SlideShare a Scribd company logo
AJC
Q1. How would you characterize the project assets? What makes them different or unique?
Solution:
Assets: Transmission Cable, Repeaters, Transmission Equipment, Landing Stations and
Ships:
 There are 2 mediums for long distance data transmission: Satellite and Cable
systems. Cable systems offer better quality, lower costs and can carry much more
capacity compared to the satellite systems.
 It is the core asset for the project.
 A 12500 kilometres long fiber optic cable will be laid out for the project.
 The life of the cable is estimated at 25 years.
 The transmission cable failures usually happen in the shallow water areas. Using
collapsed ring configuration would be the major advantage for AJC as it would reduce
the capital costs considerably.
 Once the cables laid out they are highly reliable since only 1 (average) failure is
usually recorded in a cable’s life.
 It is not very expensive to upgrade traffic capacity, i.e., $25 million/40Gbps. However,
it takes around 12-15 months to implement it.
 It may be difficult to attract lenders for such project. Example, on a visit to Mundra Port
Single Point Mooring, we were explained by the instructor that it was very difficult to
convince the ‘bankers’ that a system like that could require such huge investment (INR
50-100 crores). What the bankers saw was a 200 sq ft metal floating body (most part
was invisible) and it took an effort by the engineers to explain the bankers about the
inherent complexity and hence the costs associated. AJC project might have faced a
similar issue at that time.
 Repeaters are required for every 400 kilometres to reshape and boost the signal as it
becomes attenuated when transmitted over long distances.
 Transmission Equipment comprises of transmitter, router and reception hub and
determines the capacity of the system to transfer the signals. It could be easily
upgraded to handle more traffic.
 Landing Stations and Ships are hired for the project. Ships are used to install Cables
and Repeaters.
 As the telecom sector is highly evolving (in 1999), there is always technology risk
associated with such projects. There is a possibility of bigger and better technology
(which would handle higher and much bandwidth) in such an environment.
 The revenues are front loaded as much of the revenue is recognised in the earlier
years of the project (in terms of their contribution to the NPV).
 The operation costs are fairly consistent for the life of the project.
 Most of the capital expense will occur very early in the project.
Q2. Who provide capital to the AJC project? Are they likely to earn an appropriate risk
adjusted return on their investment? What potential problems could arise that would prevent
them from earning a return on their invested capital?
Solution:
NPV and IRR for 3 scenarios has been calculated in the excel sheet.
The capital for the project would come from the sponsors and consortium of banks.
The project would have fairly high financial leverage (85%). To obtain their target debt
structure, they wanted to raise 2 debt tranches:
Senior debt: Repayments would come from presale commitments.
Junior debt: Repayments would come from future sales of capacity.
 Technology risk: Telecom Sector is evolving rapidly and hence there is technological
risk associated with the project.
 Completion Delay Risk: Since most of the revenue is front loaded, any delay in the
project will have much adverse effect on its valuation. It can also happen because of
environmental clearance delays, etc.
 Political Risk: As the project covers more than one country, we need to take into
consideration the sovereign risk. Since we have sponsors from each country
associated with the project, the risk is somewhat mitigated.
 Market Risk: To mitigate this they will need presale contracts.
 Credibility Risk: Depends on the composition of the sponsors.
 Operational Risk: Price Volatility is very high and there’s also risk of demand. They will
partner sponsors strategically to reduce uncertainty with the revenue and to reduce the
costs (landing stations).
Q3. How would you structure the project company to mitigate these problems? What are your
recommendations in terms of?
a. ownership structure (how many sponsors and which ones)
b. capital structure (project fin vs. corporate fin)
C.organizational structure
Solution:
a. Ownership Structure:
Factors to be considered are Compatibility, Affect on Project Cost and Revenue.
The project costs may be reduced by utilisation of the landing station of sponsors and also
the revenue can be made certain if the sponsors are themselves buyers for capacity.
We would go for 4 sponsors:
Telstra, Japan Telecom, Teleglobe, and AT&T: AT&T would enable us to use the Guam
Landing station and also would buy some capacity. Their debt rating is AA- which would
add to the credibility for lenders.
b. Capital Structure
Although, the financial leverage is high (85%), it would make them share the project risk
with the lenders of the project. They could allow high leverage because of high amount of
certain cash flow. Project Finance is recommended for the project as it would prevent
exposure of risk to the sponsor companies’ assets. The high debt taken by the sponsors
would be off-the balance sheet for them.
As there is high free cash flows associated with the project, there is bound to be
mismanagement risk of the fund. Having high leverage position would prevent this as free
cash flow would reduce in high debt situation.
c. Organisational Structure
The sponsors will have equal stake in the shareholding pattern. This way all of them will
have equal say in the functioning of the project. All the shareholders hold strong positions
and add value to the project; the board will be represented equally by the sponsors. This
would prevent any conflicts in the decision making.

