Risk Management and Supply Continuity:
Establishing Low Cost Country Supply
September 13, 2011
Dragon Sourcing - 龙 源
Your Tailored Sourcing Approach to LCC Sourcing
Agenda
A. Background
B. Macro Market Understanding
C. Micro Cost To Serve
D. Managing Risk and Continuity
© 2011 Dragon Sourcing. All rights reserved.
Introduction
• Many companies, as part of their global portfolio, are manufacturing or considering
manufacturing in low-cost countries.
• Historically, the critical driver of this decision has been low-cost labor however this underplays
the total potential value in a low-cost strategy. For example, products exported from Mexico to
the United States today only include on average 5% Mexican value added, a lot of effort for a
marginal impact.
• When total costs, changing market dynamics, and supply risks are considered many
companies have been retrenching from their initial decisions. But is the pendulum swinging
too far the other way today?
• The Issues are:
– What are they keys to developing a successful Low Cost Country Strategy?
– What are the critical steps to ensuring benefit, managing risk and continuity?
– What role does Sourcing and Procurement play?
• We will explore two cases and the critical lessons learned.
© 2011 Dragon Sourcing. All rights reserved.
Driving a Strategy
• What is the driver behind my strategy?
– Low Cost? -- Expanded Capabilities?
– Market Access? -- New Growth (Acquisitions)?
• How do I choose to source or site LCC capabilities?
– Macro Economics -- Sub-Regional Dynamics
– Financials and Business Attractiveness
– Availability of local or proximate supply
• How do I manage risks?
– Political and Economic Risk
– Business and Financial Risks
– Supply Chain Risks
– Supply Risk
© 2009 Dragon Sourcing. All rights reserved.
© 2010 Dragon Sourcing. All rights reserved. 5
Massively Changing Market Dynamics
• China, Vietnam, India, Turkey Mexico and Brazil are
countries experiencing unprecedented and exponential
economic growth which offer unique opportunities (and
risks)
• After a period of decline in Chinese exports caused by
the financial crisis of 2008  exports from China to the
western world have once again reached unprecedented
speed in 2011.
• Tension in bilateral relations between the EU and China
and the US and China
• Chinese government modified its exchange rate policy
by shifting from a hard peg to the US$ to a link to a
basket of international currencies
• In addition, we are seeing…
– Renewed labor wage inflation on the eastern coast of
China
– Labor unrest in several factories that have made
headlines recently (Foxconn, Toyota)
– Significant increases in container transportation costs
– The imposition of new anti dumping taxes by US and
EU
These trends combined with changing
market dynamics is triggering some
strategic rethinking in companies' global
sourcing strategies
Source: World Bank.
Case Study Background
• About a $200 Million Dollar Division of a major company was under significant economic pressure
in its traditional manufacturing structure
• The current default strategy was to source from China, but that led to competitive vulnerability
• The issue was whether there was an opportunity to leap frog competition and gain leverage
through a low cost country strategy.
• The issue was where is the world? At what economics? And what was necessary to manage
risks?
• The analysis involved four stages:
– A Macro Look at Markets for the best cost country and location to potentially position
operations
– A Micro look at comparative economics and risks by down selected location
– Supply localization for targeted regions
– Site Selection, support contacting and launch planning
© 2009 Dragon Sourcing. All rights reserved.
Agenda
A. Background
B. Macro Market Understanding
C. Micro Cost To Serve
D. Managing Risk and Continuity
© 2011 Dragon Sourcing. All rights reserved.
© 2010 Dragon Sourcing. All rights reserved. 8
Starting Point -- Macro Market Analysis
Main Criteria
Total
Weight
Subcriteria Weight Indicators
Political stability 8% World Bank - Governance indicator
Commitment to reforms 4% Composite indicator
Corruption and bureaucracy 4% Transparency International - Corruption Perception Index
Legal framework and rule of law 4% World Bank - Governance indicator
International performance 12% External trade, product portfolio, FDI
International competitivity 12% GDP/capita, labor costs level and evolution
National performance 8% Growth, unemployment rate, inflation
Financial situation 8% Indebtness, savings and banking performance
Education 8% Literacy rate, tertiary enrolment
Human development 8% Poverty, health, sanitation, access to PC, internet
Age profile 4% Age distribution and expected evolution
Transport infrastructure 8% Ports, roads
Energy and power supply 8% Consumption, dependency, diversification
R&D expenditure 4% Public spending
TOTAL 100% 100%
Infrastructure
and
technologies
20%
Political and
legal
20%
Economic 40%
Social and
demographic
20%
© 2010 Dragon Sourcing. All rights reserved. 9
Comparison of Asian Economies
Pakistan
India
China
Thailand
Indonesia
Philippines
Vietnam
0%
2%
4%
6%
8%
10%
12%
0 500 1 000 1 500 2 000 2 500 3 000
GDP / Capita ($)
GDPGrowthRate
Political and Economic
Political Economic
IRAQ
ICELAND
VIETNAM
CHINA
THAILAND
INDIA
PHILIPPINES
INDONESIA
PAKISTAN
Politicalstability
OECD
SOMALIA
ICELAND
VIETNAM
CHINA
THAILAND
INDIA
PHILIPPINES
INDONESIA
PAKISTAN
RuleofLaw
OECD
Source:WorldBank
Population
Sources:ADB,IMF
MEXICO
MEXICO
© 2010 Dragon Sourcing. All rights reserved. 10
Energy per capita
(kg of oil equivalent)
and per sources
0
250
500
750
1 000
1 250
1 500
China India Indonesia Pakistan Philippines Thailand Vietnam
Coal Gas
Hydro Oil
Nuclear Geothermal
Social and Infrastructure
Socio-demographic Infrastructure
Own
production
Source:WorldBank
MALI
UNITED STATES
VIETNAM
CHINA
THAILAND
INDIA
PHILIPPINES
INDONESIA
PAKISTAN
Poverty/Wealth
Health
AccessPC/internet
TAJIKISTAN
UNITED STATES
VIETNAM
CHINA
THAILAND
INDIA
PHILIPPINES
INDONESIA
PAKISTAN
Source:UnitedNationsDevpmtPrg.(UNDP)
EQUAT. GUINEA
UNITED STATES
VIETNAM
CHINA
THAILAND
INDIA
PHILIPPINES
INDONESIA
PAKISTAN
Source:UnitedNationsDevpmtPrg.(UNDP)
Source:ADB,WorldBank,JapanBank
forInternationalCooperation(JBIC)
Education
Pakistan
India
Thailand
Philippines
Vietnam
Indonesia
China
40%
50%
60%
70%
80%
90%
100%
0% 10% 20% 30% 40% 50%
University enrolment
Literacyrate
Investment in education
= 1% GDP Transportation (roads, maritime)
Pakistan
India
Vietnam
Thailand
Philippines
China
Indonesia
0
10
20
30
40
0 5 10 15 20
Paved road density
(km / 100km2)
Maritime
export(TEU/
1000$export)
Investment in infrastructure
= 1% of GDP
*
(*) TEU: Ton-Equivalent Unit
© 2010 Dragon Sourcing. All rights reserved. 11
One of Many Economic Drivers -- Relative
Factor
Sub Criteria
Total tax rate
(TTR)
Wages &
Social Security Logistics Cost
Import Duty
Rates
 China offer highest social security to workers.
 Vietnam is the lowest in total average wages.
Social Security
Source: www. eiu.com
China 20-30%
Mexico 15-25%
Vietnam 19.0%
Malaysia 12.0%
Indonesia 4.89%
Thailand 4.5%
Social Security
US $ 490-530
US $ 529
US $ 390
US $ 281
US $ 138
China
Malaysia
Thailand
Indonesia
Vietnam
Total average wages
including Social Security
Mexico US $ 495- 538
Macro View of Supply Market Attractiveness…
