Photo credits (L to R): Meena Kadri, Jacek.NL, Gerardo Arévalo Tamayo (all via Flickr)
National programs studied




                      Reviewed
                      Review pending
Contextual factors that influence evaluation
processes
 Categories of project
 supported by program             Mass
                                 transit
 National mass transit
 policies                        Surface
                                transport
 Age of program
                             Urban / national
 Planning requirements        infrastructure
Evaluation frameworks
 Justification for project
 • Socioeconomic analysis (CBA, cost-
   effectiveness, assessment of indirect effects)
 • Policy and strategic factors (examples to come)
 • Factors may be
    • Treated as requirements (i.e., project must achieve a
      minimum internal rate of return, must display
      consistency with policy factors)
    • Rated (i.e., ‘high’, ‘medium’, ‘low’)
 Other viability analyses
 • Financial, legal, technical, commercial, planning, etc.
 • Usually treated as requirements
Socioeconomic evaluation: Cost-benefit
  analysis
     Focus on (discounted) direct, monetizable
     societal impacts of a project over its life
 Consumer surplus
 • Travel time
 • Vehicle operating costs /
   fares                                                      Costs to government
 • Travel quality                                             • Project capital
                                                                contributions
                                              Benefit-cost
 Producer surplus                                             • (Project operating and
                                                 ratio
 • Vehicle operating costs                                      maintenance subsidies)
                                              Internal rate
                                                of return
 Externalities                                Net present
                                                              Costs to infrastructure
 • Noise                                         value
                                                              managers / project operators
 • Air pollution / GHG
                                                              • Project capital
   emissions
                                                                contributions
 • Traffic collisions

(Also negative impacts during construction)
Complementary socioeconomic evaluations
  Further socioeconomic impacts may serve to
  ‘adjust’ cost-benefit analysis results
• Wider / indirect
  economic benefits
  (i.e., agglomeration, imp
  roved job matching)
• Environmental impacts
  (i.e., water
  quality, habitats, viewsh
  eds, physical activity)
• Equity / distributional
  effects
                               Photo credit: Ariel Cruz Pizarro (via Flickr)
Strategic and policy evaluation factors
 Consistency with national government policies
 and priorities
  • Investments
  • Reforms
 Urban
 development and
 transport priorities
  • Land use
  • Transport plans and
    other investments

                                    Photo credit: Ferdi (via Flickr)
Policy consistency: Colombia
 Objectives: reverse decreases in transit mode
 share through better service quality, balance
 supply and demand
 Cities must
 commit to
 coordinating /
 rationalizing
 privately operated
 transport services
 as part of funding
 agreements                      Photo credit: miguelmatus (via Flickr)
Policy consistency: New Zealand
 Objectives: support economic growth and productivity
 improvements
 Projects rated
 on how
 effectively
 they meet
 associated
 objectives
 (reduce
 congestion, i
 mprove travel
 time
                                     Photo credit: Nankai (via Wikipedia)
 reliability)
Land use: United States
 Projects evaluated based
 on
  • Existing land use in
    corridor (population
    density, employment, p
    arking supply, etc.)
  • Potential to shape
    corridor and regional
    economic
    development, based on
    policies and plans       Photo: Jeff Wood (via Flickr)
Evaluations and decision-making
 In most cases, technical staff at national agency
 or technical committee conducts evaluation
  • May be at multiple points during project development
 … but funding decision-makers are non-
 technical (i.e., political figures)
 Evaluation process should yield information that
 supports informed decisions
  • Costs and benefits, socioeconomic and otherwise
  • May be scaled to project cost/complexity
  • Rationale for a viability determination or rating (or
    rejection)
Thank you!
                                                   Ben Owen
                                                bowen@wri.org
                                                +1 202 729-7600



                                                   www.embarq.org
Photo credits (L to R): Aaron Hockley, Omar Bárcena, Rupert Brun (all via Flickr)

More Related Content

Similar to Ben Owen - International Experiences in Evaluation and Selection of Mass Transit Projects

