs. Readings showed the circuit was wired correctly. A live test under tutor supervision proved functionality of all switches and lamps.
This document provides information on cables and cable termination for electricians. It defines key terms and lists common electrical conducting and insulating materials. It describes the construction and applications of PVC, PVC/PVC, and flexible cords. It also covers tools, marking, fixing, clipping, terminating cables, and the roles of electrical bodies and rules. The purpose is to familiarize electrician apprentices with cables, tools, and installation standards.
Ebbin Daniel performed maintenance and troubleshooting tasks from October 11-16. This included rewiring hydraulic connectors on the cuber arm, troubleshooting a power outage on the dry side by reconnecting loose wires, troubleshooting issues with the BSA panel by rewiring various inputs and outputs, adjusting the safe position photo eye on the wrapper machine, and fixing a cuber up/down mechanism by replacing a loose wire and blown fuse. Current projects include adjusting heights for pavers on the wet side by contacting manufacturers for measurement systems and replacing limit switches on conveyors for the block plant.
This document provides details on the fabrication of a regulated DC power supply project. It includes a block diagram showing the main components - step down transformer, rectifier, smoothing capacitor and voltage regulators. The circuit diagram and list of components used are also included. The project aims to construct 12V and 5V regulated DC power supplies using a transformer, bridge rectifier, filtering capacitor and IC voltage regulators 7812 and 7805 respectively.
Report on PCB designing and fabrication by Prince RohanRohan Das
This is a report on our printed circuit board training on Central Mechanical Engineering Research Institute, Durgapur.
I hope this will help some student. Thank you
D2 (A4) Björn Täljsten - Wireless monitoring for assessment of concrete railw...Svenska Betongföreningen
The document summarizes wireless monitoring of a concrete railway bridge in Sweden to investigate the cause of cracks and the bridge's ability to handle increased axle loads. A monitoring system was installed using sensors to measure temperature, strain, deflection, and acceleration. Non-destructive testing mapped rebar location, tendon placement, and crack depths. Preliminary results found the concrete cover varies significantly and temperature does not cause the cracks, which are likely from bursting forces during construction. Modelling of the bridge is ongoing.
It's electric accessory that protects and conceals electrical wires. It is normally a hollow pipe which can be made from various materials. Normally, electrical conduits are really simple to setup. The way you install electrical conduits depends on the material they are made from plus the set up layout. Your expertise and experience in the subject will additionally play a decisive role in how efficiently you can do the installation.
An example of a storyboard that employs Merrill's First Principles of Instruction model to structure the learning. This is for a lesson on Basic Hand Tools for Electricians.
How to Make an LED Microcope Light from a FlashlightSam Droege
German Perilla has created a lovely demonstration on how to modify a LED flashlight and make it into a high powered microscope light that can be plugged into an electrical outlet. Comparable to, but much cheaper than, fiber optic lights.
Do it!
The document describes the design and working of an AC generator. It includes:
- The main components of an AC generator are the stator, which has copper coil windings, and the rotor, which has magnets and spins inside the stator.
- Electromagnetic induction causes an alternating current to be generated in the stator coils as the rotor's magnetic field cuts across them during rotation.
- The document provides step-by-step instructions to construct a simple AC generator using readily available materials like copper wire, magnets, pipes, and wood. It also includes diagrams of the circuit and internal components.
Rishabh Kumar completed a physics project on assembling an electrical extension board under the guidance of his teacher Mr. Vivek Chauhan. The project involved identifying live, neutral and earth terminals of sockets and wires. It explains how to safely assemble the extension board by connecting wires between sockets and switches according to a circuit diagram. Proper twisting of wires and tightening of screws is important for safety. The extension board allows supplying electricity from one main socket to multiple sockets.
The document describes a project to build a portable FM transmitter and receiver. Key requirements were that the devices be handheld, use a portable power source, transmit and receive wireless signals, and be able to change frequencies. Prototypes were created and tested. The transmitter was able to broadcast between 89.5-93.5 MHz and the receiver could receive signals from 105.5-107.5 MHz. Future improvements discussed include adding casing and external antennae to both devices.
1. WTA.05 Two Way Conduit Lighting
To beginthisjobI had to learna whole new setof skills.Istartedbyreceivinginstructionfrommy
tutor ontechniquesof pipe bending. Thiswasdone usingapipe bendingmachine.
The outcomesof the taskwere to:
Benda 900
bendin20mm metal conduit
Use a die and cast to create a threadedconduitendpiece
Attach the conduittoa ConsumerUnit(CU) usingthe correct fittings
Create a "kick"bendto the C.U
Attach the assemblytothe wall usingthe correctfittings
Afterbeingshownthe above tasksbymytutor, I proceededtothe WTA.05 project.
I startedby makingsure mywork areawas cleanand tidy,free frommaterialsandequipment.I
gatheredthe toolsIwouldneedforthe job,and collectedacomponentsbasket fromthe store.I
alsocollectedseparately,one lengthof 20mmmetal conduit.
The firsttask was to markout the job onmy workboard. Thisincludedthe componentlocationsand
the conduitlayout.Thiswasdone to the layoutdiagraminmy practice book.
First Fix
I nextproceededtomarkout andcut the 20mm steel conduittothe correct lengths,Iwouldneed4
lengthsforthisjob.Each piece of conduitwasthreaded,thiswasdone withastock and die.Ifirst
securedthe pipe lengthsinapipe vice.Thiskeepsthe tubingsteadywhilstworkisbeingcarriedout.
