CIMENTACIÓN Y ARRANQUE DE COLUMNAS




                                                                1




           CARTILLA DE HIERROS
  EDIFICIO MIRADOR DEL PARQUE
          CALLE 18 SUR No 38S-31
                AGOSTO 24 2012
                        BOGOTÁ




CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
CIMENTACIÓN Y ARRANQUE DE COLUMNAS




                                                                          2




      MALLAS ELECTROSOLDADAS

         LOSA DE CONTRAPISO

        Φ 6.50 mm .15 x ,15
         CANTIDAD 1 UNIDAD
            ÁREA 9.50 M2
           PESO 35.53 Kgs

LOSA DE CIMENTACIÓN REFUERZO SUPERIOR
        Φ 6.00 mm .15 x ,15
        CANTIDAD 8 UNIDADES
             ÁREA 100 M2
           PESO 42.18 Kgs




          CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
CIMENTACIÓN Y ARRANQUE DE COLUMNAS




                                                                                        3




╔══════Ð════════════════════Ð═══════Ð═══════════════Ð════════════════╗
║ Ítem │     Nombre         │ Cant. │ Peso Unitario │   Peso Total   ║
╠══════Ï════════════════════Ï═══════Ï═══════════════Ï════════════════╣
║      │                    │       │               │                ║
║    1 │ CIMENTACIÓN        │    1. │      4,830.38 │       4,830.38 ║
║      │                    │       │               │                ║
║    2 │ TANQUE             │    1. │        861.40 │         861.40 ║
║      │                    │       │               │                ║
║    3 │ COLUMNAS           │    1. │      3,140.24 │       3,140.24 ║
║      │                    │       │               │                ║
║    4 │ ESCALERAS          │    1. │        341.10 │         341.10 ║
║      │                    │       │               │                ║
╚══════¤════════════════════¤═══════¤═══════════════¤════════════════╝




                     CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
CIMENTACIÓN Y ARRANQUE DE COLUMNAS



      ITEM N° - 1 NOMBRE - CIMENTACIÓN                          CANTI. - 1 PESO -         4,830.38 Kg/Item
 1)   4#7.810      ┌─────────────────────────────────────────────────────────────────                               4
                30 │                              780
                   │

 2)   4#7.770      ┌─────────────────────────────────────────────────────────────
                30 │                            740
                   │

 3)   4#7.760      ┌────────────────────────────────────────────────────────────
                30 │                            730
                   │

 4)   8#7.760      ───────────────────────────────────────────────────────────────
                                                760

 5)   4#7.750      ┌────────────────────────────────────────────────────────────
                30 │                            720
                   │

 6)   4#7.700      ┌───────────────────────────────────────────────────────
                30 │                         670
                   │

 7)   4#7.690      ┌───────────────────────────────────────────────────────
                30 │                         660
                   │

 8)   4#7.690      ─────────────────────────────────────────────────────────
                                             690

 9)   4#7.670      ┌─────────────────────────────────────────────────────
                30 │                        640
                   │

10)   4#7.650      ┌───────────────────────────────────────────────────
                30 │                       620
                   │

11)   4#7.610      ──────────────────────────────────────────────────
                                          610

12)   8#7.575      ┌──────────────────────────────────────────┐
                30 │                   515                    │ 30

13)   4#7.570      ┌─────────────────────────────────────────────
                30 │                    540
                   │

14)   4#7.560      ┌────────────────────────────────────────────
                30 │                    530
                   │

15)   4#7.530      ┌─────────────────────────────────────────
                30 │                  500
                   │

16)   8#7.500      ┌───────────────────────────────────────
                30 │                 470
                   │

17)   4#7.490      ┌──────────────────────────────────────
                30 │                 460
                   │

18)   4#7.485      ┌─────────────────────────────────────
                30 │                455
                   │

19)   4#7.480      ┌─────────────────────────────────────
                30 │                450
                   │

20)   8#7.470      ┌────────────────────────────────────
                30 │                440
                   │

21)   8#7.450      ┌────────────────────────────────┐
                30 │              390               │ 30

22)   4#7.410      ┌───────────────────────────────
                30 │             380
                   │




                                              CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
CIMENTACIÓN Y ARRANQUE DE COLUMNAS



23)    8#7.400      ┌────────────────────────────┐
                 30 │            340             │ 30

