The extension work on the Sarnath school is ongoing. The rooms are being plastered and pipes for water and electricity are being installed on the walls. Toilets have been completed on the first two floors and are being built on the third floor. Floors still need to be prepared. Painters are painting doors and window frames. Two classrooms behind the stupa are being converted into four guest rooms with attached bathrooms. The library is also being repainted with new colors suggested by Grazeilla ji. Construction of the new Junior Bodhagaya High School has been delayed due to finances and weather but is almost finished, with inside setup work beginning.