© 2010 Dragon Sourcing. All rights reserved.
• At a Macro Level Certain markets continue to be very attractive…
• … but need to understand in both a static and dynamic context and in the context of your strategy
.. And a Total Cost View of Relative Value Added Costs
© 2010 Dragon Sourcing. All rights reserved. 13
$3,203,983
$3,736,323
$2,761,897
$3,722,127
$3,647,270
Agenda
A. Background
B. Macro Market Understanding
C. Micro Cost To Serve
D. Managing Risk and Continuity
© 2011 Dragon Sourcing. All rights reserved.
Beyond Country Economics  Regional Understanding
© 2009 Dragon Sourcing. All rights reserved.
• What skill base and capabilities exist?
• What are the financial incentives?
• What is the local infrastructure?
• What is the export infrastructure?
• How accessible and comfortable for
expats or visitors?
Critical Issue Available Supply as purchase costs were
80% of total costs
© 2009 Dragon Sourcing. All rights reserved.
Critical - Sourcing and Supply Market Understanding
© 2009 Dragon Sourcing. All rights reserved.
Top 50 Best Qualified
China 40
Mexico 6
Vietnam 2
Indonesia 2
A strategic view to Supplier capabilities
© 2010 Dragon Sourcing. All rights reserved. 18
Laminates
Machined Castings
Tube Housing
Leadwire
Hardware
Painting
Plastics
And, “safe” locations proximate to the market and supply
base
19© 2012 Dragon Sourcing. All rights reserved.
Target C
Target B
Target A
Supported by Detailed Site Selection
• Operates as an industrial as an
industrial developer in 1987 with 5
major developments between
Tijuana and Mexicali
• Services
– Maximum Security: Controlled Access,
Wall Perimeter and CCTV 24/7
– 7 Public Bus lines
– Food, Medical, police and fire either
outside main gain or within 5km
– Solar energy
– Concrete Tilt-Up Buildings with the
same quality standard as US.
© 2012 Dragon Sourcing. All rights reserved. 20
Proposed - El Dorado Park
Established: 2000
Size: 34 ha
Sq ft Sold: 5,621,155
Facility – 78,500 sq ft, $0.35/sq ft
Bringing It Together – In the Client’s Case -- Mexico
© 2010 Dragon Sourcing. All rights reserved.
• Beyond The Macro the Key Became…
– Specifically targeting regions and
capabilities
– Identifying and qualifying suppliers
– Sourcing and working with suppliers
for low cost supply
– Mitigating sub-scale operations and
lack of local knowledge
Time Phased Estimate of Results
© 2012 Dragon Sourcing. All rights reserved. 22
2012 2013 2014 2015
Product A Forecast - 80,540 146,081 145,631
Hours Fcst - 18,920 34,317 34,211
People Fcst 0 10.31 18.13 18.08
Staff Plan 0 14.42 19.17 15.50
Product B Forecast - 3,916 22,910 23,374
Hours Fcst - 2,136 12,499 12,752
People Fcst 0 1.33 7.17 7.33
Staff Plan 0 2.83 8.00 7.50
Product C Forecast 26,709 169,625 170,938 172,900
Hours Fcst 5,427 34,464 34,731 35,130
People Fcst 13.00 18.58 19.50 19.75
Staff Plan 16.67 18.58 19.17 20.08
Total Forecast 26,709 254,081 339,929 341,905
Hours Fcst 5,427 55,521 81,547 82,093
People Fcst 13.00 30.22 44.80 45.16
Staff Plan 16.67 35.83 46.33 43.08
Draft Plan
2012 2013 2014 2015
Baseline Manufacturing Costs
Product A -$ 896,709$ 1,626,417$ 1,621,407$
Product B -$ 119,880$ 701,338$ 715,542$
Product C -$ 1,016,589$ 2,327,755$ 2,336,949$
New Manfacturing Costs
Labor -$ 110,943$ 174,722$ 147,924$
Mfg Overhead 380,400$ 965,800$ 965,800$ 965,800$
Support Overhead 290,444$ 1,253,895$ 1,253,895$ 1,253,895$
Les LU Absorbed (143,408)$ (910,772)$ (917,823)$ (928,357)$
Total Manufacturing 527,437$ 1,419,866$ 1,476,593$ 1,439,262$
Net Manufacturing savings (527,437)$ (403,277)$ 851,162$ 897,687$
Lower Unit Savings 114,488$ 727,105$ 732,735$ 741,144$
Materials Savings 266,140$ 532,527$ 532,571$
Total Manufacturing Savings (412,949)$ 589,968$ 2,116,423$ 2,171,401$
Less Unasorbed Burden (13,056)$ (186,308)$ (461,507)$ (461,507)$
Less Logistics Penalty (57,084) (204,916)$ (410,021)$ (410,055)$
(483,088)$ 198,744$ 1,244,895$ 1,299,839$
Draft Plan
Net savings
Agenda
A. Background
B. Macro Market Understanding
C. Micro Cost To Serve
D. Managing Risk and Continuity
© 2011 Dragon Sourcing. All rights reserved.
Managing Political and Economic Risk – Market Intelligence
© 2011 Dragon Sourcing. All rights reserved. 24
CLIENT
BENEFITS
Clarifying
Supply Chain
Risks
Discovering
Market
Opportunities
Informed
Buying
Decisions
PROCUREMENT INTELLIGENCE
SUITE
Supply Market Analysis
Supplier Analysis
Industry Best Practices Analysis
Price Tracking & Forecasting
Category Executive Dashboards
Dynamic Should-Cost Models
Value Chain Analysis
Supplier Financial Assessment
Supplier Ethics Assessment
- Which countries have potential?
- Should we buy-in or manufacture?
- Who are the top suppliers?
- What are the market dynamics?
- Should we buy now or later?
- Latest category news?
- What will the impact of inflation be?
- Is the market trending up?
- What are the raw materials?
- What are the key risks to supply?
- Do these suppliers meet our CSR
requirements?
KEY CLIENT
QUESTIONS
Business Challenges
Supplier Performance
Management
Improve Cost Position
Approach
• Competent Global Sourcing
• Focus on Key Cost Driver
• Strategic Globalization Plan
• Supplier Selection Process
• Systematic Supplier Performance
Management
• Technical Support (Six Sigma/Lean)
Competitiveness • Flexible Supply Chain
• Compresses Supply Chain Lead-times
• Supply Chain Integration
Managing Business Risk – A Clear Strategy
Results
Reduced Cost
Improved
Market Position
Global Supply Chain Becomes Competitive Advantage
Improved PPM
>95% OTD
Managing Business Risk - In Country Management Resources
© 2010 Dragon Sourcing. All rights reserved.
DS Mexico
•Over Twenty Years of Aerospace Supply Chain Experience
• Experienced in Developing /Maintaining Supplier Performance
• Enhanced Supplier Management Process
• Strong Collaborative Effort with Mexican Economical Development
Staff
• Experienced in High Risk Sourcing to Achieve Improved Business
Performance
• Strong Bilingual In-Country Sourcing Team
Managing Supply Risk - Localize Supplier Management
© 2010 Dragon Sourcing. All rights reserved.
Overall methodology & 7-step process
Managing Supply Chain Risk - Formalized In Country
Supplier and Quality Management
Sampling & Criterias
Checkitem #
Box # 
Marking Inner carton Mug Quantity Mug heigth
Mug upper
diameter
Mug lower
diameter
Wall
thickness
Mug weigth Material type Quality
1 OK OK 48 104.3 64.9 3.6 326 OK OK
2 OK OK 48 103.4 64.5 4.2 346 OK OK
3 OK OK 48 104 64.6 3.9 344 OK OK
4 OK OK 48 104.6 64.8 3.8 317 OK OK
5 OK OK 48 104.3 57 3.6 308 OK OK
6 OK OK 48 104.8 61 3.8 317 OK OK
7 OK OK 48 103.7 64.5 3.9 328 OK OK
8 OK NO 48 103.8 62 3.9 345 OK OK
9 OK OK 48 103.3 64.1 3.1 322 OK OK
10 OK OK 48 103.2 63.4 3.7 325 OK OK
11 OK OK 48 104.4 64.8 3.9 317 OK OK
12 OK OK 48 102.3 64.2 3.2 316 OK OK
13 OK OK 48 105.4 63 4 316 MO OK
14 OK OK 45 105.6 65 4 322 OK OK
15 OK OK 48 106.3 65.6 4.1 357 OK OK
16 OK OK 48 103.4 65.5 3.9 311 NO OK
17 OK NO 48 104.7 64.1 3.8 300 OK OK
18 OK OK 48 104 60 3.8 342 OK OK
28
Supplier Summary
Supplier Capabilities
Supplier Assessments
On Going
QC Reporting and
Supplier Development
Dragon Sourcing - 龙 源
Your Tailored Sourcing Approach to LCC Sourcing
Steve Griffiths
Managing Director USA
Phone: 216-533-8972
steven.griffiths@dragonsourcing .com
Richard Laub
CEO
Phone: +32 (499) 56.72.71
richard.laub@dragonsourcing .com

