Better, faster, cheaper.  Lean and agile approaches to IT development Marc McNeill, ThoughtWorks
IT doesn’t have a track record
“Two thirds of (IT) projects are challenged.”. Source: The Standish Group CHAOS Reports
  Over budget by  189% . Source: The Standish Group CHAOS Reports
  Over schedule by  220% . Source: The Standish Group CHAOS Reports
  Only  61%  of features delivered. Source: The Standish Group CHAOS Reports
66%  of projects fail or are ‘marginal’. Source: The Standish Group CHAOS Reports
$3.45 billion tax-credit overpayment UK Inland Revenue $2.6 billion spent system cancelled US Federal Aviation Administration $160 million lost because of ERP system problems Hewlett-Packard $527 million written off  supply chain system abandoned J Sainsbury plc
Poor Quality Slow to Deliver Expensive
Better Faster Cheaper
What if…
Lean
Agile
but first...
Context just a little
 
A Company with a purpose
To be the home for the best knowledge workers in the world
To revolutionise the way software is delivered  to make a positive difference to business and to society
Consultancy Global Delivery Training Products 1000+ employees 6 countries 15 years
A story
The business has an idea Increase revenue Decrease costs Regulatory pressures Cartoons courtesy of http://designcomics.org/
The idea is analysed High level design Detailed design
This takes time
The business sign off on the requirements
(Lots of requirements)
Developers start writing code
It gets tested
Then deployed
But it doesn’t always work like this
Long feedback cycles
The business  changes
Dates slip, scope gets cut, effort wasted
Value is not delivered High project failure rate High cost of change Permanent state of maintenance Little innovation Unhappy stakeholders Poor customer experience
A  different  story?
01.  Agile
http://agilemanifesto.org/
02.  Lean
Scientific management “ It is only through  enforced  standardization of methods,  enforced  adoption of the best implements and working conditions and  enforced  cooperation that this faster work can be assured. And the duty of  enforcing  the adoption of standards and  enforcing  this cooperation rests with management alone.” Frederick Winslow Taylor Any colour so long as it is black
Lean Just in time “ All we are doing is looking at the time line, from the point the customer gives us an order to the point when we collect the cash. And we are reducing the time line by reducing the non-value added wastes.” Taiichi Ohno
Just in time Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement
The story revisited
(v) Value-Added Time (e) Elapsed Time (c) Cumulative Elapsed Time Adapted from http://www.thoughtworks.com/pdfs/lean-qtb-jun08.pdf Requirements Gathering & Analysis (v) 1 Week (e) 4 Weeks (c) 4 Weeks Review & Approve Req. Spec. (v) 1 Day (e) 2 Weeks (c) 6 Weeks Solution Design (v) 2 Weeks (e) 6 Weeks (c) 12 Weeks Review & Approve Tech. Spec. (v) 1 Day (e) 2 Weeks (c) 14 Weeks Build Solution (Coding) (v) 8 Weeks (e) 14 Weeks (c) 28 Weeks System testing (v) 3 Weeks (e) 3 Weeks (c) 31 Weeks User Acceptance Testing (UAT) (v) 3 Weeks (e) 3 Weeks (c) 34 Weeks Deploy (v) 1 Week (e) 2 Weeks (c) 36 Weeks
Requirements Gathering & Analysis Review & Approve Req. Spec. Solution Design Review & Approve Tech. Spec. (v) 1 Week (e) 4 Weeks (c) 4 Weeks (v) 1 Day (e) 2 Weeks (c) 6 Weeks (v) 2 Weeks (e) 6 Weeks (c) 12 Weeks (v) 1 Day (e) 2 Weeks (c) 14 Weeks Deploy User Acceptance Testing (UAT) System testing Build Solution (Coding) (v) 1 Week (e) 2 Weeks (c) 36 Weeks (v) 3 Weeks (e) 3 Weeks (c) 34 Weeks (v) 3 Weeks (e) 3 Weeks (c) 31 Weeks (v) 8 Weeks (e) 14 Weeks (c) 28 Weeks Total Elapsed Time = 36 Weeks Estimated Project Cost (at $50k per week) = $1.8M Cycle Time Efficiency = 53% Systemic Faults: Inefficient Slow, expensive & poor quality Inflexible System often fails
Requirements Gathering & Analysis Review & Approve Req. Spec. Solution Design Review & Approve Tech. Spec. (v) 1 Week (e) 4 Weeks (c) 4 Weeks (v) 1 Day (e) 2 Weeks (c) 6 Weeks (v) 2 Weeks (e) 6 Weeks (c) 12 Weeks (v) 1 Day (e) 2 Weeks (c) 14 Weeks Deploy User Acceptance Testing (UAT) System testing Build Solution (Coding) (v) 1 Week (e) 2 Weeks (c) 36 Weeks (v) 3 Weeks (e) 3 Weeks (c) 34 Weeks (v) 3 Weeks (e) 3 Weeks (c) 31 Weeks (v) 8 Weeks (e) 14 Weeks (c) 28 Weeks Extra Features Defects Defects Waiting (v) Value-Added Time (e) Elapsed Time (c) Cumulative Elapsed Time Movement Waiting Excess Inventory Movement Waiting Excess Inventory
