The document outlines the budget and schedule for the Hollywood Wellington Casino & Resort project. It lists a total budget of $365 million, including $340 million for land development, construction, furniture and other costs, and a $25 million license fee. The schedule details permits and pre-construction from September 2008 to December 2008, foundations and site construction from December 2008 to May 2009, casino and hotel construction from May 2009 to November 2010, followed by completion of certificates and pre-opening until the facility opens in December 2010. Environmental studies found no adverse effects.