More Related Content

What's hot

Drivers, globalization of market, production,
Drivers, globalization of market, production,Drivers, globalization of market, production,
Drivers, globalization of market, production,Anmol Nekpuri
 
Newman aerc mar2017_final
Newman aerc mar2017_finalNewman aerc mar2017_final
Newman aerc mar2017_finalUNU-WIDER
 
Globalization in detail and international business
Globalization in detail and international businessGlobalization in detail and international business
Globalization in detail and international businessYashraj Tahilramani
 
Hoekman wbg trade strategy jamaica
Hoekman wbg trade strategy jamaicaHoekman wbg trade strategy jamaica
Hoekman wbg trade strategy jamaicacgrowth
 
Emerging Markets: Pathways to Selection
Emerging Markets: Pathways to Selection Emerging Markets: Pathways to Selection
Emerging Markets: Pathways to Selection Kimberlee Luce
 
Globalization by umair farooq mughal
Globalization by umair farooq mughalGlobalization by umair farooq mughal
Globalization by umair farooq mughalUmair Farooq Mughal
 
3 eso unit 7 answer key
3 eso unit 7 answer key3 eso unit 7 answer key
3 eso unit 7 answer keyRubén López
 
Case study: FDI in Automobile Sector in India
Case study: FDI in Automobile Sector in IndiaCase study: FDI in Automobile Sector in India
Case study: FDI in Automobile Sector in IndiaRahul S
 
Impact Hub_Abidjan - Columbia Ci3
Impact Hub_Abidjan - Columbia Ci3Impact Hub_Abidjan - Columbia Ci3
Impact Hub_Abidjan - Columbia Ci3Kathy Liu, MPA CIPP
 
FTA, Free trade agreement, USA, ASEAN AEC
FTA, Free trade agreement, USA, ASEAN AECFTA, Free trade agreement, USA, ASEAN AEC
FTA, Free trade agreement, USA, ASEAN AECShawn Goh
 
Emerging markets presentation+part+2
Emerging markets presentation+part+2Emerging markets presentation+part+2
Emerging markets presentation+part+2Patrick Ressa
 
Global Business Challenges
Global Business ChallengesGlobal Business Challenges
Global Business ChallengesHimanshusood88
 
Foreign trade and its importance in the economy of Iran in the international ...
Foreign trade and its importance in the economy of Iran in the international ...Foreign trade and its importance in the economy of Iran in the international ...
Foreign trade and its importance in the economy of Iran in the international ...Private
 
[Challenge:Future] The Vision: The Future of Work
[Challenge:Future] The Vision: The Future of Work[Challenge:Future] The Vision: The Future of Work
[Challenge:Future] The Vision: The Future of WorkChallenge:Future
 
Emerging trends in global trade
Emerging trends in global tradeEmerging trends in global trade
Emerging trends in global tradePaul Authachinda
 
Eco 410 week 2 quiz strayer
Eco 410 week 2 quiz   strayerEco 410 week 2 quiz   strayer
Eco 410 week 2 quiz strayerLindaAdams2017
 

What's hot (20)

Drivers, globalization of market, production,
Drivers, globalization of market, production,Drivers, globalization of market, production,
Drivers, globalization of market, production,
 
Newman aerc mar2017_final
Newman aerc mar2017_finalNewman aerc mar2017_final
Newman aerc mar2017_final
 
Globalization in detail and international business
Globalization in detail and international businessGlobalization in detail and international business
Globalization in detail and international business
 
Hoekman wbg trade strategy jamaica
Hoekman wbg trade strategy jamaicaHoekman wbg trade strategy jamaica
Hoekman wbg trade strategy jamaica
 
Be
BeBe
Be
 
Emerging Markets: Pathways to Selection
Emerging Markets: Pathways to Selection Emerging Markets: Pathways to Selection
Emerging Markets: Pathways to Selection
 
Globalization by umair farooq mughal
Globalization by umair farooq mughalGlobalization by umair farooq mughal
Globalization by umair farooq mughal
 
3 eso unit 7 answer key
3 eso unit 7 answer key3 eso unit 7 answer key
3 eso unit 7 answer key
 
Globalisation Stalled? Exploring the shifting landscapes of 21st century supp...
Globalisation Stalled? Exploring the shifting landscapes of 21st century supp...Globalisation Stalled? Exploring the shifting landscapes of 21st century supp...
Globalisation Stalled? Exploring the shifting landscapes of 21st century supp...
 
Ethiopia
EthiopiaEthiopia
Ethiopia
 
Case study: FDI in Automobile Sector in India
Case study: FDI in Automobile Sector in IndiaCase study: FDI in Automobile Sector in India
Case study: FDI in Automobile Sector in India
 
Emerging Markes [SAV Lecture Notes]
Emerging Markes [SAV Lecture Notes]Emerging Markes [SAV Lecture Notes]
Emerging Markes [SAV Lecture Notes]
 
Impact Hub_Abidjan - Columbia Ci3
Impact Hub_Abidjan - Columbia Ci3Impact Hub_Abidjan - Columbia Ci3
Impact Hub_Abidjan - Columbia Ci3
 
FTA, Free trade agreement, USA, ASEAN AEC
FTA, Free trade agreement, USA, ASEAN AECFTA, Free trade agreement, USA, ASEAN AEC
FTA, Free trade agreement, USA, ASEAN AEC
 
Emerging markets presentation+part+2
Emerging markets presentation+part+2Emerging markets presentation+part+2
Emerging markets presentation+part+2
 
Global Business Challenges
Global Business ChallengesGlobal Business Challenges
Global Business Challenges
 
Foreign trade and its importance in the economy of Iran in the international ...
Foreign trade and its importance in the economy of Iran in the international ...Foreign trade and its importance in the economy of Iran in the international ...
Foreign trade and its importance in the economy of Iran in the international ...
 
[Challenge:Future] The Vision: The Future of Work
[Challenge:Future] The Vision: The Future of Work[Challenge:Future] The Vision: The Future of Work
[Challenge:Future] The Vision: The Future of Work
 
Emerging trends in global trade
Emerging trends in global tradeEmerging trends in global trade
Emerging trends in global trade
 
Eco 410 week 2 quiz strayer
Eco 410 week 2 quiz   strayerEco 410 week 2 quiz   strayer
Eco 410 week 2 quiz strayer
 

Similar to Case Study-Risk Management & Supply Continuity for Low Cost Country Supply

2. fundamentals of global strategy 2014 2 st
2. fundamentals of global strategy 2014 2 st2. fundamentals of global strategy 2014 2 st
2. fundamentals of global strategy 2014 2 stAlejandra Pasqualotto
 
Industrial Minerals Congress
Industrial Minerals CongressIndustrial Minerals Congress
Industrial Minerals CongressRio Tinto plc
 
FDI is a savier for Vietnam Recovery
FDI is a savier for Vietnam RecoveryFDI is a savier for Vietnam Recovery
FDI is a savier for Vietnam RecoveryDienPham20
 
Cairo Brokerage Conference- Global MBA Brazil
Cairo Brokerage Conference- Global MBA BrazilCairo Brokerage Conference- Global MBA Brazil
Cairo Brokerage Conference- Global MBA BrazilGlobal MBA Brazil
 
Doing Business in Malaysia, A Business and Economic overview
Doing Business in Malaysia, A Business and Economic overviewDoing Business in Malaysia, A Business and Economic overview
Doing Business in Malaysia, A Business and Economic overviewGertjan Tijms
 
Naat bat louisville, ky 07 sep 2011 - 11 09 05 ep
Naat bat louisville, ky   07 sep 2011 - 11 09 05 epNaat bat louisville, ky   07 sep 2011 - 11 09 05 ep
Naat bat louisville, ky 07 sep 2011 - 11 09 05 epEmmanuel Pouliquen
 
Current Challenges in International Business
Current Challenges in International BusinessCurrent Challenges in International Business
Current Challenges in International BusinessOliver Parker
 
Mooc final project Sept 2020
Mooc final project Sept 2020Mooc final project Sept 2020
Mooc final project Sept 2020Samuel Djaryang
 