2040 RTP Leadership Symposium II 3.13.13
2040 RTP Leadership Symposium II 3.13.132040 RTP Leadership Symposium II 3.13.13
2040 RTP Leadership Symposium II 3.13.13CHCRPA
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...marcus evans Network
 
2018 04 03-abc conference_slides_meliora
2018 04 03-abc conference_slides_meliora2018 04 03-abc conference_slides_meliora
2018 04 03-abc conference_slides_melioraNew Jersey Future
 
Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPMA Consultants
 
Project Financing in Public Projects
Project Financing in Public ProjectsProject Financing in Public Projects
Project Financing in Public ProjectsXinyi (Sophia) Xue
 
Understanding challenges of developing transportation PPPs in the Middle East
Understanding challenges of developing transportation PPPs in the Middle EastUnderstanding challenges of developing transportation PPPs in the Middle East
Understanding challenges of developing transportation PPPs in the Middle EastDr Rupert Booth
 
BIM_PPT_HowItAffectsYourWorkflow_073020.pdf
BIM_PPT_HowItAffectsYourWorkflow_073020.pdfBIM_PPT_HowItAffectsYourWorkflow_073020.pdf
BIM_PPT_HowItAffectsYourWorkflow_073020.pdfRavenousSolos
 
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...Aconex
 
MKAQ1063 W9 -Transit System Planning CRIed (4).pptx
MKAQ1063 W9 -Transit System Planning CRIed (4).pptxMKAQ1063 W9 -Transit System Planning CRIed (4).pptx
MKAQ1063 W9 -Transit System Planning CRIed (4).pptxNURSUHANABINTIBORHAN
 
Strategies for Reducing Risk on Design-Build Public Transit Projects
Strategies for Reducing Risk on Design-Build Public Transit ProjectsStrategies for Reducing Risk on Design-Build Public Transit Projects
Strategies for Reducing Risk on Design-Build Public Transit ProjectsGannett Fleming, Inc.
 
Dayton ASCE Sustainability Presentation
Dayton ASCE Sustainability PresentationDayton ASCE Sustainability Presentation
Dayton ASCE Sustainability PresentationScott DeGaro
 
Feasibility assessment of selected sites for the pilot project on the feasibi...
Feasibility assessment of selected sites for the pilot project on the feasibi...Feasibility assessment of selected sites for the pilot project on the feasibi...
Feasibility assessment of selected sites for the pilot project on the feasibi...ILRI
 
Chicago Infrastructure Trust Briefing
Chicago Infrastructure Trust BriefingChicago Infrastructure Trust Briefing
Chicago Infrastructure Trust BriefingTom Tresser
 
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...OECD Environment
 
Efficiency Based Comparison of Project Delivery Methods
Efficiency Based Comparison of Project Delivery MethodsEfficiency Based Comparison of Project Delivery Methods
Efficiency Based Comparison of Project Delivery MethodsRajnish Lekhi M.S, LEED GA
 

Similar to Ben Owen - International Experiences in Evaluation and Selection of Mass Transit Projects (20)

2040 RTP Leadership Symposium II 3.13.13
2040 RTP Leadership Symposium II 3.13.132040 RTP Leadership Symposium II 3.13.13
2040 RTP Leadership Symposium II 3.13.13
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
 
PPP Workshop
PPP WorkshopPPP Workshop
PPP Workshop
 
Session 2_Yoo-Eun Koh.pdf
Session 2_Yoo-Eun Koh.pdfSession 2_Yoo-Eun Koh.pdf
Session 2_Yoo-Eun Koh.pdf
 
2018 04 03-abc conference_slides_meliora
2018 04 03-abc conference_slides_meliora2018 04 03-abc conference_slides_meliora
2018 04 03-abc conference_slides_meliora
 
Coastal Road Project
Coastal Road ProjectCoastal Road Project
Coastal Road Project
 
Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital Projects
 
Project Financing in Public Projects
Project Financing in Public ProjectsProject Financing in Public Projects
Project Financing in Public Projects
 
Understanding challenges of developing transportation PPPs in the Middle East
Understanding challenges of developing transportation PPPs in the Middle EastUnderstanding challenges of developing transportation PPPs in the Middle East
Understanding challenges of developing transportation PPPs in the Middle East
 