24)    8#7.380      ┌──────────────────────────┐
                                                                                                                  5
                 30 │           320            │ 30

25)    4#7.360      ┌───────────────────────────
                 30 │           330
                    │


26)    4#7.350      ┌──────────────────────────
                 30 │           320
                    │

27)    4#7.300      ┌──────────────────────
                 30 │         270
                    │

28)    4#7.260      ┌───────────────────
                 30 │       230
                    │

29)    4#7.240      ┌─────────────────
                 30 │      210
                    │

30)    4#7.227      ┌─────────────┐
                 30 │    167      │ 30

31)    8#6.800      ┌────────────────────────────────────────────────────────────────
                 25 │                              775
                    │

32)    4#6.685      ─────────────────────────────────────────────────────────
                                              685

33)   12#6.640      ┌───────────────────────────────────────────────────
                 25 │                       615
                    │

34)    8#6.550      ┌───────────────────────────────────────────
                 25 │                   525
                    │

35)    4#6.500      ┌───────────────────────────────────────
                 25 │                 475
                    │

36)   16#6.420      ┌──────────────────────────────┐
                 25 │             370              │ 25

37)    8#6.370      ┌────────────────────────────
                 25 │            345
                    │

38)    4#6.350      ┌───────────────────────────
                 25 │           325
                    │

39)    4#6.217      ┌─────────────┐
                 25 │    167      │ 25

40)    4#6.200      ┌──────────────
                 25 │     175
                    │

41)   55#4.600      ──────────────────────────────────────────────────
                                           600

42)    9#4.400      ─────────────────────────────────
                                  400 Figurar En Obra

43)    9#4.220      ──────────────────
                           220 Figurar En Obra

44)   18#4.145      ┌─────────┐
                 15 └ 115     ┘ 15

45)   77#3.600      ──────────────────────────────────────────────────
                                           600




                                                  CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
CIMENTACIÓN Y ARRANQUE DE COLUMNAS



46)   394#3.238        ┌────────────────────────┬┐
                    27 │                         ┤ 10
                       │
                       │
                                                 │
                                                 │
                                                                                                                   6
                       └─────────────────────────┘
                                   82

47)     8#3.218        ┌────────────────────────┬┐
                    17 │                         ┤ 10
                       └─────────────────────────┘
                                   82

48)    20#3.206        ┌────────────────────────┬┐
                    10 │                         ┤ 10
                       └─────────────────────────┘
                                   83

49)   342#3.200         ┌────────────────────────┬┐
                    8   │                         ┤ 10
                        └─────────────────────────┘
                                    82

50)    32#3.110        ┌──────┬┐
                    17 │       ┤ 10
                       └───────┘
                          28

51)    32#3.63         ┌───┐
                    10 └    ┘ 10
                         43


                 ITEM N° - 2 NOMBRE - TANQUE                         CANTI. - 1 PESO -     861.40 Kg/Item
 1)    36#4.470        ┌────────────────────────────────────┐
                    15 └                440                 ┘ 15

 2)    18#4.410        ┌───────────────────────────────┐
                    15 └             380               ┘ 15

 3)    30#4.280         ───────────────────────
                                 280 Figurar En Obra

 4)    30#4.240        ┌─────────────────┐
                    15 └      210        ┘ 15

 5)   156#4.160        ┌──────────┐
                    15 └   130    ┘ 15

 6)    24#4.125         ──────────
                           125 Figurar En Obra

 7)    44#4.110         ─────────
                          110 Figurar En Obra

 8)    60#3.230        ┌─────────────────┐
                    10 └      210        ┘ 10

 9)    60#3.170        ┌────────────┐
                    10 └    150     ┘ 10



         ITEM N° - 3 NOMBRE - COLUMNAS                              CANTI. - 1 PESO -    3,140.24 Kg/Item
 1)     6#6.660         ───────────────────────────────────────────────────────
                                                 660

 2)     1#6.625         ────────────────────────────────────────────────────
                                                625

 3)     4#6.620         ───────────────────────────────────────────────────
                                               620

 4)     6#6.530        ┌──────────────────────────────────────────
                    25 │                   505
                       │

 5)    36#6.520        ┌─────────────────────────────────────────
                    25 │                  495
                       │

 6)     6#6.280        ┌─────────────────────
                    25 │        255
                       │