How can india become globally competitive
How can india become globally competitiveHow can india become globally competitive
How can india become globally competitiveShwetan Burkule
 
Economic Development 411 | 2015 | Sarah Raehl
Economic Development 411 | 2015 | Sarah RaehlEconomic Development 411 | 2015 | Sarah Raehl
Economic Development 411 | 2015 | Sarah RaehlOne Columbus
 
Sustainability and Disruptions
Sustainability and DisruptionsSustainability and Disruptions
Sustainability and DisruptionsSDGsPlus
 
15 globalization
15 globalization15 globalization
15 globalizationwei liang
 
Mexico country report
Mexico  country reportMexico  country report
Mexico country reportIrr India
 
Global Drivers for Sustainable Business September 2012
Global Drivers for Sustainable Business September 2012Global Drivers for Sustainable Business September 2012
Global Drivers for Sustainable Business September 2012Innovation Forum Publishing
 
What is next for Hamilton, Ontario - September 2022.pptx
What is next for Hamilton, Ontario - September 2022.pptxWhat is next for Hamilton, Ontario - September 2022.pptx
What is next for Hamilton, Ontario - September 2022.pptxpaul young cpa, cga
 
Supply Chain Disruptions: Growth, Transformations and Implications for Panama
Supply Chain Disruptions: Growth, Transformations and Implications for PanamaSupply Chain Disruptions: Growth, Transformations and Implications for Panama
Supply Chain Disruptions: Growth, Transformations and Implications for PanamaBenjamin Gordon
 
Study on Vietnam's development
Study on Vietnam's developmentStudy on Vietnam's development
Study on Vietnam's developmentOfficience
 

Similar to Case Study-Risk Management & Supply Continuity for Low Cost Country Supply (20)

2. fundamentals of global strategy 2014 2 st
2. fundamentals of global strategy 2014 2 st2. fundamentals of global strategy 2014 2 st
2. fundamentals of global strategy 2014 2 st
 
Industrial Minerals Congress
Industrial Minerals CongressIndustrial Minerals Congress
Industrial Minerals Congress
 
FDI is a savier for Vietnam Recovery
FDI is a savier for Vietnam RecoveryFDI is a savier for Vietnam Recovery
FDI is a savier for Vietnam Recovery
 
Cairo Brokerage Conference- Global MBA Brazil
Cairo Brokerage Conference- Global MBA BrazilCairo Brokerage Conference- Global MBA Brazil
Cairo Brokerage Conference- Global MBA Brazil
 
Malaysia; A Business and Economic overview
Malaysia; A Business and Economic overviewMalaysia; A Business and Economic overview
Malaysia; A Business and Economic overview
 
Doing Business in Malaysia, A Business and Economic overview
Doing Business in Malaysia, A Business and Economic overviewDoing Business in Malaysia, A Business and Economic overview
Doing Business in Malaysia, A Business and Economic overview
 
Naat bat louisville, ky 07 sep 2011 - 11 09 05 ep
Naat bat louisville, ky   07 sep 2011 - 11 09 05 epNaat bat louisville, ky   07 sep 2011 - 11 09 05 ep
Naat bat louisville, ky 07 sep 2011 - 11 09 05 ep
 
Current Challenges in International Business
Current Challenges in International BusinessCurrent Challenges in International Business
Current Challenges in International Business
 
Mooc final project Sept 2020
Mooc final project Sept 2020Mooc final project Sept 2020
Mooc final project Sept 2020
 
How can india become globally competitive
How can india become globally competitiveHow can india become globally competitive
How can india become globally competitive
 
Iyer
IyerIyer
Iyer
 
Economic Development 411 | 2015 | Sarah Raehl
Economic Development 411 | 2015 | Sarah RaehlEconomic Development 411 | 2015 | Sarah Raehl
Economic Development 411 | 2015 | Sarah Raehl
 
Sustainability and Disruptions
Sustainability and DisruptionsSustainability and Disruptions
Sustainability and Disruptions
 
15 globalization
15 globalization15 globalization
15 globalization
 
Mexico country report
Mexico  country reportMexico  country report
Mexico country report
 
Global Drivers for Sustainable Business September 2012
Global Drivers for Sustainable Business September 2012Global Drivers for Sustainable Business September 2012
Global Drivers for Sustainable Business September 2012
 
What is next for Hamilton, Ontario - September 2022.pptx
What is next for Hamilton, Ontario - September 2022.pptxWhat is next for Hamilton, Ontario - September 2022.pptx
What is next for Hamilton, Ontario - September 2022.pptx
 
4232369.ppt
4232369.ppt4232369.ppt
4232369.ppt
 
Supply Chain Disruptions: Growth, Transformations and Implications for Panama
Supply Chain Disruptions: Growth, Transformations and Implications for PanamaSupply Chain Disruptions: Growth, Transformations and Implications for Panama
Supply Chain Disruptions: Growth, Transformations and Implications for Panama
 
Study on Vietnam's development
Study on Vietnam's developmentStudy on Vietnam's development
Study on Vietnam's development
 

More from John William

Sheet Metal Fabrication & Machining Parts Case Study
Sheet Metal Fabrication & Machining Parts Case StudySheet Metal Fabrication & Machining Parts Case Study
Sheet Metal Fabrication & Machining Parts Case StudyJohn William
 
Sanitizer & Disinfectants During COVID 19 – A Brief Study
Sanitizer & Disinfectants During COVID 19 – A Brief StudySanitizer & Disinfectants During COVID 19 – A Brief Study
Sanitizer & Disinfectants During COVID 19 – A Brief StudyJohn William
 
Cooling Towel Sourcing Project​ ​- Case Study​
Cooling Towel Sourcing Project​ ​- Case Study​Cooling Towel Sourcing Project​ ​- Case Study​
Cooling Towel Sourcing Project​ ​- Case Study​John William
 
Newsletter on PPE: Classification of PPE and CE Certification Process in EU
Newsletter on PPE: Classification of PPE and CE Certification Process in EUNewsletter on PPE: Classification of PPE and CE Certification Process in EU
Newsletter on PPE: Classification of PPE and CE Certification Process in EUJohn William
 
Phenolic Resin Sourcing Project Case Study
Phenolic Resin Sourcing Project Case StudyPhenolic Resin Sourcing Project Case Study
Phenolic Resin Sourcing Project Case StudyJohn William
 
Study on Sourcing Opportunities in Vietnam
Study on Sourcing Opportunities in VietnamStudy on Sourcing Opportunities in Vietnam
Study on Sourcing Opportunities in VietnamJohn William
 
Study on Sourcing Opportunities in Brazil
Study on Sourcing Opportunities in BrazilStudy on Sourcing Opportunities in Brazil
Study on Sourcing Opportunities in BrazilJohn William
 
Study on Sourcing Opportunities in Ethiopia
Study on Sourcing Opportunities in EthiopiaStudy on Sourcing Opportunities in Ethiopia
Study on Sourcing Opportunities in EthiopiaJohn William
 
Sourcing Opportunities in Malaysia
Sourcing Opportunities in MalaysiaSourcing Opportunities in Malaysia
Sourcing Opportunities in MalaysiaJohn William
 
Study on Sourcing Opportunities in Pakistan
Study on Sourcing Opportunities in PakistanStudy on Sourcing Opportunities in Pakistan
Study on Sourcing Opportunities in PakistanJohn William
 
Case Study on Sourcing Opportunities in South Africa
Case Study on Sourcing Opportunities in South AfricaCase Study on Sourcing Opportunities in South Africa
Case Study on Sourcing Opportunities in South AfricaJohn William
 
Case Study on Sourcing Opportunities in Myanmar
Case Study on Sourcing Opportunities in MyanmarCase Study on Sourcing Opportunities in Myanmar
Case Study on Sourcing Opportunities in MyanmarJohn William
 
Study on Sourcing Opportunities in Indonesia
Study on Sourcing Opportunities in IndonesiaStudy on Sourcing Opportunities in Indonesia
Study on Sourcing Opportunities in IndonesiaJohn William
 
Battery Sourcing Case Study by Dragon Sourcing
Battery Sourcing Case Study by Dragon SourcingBattery Sourcing Case Study by Dragon Sourcing
Battery Sourcing Case Study by Dragon SourcingJohn William
 
Gear Box Case Study by Dragon Sourcing
Gear Box Case Study by Dragon SourcingGear Box Case Study by Dragon Sourcing
Gear Box Case Study by Dragon SourcingJohn William
 