BIM_PPT_HowItAffectsYourWorkflow_073020.pdf
BIM_PPT_HowItAffectsYourWorkflow_073020.pdfBIM_PPT_HowItAffectsYourWorkflow_073020.pdf
BIM_PPT_HowItAffectsYourWorkflow_073020.pdf
 
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
 
MKAQ1063 W9 -Transit System Planning CRIed (4).pptx
MKAQ1063 W9 -Transit System Planning CRIed (4).pptxMKAQ1063 W9 -Transit System Planning CRIed (4).pptx
MKAQ1063 W9 -Transit System Planning CRIed (4).pptx
 
Strategies for Reducing Risk on Design-Build Public Transit Projects
Strategies for Reducing Risk on Design-Build Public Transit ProjectsStrategies for Reducing Risk on Design-Build Public Transit Projects
Strategies for Reducing Risk on Design-Build Public Transit Projects
 
Dayton ASCE Sustainability Presentation
Dayton ASCE Sustainability PresentationDayton ASCE Sustainability Presentation
Dayton ASCE Sustainability Presentation
 
Toll Roads
Toll RoadsToll Roads
Toll Roads
 
Feasibility assessment of selected sites for the pilot project on the feasibi...
Feasibility assessment of selected sites for the pilot project on the feasibi...Feasibility assessment of selected sites for the pilot project on the feasibi...
Feasibility assessment of selected sites for the pilot project on the feasibi...
 
Chicago Infrastructure Trust Briefing
Chicago Infrastructure Trust BriefingChicago Infrastructure Trust Briefing
Chicago Infrastructure Trust Briefing
 
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...
2022 GATF Annual Meeting - Item 7.5 - Sustainable Infrastructure Programme in...
 
Julian_Carroll resume 2015 link
Julian_Carroll resume 2015 linkJulian_Carroll resume 2015 link
Julian_Carroll resume 2015 link
 
Efficiency Based Comparison of Project Delivery Methods
Efficiency Based Comparison of Project Delivery MethodsEfficiency Based Comparison of Project Delivery Methods
Efficiency Based Comparison of Project Delivery Methods
 

More from WRI Ross Center for Sustainable Cities

Restoration of Urban Blue Acres_Nualgi Pyco-remediation of sewage and lakes
Restoration of Urban Blue Acres_Nualgi Pyco-remediation of sewage and lakesRestoration of Urban Blue Acres_Nualgi Pyco-remediation of sewage and lakes
Restoration of Urban Blue Acres_Nualgi Pyco-remediation of sewage and lakesWRI Ross Center for Sustainable Cities
 
Unlock Bengaluru 2018: Roadmap to the Townships and Campuses of the Future
Unlock Bengaluru 2018: Roadmap to the Townships and Campuses of the FutureUnlock Bengaluru 2018: Roadmap to the Townships and Campuses of the Future
Unlock Bengaluru 2018: Roadmap to the Townships and Campuses of the FutureWRI Ross Center for Sustainable Cities
 
CK2018: Assessment of Istanbul Historic Peninsula Pedestrianization Project
CK2018: Assessment of Istanbul Historic Peninsula Pedestrianization ProjectCK2018: Assessment of Istanbul Historic Peninsula Pedestrianization Project
CK2018: Assessment of Istanbul Historic Peninsula Pedestrianization ProjectWRI Ross Center for Sustainable Cities
 
CK2018: Global Convenant of Mayors approach to Climate Action Planning
CK2018: Global Convenant of Mayors approach to Climate Action PlanningCK2018: Global Convenant of Mayors approach to Climate Action Planning
CK2018: Global Convenant of Mayors approach to Climate Action PlanningWRI Ross Center for Sustainable Cities
 

More from WRI Ross Center for Sustainable Cities (20)

Restoration of Urban Blue Acres_Case of Rajokari Village
Restoration of Urban Blue Acres_Case of Rajokari VillageRestoration of Urban Blue Acres_Case of Rajokari Village
Restoration of Urban Blue Acres_Case of Rajokari Village
 