More Related Content

What's hot

Merger & acquisition, Hindalco Novelis
Merger & acquisition, Hindalco NovelisMerger & acquisition, Hindalco Novelis
Merger & acquisition, Hindalco Novelis
Gagan Pareek, PMP
 
Poland’s A2 Motorway
Poland’s A2 MotorwayPoland’s A2 Motorway
Poland’s A2 MotorwayAnkit Agarwal
 
Airbus a3xx developing the worlds largest commercial jet Case Analysis
Airbus a3xx developing the worlds largest commercial jet Case AnalysisAirbus a3xx developing the worlds largest commercial jet Case Analysis
Airbus a3xx developing the worlds largest commercial jet Case Analysis
Neeraj Mehra, CFA
 
Acc- Holcim Merger & Acquisition Case Study
Acc- Holcim Merger & Acquisition Case Study Acc- Holcim Merger & Acquisition Case Study
Acc- Holcim Merger & Acquisition Case Study
snigdha sarkar
 
Newell
NewellNewell
Newell
Shagun Singh
 
Jsw shoppe
Jsw shoppeJsw shoppe
Jsw shoppe
Jay K Garg
 
Hindalco’s acquisition of novelis
Hindalco’s acquisition of novelisHindalco’s acquisition of novelis
Hindalco’s acquisition of novelis
Bhupender Singh Jadon
 
Financial Policy at Apple (A) 2013
Financial Policy at Apple (A) 2013Financial Policy at Apple (A) 2013
Financial Policy at Apple (A) 2013
Fadila Pratika Alimuddin
 
APOLLO TYRES – COOPER TIRE DEAL
APOLLO TYRES – COOPER TIRE DEALAPOLLO TYRES – COOPER TIRE DEAL
APOLLO TYRES – COOPER TIRE DEAL
Ankit Kumar Gupta
 
Eli Lilly and Company, Inc. Case Analysis
Eli Lilly and Company, Inc. Case AnalysisEli Lilly and Company, Inc. Case Analysis
Eli Lilly and Company, Inc. Case Analysis
Neeraj Mehra, CFA
 
A case study presentation on Dabhol Power Plant
A case study presentation on Dabhol Power PlantA case study presentation on Dabhol Power Plant
A case study presentation on Dabhol Power Plant
Ashutosh Singh
 
Dabhol Case Study presentationn
Dabhol Case Study presentationnDabhol Case Study presentationn
Dabhol Case Study presentationn
Manoj Kumar Mishra
 
Corporate governance failure at satyam
Corporate governance failure at satyamCorporate governance failure at satyam
Corporate governance failure at satyam
Ankit Uttam
 
Crown Cork & Seal/CarnaudMetalbox Merger
Crown Cork & Seal/CarnaudMetalbox MergerCrown Cork & Seal/CarnaudMetalbox Merger
Crown Cork & Seal/CarnaudMetalbox Merger
rapidravi
 
Ducati hbr case analysis
Ducati hbr  case analysisDucati hbr  case analysis
Ducati hbr case analysis
Sandeep_Srivastava
 
DABHOL POWER COMPANY, INDIA
DABHOL POWER COMPANY,  INDIADABHOL POWER COMPANY,  INDIA
DABHOL POWER COMPANY, INDIA
Ankit Kumar Gupta
 
Intel 64 Fund Case Study
Intel 64 Fund Case StudyIntel 64 Fund Case Study
Intel 64 Fund Case Study
Deepak Motiramani
 
Biopure case solution
Biopure case solutionBiopure case solution
Biopure case solution
Akhilendra Tiwari
 

What's hot (20)

Merger & acquisition, Hindalco Novelis
Merger & acquisition, Hindalco NovelisMerger & acquisition, Hindalco Novelis
Merger & acquisition, Hindalco Novelis
 
Poland’s A2 Motorway
Poland’s A2 MotorwayPoland’s A2 Motorway
Poland’s A2 Motorway
 