Slewing Bearings Case Study by Dragon Sourcing
Slewing Bearings Case Study by Dragon SourcingSlewing Bearings Case Study by Dragon Sourcing
Slewing Bearings Case Study by Dragon SourcingJohn William
 
Decorative Pots Case Study by Dragon Sourcing
Decorative Pots Case Study by Dragon SourcingDecorative Pots Case Study by Dragon Sourcing
Decorative Pots Case Study by Dragon SourcingJohn William
 
Safety Vest, Cotton Bags, College Bags Sourcing Project Case Study
Safety Vest, Cotton Bags, College Bags Sourcing Project Case StudySafety Vest, Cotton Bags, College Bags Sourcing Project Case Study
Safety Vest, Cotton Bags, College Bags Sourcing Project Case StudyJohn William
 
FAN Induction Motors Sourcing Project Case Study by Dragon Sourcing
FAN Induction Motors Sourcing Project Case Study by Dragon Sourcing  FAN Induction Motors Sourcing Project Case Study by Dragon Sourcing
FAN Induction Motors Sourcing Project Case Study by Dragon Sourcing John William
 

More from John William (20)

Sheet Metal Fabrication & Machining Parts Case Study
Sheet Metal Fabrication & Machining Parts Case StudySheet Metal Fabrication & Machining Parts Case Study
Sheet Metal Fabrication & Machining Parts Case Study
 
Sanitizer & Disinfectants During COVID 19 – A Brief Study
Sanitizer & Disinfectants During COVID 19 – A Brief StudySanitizer & Disinfectants During COVID 19 – A Brief Study
Sanitizer & Disinfectants During COVID 19 – A Brief Study
 
Cooling Towel Sourcing Project​ ​- Case Study​
Cooling Towel Sourcing Project​ ​- Case Study​Cooling Towel Sourcing Project​ ​- Case Study​
Cooling Towel Sourcing Project​ ​- Case Study​
 
Newsletter on PPE: Classification of PPE and CE Certification Process in EU
Newsletter on PPE: Classification of PPE and CE Certification Process in EUNewsletter on PPE: Classification of PPE and CE Certification Process in EU
Newsletter on PPE: Classification of PPE and CE Certification Process in EU
 
Newsletter on PPE
Newsletter on PPENewsletter on PPE
Newsletter on PPE
 
Phenolic Resin Sourcing Project Case Study
Phenolic Resin Sourcing Project Case StudyPhenolic Resin Sourcing Project Case Study
Phenolic Resin Sourcing Project Case Study
 
Study on Sourcing Opportunities in Vietnam
Study on Sourcing Opportunities in VietnamStudy on Sourcing Opportunities in Vietnam
Study on Sourcing Opportunities in Vietnam
 
Study on Sourcing Opportunities in Brazil
Study on Sourcing Opportunities in BrazilStudy on Sourcing Opportunities in Brazil
Study on Sourcing Opportunities in Brazil
 
Study on Sourcing Opportunities in Ethiopia
Study on Sourcing Opportunities in EthiopiaStudy on Sourcing Opportunities in Ethiopia
Study on Sourcing Opportunities in Ethiopia
 
Sourcing Opportunities in Malaysia
Sourcing Opportunities in MalaysiaSourcing Opportunities in Malaysia
Sourcing Opportunities in Malaysia
 
Study on Sourcing Opportunities in Pakistan
Study on Sourcing Opportunities in PakistanStudy on Sourcing Opportunities in Pakistan
Study on Sourcing Opportunities in Pakistan
 
Case Study on Sourcing Opportunities in South Africa
Case Study on Sourcing Opportunities in South AfricaCase Study on Sourcing Opportunities in South Africa
Case Study on Sourcing Opportunities in South Africa
 
Case Study on Sourcing Opportunities in Myanmar
Case Study on Sourcing Opportunities in MyanmarCase Study on Sourcing Opportunities in Myanmar
Case Study on Sourcing Opportunities in Myanmar
 
Study on Sourcing Opportunities in Indonesia
Study on Sourcing Opportunities in IndonesiaStudy on Sourcing Opportunities in Indonesia
Study on Sourcing Opportunities in Indonesia
 
Battery Sourcing Case Study by Dragon Sourcing
Battery Sourcing Case Study by Dragon SourcingBattery Sourcing Case Study by Dragon Sourcing
Battery Sourcing Case Study by Dragon Sourcing
 
Gear Box Case Study by Dragon Sourcing
Gear Box Case Study by Dragon SourcingGear Box Case Study by Dragon Sourcing
Gear Box Case Study by Dragon Sourcing
 
Slewing Bearings Case Study by Dragon Sourcing
Slewing Bearings Case Study by Dragon SourcingSlewing Bearings Case Study by Dragon Sourcing
Slewing Bearings Case Study by Dragon Sourcing
 
Decorative Pots Case Study by Dragon Sourcing
Decorative Pots Case Study by Dragon SourcingDecorative Pots Case Study by Dragon Sourcing
Decorative Pots Case Study by Dragon Sourcing
 
Safety Vest, Cotton Bags, College Bags Sourcing Project Case Study
Safety Vest, Cotton Bags, College Bags Sourcing Project Case StudySafety Vest, Cotton Bags, College Bags Sourcing Project Case Study
Safety Vest, Cotton Bags, College Bags Sourcing Project Case Study
 
FAN Induction Motors Sourcing Project Case Study by Dragon Sourcing
FAN Induction Motors Sourcing Project Case Study by Dragon Sourcing  FAN Induction Motors Sourcing Project Case Study by Dragon Sourcing
FAN Induction Motors Sourcing Project Case Study by Dragon Sourcing
 

Recently uploaded

Call Girls In Sector 29, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 29, (Gurgaon) Call Us. 9711911712Call Girls In Sector 29, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 29, (Gurgaon) Call Us. 9711911712Delhi Escorts Service
 
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...riyaescorts54
 
9811611494,Low Rate Call Girls In Connaught Place Delhi 24hrs Available
9811611494,Low Rate Call Girls In Connaught Place Delhi 24hrs Available9811611494,Low Rate Call Girls In Connaught Place Delhi 24hrs Available
9811611494,Low Rate Call Girls In Connaught Place Delhi 24hrs Availablenitugupta1209
 
Call Girls In Sector 90, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 90, (Gurgaon) Call Us. 9711911712Call Girls In Sector 90, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 90, (Gurgaon) Call Us. 9711911712Delhi Escorts Service
 
9643097474 Full Enjoy @24/7 Call Girls In Laxmi Nagar Delhi Ncr
9643097474 Full Enjoy @24/7 Call Girls In Laxmi Nagar Delhi Ncr9643097474 Full Enjoy @24/7 Call Girls In Laxmi Nagar Delhi Ncr
9643097474 Full Enjoy @24/7 Call Girls In Laxmi Nagar Delhi Ncrthapariya601
 
9643097474 Full Enjoy @24/7 Call Girls in Paschim Vihar Delhi NCR
9643097474 Full Enjoy @24/7 Call Girls in Paschim Vihar Delhi NCR9643097474 Full Enjoy @24/7 Call Girls in Paschim Vihar Delhi NCR
9643097474 Full Enjoy @24/7 Call Girls in Paschim Vihar Delhi NCRthapariya601
 
NAGPUR CALL GIRL 92628*71154 NAGPUR CALL
NAGPUR CALL GIRL 92628*71154 NAGPUR CALLNAGPUR CALL GIRL 92628*71154 NAGPUR CALL
NAGPUR CALL GIRL 92628*71154 NAGPUR CALLNiteshKumar82226
 
100% Real Call Girls In Hazrat Nizamuddin Railway Station Delhi | Just Call 9...
100% Real Call Girls In Hazrat Nizamuddin Railway Station Delhi | Just Call 9...100% Real Call Girls In Hazrat Nizamuddin Railway Station Delhi | Just Call 9...
100% Real Call Girls In Hazrat Nizamuddin Railway Station Delhi | Just Call 9...Delhi Escorts Service
 
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝thapagita
 
Genuine Call Girls In {Mahipalpur Delhi} 9667938988 Indian Russian High Profi...
Genuine Call Girls In {Mahipalpur Delhi} 9667938988 Indian Russian High Profi...Genuine Call Girls In {Mahipalpur Delhi} 9667938988 Indian Russian High Profi...
Genuine Call Girls In {Mahipalpur Delhi} 9667938988 Indian Russian High Profi...aakahthapa70
 