Restoration of Urban Blue Acres_Nualgi Pyco-remediation of sewage and lakes
Restoration of Urban Blue Acres_Nualgi Pyco-remediation of sewage and lakesRestoration of Urban Blue Acres_Nualgi Pyco-remediation of sewage and lakes
Restoration of Urban Blue Acres_Nualgi Pyco-remediation of sewage and lakes
 
Restoration of Urban Blue Acres_Green Water Revoln. Pune
Restoration of Urban Blue Acres_Green Water Revoln. PuneRestoration of Urban Blue Acres_Green Water Revoln. Pune
Restoration of Urban Blue Acres_Green Water Revoln. Pune
 
Restoration of Urban Blue Acres_Biostarts Ventures
Restoration of Urban Blue Acres_Biostarts VenturesRestoration of Urban Blue Acres_Biostarts Ventures
Restoration of Urban Blue Acres_Biostarts Ventures
 
Restoration of Urban Blue Acres_Biome Water for Cities
Restoration of Urban Blue Acres_Biome Water for CitiesRestoration of Urban Blue Acres_Biome Water for Cities
Restoration of Urban Blue Acres_Biome Water for Cities
 
Restoration of Urban Blue Acres_Relevance of Global Outlook to HYD
Restoration of Urban Blue Acres_Relevance of Global Outlook to HYDRestoration of Urban Blue Acres_Relevance of Global Outlook to HYD
Restoration of Urban Blue Acres_Relevance of Global Outlook to HYD
 
Restoration of Urban Blue Acres_Ayala
Restoration of Urban Blue Acres_AyalaRestoration of Urban Blue Acres_Ayala
Restoration of Urban Blue Acres_Ayala
 
Restoration of Urban Blue Acres_Multi-stakeholder forum HYD
Restoration of Urban Blue Acres_Multi-stakeholder forum HYDRestoration of Urban Blue Acres_Multi-stakeholder forum HYD
Restoration of Urban Blue Acres_Multi-stakeholder forum HYD
 
Unlock Bengaluru 2018: Roadmap to the Townships and Campuses of the Future
Unlock Bengaluru 2018: Roadmap to the Townships and Campuses of the FutureUnlock Bengaluru 2018: Roadmap to the Townships and Campuses of the Future
Unlock Bengaluru 2018: Roadmap to the Townships and Campuses of the Future
 
Unlock Bengaluru 2018: Water - Are we nearing Day Zero?
Unlock Bengaluru 2018: Water - Are we nearing Day Zero?Unlock Bengaluru 2018: Water - Are we nearing Day Zero?
Unlock Bengaluru 2018: Water - Are we nearing Day Zero?
 
CK2018: Assessment of Istanbul Historic Peninsula Pedestrianization Project
CK2018: Assessment of Istanbul Historic Peninsula Pedestrianization ProjectCK2018: Assessment of Istanbul Historic Peninsula Pedestrianization Project
CK2018: Assessment of Istanbul Historic Peninsula Pedestrianization Project
 
CK2018: Green Corridor TOD Project - Cali, Colombia
CK2018: Green Corridor TOD Project - Cali, ColombiaCK2018: Green Corridor TOD Project - Cali, Colombia
CK2018: Green Corridor TOD Project - Cali, Colombia
 
CK2018: Land value capture in Brazil
CK2018: Land value capture in BrazilCK2018: Land value capture in Brazil
CK2018: Land value capture in Brazil
 
CK2018: Urban Development - Examples from Mexico
CK2018: Urban Development - Examples from MexicoCK2018: Urban Development - Examples from Mexico
CK2018: Urban Development - Examples from Mexico
 
CK2018: Working with Partners & Data Sharing
CK2018: Working with Partners & Data Sharing CK2018: Working with Partners & Data Sharing
CK2018: Working with Partners & Data Sharing
 
CK2018: Global Convenant of Mayors approach to Climate Action Planning
CK2018: Global Convenant of Mayors approach to Climate Action PlanningCK2018: Global Convenant of Mayors approach to Climate Action Planning
CK2018: Global Convenant of Mayors approach to Climate Action Planning
 
CK2018: GHG Platform India
CK2018: GHG Platform IndiaCK2018: GHG Platform India
CK2018: GHG Platform India
 