                                                   CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
CIMENTACIÓN Y ARRANQUE DE COLUMNAS




 7)     1#6.270      ┌────────────────────
                                                                                                                   7
                  25 │        245
                     │

 8)     6#5.630       ────────────────────────────────────────────────────
                                              630

 9)    44#5.625       ────────────────────────────────────────────────────
                                              625

10)     6#5.620       ───────────────────────────────────────────────────
                                             620

11)    25#5.520      ┌─────────────────────────────────────────
                  20 │                  500

12)    50#5.270      ┌────────────────────
                  20 │        250

13)    36#4.660       ───────────────────────────────────────────────────────
                                               660

14)    36#4.520      ┌──────────────────────────────────────────
                  15 │                   505

15)    36#4.250      ┌───────────────────
                  15 │       235

16)    15#3.600       ──────────────────────────────────────────────────
                                             600 Figurar En Obra

17)   100#3.210      ┌───────────────┐
                  10 └     190       ┘ 10

18)    35#3.198      ┌─────────────────────┬┐
                  17 │                      ┤ 10
                     └──────────────────────┘
                                72

19)   100#3.190      ┌──────────────┐
                  10 └     170      ┘ 10

20)   105#3.138      ┌───────────┬┐
                  17 │            ┤ 10
                     └────────────┘
                           42

21)   315#3.128      ┌─────────┬┐
                  17 │          ┤ 10
                     └──────────┘
                          37

22)   140#3.92       ┌────┬┐
                  14 │     ┤ 10
                     └─────┘
                       22

23)   980#3.37       ┌─┐
                  10 └ ┘ 10
                      17

24)   300#3.34       ┌─┐
                  10 └ ┘ 10
                      14

25)   120#2.60        ┌─┬┐
                  7   │ ┤ 10
                      └──┘
                       13



  ITEM N° - 4 NOMBRE - ESCALERAS                         CANTI. - 1 PESO -      341.10 Kg/Item
 1)    36#4.600       ──────────────────────────────────────────────────
                                             600 Figurar En Obra

 2)     5#4.150       ────────────
                          150 Figurar En Obra

 3)    35#3.600       ──────────────────────────────────────────────────
                                             600



                                                   CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
CIMENTACIÓN Y ARRANQUE DE COLUMNAS



ÍTEM N° - 1 NOMBRE - CIMENTACIÓN                  CANTI. - 1 PESO -         4,830.38 Kg/Item
                  N°     NOMBRE     CANTIDAD   PESO UNITARIO   PESO TOTAL                           8
                  1    VC-1            1            539.92         539.92
                  2    VC-2            1            537.93         537.93
                  3    VC-3            1            363.85         363.85
                  4    VC-4            1            301.89         301.89
                  5    VC-5            1            293.32         293.32
                  6    VC-6            1            113.02         113.02
                  7    VC-7            1            298.94         298.94
                  8    VC-8            1            300.78         300.78
                  9    VC-9            1            126.15         126.15
                 10    VTC-1           2             57.96         115.92
                 11    VTC-3           2            156.16         312.31
                 12    VTC-4           4            157.72         630.88
                 13    VTC-5           2             56.84         113.68
                 14    VC-10           1             57.08          57.08
                 15    FOSO-ASC        1            139.02         139.02
                 16    RC              1             43.23          43.23
                 17    VC-T            1             61.24          61.24
                 18    LC(TORTA        1            481.20         481.20


 ÍTEM N° - 2 NOMBRE - TANQUE                    CANTI. - 1 PESO -           861.40 Kg/Item
                  N°     NOMBRE     CANTIDAD   PESO UNITARIO   PESO TOTAL

                 1     TANQUE          1            861.40         861.40




ÍTEM N° - 3 NOMBRE - COLUMNAS                    CANTI. - 1 PESO -          3,140.24 Kg/Item
                  N°     NOMBRE     CANTIDAD   PESO UNITARIO   PESO TOTAL

                 1     C-1             2            149.96         299.92
                 2     C-2             1            194.03         194.03
                 3     C-3             5            167.90         839.51
                 4     C-4             1            159.73         159.73
                 5     C-5             2            146.20         292.41
                 6     C-6             1            151.92         151.92
                 7     C-7             1            266.27         266.27
                 8     CT              1             68.40          68.40
                 9     M-1             1            868.05         868.05