I startedby puttingthe die onthe endof the tubing,andmakinga small turnto start the threading
process;afterthisthe die was removed.Iproceededtoapplya small amountof cuttinglubrication
to the conduitend.Thiswouldhelpgive me asmooththreadcuttingand preventdamage tothe
tubing.The threadingwascarriedoutby turningthe die 3 times,thengoingbackover3 times.This
continueduntil Ihada threadof roughly20mm. Thisprocesswascarried outon each conduitlength
(excludinglarge lengthforbending.)
The nextstepwas to putthe 900
bendinthe large lengthof conduit.Thiswasdone usinga pipe
bendingmachine.Afterbendingthe pipe andcheckingitforsquare;Iproceededtothreadthe ends
of thislengthasdone before.Onthe topof the 900
bendthe threadingwasmade longer.Thiswasto
incorporate a runningcouplingjoint.The threadingwasmade the lengthof afull coupler,plus5mm.
I beganattachingthe conduit to the work board.
FirstlyIattachedthe inspectionelbow tothe CU(Fig.3).Thiswasdone witha threadedgland(Fig.2).
The gland wastightenedwithabushspanner.Ithenattachedthe firstlengthof conduit,thiswas
done byscrewingthe conduitintothe inspectionelbow.Ithendrew linesdowneachside of the
conduitsoI could place a conduitsaddle inthe center(Fig.1). The conduitwasthenremovedsoI
couldfitthe saddle to the back boardwitha 20mm woodscrew.The conduitwasattachedagain,this
time withthe lampholdermetal backbox attachedto the end.The saddle hadthe toppiece
screwedinto secure the conduitandanother20mm woodscrew fixedthroughthe lampholderback
box.
. Fig.1 Fig.2 Fig.3
2. The same processwasrepeatedfrom the undersideof the lampholderbackbox to secure the first
metal cladswitch.Thisleftthe attachmentof the secondswitchandthe 900
conduitbend.
To connectthispiece of conduitI wouldhave tocomplete arunningcoupling.Istartedthisprocess
by attachinga lockingringand a couplertothe endof my elbow.Ithencut andthreadeda small
piece of conduittobe threadedinsidethe lampholderbackbox.These 2pieceswere butted
togetherandthe couplerturnedinplace.Thisconnectedthe conduit tothe lampholderbackbox,
and the lockingringbehindthe couplersecuredthe piecestogether.A saddle wasattachedonthe
vertical piece of tubing,aswell asanotherlightingswitchbackbox.Back boxes were securedwith
20mm woodscrews.
Thisended the firstfix of the project.
SecondFix
The wiringof the conduitsystembeganwithcutting1lengthof blue/neutral/rnwire,4lengthsof
brown/line/r1wire,and2lengthsof greenyellow/earth/r2wire.These were all single wires1.5mm.
I removedthe coveronthe inspectionelbowandthreadedthe neutral wire first.Ithenthreaded1
line wire fromthe CU to switch1; two line wiresfromswitch1to switch2; and a final line wire from
switch2 to the lampholder.Earthwire was threadedfromthe CU, to the lamp andfrom the lampto
switch1 and 2. Thiswouldact as the circuitprotective conductor(CPC).All wireswere strippedto
the cores at the endsreadyfor terminating.
In the lampholderbackbox,I connectedthe rn wire tothe neutral terminal onthe lampholder.Also
the line wire fromswitch2 connectedtothe line terminal onthe lampholder.
Switch1 connectedthe commonterminal tothe consumerunit(B16MCB), whilstthe tworemaining
line wiresconnectedinterminalsL1and L2. (L1 and L2 terminal wireswere markedaccordinglyon
installation,soeasyidentificationwouldbe possibleatthisstage.) All circuitprotectiveconductor
(CPC) wireswere connectedinthe earthterminal,includingthe CPCwire fromthe metal switching
box.
Switch2 hada line wire fromthe commontothe lampholder.TerminalsL1and L2 were connected
withL1 andL2 from switch1.
At thisstage,all switchcoverswere attachedtothe back boxes.The lampholderandCU wireswere
leftaccessible fortesting.
Dead Test
Continuitytestingwasdone withamulti-functional tester(MFT). Iusedpinconnectionsfromthe
MFT, connectedtothe positive andnegative portsonthe back of the unit.The unitwassetto ohms.
Placingthe pinsonthe lightingrose terminals,ItookreadingsforR1-R2,R1-Rn, andR2-Rn. (Whilst
takingthe readings,the correspondingconnectionswere made withinthe consumerunit,using
terminal blocks.)
The rn wastestedfromthe neutral terminal inthe ceilingrose,the r2from the earthterminal,and
the r1 fromthe looplive terminal.Whentestingthroughthe line connection,switches1and 2 were
switchedtotestthe functionality.
Insulationresistance wasalsocarriedoutwiththe MFT, usingthe crocodile clipconnections,again
inthe positive andnegative portsof the MFT. I connectedthe clipstopairedwiresinthe consumer
unit,(R1-R2,R1-Rn, and R2-Rn) the unitwas setto 500v. Whilstthe wireswere connectedIheld
downthe testbuttonon the unit;thisputs 500v throughthe circuit to testforany damage to
insulationortoughingwires.
Whentestingforcontinuity,bytestingall three wirespairedtogether, (R1-R2,R1-Rn,and R2-Rn)
thisprovespolarityinthe circuit.
3. Live test
Afterall mydeadtest wascompleted,I movedontothe live test.Thiswascarriedoutunderthe
supervisionof atutor. The consumerunitwasfirstconnectedtolive power.The masterswitchand
MCB were switchedon,providingpowertothe circuit.The switcheswere pressedsimultaneouslyto
testthe functionalityof the switchesworking.All testscame backcorrect.