CK2018: Climate Actions for Cities India's NDC, NAPCC and SAPCC
CK2018: Climate Actions for Cities India's NDC, NAPCC and SAPCCCK2018: Climate Actions for Cities India's NDC, NAPCC and SAPCC
CK2018: Climate Actions for Cities India's NDC, NAPCC and SAPCC
 
CK2018: Barriers and Global Innovations for Electric Bus Fleets
CK2018: Barriers and Global Innovations for Electric Bus FleetsCK2018: Barriers and Global Innovations for Electric Bus Fleets
CK2018: Barriers and Global Innovations for Electric Bus Fleets
 
CK2018: Electric Vehicle Financing
CK2018: Electric Vehicle FinancingCK2018: Electric Vehicle Financing
CK2018: Electric Vehicle Financing
 

Recently uploaded

Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 

Recently uploaded (20)

Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 

Ben Owen - International Experiences in Evaluation and Selection of Mass Transit Projects

  • 1. International experiences in evaluation and selection of mass transit projects Ben Owen Visiting Fellow www.embarq.org Photo credits (L to R): Meena Kadri, Jacek.NL, Gerardo Arévalo Tamayo (all via Flickr)
  • 2. National programs studied Reviewed Review pending
  • 3. Contextual factors that influence evaluation processes Categories of project supported by program Mass transit National mass transit policies Surface transport Age of program Urban / national Planning requirements infrastructure
  • 4. Evaluation frameworks Justification for project • Socioeconomic analysis (CBA, cost- effectiveness, assessment of indirect effects) • Policy and strategic factors (examples to come) • Factors may be • Treated as requirements (i.e., project must achieve a minimum internal rate of return, must display consistency with policy factors) • Rated (i.e., ‘high’, ‘medium’, ‘low’) Other viability analyses • Financial, legal, technical, commercial, planning, etc. • Usually treated as requirements
  • 5. Socioeconomic evaluation: Cost-benefit analysis Focus on (discounted) direct, monetizable societal impacts of a project over its life Consumer surplus • Travel time • Vehicle operating costs / fares Costs to government • Travel quality • Project capital contributions Benefit-cost Producer surplus • (Project operating and ratio • Vehicle operating costs maintenance subsidies) Internal rate of return Externalities Net present Costs to infrastructure • Noise value managers / project operators • Air pollution / GHG • Project capital emissions contributions • Traffic collisions (Also negative impacts during construction)
  • 6. Complementary socioeconomic evaluations Further socioeconomic impacts may serve to ‘adjust’ cost-benefit analysis results • Wider / indirect economic benefits (i.e., agglomeration, imp roved job matching) • Environmental impacts (i.e., water quality, habitats, viewsh eds, physical activity) • Equity / distributional effects Photo credit: Ariel Cruz Pizarro (via Flickr)
  • 7. Strategic and policy evaluation factors Consistency with national government policies and priorities • Investments • Reforms Urban development and transport priorities • Land use • Transport plans and other investments Photo credit: Ferdi (via Flickr)
  • 8. Policy consistency: Colombia Objectives: reverse decreases in transit mode share through better service quality, balance supply and demand Cities must commit to coordinating / rationalizing privately operated transport services as part of funding agreements Photo credit: miguelmatus (via Flickr)
  • 9. Policy consistency: New Zealand Objectives: support economic growth and productivity improvements Projects rated on how effectively they meet associated objectives (reduce congestion, i mprove travel time Photo credit: Nankai (via Wikipedia) reliability)
  • 10. Land use: United States Projects evaluated based on • Existing land use in corridor (population density, employment, p arking supply, etc.) • Potential to shape corridor and regional economic development, based on policies and plans Photo: Jeff Wood (via Flickr)
  • 11. Evaluations and decision-making In most cases, technical staff at national agency or technical committee conducts evaluation • May be at multiple points during project development … but funding decision-makers are non- technical (i.e., political figures) Evaluation process should yield information that supports informed decisions • Costs and benefits, socioeconomic and otherwise • May be scaled to project cost/complexity • Rationale for a viability determination or rating (or rejection)