Airbus a3xx developing the worlds largest commercial jet Case Analysis
Airbus a3xx developing the worlds largest commercial jet Case AnalysisAirbus a3xx developing the worlds largest commercial jet Case Analysis
Airbus a3xx developing the worlds largest commercial jet Case Analysis
 
Bp Amoco (case study)
Bp Amoco (case study)Bp Amoco (case study)
Bp Amoco (case study)
 
Acc- Holcim Merger & Acquisition Case Study
Acc- Holcim Merger & Acquisition Case Study Acc- Holcim Merger & Acquisition Case Study
Acc- Holcim Merger & Acquisition Case Study
 
Ocean Carriers - Titanic
Ocean Carriers - TitanicOcean Carriers - Titanic
Ocean Carriers - Titanic
 
Newell
NewellNewell
Newell
 
Jsw shoppe
Jsw shoppeJsw shoppe
Jsw shoppe
 
Hindalco’s acquisition of novelis
Hindalco’s acquisition of novelisHindalco’s acquisition of novelis
Hindalco’s acquisition of novelis
 
Financial Policy at Apple (A) 2013
Financial Policy at Apple (A) 2013Financial Policy at Apple (A) 2013
Financial Policy at Apple (A) 2013
 
APOLLO TYRES – COOPER TIRE DEAL
APOLLO TYRES – COOPER TIRE DEALAPOLLO TYRES – COOPER TIRE DEAL
APOLLO TYRES – COOPER TIRE DEAL
 
Eli Lilly and Company, Inc. Case Analysis
Eli Lilly and Company, Inc. Case AnalysisEli Lilly and Company, Inc. Case Analysis
Eli Lilly and Company, Inc. Case Analysis
 
A case study presentation on Dabhol Power Plant
A case study presentation on Dabhol Power PlantA case study presentation on Dabhol Power Plant
A case study presentation on Dabhol Power Plant
 
Dabhol Case Study presentationn
Dabhol Case Study presentationnDabhol Case Study presentationn
Dabhol Case Study presentationn
 
Corporate governance failure at satyam
Corporate governance failure at satyamCorporate governance failure at satyam
Corporate governance failure at satyam
 
Crown Cork & Seal/CarnaudMetalbox Merger
Crown Cork & Seal/CarnaudMetalbox MergerCrown Cork & Seal/CarnaudMetalbox Merger
Crown Cork & Seal/CarnaudMetalbox Merger
 
Ducati hbr case analysis
Ducati hbr  case analysisDucati hbr  case analysis
Ducati hbr case analysis
 
DABHOL POWER COMPANY, INDIA
DABHOL POWER COMPANY,  INDIADABHOL POWER COMPANY,  INDIA
DABHOL POWER COMPANY, INDIA
 
Intel 64 Fund Case Study
Intel 64 Fund Case StudyIntel 64 Fund Case Study
Intel 64 Fund Case Study
 
Biopure case solution
Biopure case solutionBiopure case solution
Biopure case solution
 

Similar to AJC Case Analysis

Submarine cables - Structuring and Financing Options Jan 2015_final
Submarine cables - Structuring and Financing Options Jan 2015_finalSubmarine cables - Structuring and Financing Options Jan 2015_final
Submarine cables - Structuring and Financing Options Jan 2015_finalDominique Reverdy
 
Submarine cables structuring and financing options
Submarine cables   structuring and financing optionsSubmarine cables   structuring and financing options
Submarine cables structuring and financing options
Amy Walls
 
Economics of solar farms india dec 3 2015
Economics of solar farms  india dec 3 2015Economics of solar farms  india dec 3 2015
Economics of solar farms india dec 3 2015
Vinod K Kala
 
M2 M Brett O Riley Comms Day 2008
M2 M   Brett O Riley Comms Day 2008M2 M   Brett O Riley Comms Day 2008
M2 M Brett O Riley Comms Day 20088bits
 
Microgrid invest risk summary v08-02c
Microgrid invest risk summary v08-02cMicrogrid invest risk summary v08-02c
Microgrid invest risk summary v08-02c
James Finlay
 
Byline: Harris CapRock Communications - "Global Maritime Communications: Deli...
Byline: Harris CapRock Communications - "Global Maritime Communications: Deli...Byline: Harris CapRock Communications - "Global Maritime Communications: Deli...
Byline: Harris CapRock Communications - "Global Maritime Communications: Deli...claytonroot
 