The lean and agile way
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Collaborative workshops
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Visioning
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Shared understanding
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Lo-fi prototyping
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Collaborative prioritisation
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Group estimation
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Lightweight documentation
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Just in time
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Just in time Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement User stories
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Just in time Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Adaptive planning
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Just in time Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Spike to solve hard technical problems through real experiments
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Test driven development Just in time Build in quality
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Continuous integration Just in time Build in quality
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Paired programming Just in time Build in quality
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement The right documentation Just in time
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Continuous feedback - showcases Just in time
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Collective ownership Just in time Reduce waste
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Stand-ups Just in time Reduce waste
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Time boxed increments Just in time Reduce waste People and teamwork
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Sustainable pace Just in time Reduce waste People and teamwork
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Patterns, standards and ubiquitous language Just in time Reduce waste People and teamwork
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Information radiators Just in time Reduce waste People and teamwork
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance (v) 8 Weeks (e) 10 Weeks (c) 14 Weeks (v) Value-Added Time (e) Elapsed Time (c) Cumulative Elapsed Time
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance (v) 8 Weeks (e) 10 Weeks (c) 14 Weeks (v) Value-Added Time (e) Elapsed Time (c) Cumulative Elapsed Time Deploy User Acceptance Testing (UAT) System testing (v) 1 Week (e) 2 Weeks (c) 18 Weeks (v) 1 Week (e) 1 Week (c) 16 Weeks (v) 1 Week (e) 1 Week (c15 Weeks
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance (v) 8 Weeks (e) 10 Weeks (c) 14 Weeks Deploy User Acceptance Testing (UAT) System testing (v) 1 Week (e) 2 Weeks (c) 18 Weeks (v) 1 Week (e) 1 Week (c) 16 Weeks (v) 1 Week (e) 1 Week (c15 Weeks (v) Value-Added Time (e) Elapsed Time (c) Cumulative Elapsed Time
Requirements Gathering & Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance (v) 8 Weeks (e) 10 Weeks (c) 14 Weeks Deploy User Acceptance Testing (UAT) System testing (v) 1 Week (e) 2 Weeks (c) 18 Weeks (v) 1 Week (e) 1 Week (c) 16 Weeks (v) 1 Week (e) 1 Week (c15 Weeks Total Elapsed Time = 18 Weeks (from 36 weeks) Estimated Project Cost = $900,000 (from $1.8M) Cycle Time Efficiency = 78% (from 53%) Lean Concepts Applied: Eliminate Waste Build Quality In Defer decision making and adaptively plan
Lower cost of change Cost of Change Time More defects prevented and fixed Continuous testing Fast feedback Adaptive planning Traditional Project Agile Project
Adaptive planning Scope Time Release
Adaptive planning Scope Time Release
So who does this?
http://www.thoughtworks.com/our-clients/case-studies/case-studies.html
“Too  risky  for my mission critical applications”
http://www.thoughtworks.com/our-clients/case-studies/case-studies.html
Marc McNeill Hong Kong Practice Lead [email_address]

Better, faster, cheaper. Lean and agile approaches to IT development

  • 1.
    Better, faster, cheaper. Lean and agile approaches to IT development Marc McNeill, ThoughtWorks
  • 2.
    IT doesn’t havea track record
  • 3.
    “Two thirds of(IT) projects are challenged.”. Source: The Standish Group CHAOS Reports
  • 4.
    Overbudget by 189% . Source: The Standish Group CHAOS Reports
  • 5.
