The document provides a weekly accomplishment report from November 7-13, 2022 for dredging operations in the Bicol River Basin. It summarizes that Phase 1 dredging in San Roque and Camaligan sections has been completed, while Phase 2 dredging in the Gainza-Camaligan section has removed 713,015 cubic meters of material so far, achieving a 10.3% completion rate. It also lists the locations and machines used for current dredging work.