SG European Cable Sector initiation (Alejandro Nunez 201104)
SG European Cable Sector initiation (Alejandro Nunez 201104)SG European Cable Sector initiation (Alejandro Nunez 201104)
SG European Cable Sector initiation (Alejandro Nunez 201104)Maragat0
 
Guideline for the Preparation of a Concept Note
Guideline for the Preparation of a Concept NoteGuideline for the Preparation of a Concept Note
Guideline for the Preparation of a Concept Note
EEP Mekong
 
How to create an energy storage market?
How to create an energy storage market? 	How to create an energy storage market?
How to create an energy storage market?
Bushveld Energy
 
Navigating Interconnecion and Transmission in the Major US Markets
Navigating Interconnecion and Transmission in the Major US MarketsNavigating Interconnecion and Transmission in the Major US Markets
Navigating Interconnecion and Transmission in the Major US Markets
brokish
 
Navigating I T
Navigating I  TNavigating I  T
Navigating I Trpeters
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
mtingle
 
Grid diagnostic study Philippines - ETP.pdf
Grid diagnostic study Philippines - ETP.pdfGrid diagnostic study Philippines - ETP.pdf
Grid diagnostic study Philippines - ETP.pdf
OECD Environment
 
Economics of Electricity Transmission Line Rehabilitation Investments
Economics of Electricity Transmission Line Rehabilitation Investments Economics of Electricity Transmission Line Rehabilitation Investments
Economics of Electricity Transmission Line Rehabilitation Investments
Sener Salci
 
NEDAS Toronto 2015 - Presentations
NEDAS Toronto 2015 - PresentationsNEDAS Toronto 2015 - Presentations
NEDAS Toronto 2015 - Presentations
Ilissa Miller
 
Project and Infrastructure Finance slides Module1_Ver3.ppt
Project and Infrastructure Finance slides Module1_Ver3.pptProject and Infrastructure Finance slides Module1_Ver3.ppt
Project and Infrastructure Finance slides Module1_Ver3.ppt
Govind Raj
 
Choose quality-with-cost-justification
Choose quality-with-cost-justificationChoose quality-with-cost-justification
Choose quality-with-cost-justificationdrottmayer
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
HIMADRI BANERJI
 
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
Forum for the Future
 

Similar to AJC Case Analysis (20)

Submarine cables - Structuring and Financing Options Jan 2015_final
Submarine cables - Structuring and Financing Options Jan 2015_finalSubmarine cables - Structuring and Financing Options Jan 2015_final
Submarine cables - Structuring and Financing Options Jan 2015_final
 
Submarine cables structuring and financing options
Submarine cables   structuring and financing optionsSubmarine cables   structuring and financing options
Submarine cables structuring and financing options
 
Economics of solar farms india dec 3 2015
Economics of solar farms  india dec 3 2015Economics of solar farms  india dec 3 2015
Economics of solar farms india dec 3 2015
 
M2 M Brett O Riley Comms Day 2008
M2 M   Brett O Riley Comms Day 2008M2 M   Brett O Riley Comms Day 2008
M2 M Brett O Riley Comms Day 2008
 
Microgrid invest risk summary v08-02c
Microgrid invest risk summary v08-02cMicrogrid invest risk summary v08-02c
Microgrid invest risk summary v08-02c
 
Byline: Harris CapRock Communications - "Global Maritime Communications: Deli...
Byline: Harris CapRock Communications - "Global Maritime Communications: Deli...Byline: Harris CapRock Communications - "Global Maritime Communications: Deli...
Byline: Harris CapRock Communications - "Global Maritime Communications: Deli...
 
SG European Cable Sector initiation (Alejandro Nunez 201104)
SG European Cable Sector initiation (Alejandro Nunez 201104)SG European Cable Sector initiation (Alejandro Nunez 201104)
SG European Cable Sector initiation (Alejandro Nunez 201104)
 
Guideline for the Preparation of a Concept Note
Guideline for the Preparation of a Concept NoteGuideline for the Preparation of a Concept Note
Guideline for the Preparation of a Concept Note
 
How to create an energy storage market?
How to create an energy storage market? 	How to create an energy storage market?
How to create an energy storage market?
 