 ÍTEM N° - 4 NOMBRE - ESCALERAS                  CANTI. - 1 PESO -           341.10 Kg/Item
                  N°     NOMBRE     CANTIDAD   PESO UNITARIO   PESO TOTAL

                 1     E-1             1            341.10         341.10




                                  CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
CIMENTACIÓN Y ARRANQUE DE COLUMNAS

                                         RESUMEN POR ÍTEMS Y POR DIÁMETROS
╔═══════════════════╦════╦══════════Ð══════════Ð══════════Ð══════════Ð══════════Ð══════════Ð══════════Ð══════════Ð══════════╦═══════════╗              9
║        Item       ║ CT ║    #2    │    #3     │   #4     │   #5     │   #6     │   #7    │    #8    │    #9    │    #10   ║   TOTAL   ║
╠═══════════════════╬════╬══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════╬═══════════╣
║ CIMENTACIÓN       ║ 1 ║         0 │    1,231 │       412 │        0 │      809 │   2,378 │        0 │        0 │        0 ║     4,830 ║
║ TANQUE            ║ 1 ║         0 │       134 │      727 │        0 │        0 │       0 │        0 │        0 │        0 ║       861 ║
║ COLUMNAS          ║ 1 ║        18 │       952 │      515 │      959 │      696 │       0 │        0 │        0 │        0 ║     3,140 ║
║ ESCALERAS         ║ 1 ║         0 │       118 │      223 │        0 │        0 │       0 │        0 │        0 │        0 ║       341 ║
╠═══════════════════╬════╬══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════╬═══════════╣
║        TOTAL      ║    ║       18 │    2,435 │    1,877 │       959 │   1,505 │    2,378 │        0 │        0 │        0 ║     9,173 ║
╚═══════════════════╩════╩══════════¤══════════¤══════════¤══════════¤══════════¤══════════¤══════════¤══════════¤══════════╩═══════════╝




                                                                                    CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
CIMENTACIÓN Y ARRANQUE DE COLUMNAS


                                                                10




CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012

More Related Content

Featured

Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
Skeleton Technologies
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
Neil Kimberley
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
contently
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
Albert Qian
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
Search Engine Journal
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
SpeakerHub
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
Tessa Mero
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Lily Ray
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
Rajiv Jayarajah, MAppComm, ACC
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
Christy Abraham Joy
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
Vit Horky
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
MindGenius
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
RachelPearson36
 
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Applitools
 
12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work
GetSmarter
 
ChatGPT webinar slides
ChatGPT webinar slidesChatGPT webinar slides
ChatGPT webinar slides
Alireza Esmikhani
 
More than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike RoutesMore than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike Routes
Project for Public Spaces & National Center for Biking and Walking
 
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
DevGAMM Conference
 

Featured (20)

Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
 
12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work
 
ChatGPT webinar slides
ChatGPT webinar slidesChatGPT webinar slides
ChatGPT webinar slides
 
More than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike RoutesMore than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike Routes
 