(9599264170) ↫ Call Girls In Rk Puram ↫ Delhi NCR
(9599264170) ↫ Call Girls In Rk Puram ↫ Delhi NCR(9599264170) ↫ Call Girls In Rk Puram ↫ Delhi NCR
(9599264170) ↫ Call Girls In Rk Puram ↫ Delhi NCREscort Service
 
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...aakahthapa70
 
9899855202 Call Girls In Goa This Ads Is Only For Those Clients Who Are Looki...
9899855202 Call Girls In Goa This Ads Is Only For Those Clients Who Are Looki...9899855202 Call Girls In Goa This Ads Is Only For Those Clients Who Are Looki...
9899855202 Call Girls In Goa This Ads Is Only For Those Clients Who Are Looki...delhincr993
 
Call Girls in Janakpuri Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Janakpuri Delhi 💯 Call Us 🔝9667422720🔝Call Girls in Janakpuri Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Janakpuri Delhi 💯 Call Us 🔝9667422720🔝Lipikasharma29
 
Call Girls In Sector 26, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 26, (Gurgaon) Call Us. 9711911712Call Girls In Sector 26, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 26, (Gurgaon) Call Us. 9711911712Delhi Escorts Service
 
Call Girls In Naraina (Delhi) +91-9667422720 Escorts Service
Call Girls In Naraina (Delhi) +91-9667422720 Escorts ServiceCall Girls In Naraina (Delhi) +91-9667422720 Escorts Service
Call Girls In Naraina (Delhi) +91-9667422720 Escorts ServiceLipikasharma29
 
Call Girls In Majnu-ka-Tilla 9711800081 Low Cheap Price ...
Call Girls In Majnu-ka-Tilla 9711800081 Low Cheap Price ...Call Girls In Majnu-ka-Tilla 9711800081 Low Cheap Price ...
Call Girls In Majnu-ka-Tilla 9711800081 Low Cheap Price ...gitathapa4
 
Call Girls in Chattarpur Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Chattarpur Delhi 💯 Call Us 🔝9667422720🔝Call Girls in Chattarpur Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Chattarpur Delhi 💯 Call Us 🔝9667422720🔝Lipikasharma29
 
Book Call Girls in Lahore || 03070433345 || Young, Hot, Sexy, VIP Girls Avail...
Book Call Girls in Lahore || 03070433345 || Young, Hot, Sexy, VIP Girls Avail...Book Call Girls in Lahore || 03070433345 || Young, Hot, Sexy, VIP Girls Avail...
Book Call Girls in Lahore || 03070433345 || Young, Hot, Sexy, VIP Girls Avail...Ayesha Khan
 

Recently uploaded (20)

Call Girls In Sector 29, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 29, (Gurgaon) Call Us. 9711911712Call Girls In Sector 29, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 29, (Gurgaon) Call Us. 9711911712
 
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...
Hot Vip Call Girls Service In Sector 149,9818099198 Young Female Escorts Serv...
 
9811611494,Low Rate Call Girls In Connaught Place Delhi 24hrs Available
9811611494,Low Rate Call Girls In Connaught Place Delhi 24hrs Available9811611494,Low Rate Call Girls In Connaught Place Delhi 24hrs Available
9811611494,Low Rate Call Girls In Connaught Place Delhi 24hrs Available
 
Call Girls In Sector 90, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 90, (Gurgaon) Call Us. 9711911712Call Girls In Sector 90, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 90, (Gurgaon) Call Us. 9711911712
 
9643097474 Full Enjoy @24/7 Call Girls In Laxmi Nagar Delhi Ncr
9643097474 Full Enjoy @24/7 Call Girls In Laxmi Nagar Delhi Ncr9643097474 Full Enjoy @24/7 Call Girls In Laxmi Nagar Delhi Ncr
9643097474 Full Enjoy @24/7 Call Girls In Laxmi Nagar Delhi Ncr
 
9643097474 Full Enjoy @24/7 Call Girls in Paschim Vihar Delhi NCR
9643097474 Full Enjoy @24/7 Call Girls in Paschim Vihar Delhi NCR9643097474 Full Enjoy @24/7 Call Girls in Paschim Vihar Delhi NCR
9643097474 Full Enjoy @24/7 Call Girls in Paschim Vihar Delhi NCR
 
NAGPUR CALL GIRL 92628*71154 NAGPUR CALL
NAGPUR CALL GIRL 92628*71154 NAGPUR CALLNAGPUR CALL GIRL 92628*71154 NAGPUR CALL
NAGPUR CALL GIRL 92628*71154 NAGPUR CALL
 
100% Real Call Girls In Hazrat Nizamuddin Railway Station Delhi | Just Call 9...
100% Real Call Girls In Hazrat Nizamuddin Railway Station Delhi | Just Call 9...100% Real Call Girls In Hazrat Nizamuddin Railway Station Delhi | Just Call 9...
100% Real Call Girls In Hazrat Nizamuddin Railway Station Delhi | Just Call 9...
 
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝
Call Girls In Dwarka Delhi 💯Call Us 🔝9711014705🔝
 
Genuine Call Girls In {Mahipalpur Delhi} 9667938988 Indian Russian High Profi...
Genuine Call Girls In {Mahipalpur Delhi} 9667938988 Indian Russian High Profi...Genuine Call Girls In {Mahipalpur Delhi} 9667938988 Indian Russian High Profi...
Genuine Call Girls In {Mahipalpur Delhi} 9667938988 Indian Russian High Profi...
 
(9599264170) ↫ Call Girls In Rk Puram ↫ Delhi NCR
(9599264170) ↫ Call Girls In Rk Puram ↫ Delhi NCR(9599264170) ↫ Call Girls In Rk Puram ↫ Delhi NCR
(9599264170) ↫ Call Girls In Rk Puram ↫ Delhi NCR
 
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...
Call Girls In {Green Park Delhi} 9667938988 Indian Russian High Profile Girls...
 
9899855202 Call Girls In Goa This Ads Is Only For Those Clients Who Are Looki...
9899855202 Call Girls In Goa This Ads Is Only For Those Clients Who Are Looki...9899855202 Call Girls In Goa This Ads Is Only For Those Clients Who Are Looki...
9899855202 Call Girls In Goa This Ads Is Only For Those Clients Who Are Looki...
 
Call Girls in Janakpuri Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Janakpuri Delhi 💯 Call Us 🔝9667422720🔝Call Girls in Janakpuri Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Janakpuri Delhi 💯 Call Us 🔝9667422720🔝
 
Call Girls In Sector 26, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 26, (Gurgaon) Call Us. 9711911712Call Girls In Sector 26, (Gurgaon) Call Us. 9711911712
Call Girls In Sector 26, (Gurgaon) Call Us. 9711911712
 
Call Girls In Naraina (Delhi) +91-9667422720 Escorts Service
Call Girls In Naraina (Delhi) +91-9667422720 Escorts ServiceCall Girls In Naraina (Delhi) +91-9667422720 Escorts Service
Call Girls In Naraina (Delhi) +91-9667422720 Escorts Service
 
Call Girls In Majnu-ka-Tilla 9711800081 Low Cheap Price ...
Call Girls In Majnu-ka-Tilla 9711800081 Low Cheap Price ...Call Girls In Majnu-ka-Tilla 9711800081 Low Cheap Price ...
Call Girls In Majnu-ka-Tilla 9711800081 Low Cheap Price ...
 
Call Girls in Chattarpur Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Chattarpur Delhi 💯 Call Us 🔝9667422720🔝Call Girls in Chattarpur Delhi 💯 Call Us 🔝9667422720🔝
Call Girls in Chattarpur Delhi 💯 Call Us 🔝9667422720🔝
 
Book Call Girls in Lahore || 03070433345 || Young, Hot, Sexy, VIP Girls Avail...
Book Call Girls in Lahore || 03070433345 || Young, Hot, Sexy, VIP Girls Avail...Book Call Girls in Lahore || 03070433345 || Young, Hot, Sexy, VIP Girls Avail...
Book Call Girls in Lahore || 03070433345 || Young, Hot, Sexy, VIP Girls Avail...
 