Navigating Interconnecion and Transmission in the Major US Markets
Navigating Interconnecion and Transmission in the Major US MarketsNavigating Interconnecion and Transmission in the Major US Markets
Navigating Interconnecion and Transmission in the Major US Markets
 
Navigating I T
Navigating I  TNavigating I  T
Navigating I T
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
 
Grid diagnostic study Philippines - ETP.pdf
Grid diagnostic study Philippines - ETP.pdfGrid diagnostic study Philippines - ETP.pdf
Grid diagnostic study Philippines - ETP.pdf
 
Economics of Electricity Transmission Line Rehabilitation Investments
Economics of Electricity Transmission Line Rehabilitation Investments Economics of Electricity Transmission Line Rehabilitation Investments
Economics of Electricity Transmission Line Rehabilitation Investments
 
NEDAS Toronto 2015 - Presentations
NEDAS Toronto 2015 - PresentationsNEDAS Toronto 2015 - Presentations
NEDAS Toronto 2015 - Presentations
 
Project and Infrastructure Finance slides Module1_Ver3.ppt
Project and Infrastructure Finance slides Module1_Ver3.pptProject and Infrastructure Finance slides Module1_Ver3.ppt
Project and Infrastructure Finance slides Module1_Ver3.ppt
 
Choose quality-with-cost-justification
Choose quality-with-cost-justificationChoose quality-with-cost-justification
Choose quality-with-cost-justification
 
Investment pitch deck-v10
Investment pitch deck-v10Investment pitch deck-v10
Investment pitch deck-v10
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
 
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
 

Recently uploaded

Intro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptxIntro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptx
shetivia
 
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
Quotidiano Piemontese
 
what is the future of Pi Network currency.
what is the future of Pi Network currency.what is the future of Pi Network currency.
what is the future of Pi Network currency.
DOT TECH
 
how to sell pi coins at high rate quickly.
how to sell pi coins at high rate quickly.how to sell pi coins at high rate quickly.
how to sell pi coins at high rate quickly.
DOT TECH
 
Summary of financial results for 1Q2024
Summary of financial  results for 1Q2024Summary of financial  results for 1Q2024
Summary of financial results for 1Q2024
InterCars
 
how can I sell my pi coins for cash in a pi APP
how can I sell my pi coins for cash in a pi APPhow can I sell my pi coins for cash in a pi APP
how can I sell my pi coins for cash in a pi APP
DOT TECH
 
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit CardPoonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
nickysharmasucks
 
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
ydubwyt
 
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdfWhich Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
Kezex (KZX)
 
Introduction to Indian Financial System ()
Introduction to Indian Financial System ()Introduction to Indian Financial System ()
Introduction to Indian Financial System ()
Avanish Goel
 
NO1 Uk Black Magic Specialist Expert In Sahiwal, Okara, Hafizabad, Mandi Bah...
NO1 Uk Black Magic Specialist Expert In Sahiwal, Okara, Hafizabad,  Mandi Bah...NO1 Uk Black Magic Specialist Expert In Sahiwal, Okara, Hafizabad,  Mandi Bah...
NO1 Uk Black Magic Specialist Expert In Sahiwal, Okara, Hafizabad, Mandi Bah...
Amil Baba Dawood bangali
 
PF-Wagner's Theory of Public Expenditure.pptx
PF-Wagner's Theory of Public Expenditure.pptxPF-Wagner's Theory of Public Expenditure.pptx
PF-Wagner's Theory of Public Expenditure.pptx
GunjanSharma28848
 
how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.
DOT TECH
 
how can I sell pi coins after successfully completing KYC
how can I sell pi coins after successfully completing KYChow can I sell pi coins after successfully completing KYC
how can I sell pi coins after successfully completing KYC
DOT TECH
 
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
betoozp
 
USDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptxUSDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptx
marketing367770
 
how to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchangehow to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchange
DOT TECH
 
innovative-invoice-discounting-platforms-in-india-empowering-retail-investors...
innovative-invoice-discounting-platforms-in-india-empowering-retail-investors...innovative-invoice-discounting-platforms-in-india-empowering-retail-investors...
innovative-invoice-discounting-platforms-in-india-empowering-retail-investors...
Falcon Invoice Discounting
 
Greek trade a pillar of dynamic economic growth - European Business Review
Greek trade a pillar of dynamic economic growth - European Business ReviewGreek trade a pillar of dynamic economic growth - European Business Review
Greek trade a pillar of dynamic economic growth - European Business Review
Antonis Zairis
 