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
 

Cartilla 001 hierros_edificio_mirador_del_parque

  • 1. CIMENTACIÓN Y ARRANQUE DE COLUMNAS 1 CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE CALLE 18 SUR No 38S-31 AGOSTO 24 2012 BOGOTÁ CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
  • 2. CIMENTACIÓN Y ARRANQUE DE COLUMNAS 2 MALLAS ELECTROSOLDADAS LOSA DE CONTRAPISO Φ 6.50 mm .15 x ,15 CANTIDAD 1 UNIDAD ÁREA 9.50 M2 PESO 35.53 Kgs LOSA DE CIMENTACIÓN REFUERZO SUPERIOR Φ 6.00 mm .15 x ,15 CANTIDAD 8 UNIDADES ÁREA 100 M2 PESO 42.18 Kgs CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
  • 3. CIMENTACIÓN Y ARRANQUE DE COLUMNAS 3 ╔══════Ð════════════════════Ð═══════Ð═══════════════Ð════════════════╗ ║ Ítem │ Nombre │ Cant. │ Peso Unitario │ Peso Total ║ ╠══════Ï════════════════════Ï═══════Ï═══════════════Ï════════════════╣ ║ │ │ │ │ ║ ║ 1 │ CIMENTACIÓN │ 1. │ 4,830.38 │ 4,830.38 ║ ║ │ │ │ │ ║ ║ 2 │ TANQUE │ 1. │ 861.40 │ 861.40 ║ ║ │ │ │ │ ║ ║ 3 │ COLUMNAS │ 1. │ 3,140.24 │ 3,140.24 ║ ║ │ │ │ │ ║ ║ 4 │ ESCALERAS │ 1. │ 341.10 │ 341.10 ║ ║ │ │ │ │ ║ ╚══════¤════════════════════¤═══════¤═══════════════¤════════════════╝ CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
  • 4. CIMENTACIÓN Y ARRANQUE DE COLUMNAS ITEM N° - 1 NOMBRE - CIMENTACIÓN CANTI. - 1 PESO - 4,830.38 Kg/Item 1) 4#7.810 ┌───────────────────────────────────────────────────────────────── 4 30 │ 780 │ 2) 4#7.770 ┌───────────────────────────────────────────────────────────── 30 │ 740 │ 3) 4#7.760 ┌──────────────────────────────────────────────────────────── 30 │ 730 │ 4) 8#7.760 ─────────────────────────────────────────────────────────────── 760 5) 4#7.750 ┌──────────────────────────────────────────────────────────── 30 │ 720 │ 6) 4#7.700 ┌─────────────────────────────────────────────────────── 30 │ 670 │ 7) 4#7.690 ┌─────────────────────────────────────────────────────── 30 │ 660 │ 8) 4#7.690 ───────────────────────────────────────────────────────── 690 9) 4#7.670 ┌───────────────────────────────────────────────────── 30 │ 640 │ 10) 4#7.650 ┌─────────────────────────────────────────────────── 30 │ 620 │ 11) 4#7.610 ────────────────────────────────────────────────── 610 12) 8#7.575 ┌──────────────────────────────────────────┐ 30 │ 515 │ 30 13) 4#7.570 ┌───────────────────────────────────────────── 30 │ 540 │ 14) 4#7.560 ┌──────────────────────────────────────────── 30 │ 530 │ 15) 4#7.530 ┌───────────────────────────────────────── 30 │ 500 │ 16) 8#7.500 ┌─────────────────────────────────────── 30 │ 470 │ 17) 4#7.490 ┌────────────────────────────────────── 30 │ 460 │ 18) 4#7.485 ┌───────────────────────────────────── 30 │ 455 │ 19) 4#7.480 ┌───────────────────────────────────── 30 │ 450 │ 20) 8#7.470 ┌──────────────────────────────────── 30 │ 440 │ 21) 8#7.450 ┌────────────────────────────────┐ 30 │ 390 │ 30 22) 4#7.410 ┌─────────────────────────────── 30 │ 380 │ CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