Call Girls In Saket Delhi 9953056974 (Low Price) Escort Service Saket Delhi
Call Girls In Saket Delhi 9953056974 (Low Price) Escort Service Saket DelhiCall Girls In Saket Delhi 9953056974 (Low Price) Escort Service Saket Delhi
Call Girls In Saket Delhi 9953056974 (Low Price) Escort Service Saket Delhi
 

Case Study-Risk Management & Supply Continuity for Low Cost Country Supply

  • 1. Risk Management and Supply Continuity: Establishing Low Cost Country Supply September 13, 2011 Dragon Sourcing - 龙 源 Your Tailored Sourcing Approach to LCC Sourcing
  • 2. Agenda A. Background B. Macro Market Understanding C. Micro Cost To Serve D. Managing Risk and Continuity © 2011 Dragon Sourcing. All rights reserved.
  • 3. Introduction • Many companies, as part of their global portfolio, are manufacturing or considering manufacturing in low-cost countries. • Historically, the critical driver of this decision has been low-cost labor however this underplays the total potential value in a low-cost strategy. For example, products exported from Mexico to the United States today only include on average 5% Mexican value added, a lot of effort for a marginal impact. • When total costs, changing market dynamics, and supply risks are considered many companies have been retrenching from their initial decisions. But is the pendulum swinging too far the other way today? • The Issues are: – What are they keys to developing a successful Low Cost Country Strategy? – What are the critical steps to ensuring benefit, managing risk and continuity? – What role does Sourcing and Procurement play? • We will explore two cases and the critical lessons learned. © 2011 Dragon Sourcing. All rights reserved.
  • 4. Driving a Strategy • What is the driver behind my strategy? – Low Cost? -- Expanded Capabilities? – Market Access? -- New Growth (Acquisitions)? • How do I choose to source or site LCC capabilities? – Macro Economics -- Sub-Regional Dynamics – Financials and Business Attractiveness – Availability of local or proximate supply • How do I manage risks? – Political and Economic Risk – Business and Financial Risks – Supply Chain Risks – Supply Risk © 2009 Dragon Sourcing. All rights reserved.
  • 5. © 2010 Dragon Sourcing. All rights reserved. 5 Massively Changing Market Dynamics • China, Vietnam, India, Turkey Mexico and Brazil are countries experiencing unprecedented and exponential economic growth which offer unique opportunities (and risks) • After a period of decline in Chinese exports caused by the financial crisis of 2008  exports from China to the western world have once again reached unprecedented speed in 2011. • Tension in bilateral relations between the EU and China and the US and China • Chinese government modified its exchange rate policy by shifting from a hard peg to the US$ to a link to a basket of international currencies • In addition, we are seeing… – Renewed labor wage inflation on the eastern coast of China – Labor unrest in several factories that have made headlines recently (Foxconn, Toyota) – Significant increases in container transportation costs – The imposition of new anti dumping taxes by US and EU These trends combined with changing market dynamics is triggering some strategic rethinking in companies' global sourcing strategies Source: World Bank.
  • 6. Case Study Background • About a $200 Million Dollar Division of a major company was under significant economic pressure in its traditional manufacturing structure • The current default strategy was to source from China, but that led to competitive vulnerability • The issue was whether there was an opportunity to leap frog competition and gain leverage through a low cost country strategy. • The issue was where is the world? At what economics? And what was necessary to manage risks? • The analysis involved four stages: – A Macro Look at Markets for the best cost country and location to potentially position operations – A Micro look at comparative economics and risks by down selected location – Supply localization for targeted regions – Site Selection, support contacting and launch planning © 2009 Dragon Sourcing. All rights reserved.
  • 7. Agenda A. Background B. Macro Market Understanding C. Micro Cost To Serve D. Managing Risk and Continuity © 2011 Dragon Sourcing. All rights reserved.
  • 8. © 2010 Dragon Sourcing. All rights reserved. 8 Starting Point -- Macro Market Analysis Main Criteria Total Weight Subcriteria Weight Indicators Political stability 8% World Bank - Governance indicator Commitment to reforms 4% Composite indicator Corruption and bureaucracy 4% Transparency International - Corruption Perception Index Legal framework and rule of law 4% World Bank - Governance indicator International performance 12% External trade, product portfolio, FDI International competitivity 12% GDP/capita, labor costs level and evolution National performance 8% Growth, unemployment rate, inflation Financial situation 8% Indebtness, savings and banking performance Education 8% Literacy rate, tertiary enrolment Human development 8% Poverty, health, sanitation, access to PC, internet Age profile 4% Age distribution and expected evolution Transport infrastructure 8% Ports, roads Energy and power supply 8% Consumption, dependency, diversification R&D expenditure 4% Public spending TOTAL 100% 100% Infrastructure and technologies 20% Political and legal 20% Economic 40% Social and demographic 20%
  • 9. © 2010 Dragon Sourcing. All rights reserved. 9 Comparison of Asian Economies Pakistan India China Thailand Indonesia Philippines Vietnam 0% 2% 4% 6% 8% 10% 12% 0 500 1 000 1 500 2 000 2 500 3 000 GDP / Capita ($) GDPGrowthRate Political and Economic Political Economic IRAQ ICELAND VIETNAM CHINA THAILAND INDIA PHILIPPINES INDONESIA PAKISTAN Politicalstability OECD SOMALIA ICELAND VIETNAM CHINA THAILAND INDIA PHILIPPINES INDONESIA PAKISTAN RuleofLaw OECD Source:WorldBank Population Sources:ADB,IMF MEXICO MEXICO
  • 10. © 2010 Dragon Sourcing. All rights reserved. 10 Energy per capita (kg of oil equivalent) and per sources 0 250 500 750 1 000 1 250 1 500 China India Indonesia Pakistan Philippines Thailand Vietnam Coal Gas Hydro Oil Nuclear Geothermal Social and Infrastructure Socio-demographic Infrastructure Own production Source:WorldBank MALI UNITED STATES VIETNAM CHINA THAILAND INDIA PHILIPPINES INDONESIA PAKISTAN Poverty/Wealth Health AccessPC/internet TAJIKISTAN UNITED STATES VIETNAM CHINA THAILAND INDIA PHILIPPINES INDONESIA PAKISTAN Source:UnitedNationsDevpmtPrg.(UNDP) EQUAT. GUINEA UNITED STATES VIETNAM CHINA THAILAND INDIA PHILIPPINES INDONESIA PAKISTAN Source:UnitedNationsDevpmtPrg.(UNDP) Source:ADB,WorldBank,JapanBank forInternationalCooperation(JBIC) Education Pakistan India Thailand Philippines Vietnam Indonesia China 40% 50% 60% 70% 80% 90% 100% 0% 10% 20% 30% 40% 50% University enrolment Literacyrate Investment in education = 1% GDP Transportation (roads, maritime) Pakistan India Vietnam Thailand Philippines China Indonesia 0 10 20 30 40 0 5 10 15 20 Paved road density (km / 100km2) Maritime export(TEU/ 1000$export) Investment in infrastructure = 1% of GDP * (*) TEU: Ton-Equivalent Unit
  • 11. © 2010 Dragon Sourcing. All rights reserved. 11 One of Many Economic Drivers -- Relative Factor Sub Criteria Total tax rate (TTR) Wages & Social Security Logistics Cost Import Duty Rates  China offer highest social security to workers.  Vietnam is the lowest in total average wages. Social Security Source: www. eiu.com China 20-30% Mexico 15-25% Vietnam 19.0% Malaysia 12.0% Indonesia 4.89% Thailand 4.5% Social Security US $ 490-530 US $ 529 US $ 390 US $ 281 US $ 138 China Malaysia Thailand Indonesia Vietnam Total average wages including Social Security Mexico US $ 495- 538