    Overschedule by 220% . Source: The Standish Group CHAOS Reports
  • 6.
    Only 61% of features delivered. Source: The Standish Group CHAOS Reports
  • 7.
    66% ofprojects fail or are ‘marginal’. Source: The Standish Group CHAOS Reports
  • 8.
    $3.45 billion tax-creditoverpayment UK Inland Revenue $2.6 billion spent system cancelled US Federal Aviation Administration $160 million lost because of ERP system problems Hewlett-Packard $527 million written off supply chain system abandoned J Sainsbury plc
  • 9.
    Poor Quality Slowto Deliver Expensive
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
    A Company witha purpose
  • 18.
    To be thehome for the best knowledge workers in the world
  • 19.
    To revolutionise theway software is delivered to make a positive difference to business and to society
  • 20.
    Consultancy Global DeliveryTraining Products 1000+ employees 6 countries 15 years
  • 21.
  • 22.
    The business hasan idea Increase revenue Decrease costs Regulatory pressures Cartoons courtesy of http://designcomics.org/
  • 23.
    The idea isanalysed High level design Detailed design
  • 24.
  • 25.
    The business signoff on the requirements
  • 26.
  • 27.
  • 28.
  • 29.
  • 30.
    But it doesn’talways work like this
  • 31.
  • 32.
  • 33.
    Dates slip, scopegets cut, effort wasted
  • 34.
    Value is notdelivered High project failure rate High cost of change Permanent state of maintenance Little innovation Unhappy stakeholders Poor customer experience
  • 35.
    A different story?
  • 36.
  • 37.
  • 38.
  • 39.
    Scientific management “It is only through enforced standardization of methods, enforced adoption of the best implements and working conditions and enforced cooperation that this faster work can be assured. And the duty of enforcing the adoption of standards and enforcing this cooperation rests with management alone.” Frederick Winslow Taylor Any colour so long as it is black
  • 40.
    Lean Just intime “ All we are doing is looking at the time line, from the point the customer gives us an order to the point when we collect the cash. And we are reducing the time line by reducing the non-value added wastes.” Taiichi Ohno
  • 41.
    Just in timeBuild in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement
  • 42.
  • 43.
    (v) Value-Added Time(e) Elapsed Time (c) Cumulative Elapsed Time Adapted from http://www.thoughtworks.com/pdfs/lean-qtb-jun08.pdf Requirements Gathering & Analysis (v) 1 Week (e) 4 Weeks (c) 4 Weeks Review & Approve Req. Spec. (v) 1 Day (e) 2 Weeks (c) 6 Weeks Solution Design (v) 2 Weeks (e) 6 Weeks (c) 12 Weeks Review & Approve Tech. Spec. (v) 1 Day (e) 2 Weeks (c) 14 Weeks Build Solution (Coding) (v) 8 Weeks (e) 14 Weeks (c) 28 Weeks System testing (v) 3 Weeks (e) 3 Weeks (c) 31 Weeks User Acceptance Testing (UAT) (v) 3 Weeks (e) 3 Weeks (c) 34 Weeks Deploy (v) 1 Week (e) 2 Weeks (c) 36 Weeks
  • 44.
    Requirements Gathering &Analysis Review & Approve Req. Spec. Solution Design Review & Approve Tech. Spec. (v) 1 Week (e) 4 Weeks (c) 4 Weeks (v) 1 Day (e) 2 Weeks (c) 6 Weeks (v) 2 Weeks (e) 6 Weeks (c) 12 Weeks (v) 1 Day (e) 2 Weeks (c) 14 Weeks Deploy User Acceptance Testing (UAT) System testing Build Solution (Coding) (v) 1 Week (e) 2 Weeks (c) 36 Weeks (v) 3 Weeks (e) 3 Weeks (c) 34 Weeks (v) 3 Weeks (e) 3 Weeks (c) 31 Weeks (v) 8 Weeks (e) 14 Weeks (c) 28 Weeks Total Elapsed Time = 36 Weeks Estimated Project Cost (at $50k per week) = $1.8M Cycle Time Efficiency = 53% Systemic Faults: Inefficient Slow, expensive & poor quality Inflexible System often fails
  • 45.