一比一原版UOL毕业证利物浦大学毕业证成绩单如何办理
一比一原版UOL毕业证利物浦大学毕业证成绩单如何办理一比一原版UOL毕业证利物浦大学毕业证成绩单如何办理
一比一原版UOL毕业证利物浦大学毕业证成绩单如何办理
ydubwyt
 

Recently uploaded (20)

Intro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptxIntro_Economics_ GPresentation Week 4.pptx
Intro_Economics_ GPresentation Week 4.pptx
 
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...Turin Startup Ecosystem 2024  - Ricerca sulle Startup e il Sistema dell'Innov...
Turin Startup Ecosystem 2024 - Ricerca sulle Startup e il Sistema dell'Innov...
 
what is the future of Pi Network currency.
what is the future of Pi Network currency.what is the future of Pi Network currency.
what is the future of Pi Network currency.
 
how to sell pi coins at high rate quickly.
how to sell pi coins at high rate quickly.how to sell pi coins at high rate quickly.
how to sell pi coins at high rate quickly.
 
Summary of financial results for 1Q2024
Summary of financial  results for 1Q2024Summary of financial  results for 1Q2024
Summary of financial results for 1Q2024
 
how can I sell my pi coins for cash in a pi APP
how can I sell my pi coins for cash in a pi APPhow can I sell my pi coins for cash in a pi APP
how can I sell my pi coins for cash in a pi APP
 
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit CardPoonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
Poonawalla Fincorp and IndusInd Bank Introduce New Co-Branded Credit Card
 
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
一比一原版BCU毕业证伯明翰城市大学毕业证成绩单如何办理
 
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdfWhich Crypto to Buy Today for Short-Term in May-June 2024.pdf
Which Crypto to Buy Today for Short-Term in May-June 2024.pdf
 
Introduction to Indian Financial System ()
Introduction to Indian Financial System ()Introduction to Indian Financial System ()
Introduction to Indian Financial System ()
 
NO1 Uk Black Magic Specialist Expert In Sahiwal, Okara, Hafizabad, Mandi Bah...
NO1 Uk Black Magic Specialist Expert In Sahiwal, Okara, Hafizabad,  Mandi Bah...NO1 Uk Black Magic Specialist Expert In Sahiwal, Okara, Hafizabad,  Mandi Bah...
NO1 Uk Black Magic Specialist Expert In Sahiwal, Okara, Hafizabad, Mandi Bah...
 
PF-Wagner's Theory of Public Expenditure.pptx
PF-Wagner's Theory of Public Expenditure.pptxPF-Wagner's Theory of Public Expenditure.pptx
PF-Wagner's Theory of Public Expenditure.pptx
 
how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.how to sell pi coins in South Korea profitably.
how to sell pi coins in South Korea profitably.
 
how can I sell pi coins after successfully completing KYC
how can I sell pi coins after successfully completing KYChow can I sell pi coins after successfully completing KYC
how can I sell pi coins after successfully completing KYC
 
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
一比一原版Birmingham毕业证伯明翰大学|学院毕业证成绩单如何办理
 
USDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptxUSDA Loans in California: A Comprehensive Overview.pptx
USDA Loans in California: A Comprehensive Overview.pptx
 
how to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchangehow to sell pi coins on Bitmart crypto exchange
how to sell pi coins on Bitmart crypto exchange
 
innovative-invoice-discounting-platforms-in-india-empowering-retail-investors...
innovative-invoice-discounting-platforms-in-india-empowering-retail-investors...innovative-invoice-discounting-platforms-in-india-empowering-retail-investors...
innovative-invoice-discounting-platforms-in-india-empowering-retail-investors...
 
Greek trade a pillar of dynamic economic growth - European Business Review
Greek trade a pillar of dynamic economic growth - European Business ReviewGreek trade a pillar of dynamic economic growth - European Business Review
Greek trade a pillar of dynamic economic growth - European Business Review
 
一比一原版UOL毕业证利物浦大学毕业证成绩单如何办理
一比一原版UOL毕业证利物浦大学毕业证成绩单如何办理一比一原版UOL毕业证利物浦大学毕业证成绩单如何办理
一比一原版UOL毕业证利物浦大学毕业证成绩单如何办理
 