  • 5. CIMENTACIÓN Y ARRANQUE DE COLUMNAS 23) 8#7.400 ┌────────────────────────────┐ 30 │ 340 │ 30 24) 8#7.380 ┌──────────────────────────┐ 5 30 │ 320 │ 30 25) 4#7.360 ┌─────────────────────────── 30 │ 330 │ 26) 4#7.350 ┌────────────────────────── 30 │ 320 │ 27) 4#7.300 ┌────────────────────── 30 │ 270 │ 28) 4#7.260 ┌─────────────────── 30 │ 230 │ 29) 4#7.240 ┌───────────────── 30 │ 210 │ 30) 4#7.227 ┌─────────────┐ 30 │ 167 │ 30 31) 8#6.800 ┌──────────────────────────────────────────────────────────────── 25 │ 775 │ 32) 4#6.685 ───────────────────────────────────────────────────────── 685 33) 12#6.640 ┌─────────────────────────────────────────────────── 25 │ 615 │ 34) 8#6.550 ┌─────────────────────────────────────────── 25 │ 525 │ 35) 4#6.500 ┌─────────────────────────────────────── 25 │ 475 │ 36) 16#6.420 ┌──────────────────────────────┐ 25 │ 370 │ 25 37) 8#6.370 ┌──────────────────────────── 25 │ 345 │ 38) 4#6.350 ┌─────────────────────────── 25 │ 325 │ 39) 4#6.217 ┌─────────────┐ 25 │ 167 │ 25 40) 4#6.200 ┌────────────── 25 │ 175 │ 41) 55#4.600 ────────────────────────────────────────────────── 600 42) 9#4.400 ───────────────────────────────── 400 Figurar En Obra 43) 9#4.220 ────────────────── 220 Figurar En Obra 44) 18#4.145 ┌─────────┐ 15 └ 115 ┘ 15 45) 77#3.600 ────────────────────────────────────────────────── 600 CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
  • 6. CIMENTACIÓN Y ARRANQUE DE COLUMNAS 46) 394#3.238 ┌────────────────────────┬┐ 27 │ ┤ 10 │ │ │ │ 6 └─────────────────────────┘ 82 47) 8#3.218 ┌────────────────────────┬┐ 17 │ ┤ 10 └─────────────────────────┘ 82 48) 20#3.206 ┌────────────────────────┬┐ 10 │ ┤ 10 └─────────────────────────┘ 83 49) 342#3.200 ┌────────────────────────┬┐ 8 │ ┤ 10 └─────────────────────────┘ 82 50) 32#3.110 ┌──────┬┐ 17 │ ┤ 10 └───────┘ 28 51) 32#3.63 ┌───┐ 10 └ ┘ 10 43 ITEM N° - 2 NOMBRE - TANQUE CANTI. - 1 PESO - 861.40 Kg/Item 1) 36#4.470 ┌────────────────────────────────────┐ 15 └ 440 ┘ 15 2) 18#4.410 ┌───────────────────────────────┐ 15 └ 380 ┘ 15 3) 30#4.280 ─────────────────────── 280 Figurar En Obra 4) 30#4.240 ┌─────────────────┐ 15 └ 210 ┘ 15 5) 156#4.160 ┌──────────┐ 15 └ 130 ┘ 15 6) 24#4.125 ────────── 125 Figurar En Obra 7) 44#4.110 ───────── 110 Figurar En Obra 8) 60#3.230 ┌─────────────────┐ 10 └ 210 ┘ 10 9) 60#3.170 ┌────────────┐ 10 └ 150 ┘ 10 ITEM N° - 3 NOMBRE - COLUMNAS CANTI. - 1 PESO - 3,140.24 Kg/Item 1) 6#6.660 ─────────────────────────────────────────────────────── 660 2) 1#6.625 ──────────────────────────────────────────────────── 625 3) 4#6.620 ─────────────────────────────────────────────────── 620 4) 6#6.530 ┌────────────────────────────────────────── 25 │ 505 │ 5) 36#6.520 ┌───────────────────────────────────────── 25 │ 495 │ 6) 6#6.280 ┌───────────────────── 25 │ 255 │ CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
  • 7. CIMENTACIÓN Y ARRANQUE DE COLUMNAS 7) 1#6.270 ┌──────────────────── 7 25 │ 245 │ 8) 6#5.630 ──────────────────────────────────────────────────── 630 9) 44#5.625 ──────────────────────────────────────────────────── 625 10) 6#5.620 ─────────────────────────────────────────────────── 620 11) 25#5.520 ┌───────────────────────────────────────── 20 │ 500 12) 50#5.270 ┌──────────────────── 20 │ 250 13) 36#4.660 ─────────────────────────────────────────────────────── 660 14) 36#4.520 ┌────────────────────────────────────────── 15 │ 505 15) 36#4.250 ┌─────────────────── 15 │ 235 16) 15#3.600 ────────────────────────────────────────────────── 600 Figurar En Obra 17) 100#3.210 ┌───────────────┐ 10 └ 190 ┘ 10 18) 35#3.198 ┌─────────────────────┬┐ 17 │ ┤ 10 └──────────────────────┘ 72 19) 100#3.190 ┌──────────────┐ 10 └ 170 ┘ 10 20) 105#3.138 ┌───────────┬┐ 17 │ ┤ 10 └────────────┘ 42 21) 315#3.128 ┌─────────┬┐ 17 │ ┤ 10 └──────────┘ 37 22) 140#3.92 ┌────┬┐ 14 │ ┤ 10 └─────┘ 22 23) 980#3.37 ┌─┐ 10 └ ┘ 10 17 24) 300#3.34 ┌─┐ 10 └ ┘ 10 14 25) 120#2.60 ┌─┬┐ 7 │ ┤ 10 └──┘ 13 ITEM N° - 4 NOMBRE - ESCALERAS CANTI. - 1 PESO - 341.10 Kg/Item 1) 36#4.600 ────────────────────────────────────────────────── 600 Figurar En Obra 2) 5#4.150 ──────────── 150 Figurar En Obra 3) 35#3.600 ────────────────────────────────────────────────── 600 CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
  • 8. CIMENTACIÓN Y ARRANQUE DE COLUMNAS ÍTEM N° - 1 NOMBRE - CIMENTACIÓN CANTI. - 1 PESO - 4,830.38 Kg/Item N° NOMBRE CANTIDAD PESO UNITARIO PESO TOTAL 8 1 VC-1 1 539.92 539.92 2 VC-2 1 537.93 537.93 3 VC-3 1 363.85 363.85 4 VC-4 1 301.89 301.89 5 VC-5 1 293.32 293.32 6 VC-6 1 113.02 113.02 7 VC-7 1 298.94 298.94 8 VC-8 1 300.78 300.78 9 VC-9 1 126.15 126.15 10 VTC-1 2 57.96 115.92 11 VTC-3 2 156.16 312.31 12 VTC-4 4 157.72 630.88 13 VTC-5 2 56.84 113.68 14 VC-10 1 57.08 57.08 15 FOSO-ASC 1 139.02 139.02 16 RC 1 43.23 43.23 17 VC-T 1 61.24 61.24 18 LC(TORTA 1 481.20 481.20 ÍTEM N° - 2 NOMBRE - TANQUE CANTI. - 1 PESO - 861.40 Kg/Item N° NOMBRE CANTIDAD PESO UNITARIO PESO TOTAL 1 TANQUE 1 861.40 861.40 ÍTEM N° - 3 NOMBRE - COLUMNAS CANTI. - 1 PESO - 3,140.24 Kg/Item N° NOMBRE CANTIDAD PESO UNITARIO PESO TOTAL 1 C-1 2 149.96 299.92 2 C-2 1 194.03 194.03 3 C-3 5 167.90 839.51 4 C-4 1 159.73 159.73 5 C-5 2 146.20 292.41 6 C-6 1 151.92 151.92 7 C-7 1 266.27 266.27 8 CT 1 68.40 68.40 9 M-1 1 868.05 868.05 ÍTEM N° - 4 NOMBRE - ESCALERAS CANTI. - 1 PESO - 341.10 Kg/Item N° NOMBRE CANTIDAD PESO UNITARIO PESO TOTAL 1 E-1 1 341.10 341.10 CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
  • 9. CIMENTACIÓN Y ARRANQUE DE COLUMNAS RESUMEN POR ÍTEMS Y POR DIÁMETROS ╔═══════════════════╦════╦══════════Ð══════════Ð══════════Ð══════════Ð══════════Ð══════════Ð══════════Ð══════════Ð══════════╦═══════════╗ 9 ║ Item ║ CT ║ #2 │ #3 │ #4 │ #5 │ #6 │ #7 │ #8 │ #9 │ #10 ║ TOTAL ║ ╠═══════════════════╬════╬══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════╬═══════════╣ ║ CIMENTACIÓN ║ 1 ║ 0 │ 1,231 │ 412 │ 0 │ 809 │ 2,378 │ 0 │ 0 │ 0 ║ 4,830 ║ ║ TANQUE ║ 1 ║ 0 │ 134 │ 727 │ 0 │ 0 │ 0 │ 0 │ 0 │ 0 ║ 861 ║ ║ COLUMNAS ║ 1 ║ 18 │ 952 │ 515 │ 959 │ 696 │ 0 │ 0 │ 0 │ 0 ║ 3,140 ║ ║ ESCALERAS ║ 1 ║ 0 │ 118 │ 223 │ 0 │ 0 │ 0 │ 0 │ 0 │ 0 ║ 341 ║ ╠═══════════════════╬════╬══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════Ï══════════╬═══════════╣ ║ TOTAL ║ ║ 18 │ 2,435 │ 1,877 │ 959 │ 1,505 │ 2,378 │ 0 │ 0 │ 0 ║ 9,173 ║ ╚═══════════════════╩════╩══════════¤══════════¤══════════¤══════════¤══════════¤══════════¤══════════¤══════════¤══════════╩═══════════╝ CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012
  • 10. CIMENTACIÓN Y ARRANQUE DE COLUMNAS 10 CARTILLA DE HIERROS EDIFICIO MIRADOR DEL PARQUE AGOTO 24 2012