  • 12. Macro View of Supply Market Attractiveness… © 2010 Dragon Sourcing. All rights reserved. • At a Macro Level Certain markets continue to be very attractive… • … but need to understand in both a static and dynamic context and in the context of your strategy
  • 13. .. And a Total Cost View of Relative Value Added Costs © 2010 Dragon Sourcing. All rights reserved. 13 $3,203,983 $3,736,323 $2,761,897 $3,722,127 $3,647,270
  • 14. Agenda A. Background B. Macro Market Understanding C. Micro Cost To Serve D. Managing Risk and Continuity © 2011 Dragon Sourcing. All rights reserved.
  • 15. Beyond Country Economics  Regional Understanding © 2009 Dragon Sourcing. All rights reserved. • What skill base and capabilities exist? • What are the financial incentives? • What is the local infrastructure? • What is the export infrastructure? • How accessible and comfortable for expats or visitors?
  • 16. Critical Issue Available Supply as purchase costs were 80% of total costs © 2009 Dragon Sourcing. All rights reserved.
  • 17. Critical - Sourcing and Supply Market Understanding © 2009 Dragon Sourcing. All rights reserved. Top 50 Best Qualified China 40 Mexico 6 Vietnam 2 Indonesia 2
  • 18. A strategic view to Supplier capabilities © 2010 Dragon Sourcing. All rights reserved. 18
  • 19. Laminates Machined Castings Tube Housing Leadwire Hardware Painting Plastics And, “safe” locations proximate to the market and supply base 19© 2012 Dragon Sourcing. All rights reserved. Target C Target B Target A
  • 20. Supported by Detailed Site Selection • Operates as an industrial as an industrial developer in 1987 with 5 major developments between Tijuana and Mexicali • Services – Maximum Security: Controlled Access, Wall Perimeter and CCTV 24/7 – 7 Public Bus lines – Food, Medical, police and fire either outside main gain or within 5km – Solar energy – Concrete Tilt-Up Buildings with the same quality standard as US. © 2012 Dragon Sourcing. All rights reserved. 20 Proposed - El Dorado Park Established: 2000 Size: 34 ha Sq ft Sold: 5,621,155 Facility – 78,500 sq ft, $0.35/sq ft
  • 21. Bringing It Together – In the Client’s Case -- Mexico © 2010 Dragon Sourcing. All rights reserved. • Beyond The Macro the Key Became… – Specifically targeting regions and capabilities – Identifying and qualifying suppliers – Sourcing and working with suppliers for low cost supply – Mitigating sub-scale operations and lack of local knowledge
  • 22. Time Phased Estimate of Results © 2012 Dragon Sourcing. All rights reserved. 22 2012 2013 2014 2015 Product A Forecast - 80,540 146,081 145,631 Hours Fcst - 18,920 34,317 34,211 People Fcst 0 10.31 18.13 18.08 Staff Plan 0 14.42 19.17 15.50 Product B Forecast - 3,916 22,910 23,374 Hours Fcst - 2,136 12,499 12,752 People Fcst 0 1.33 7.17 7.33 Staff Plan 0 2.83 8.00 7.50 Product C Forecast 26,709 169,625 170,938 172,900 Hours Fcst 5,427 34,464 34,731 35,130 People Fcst 13.00 18.58 19.50 19.75 Staff Plan 16.67 18.58 19.17 20.08 Total Forecast 26,709 254,081 339,929 341,905 Hours Fcst 5,427 55,521 81,547 82,093 People Fcst 13.00 30.22 44.80 45.16 Staff Plan 16.67 35.83 46.33 43.08 Draft Plan 2012 2013 2014 2015 Baseline Manufacturing Costs Product A -$ 896,709$ 1,626,417$ 1,621,407$ Product B -$ 119,880$ 701,338$ 715,542$ Product C -$ 1,016,589$ 2,327,755$ 2,336,949$ New Manfacturing Costs Labor -$ 110,943$ 174,722$ 147,924$ Mfg Overhead 380,400$ 965,800$ 965,800$ 965,800$ Support Overhead 290,444$ 1,253,895$ 1,253,895$ 1,253,895$ Les LU Absorbed (143,408)$ (910,772)$ (917,823)$ (928,357)$ Total Manufacturing 527,437$ 1,419,866$ 1,476,593$ 1,439,262$ Net Manufacturing savings (527,437)$ (403,277)$ 851,162$ 897,687$ Lower Unit Savings 114,488$ 727,105$ 732,735$ 741,144$ Materials Savings 266,140$ 532,527$ 532,571$ Total Manufacturing Savings (412,949)$ 589,968$ 2,116,423$ 2,171,401$ Less Unasorbed Burden (13,056)$ (186,308)$ (461,507)$ (461,507)$ Less Logistics Penalty (57,084) (204,916)$ (410,021)$ (410,055)$ (483,088)$ 198,744$ 1,244,895$ 1,299,839$ Draft Plan Net savings
  • 23. Agenda A. Background B. Macro Market Understanding C. Micro Cost To Serve D. Managing Risk and Continuity © 2011 Dragon Sourcing. All rights reserved.
  • 24. Managing Political and Economic Risk – Market Intelligence © 2011 Dragon Sourcing. All rights reserved. 24 CLIENT BENEFITS Clarifying Supply Chain Risks Discovering Market Opportunities Informed Buying Decisions PROCUREMENT INTELLIGENCE SUITE Supply Market Analysis Supplier Analysis Industry Best Practices Analysis Price Tracking & Forecasting Category Executive Dashboards Dynamic Should-Cost Models Value Chain Analysis Supplier Financial Assessment Supplier Ethics Assessment - Which countries have potential? - Should we buy-in or manufacture? - Who are the top suppliers? - What are the market dynamics? - Should we buy now or later? - Latest category news? - What will the impact of inflation be? - Is the market trending up? - What are the raw materials? - What are the key risks to supply? - Do these suppliers meet our CSR requirements? KEY CLIENT QUESTIONS
  • 25. Business Challenges Supplier Performance Management Improve Cost Position Approach • Competent Global Sourcing • Focus on Key Cost Driver • Strategic Globalization Plan • Supplier Selection Process • Systematic Supplier Performance Management • Technical Support (Six Sigma/Lean) Competitiveness • Flexible Supply Chain • Compresses Supply Chain Lead-times • Supply Chain Integration Managing Business Risk – A Clear Strategy Results Reduced Cost Improved Market Position Global Supply Chain Becomes Competitive Advantage Improved PPM >95% OTD
  • 26. Managing Business Risk - In Country Management Resources © 2010 Dragon Sourcing. All rights reserved. DS Mexico •Over Twenty Years of Aerospace Supply Chain Experience • Experienced in Developing /Maintaining Supplier Performance • Enhanced Supplier Management Process • Strong Collaborative Effort with Mexican Economical Development Staff • Experienced in High Risk Sourcing to Achieve Improved Business Performance • Strong Bilingual In-Country Sourcing Team
  • 27. Managing Supply Risk - Localize Supplier Management © 2010 Dragon Sourcing. All rights reserved.
  • 28. Overall methodology & 7-step process Managing Supply Chain Risk - Formalized In Country Supplier and Quality Management Sampling & Criterias Checkitem # Box # Marking Inner carton Mug Quantity Mug heigth Mug upper diameter Mug lower diameter Wall thickness Mug weigth Material type Quality 1 OK OK 48 104.3 64.9 3.6 326 OK OK 2 OK OK 48 103.4 64.5 4.2 346 OK OK 3 OK OK 48 104 64.6 3.9 344 OK OK 4 OK OK 48 104.6 64.8 3.8 317 OK OK 5 OK OK 48 104.3 57 3.6 308 OK OK 6 OK OK 48 104.8 61 3.8 317 OK OK 7 OK OK 48 103.7 64.5 3.9 328 OK OK 8 OK NO 48 103.8 62 3.9 345 OK OK 9 OK OK 48 103.3 64.1 3.1 322 OK OK 10 OK OK 48 103.2 63.4 3.7 325 OK OK 11 OK OK 48 104.4 64.8 3.9 317 OK OK 12 OK OK 48 102.3 64.2 3.2 316 OK OK 13 OK OK 48 105.4 63 4 316 MO OK 14 OK OK 45 105.6 65 4 322 OK OK 15 OK OK 48 106.3 65.6 4.1 357 OK OK 16 OK OK 48 103.4 65.5 3.9 311 NO OK 17 OK NO 48 104.7 64.1 3.8 300 OK OK 18 OK OK 48 104 60 3.8 342 OK OK 28 Supplier Summary Supplier Capabilities Supplier Assessments On Going QC Reporting and Supplier Development
  • 29. Dragon Sourcing - 龙 源 Your Tailored Sourcing Approach to LCC Sourcing Steve Griffiths Managing Director USA Phone: 216-533-8972 steven.griffiths@dragonsourcing .com Richard Laub CEO Phone: +32 (499) 56.72.71 richard.laub@dragonsourcing .com