AJC Case Analysis

  • 1. AJC Q1. How would you characterize the project assets? What makes them different or unique? Solution: Assets: Transmission Cable, Repeaters, Transmission Equipment, Landing Stations and Ships:  There are 2 mediums for long distance data transmission: Satellite and Cable systems. Cable systems offer better quality, lower costs and can carry much more capacity compared to the satellite systems.  It is the core asset for the project.  A 12500 kilometres long fiber optic cable will be laid out for the project.  The life of the cable is estimated at 25 years.  The transmission cable failures usually happen in the shallow water areas. Using collapsed ring configuration would be the major advantage for AJC as it would reduce the capital costs considerably.  Once the cables laid out they are highly reliable since only 1 (average) failure is usually recorded in a cable’s life.  It is not very expensive to upgrade traffic capacity, i.e., $25 million/40Gbps. However, it takes around 12-15 months to implement it.  It may be difficult to attract lenders for such project. Example, on a visit to Mundra Port Single Point Mooring, we were explained by the instructor that it was very difficult to convince the ‘bankers’ that a system like that could require such huge investment (INR 50-100 crores). What the bankers saw was a 200 sq ft metal floating body (most part was invisible) and it took an effort by the engineers to explain the bankers about the inherent complexity and hence the costs associated. AJC project might have faced a similar issue at that time.  Repeaters are required for every 400 kilometres to reshape and boost the signal as it becomes attenuated when transmitted over long distances.  Transmission Equipment comprises of transmitter, router and reception hub and determines the capacity of the system to transfer the signals. It could be easily upgraded to handle more traffic.  Landing Stations and Ships are hired for the project. Ships are used to install Cables and Repeaters.  As the telecom sector is highly evolving (in 1999), there is always technology risk associated with such projects. There is a possibility of bigger and better technology (which would handle higher and much bandwidth) in such an environment.  The revenues are front loaded as much of the revenue is recognised in the earlier years of the project (in terms of their contribution to the NPV).  The operation costs are fairly consistent for the life of the project.  Most of the capital expense will occur very early in the project.
  • 2. Q2. Who provide capital to the AJC project? Are they likely to earn an appropriate risk adjusted return on their investment? What potential problems could arise that would prevent them from earning a return on their invested capital? Solution: NPV and IRR for 3 scenarios has been calculated in the excel sheet. The capital for the project would come from the sponsors and consortium of banks. The project would have fairly high financial leverage (85%). To obtain their target debt structure, they wanted to raise 2 debt tranches: Senior debt: Repayments would come from presale commitments. Junior debt: Repayments would come from future sales of capacity.  Technology risk: Telecom Sector is evolving rapidly and hence there is technological risk associated with the project.  Completion Delay Risk: Since most of the revenue is front loaded, any delay in the project will have much adverse effect on its valuation. It can also happen because of environmental clearance delays, etc.  Political Risk: As the project covers more than one country, we need to take into consideration the sovereign risk. Since we have sponsors from each country associated with the project, the risk is somewhat mitigated.  Market Risk: To mitigate this they will need presale contracts.  Credibility Risk: Depends on the composition of the sponsors.  Operational Risk: Price Volatility is very high and there’s also risk of demand. They will partner sponsors strategically to reduce uncertainty with the revenue and to reduce the costs (landing stations). Q3. How would you structure the project company to mitigate these problems? What are your recommendations in terms of? a. ownership structure (how many sponsors and which ones) b. capital structure (project fin vs. corporate fin) C.organizational structure Solution: a. Ownership Structure: Factors to be considered are Compatibility, Affect on Project Cost and Revenue. The project costs may be reduced by utilisation of the landing station of sponsors and also the revenue can be made certain if the sponsors are themselves buyers for capacity. We would go for 4 sponsors: Telstra, Japan Telecom, Teleglobe, and AT&T: AT&T would enable us to use the Guam Landing station and also would buy some capacity. Their debt rating is AA- which would add to the credibility for lenders.
  • 3. b. Capital Structure Although, the financial leverage is high (85%), it would make them share the project risk with the lenders of the project. They could allow high leverage because of high amount of certain cash flow. Project Finance is recommended for the project as it would prevent exposure of risk to the sponsor companies’ assets. The high debt taken by the sponsors would be off-the balance sheet for them. As there is high free cash flows associated with the project, there is bound to be mismanagement risk of the fund. Having high leverage position would prevent this as free cash flow would reduce in high debt situation. c. Organisational Structure The sponsors will have equal stake in the shareholding pattern. This way all of them will have equal say in the functioning of the project. All the shareholders hold strong positions and add value to the project; the board will be represented equally by the sponsors. This would prevent any conflicts in the decision making.