    Requirements Gathering &Analysis Review & Approve Req. Spec. Solution Design Review & Approve Tech. Spec. (v) 1 Week (e) 4 Weeks (c) 4 Weeks (v) 1 Day (e) 2 Weeks (c) 6 Weeks (v) 2 Weeks (e) 6 Weeks (c) 12 Weeks (v) 1 Day (e) 2 Weeks (c) 14 Weeks Deploy User Acceptance Testing (UAT) System testing Build Solution (Coding) (v) 1 Week (e) 2 Weeks (c) 36 Weeks (v) 3 Weeks (e) 3 Weeks (c) 34 Weeks (v) 3 Weeks (e) 3 Weeks (c) 31 Weeks (v) 8 Weeks (e) 14 Weeks (c) 28 Weeks Extra Features Defects Defects Waiting (v) Value-Added Time (e) Elapsed Time (c) Cumulative Elapsed Time Movement Waiting Excess Inventory Movement Waiting Excess Inventory
  • 46.
    The lean andagile way
  • 47.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks
  • 48.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Collaborative workshops
  • 49.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Visioning
  • 50.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Shared understanding
  • 51.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Lo-fi prototyping
  • 52.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Collaborative prioritisation
  • 53.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Group estimation
  • 54.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Lightweight documentation
  • 55.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks
  • 56.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance
  • 57.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Just in time
  • 58.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Just in time Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement User stories
  • 59.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Just in time Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Adaptive planning
  • 60.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Just in time Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Spike to solve hard technical problems through real experiments
  • 61.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Test driven development Just in time Build in quality
  • 62.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Continuous integration Just in time Build in quality
  • 63.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Paired programming Just in time Build in quality
  • 64.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement The right documentation Just in time
  • 65.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Reduce waste Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Continuous feedback - showcases Just in time
  • 66.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Collective ownership Just in time Reduce waste
  • 67.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality People and teamwork Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Stand-ups Just in time Reduce waste
  • 68.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Time boxed increments Just in time Reduce waste People and teamwork
  • 69.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Sustainable pace Just in time Reduce waste People and teamwork
  • 70.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Patterns, standards and ubiquitous language Just in time Reduce waste People and teamwork
  • 71.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance Build in quality Regular cadence Stabilise and standardise Make problems visible Better quality Lower cost Shorter lead times Higher morale Continuous improvement Information radiators Just in time Reduce waste People and teamwork
  • 72.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance (v) 8 Weeks (e) 10 Weeks (c) 14 Weeks (v) Value-Added Time (e) Elapsed Time (c) Cumulative Elapsed Time
  • 73.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance (v) 8 Weeks (e) 10 Weeks (c) 14 Weeks (v) Value-Added Time (e) Elapsed Time (c) Cumulative Elapsed Time Deploy User Acceptance Testing (UAT) System testing (v) 1 Week (e) 2 Weeks (c) 18 Weeks (v) 1 Week (e) 1 Week (c) 16 Weeks (v) 1 Week (e) 1 Week (c15 Weeks
  • 74.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance (v) 8 Weeks (e) 10 Weeks (c) 14 Weeks Deploy User Acceptance Testing (UAT) System testing (v) 1 Week (e) 2 Weeks (c) 18 Weeks (v) 1 Week (e) 1 Week (c) 16 Weeks (v) 1 Week (e) 1 Week (c15 Weeks (v) Value-Added Time (e) Elapsed Time (c) Cumulative Elapsed Time
  • 75.
    Requirements Gathering &Analysis (v) 3 Week (e) 4 Weeks (c) 4 Weeks Testing Design & Build User Acceptance (v) 8 Weeks (e) 10 Weeks (c) 14 Weeks Deploy User Acceptance Testing (UAT) System testing (v) 1 Week (e) 2 Weeks (c) 18 Weeks (v) 1 Week (e) 1 Week (c) 16 Weeks (v) 1 Week (e) 1 Week (c15 Weeks Total Elapsed Time = 18 Weeks (from 36 weeks) Estimated Project Cost = $900,000 (from $1.8M) Cycle Time Efficiency = 78% (from 53%) Lean Concepts Applied: Eliminate Waste Build Quality In Defer decision making and adaptively plan
  • 76.
    Lower cost ofchange Cost of Change Time More defects prevented and fixed Continuous testing Fast feedback Adaptive planning Traditional Project Agile Project
  • 77.
  • 78.
  • 79.
  • 80.
  • 81.
    “Too risky for my mission critical applications”
  • 82.
  • 83.
    Marc McNeill HongKong Practice Lead [email_address]